Beijing Daxing Airport
Infrastructure0% cost On time
Beijing Daxing opened on 25 September 2019, five days ahead of plan, against an approved investment of CNY 79.98 billion.
Interactive dataset · 100 projects · Updated October 25, 2026
From the Great Pyramid to the James Webb Space Telescope, we rebuilt 100 famous projects as Gantt charts that set the plan people approved against what actually happened. Most finished late and over budget, a few beat the plan, and every number links to its source. It is the clearest evidence we know of the gap between project time estimation and reality.
Explore the map Play Over or Under?
Every pin is a project. Bigger pins cost more in today’s dollars; small dots mean the cost was never published. Choose what the colors show, click a legend item to filter, and click a pin to open its Gantt chart.
The interactive map needs JavaScript. All 100 projects are listed in full under All project records.
0% cost On time
Beijing Daxing opened on 25 September 2019, five days ahead of plan, against an approved investment of CNY 79.98 billion.
+245% cost 9 years late
Berlin's BER airport opened nine years late, in October 2020, after its cost rose from about €2 billion to roughly €6.5 to 7.3 billion.
+44% cost 8 years late
John Roebling expected five years and about $10.8 million; the Brooklyn Bridge took 13 years and about $15.5 million.
+275% cost 20 years late
California voters were told in 2008 that high-speed rail from San Francisco to Anaheim would cost $33.6 billion by 2020; the 2026 plan says about $126 billion and 2040.
+421% cost 10 years late
Boston's Big Dig was planned at $2.8 billion for 1998 and finished in December 2007 at $14.6 billion, before interest.
+79% cost 12 months late
The Channel Tunnel opened a year late with an 80 percent real-terms construction overrun, £4.65 billion against £2.6 billion at 1985 prices.
Cost not public On time
Brazil built a new capital in 41 months and inaugurated it on 21 April 1960, the date set by law, at an estimated cost of about US$1.5 billion.
+19% cost 5 years late
Crossrail's central section opened three and a half years late, in May 2022, with costs at £18.9 billion against £15.9 billion first announced in 2007.
+81% cost On time
Dubai's Red Line opened on its fixed date of 9 September 2009, but the two-line metro's budget rose from AED 15.5 billion to about AED 28 billion.
+243% cost 23 years late
The Interstate System's cost estimate rose from $37.6 billion in 1958 to $128.9 billion in 1991, and it took 36 years instead of about 12.
+43% cost Delay unknown
New York built the 363-mile Erie Canal in eight years for $7.14 million, about 43 percent above the 1817 estimate of $5 million.
Cost not public 7 years early
The first US transcontinental railroad was joined at Promontory Summit on 10 May 1869, seven years ahead of the 1 July 1876 deadline set by Congress.
-4% cost Delay unknown
The Golden Gate Bridge was built for about $35 million, the size of its bond issue, and finished ahead of schedule and $1.3 million under budget.
+51% cost 7 months early
The 57 km Gotthard Base Tunnel opened about a year early in 2016, but at CHF 9.56 billion it cost 51 percent more than the 1998 estimate in constant prices.
0% cost On time
BAA delivered the £4.3 billion Heathrow Terminal 5 on time and within budget, then lost more than 500 flights in its first ten days.
+474% cost 13 years late
HS2's first phase was costed at about £16 billion and due in 2026; the May 2026 reset puts it at £87.7 to 102.7 billion and opening by 2036 to 2039.
-5% cost 13 months late
Hong Kong's Airport Core Programme finished at HK$155.3 billion, HK$8.4 billion below its 1992-93 budget, though the airport itself opened about a year after its mid-1997 target.
+27% cost 2 years late
The 55 km Hong Kong–Zhuhai–Macau crossing opened in October 2018, about two years late, and its Main Bridge budget rose from CNY 38 billion to CNY 48.07 billion.
+23% cost On time
Eiffage built the 343 m tall Millau Viaduct in about three years and opened it on 16 December 2004, 25 days ahead of plan.
+6% cost On time
The 16 km Øresund road-rail link opened on its planned date, 1 July 2000, for DKK 14.8 billion in 1990 prices.
+168% cost 4 years early
The US opened the Panama Canal in August 1914, ahead of its revised 1915 target, at about $375 million against a 1906 construction estimate of $139.7 million.
+10% cost 3 years late
The first 2.9 km of the Second Avenue Subway opened three years late on 1 January 2017, at $4.45 billion for three new stations.
+243% cost Delay unknown
The Seikan Tunnel was planned as an eight-year, ¥201.4 billion job; it took 24 years from the start of works and cost about ¥690 billion.
+371% cost 13 years late
Stuttgart 21 was agreed in 2009 at about €3.1 billion for 2019; Deutsche Bahn now forecasts €14.5 billion and December 2031.
+116% cost 4 years late
The Suez Canal took ten years instead of the six announced and cost 433 million francs against a 200-million-franc estimate.
+9% cost Delay unknown
The Sydney Harbour Bridge cost about AU£6.25 million against a 1922 statutory estimate of £5.75 million, and was paid off only in 1988.
+67% cost 13 months late
The world's tallest building opened 13 months after its end-2008 target, at about US$1.5 billion against early reports of US$900 million.
+20% cost 1 month early
Built in about 26 months for the 1889 World's Fair, the Eiffel Tower cost 7.8 million francs against an estimate of 6.5 million.
+925% cost 6 years late
Hamburg taxpayers were told the Elbphilharmonie would cost them EUR 77 million; the bill reached EUR 789 million and the hall opened seven years late.
+175% cost 16 months late
The repair of Big Ben's tower, priced at £29 million in 2016, ended up costing about £80 million and finished more than a year after its 2021 target.
-18% cost On time
The Empire State Building rose in 410 days and cost $40.9 million including land and demolition, against a $50 million budget.
+14% cost 3 years late
Expected to finish for St. Louis's 1964 bicentennial, the Gateway Arch topped out in October 1965 and cost about $13 million against an $11.4 million contract.
0% cost 4 months late
Frank Gehry's titanium museum opened in October 1997 on time and on its roughly $100 million budget, a rare result for a landmark building.
+58% cost 14 months late
Marina Bay Sands was pitched at S$3.85 billion plus land and opened in stages from 2010 at about S$8 billion.
+4% cost On time
The Dome opened on time and spent GBP 789 million against a GBP 758 million budget, but visitor income came in at about half the plan and Lottery grants rose from GBP 399 million to GBP 628 million.
+98% cost 9 years late
Expected to take five years and $500,000, the carving of Mount Rushmore took 14 years and cost $989,992.32, and the figures were never finished below the chest.
+30% cost 3 years late
The tallest building in the Western Hemisphere opened three years late, with its estimated cost up from $3 billion to $3.9 billion.
+231% cost 24 years late
Charles Barry estimated six years and about GBP 725,000 to rebuild Parliament; it took 30 years and about GBP 2.4 million.
-2% cost 8 months late
Rebuilt in five years and eight months for about EUR 703 million, Notre-Dame reopened in December 2024 within budget, according to France's Court of Audit.
+304% cost 8 years late
Planned in 2000 as a 202-million-guilder (about EUR 92 million) job finishing in 2005, the Rijksmuseum renovation reopened in April 2013 at about EUR 370 million.
+936% cost 3 years late
Holyrood was first priced at GBP 10-40 million and finished three years late at GBP 414 million.
+126% cost 10 years late
Meant for the 1876 centennial, the statue was dedicated ten years late, and its pedestal cost about twice the $125,000 first estimated.
+1357% cost 11 years late
Estimated at A$7 million and due on Australia Day 1963, the Opera House opened ten years late at A$102 million.
+31% cost 6 years late
Planned to open in 1997 for about $210 million, Frank Gehry's hall opened six years late in 2003 at $274 million.
+5% cost 10 months late
The new Wembley opened a year late, and contractor Multiplex lost about A$251 million on its GBP 445 million fixed-price deal.
+27% cost 5 months early
NASA met Kennedy's end-of-decade deadline with five months to spare, for $25.4 billion against an early estimate of $20 billion.
Cost not public Delay unknown
Cassini–Huygens cost about $3.26 billion and survived the cancellation of its twin mission CRAF, then flew to Saturn and operated for 13 years.
+150% cost 10 years late
Hubble reached orbit seven years late at about $1.5 billion, more than double its original $600 million estimate, then needed a 1993 repair mission to see clearly.
-10% cost 2 years early
The Human Genome Project finished in April 2003, more than two years early, at about $2.7 billion against a $3 billion estimate.
+288% cost 17 years late
Approved in 1984 as an $8 billion station to be finished by 1994, the US-led space station was completed in 2011 at a construction cost NASA put at $31 billion.
+870% cost 15 years late
Webb was pitched in the late 1990s as a roughly $1 billion telescope launching in 2007; it launched on Christmas Day 2021 at a life-cycle cost of $9.7 billion.
+67% cost 5 years late
CERN's collider started physics five years after its 2005 target, and its construction cost to CERN rose from an allotted 2.6 billion Swiss francs to 4.3 billion.
0% cost 2 months late
Mars Pathfinder was built in about three years for $150 million plus $25 million for its rover, and Sojourner worked 83 days on a planned seven-day mission.
+56% cost 2 years late
Curiosity missed its 2009 launch window by two years, and its life-cycle cost rose 56 percent to about $2.5 billion.
0% cost On time
New Horizons made its 2006 launch window and reached Pluto in July 2015, the earliest date planned, within a total budget of about $700 million.
+40% cost 3 years late
A launcher failure cost Rosetta its January 2003 window and its original comet, but ESA's about 1.4 billion euro mission still became the first to orbit a comet.
+31% cost 2 years late
The Shuttle first flew in April 1981, about two years after its March 1979 target, after NASA had sold it on a $5.15 billion development estimate.
Cost not public 8 months late
Cyberpunk 2077 slipped three times from April to December 2020 on a PLN 1.2 billion budget, then was pulled from the PlayStation Store eight days after launch.
+42% cost 16 months late
A baggage system signed at $175.6 million delayed Denver's new airport by 16 months and was scrapped by United in 2005.
+43% cost Cancelled
The FBI's Virtual Case File grew from a $119.2 million plan to $170 million and was abandoned in 2005 without going into service.
+123% cost 3 months late
A federal marketplace contract estimated at $93.7 million had $209 million obligated by February 2014, and the site crashed on launch day.
+326% cost Cancelled
England's NHS IT programme started with a £2.3 billion three-year budget and was dismantled in 2011 with a forecast cost of £9.8 billion.
+1551% cost 10 months late
Approved at about C$309 million to save money on federal pay, Phoenix has cost an estimated C$5.1 billion to launch and fix.
+1176% cost Delay unknown
A $98 million IBM contract produced a payroll that mispaid 78,000 health workers and was estimated in 2012 to cost at least $1.25 billion to fix.
Cost not public On time
Apple met its own June 2007 launch promise for the iPhone, at a development cost an insider later put at about $150 million.
+22% cost 9 years late
Universal Credit was due by 2017 for £2.4 billion; the latest forecast is £2.9 billion and legacy benefits ending in March 2026.
Cost not public 4 years late
Planned as a minor 2003 update, Windows Vista shipped to consumers in January 2007 after a reported $6 billion and a full development reset.
+266% cost 2 months late
The federal Y2K fix was first estimated at $2.3 billion in 1997 and ended at about $8.4 billion, with 99.9% of critical systems ready.
+90% cost 18 months late
Airbus launched the A380 at a projected €9.5 billion in 2000; wiring problems made the first delivery 18 months late and Airbus put total development at about €18 billion by 2006.
Cost not public On time
Boeing promised Pan Am a 747 by the end of 1969, about 28 months after the order, and delivered on time, but development passed $1 billion and the company's debt exceeded $2 billion.
+25% cost On time
Boeing designed the 777 almost entirely on computer with 238 design-build teams and delivered the first aircraft to United on time in May 1995, for a reported $4-5 billion.
+357% cost 3 years late
Boeing's board approved a $7 billion development budget for the 787; the program reportedly cost $32 billion and the first jet reached ANA more than three years late.
+1025% cost 6 years late
Concorde's development estimate rose from £150-170 million at the 1962 treaty to an estimated £1.5-2.1 billion, and passenger service began six years late, in 1976.
+8% cost On time
Chantiers de l'Atlantique built Queen Mary 2, the largest ocean liner ever, on schedule in about three years after a contract worth about $780 million.
Cost not public On time
Harland & Wolff built Titanic for about £1.5 million, but repairs to her sister ship Olympic pushed the maiden voyage back three weeks, from 20 March to 10 April 1912.
Cost not public 7 months late
Tesla planned to build 5,000 Model 3s a week by December 2017; it built 2,425 in the whole fourth quarter and reached 5,031 in a week only at the end of June 2018.
+95% cost On time
The Tōkaidō Shinkansen opened on time for the 1964 Tokyo Olympics, but cost about ¥380 billion against a ¥194.8 billion estimate, and its two leaders resigned.
Cost not public 12 months early
Toyota's management pulled the Prius launch forward by a year, from the end of 1998 to December 1997, and the world's first mass-produced hybrid went on sale on 10 December 1997.
+618% cost 13 years late
France's first EPR was budgeted at EUR 3.3bn for 2012; the Cour des comptes puts its full cost at EUR 23.7bn and it reached the grid 12 years late.
+119% cost 7 years late
Hinkley Point C was presented in 2012 as a GBP 16bn plant generating by 2023; EDF now expects about GBP 35bn in 2015 prices and Unit 1 in 2030.
-15% cost 2 years early
Six Companies had seven years to build Hoover Dam and handed it over in under five, about two years early.
+626% cost Delay unknown
Itaipu was first costed at about US$2.7bn; it ended up at roughly US$19.6bn, and its debt took 50 years and US$63.5bn to repay.
+239% cost 18 years late
Signed in 2006 at an estimated EUR 5.9bn with first plasma due in 2016, ITER now expects research operation in 2034 after cost estimates passed EUR 20bn.
+267% cost 14 years late
Finland's first EPR was sold as a EUR 3bn fixed-price turnkey job due in 2009; it entered commercial operation in 2023 at an estimated EUR 11bn.
+500% cost 5 years late
Snowy 2.0 was floated at about A$2bn in 2017; the official cost to complete is now A$12bn and full operation has slipped to at least December 2028.
0% cost 3 years late
The world's largest power station came in at about 203 billion yuan against an initial budget of 203.9 billion, but full operation slipped three years to 2012.
+39% cost On time
South Africa's World Cup stadiums cost the state about R11.7 billion, some 39 percent more than the R8.4 billion expected in 2006.
+200% cost On time
Athens 2004 opened on time, but government and organizing costs grew from about EUR 3 billion to near EUR 9 billion.
+266% cost On time
Barcelona's sports-related Olympic costs ran 266 percent over the bid in real terms, to US$9.7 billion in 2015 dollars, but the Games are widely seen as a model of urban regeneration.
-29% cost On time
Expo 2015 opened on its fixed date of May 1, 2015, and its organizing company spent EUR 2.25 billion from 2009 to 2015.
+123% cost On time
London 2012 finished GBP 377 million under its 2007 budget of GBP 9.3 billion, but that budget was more than double the 2005 bid.
+1233% cost On time
Estimated at C$120 million in 1970, the Montreal Games ended at about C$1.6 billion and took Quebec 30 years to pay off.
+352% cost On time
Rio 2016's sports-related costs came in 352 percent over the bid in real terms, the second-largest Summer Games overrun on Oxford's list.
+94% cost 12 months late
Tokyo's Games cost 1.42 trillion yen, nearly double the 734 billion yen in the 2013 bid, and opened a year late because of the pandemic.
Cost not public 9 years late
The 2026 Gaudí-centenary target was met for the 172.5 m central tower, but the full basilica is now expected around 2035, 153 years after work began.
Cost not public Delay unknown
Cologne Cathedral took 632 years to finish, including more than three centuries when no one worked on it at all.
Cost not public Delay unknown
About 2.3 million stone blocks were set in place in roughly 20 to 27 years, the length of one pharaoh's reign.
Cost not public Delay unknown
Over 276 years the Ming dynasty built a system of walls that a 2009 survey measured at 8,850 km, including 6,259 km of actual wall.
Cost not public Delay unknown
More than 20,000 workers spent about 22 years on the Taj Mahal complex, at a reported cost of 32 million rupees.
Cost not public 14 months late
Announced in 1993 for a mid-1994 release, Windows 95 reached stores on 24 August 1995, about 14 months late.
No project matches these filters.
Both Gantt charts share one time axis, measured in months from each project’s planned start, so a three-year tower and a thirty-year railway can be read against each other.
Comparing projects needs JavaScript. Each project’s full record is in All project records.
Try:
Overruns are not random bad luck. The same patterns repeat across centuries, which is why time estimates drift from reality in such predictable ways. Click any bar to open the project.
Ranked by cost overrun as a share of the first approved budget.
Ranked by the overrun in 2025 US dollars (actual minus planned, each converted at its own year’s exchange rate and inflated with US CPI).
Ranked by months between the planned and the actual (or latest forecast) finish. Planning tools cannot stop a slip, but schedule tools that keep deadlines realistic make it visible early.
Projects that finished no more than a month after their planned date, earliest first.
Shortest actual duration from start to finish among completed projects.
Longest actual (or forecast) duration from start to finish.
Ranked by actual (or forecast) cost in 2025 US dollars.
Ranked by the year work started.
Ten rounds. You see the plan; you guess the outcome. Scoring: 50 points for calling on time or late correctly, plus up to 50 points for your overrun guess, minus one point for every 4 percentage points you are off (guesses and answers are capped at 400%).
The game needs JavaScript.
Enter your plan. We look up how projects of the same kind in this dataset actually turned out and show the median and the 80th-percentile result. This is reference class forecasting, the method Bent Flyvbjerg developed to correct optimistic plans. It is illustrative only: it uses these 100 projects, not a statistical sample of all projects. Read more on why estimates and reality diverge.
The calculator needs JavaScript.
-18% cost On time
The Empire State Building rose in 410 days and cost $40.9 million including land and demolition, against a $50 million budget.
The passport needs JavaScript and stores progress only in your browser.
The Gantt chart is older than the airplane. Karol Adamiecki drew his harmonogram in 1896 and Henry Gantt’s charts spread through American industry from about 1910; the same bar-against-time idea is what every chart on this page uses. Scroll through 32 moments, from the first schedules to AI agents, and open the projects shaped by each one. If you want to draw your own, here is how to set up a project timeline.
1896
Karol Adamiecki
In 1896 Karol Adamiecki, an engineer in charge of a steel rolling mill in Dąbrowa Górnicza, in what is now southern Poland, devised a new way to display interdependent work processes on a time scale. Each operation appeared as a strip set against a calendar, so a planner could see what had to finish before the next job could start and shift work to balance the mill. He described the idea in the Polish journal Przegląd Techniczny in 1909 and gave it the name harmonogram, or harmonograf, in a better-known 1931 article. Because he published mainly in Polish and Russian, the method stayed little known abroad, and the bar chart that spread worldwide carries Henry Gantt's name instead.
Why it mattered: Adamiecki's chart is the first known attempt to show the timing and dependencies of work on a single visual schedule. It anticipated both the Gantt chart and, in its focus on dependencies, later network methods.
c. 1910–1915
Henry L. Gantt; Wallace Clark
Henry Laurence Gantt, an American mechanical engineer who had worked with Frederick Taylor, developed his charts around 1910 to 1915. His idea was to plot work against time rather than simply count output: each row showed a machine, a worker or an order, and horizontal lines compared what was planned with what had actually been done. In his 1919 book Organizing for Work he set out the principles behind the charts. The familiar version, a list of tasks with bars across a calendar, owes much to his colleague Wallace Clark, whose 1922 book The Gantt Chart: A Working Tool of Management spread the format through industry in the United States and Europe.
Why it mattered: The Gantt chart made a plan and its progress readable at a glance by anyone, not only by the planner. More than a century later it remains the most common way to present a project schedule.
Where the name comes from: what does Gantt stand for? Why the format survived a century: the benefits of Gantt charts.
Sources: Wikipedia, Internet Archive, Wikipedia
1911
Frederick Winslow Taylor
Frederick Winslow Taylor published The Principles of Scientific Management in 1911 through Harper & Brothers. Drawing on his work at Midvale Steel and Bethlehem Steel, he argued that rule-of-thumb methods wasted effort and that managers should study each task, define the best method, select and train workers for it, and share responsibility for the results. His case studies of shoveling and pig-iron handling became famous. The book drew lasting criticism for treating workers as interchangeable parts, yet its central habit, measuring work before planning it, shaped planning offices, time standards and later project controls. In 2001 Fellows of the Academy of Management voted it the most influential management book of the 20th century.
Why it mattered: Taylor made planning a distinct management job based on measurement rather than habit. Gantt and many early planners worked within the movement his book defined.
Sources: Wikipedia
1917–1918
Henry L. Gantt; Walter Polakov; US Shipping Board Emergency Fleet Corporation
On April 16, 1917, the US Shipping Board set up the Emergency Fleet Corporation to acquire, build and operate merchant ships, a program that soon spread across dozens of shipyards. Keeping track of keels laid, hulls launched and ships delivered against a national target was a scheduling problem on a new scale. Gantt and his associate Walter Polakov were hired as consultants, and according to Wallace Clark's 1922 account, Gantt charts were in use at the Emergency Fleet and the Shipping Board by 1918. The charts were also applied to managing fleet movements. A single sheet could now compare planned and actual progress across many sites, and Gantt finalized the design of his charts during this work.
Why it mattered: This was one of the first uses of Gantt charts to coordinate a program spread across many organizations and locations. It showed that the charts worked as a tool for senior managers, not only for a single shop floor.
Sources: Internet Archive, Wikipedia, Wikipedia
1931–1936
Six Companies; US Bureau of Reclamation; Frank Crowe
When the Bureau of Reclamation awarded the Hoover Dam contract to Six Companies on March 11, 1931, the consortium's $48.9 million bid came with firm deadlines: seven years to finish the job, and a $3,000-a-day fine if the river diversion tunnels were not complete by October 1, 1933. General superintendent Frank Crowe had to sequence tunneling, cofferdams, excavation and concrete placement at a remote canyon site. The project is often cited as an early large construction job run with Gantt-style bar charts, although that claim rests mostly on later secondary accounts. First concrete was poured on June 6, 1933, and the dam was turned over to the government on March 1, 1936, more than two years ahead of schedule.
Why it mattered: Hoover Dam showed that a giant public works project could be planned in stages and finished early when deadlines carried real penalties. It became a reference case for schedule discipline in heavy construction.
Projects from this era on the map: Hoover Dam
Sources: US Bureau of Reclamation, Wikipedia
1948–1953
Taiichi Ohno; Eiji Toyoda; Toyota Motor Corporation
In the years after World War II, Toyota looked for ways to cut waste and inventory. Taiichi Ohno, working with Eiji Toyoda, began developing what became the Toyota Production System in 1948, borrowing an idea from American supermarkets: a shelf is restocked only after customers take goods from it. On the factory floor, each process became the customer of the one before, withdrawing only the parts it needed, and a card, or kanban, signaled what to make next. Toyota applied this pull logic in its main plant machine shop in 1953 and adopted kanban at all plants in 1963. The system rests on two pillars, just-in-time and jidoka, and made queues of work visible.
Why it mattered: Kanban turned scheduling from a central forecast into a signal sent by the work itself. Its ideas of visible work and limited inventory later shaped lean construction and the Kanban Method in knowledge work.
Today the two ideas meet: kanban and Gantt in one tool.
Projects from this era on the map: Toyota Prius (G21)
Sources: Toyota Motor Corporation, Toyota Motor Corporation, Wikipedia
1956–1959
Morgan R. Walker (DuPont); James E. Kelley Jr. (Remington Rand UNIVAC)
In 1956 and 1957 Morgan R. Walker of DuPont and James E. Kelley Jr. of Remington Rand UNIVAC set out to reduce the time and cost of maintenance shutdowns at DuPont's chemical works. Their method broke a job into activities, linked them by dependencies and calculated the longest chain through the network, the critical path, which sets the shortest possible duration. Activities off that path have float and can slip without delaying the finish. The calculations ran on a UNIVAC computer, which could generate a schedule from task sequences and durations. Kelley and Walker published Critical-Path Planning and Scheduling at the Eastern Joint Computer Conference in December 1959, and CPM spread quickly into construction and engineering.
Why it mattered: CPM showed managers which tasks actually controlled the finish date, so attention and money could go where they made a difference. It remains the calculation at the core of almost every scheduling tool.
Sources: Project Management Institute, Wikipedia, Mosaic Project Services
1957–1958
US Navy Special Projects Office; Booz Allen Hamilton; Lockheed
In 1957 and 1958 the US Navy's Special Projects Office, working with Booz Allen Hamilton and Lockheed, developed the Program Evaluation and Review Technique to coordinate the many contractors on the Polaris program. Like CPM, PERT modeled a program as a network of events and activities, but it treated durations as uncertain. Each activity received three estimates, optimistic, most likely and pessimistic, combined as (o + 4m + p) / 6 to give an expected time and a sense of the spread. Planners could then estimate the chance of reaching a milestone by a given date. The Navy made the method public in two reports in 1958, and PERT became a standard tool on large government and aerospace programs.
Why it mattered: PERT was the first widely used method to treat a schedule as a forecast with a range rather than a single date. Its three-point estimate is still taught and used today.
Sources: Wikipedia, Mosaic Project Services
1961–1969
NASA; George E. Mueller; Samuel C. Phillips
On May 25, 1961, President John F. Kennedy asked Congress to commit to landing a person on the Moon before the decade was out. Meeting that deadline meant coordinating more than 20,000 companies and universities and, at the peak, about 400,000 people. From 1963 George Mueller led NASA's manned space flight office and pushed all-up testing of complete rockets to save time, while Samuel Phillips, seconded from the Air Force, became Apollo Program Director. Phillips introduced a configuration management manual in 1964, formal design reviews, change control and daily reports to a central control room at headquarters. These systems management practices gave managers a current view of schedule and technical status. Apollo 11 landed on July 20, 1969.
Why it mattered: Apollo showed that a fixed deadline on a program of unprecedented complexity could be met with disciplined change control, integration and reporting. Its systems management practices spread to aerospace, energy and large IT programs.
Projects from this era on the map: Apollo
1962
US Department of Defense; NASA
As PERT spread, managers found that a network of activities did not by itself show what was being built or what it cost. In June 1962 the Department of Defense, NASA and the aerospace industry published a PERT/COST guide that described the work breakdown structure: a hierarchy that divides a program into products and then into smaller packages of work, each of which can be scheduled, budgeted and assigned to someone. The Secretary of Defense endorsed the guide for adoption across all services, and in 1968 the standard MIL-STD-881 made work breakdown structures mandatory on Department of Defense contracts. PERT/COST also laid the groundwork for earned value management. The WBS is now a core element of project management standards.
Why it mattered: The WBS tied scope, schedule and cost to the same set of deliverables, so progress and spending could be measured against one structure. It is still the first planning step taught in most project management courses.
Sources: Wikipedia, Mosaic Project Services
1965
International Project Management Association (IPMA)
The International Project Management Association began in 1965 as a discussion group for managers of international projects in Europe, at a time when network planning methods such as CPM were spreading across the continent. Its first international congress, held in Vienna in 1967, drew participants from 30 countries. From that start IPMA grew into a federation of national project management associations, and today it has about 70 member associations. It publishes the IPMA Individual Competence Baseline, a standard that describes the competences expected of project, program and portfolio managers, and it certifies practitioners against it. Its work helped turn project management from a set of scheduling techniques into a recognized profession with shared standards.
Why it mattered: IPMA gave project managers in different countries a common forum and, later, a common competence standard. It made project management an international profession rather than a collection of national practices.
Sources: Projekt Management Austria (IPMA member association), IPMA, IPMA
1969
Project Management Institute (PMI)
The Project Management Institute was founded in 1969 at the Georgia Institute of Technology by five volunteers: Ned Engman, James Snyder, Susan Gallagher, Eric Jenett and J. Gordon Davis. It was incorporated as a nonprofit in Pennsylvania the same year and is now headquartered in Newtown Square, Pennsylvania. The founders wanted a professional home where people running projects in different industries could share methods and experience. PMI held its first Project Management Professional exam in 1984 and went on to publish the PMBOK Guide and a family of related standards for programs, portfolios, scheduling and risk. Its PMP credential became one of the most widely recognized certifications for project managers worldwide.
Why it mattered: PMI created a shared vocabulary and a professional credential for project managers. Its standards still define much of how project management is taught and assessed.
Sources: Wikipedia
1970
Winston W. Royce (TRW)
Winston W. Royce, a project manager in TRW's aerospace division, presented Managing the Development of Large Software Systems at IEEE WESCON in Los Angeles in August 1970. The paper's early diagram showed software moving in sequence from requirements through analysis, design, coding, testing and operations. Royce called that simple version risky and an invitation to failure, because testing came last and problems found there could force a redesign. He recommended doing a preliminary program design first, documenting the design, building the system twice, planning and monitoring testing, and involving the customer. He never used the word waterfall, which appeared later in the decade. Even so, the sequential diagram became the template for many large software contracts and standards.
Why it mattered: The paper gave large software projects their default lifecycle, even though its author argued for feedback and iteration. Many later failures of big, single-delivery IT programs trace back to running that sequence without his safeguards.
Projects from this era on the map: HealthCare.gov FBI Virtual Case File NHS NPfIT
Sources: University of Washington (reprint), Wikipedia, Wikipedia
1977–1979
Daniel Kahneman; Amos Tversky
Daniel Kahneman and Amos Tversky set out their analysis of why forecasts go wrong in Intuitive Prediction: Biases and Corrective Procedures, first issued as a Decision Research technical report in 1977 and published in TIMS Studies in Management Science in 1979. The paper introduced the term planning fallacy: the tendency to underestimate how long a task will take, even when similar tasks in the past ran late. Planners, the authors argued, focus on the details of the case in hand and neglect how comparable cases actually turned out. Their remedy was to start from that distribution of past outcomes and then adjust. Later experiments, including a 1994 study of students' thesis estimates, confirmed the effect.
Why it mattered: The paper explained late and over-budget projects as a predictable feature of human judgment rather than bad luck. It laid the foundation for reference class forecasting.
The same bias in everyday projects: project time estimation vs reality.
Projects from this era on the map: Sydney Opera House Scottish Parliament Channel Tunnel
1983–1984
Primavera Systems; Harvard Software
Network scheduling began on mainframes, but the IBM PC, launched in 1981, brought it to individual desks within a few years. In the spring of 1983 Joel Koppelman and Dick Faris founded Primavera Systems, whose Primavera Project Planner ran on DOS and was aimed at detailed engineering and construction schedules. Harvard Software's Harvard Project Manager, on sale for the IBM PC by 1984, offered a lighter tool for office projects. These programs let a planner enter activities and dependencies, compute the critical path and print Gantt charts without help from a computing department. By 1984, according to a PMI review of the decade, most of the major vendors were selling microcomputer-based tools.
Why it mattered: Desktop software put CPM and Gantt charts in the hands of individual managers. Scheduling stopped being a specialist service and became something project managers did themselves.
Sources: Wikipedia, Project Management Institute, WinWorld
1984
Microsoft
Microsoft released the first commercial version of Project for MS-DOS in 1984. The product traces to Alan M. Boyd, Microsoft's manager of product development, who specified it as an internal tool, and to Ron Bredehoeft, a former IBM systems engineer whose consulting firm developed it under an agreement with Microsoft. Microsoft bought the rights in 1985 and released version 2, followed by DOS versions 3 and 4. The first Windows version shipped in 1990, and a Macintosh version followed in 1991. Its layout, a task table on the left and bars on a timeline on the right, linked by dependency arrows, became the familiar form of a desktop project plan for a generation of office workers.
Why it mattered: Microsoft Project brought Gantt charts with linked tasks to the mass market of office PCs. Its format shaped what most people expected project software to look like for decades.
How desktop scheduling evolved into cloud tools: Microsoft project management and Kanbanchi.
Sources: Wikipedia
1986
Hirotaka Takeuchi; Ikujiro Nonaka
In the January 1986 issue of Harvard Business Review, Hirotaka Takeuchi and Ikujiro Nonaka published The New New Product Development Game. They argued that speed and flexibility had become as important as quality and cost in developing new products. The authors contrasted the traditional relay-race approach, in which work passes from one specialist group to the next, with a holistic approach in which one cross-functional team works through overlapping phases together. They compared that team to a rugby side moving the ball down the field as a unit, and used the word scrum. The paper described self-organizing teams, overlapping phases and subtle forms of management control. Software developers later borrowed its vocabulary and principles.
Why it mattered: The article gave a name and a model to small, self-organizing teams that plan and deliver in overlapping cycles. It is the direct source of the term Scrum in software development.
Sources: Harvard Business Review, Wikipedia
1987
Project Management Institute; R. Max Wideman
By the mid-1980s PMI members wanted a written statement of what a project manager needed to know. A team of about 80 volunteers chaired by R. Max Wideman built on a 1983 report of PMI's Ethics, Standards and Accreditation Committee, published a draft for comment in the Project Management Journal in August 1986, and saw PMI approve and publish The Project Management Body of Knowledge in 1987. The document organized practice into knowledge areas such as scope, time, cost and quality. In 1996 it was superseded by A Guide to the Project Management Body of Knowledge, which has since run to eight editions, the most recent in 2025, and underpins PMI's certifications.
Why it mattered: The PMBOK turned project management from a set of techniques into a defined body of knowledge that could be taught and examined. Its knowledge areas became a common checklist for planning any project.
Sources: Wikipedia, Wikipedia, Project Management Institute
1989
Central Computer and Telecommunications Agency (CCTA); Simpact Systems
In 1975 Simpact Systems developed PROMPT, a method for managing computer projects, which were often running over time and budget. The UK government's Central Computer and Telecommunications Agency, the CCTA, adopted a version of PROMPT II as its standard for government IT projects and in 1989 launched it as PRINCE. The name first stood for PROMPT II IN the CCTA Environment and was later recast as PRojects IN Controlled Environments. PRINCE organized a project into stages with defined products, roles and management controls, so that each stage could be reviewed before the next began. The method was released into the public domain in 1990, which helped it spread from government into private companies.
Why it mattered: PRINCE gave UK public bodies a single, documented way to run IT projects. Releasing it into the public domain made it a shared method rather than a proprietary one.
Sources: Wikipedia
1995
Ken Schwaber; Jeff Sutherland
In the early 1990s Jeff Sutherland, John Scumniotales and Jeff McKenna at Easel Corporation, and Ken Schwaber at his own company, were experimenting with short, team-based development cycles that drew on Takeuchi and Nonaka's ideas. In 1995 Schwaber and Sutherland co-presented Scrum at the OOPSLA conference, the first public, formal definition of the method. Scrum organizes work into fixed-length sprints, with a prioritized product backlog, a short daily meeting and a review and retrospective at the end of each cycle. It was first tried and proven at organizations including Individual Inc., Newspage, Fidelity Investments and IDX. In 2010 Schwaber and Sutherland wrote the first Scrum Guide; the current version dates from November 2020.
Why it mattered: Scrum replaced long up-front plans with short cycles that deliver working software and re-plan often. It became the most widely adopted agile framework.
Projects from this era on the map: Universal Credit
Sources: scrumguides.org, Wikipedia, Wikipedia
1996
CCTA; later AXELOS and PeopleCert
In 1996 the CCTA released PRINCE2, a generic version of PRINCE intended for any kind of project, not only IT. Its development was contracted out and checked by a review committee drawn from about 150 European organizations. PRINCE2 is built around a continuing business justification, defined roles and responsibilities, management by stages, management by exception and a focus on products. Major updates followed in 2009, 2017 and 2023, the last being the seventh edition. Ownership passed from the UK Cabinet Office to AXELOS, a joint venture with Capita, in July 2013, and to PeopleCert when it acquired AXELOS in 2021. PRINCE2 is widely used in UK government and by organizations in many other countries.
Why it mattered: PRINCE2 made a government method into a general-purpose, certifiable standard. Its emphasis on a business case that is checked at every stage addressed a common cause of failed projects.
Sources: Wikipedia
1997
Eliyahu M. Goldratt
Eliyahu M. Goldratt, the physicist who developed the theory of constraints, applied it to projects in his 1997 book Critical Chain, written as a business novel. He argued that schedules slip less because of bad estimates than because of how safety time is used: people start late, a habit known as student syndrome, fill the time available, as Parkinson's law predicts, and lose time by multitasking. Critical chain project management schedules tasks at aggressive durations, removes the padding from individual tasks and pools it into a project buffer at the end and feeding buffers where other chains join. Managers track how fast the buffers are being used, often on a fever chart, rather than chasing each task date.
Why it mattered: Critical chain added resource limits and human behavior to schedule logic that CPM had treated as purely technical. Its buffer management offered a simple way to judge whether a project was really at risk.
Sources: Wikipedia
2001
Kent Beck, Ward Cunningham, Martin Fowler, Jim Highsmith, Ken Schwaber, Jeff Sutherland and 11 other signatories
From February 11 to 13, 2001, 17 software practitioners met at The Lodge at Snowbird ski resort in Utah's Wasatch mountains. They came from approaches including Extreme Programming, Scrum, DSDM and Crystal, and they shared a dislike of heavy, document-driven development. The Manifesto for Agile Software Development they wrote values individuals and interactions over processes and tools, working software over comprehensive documentation, customer collaboration over contract negotiation, and responding to change over following a plan, while stating that the items on the right still have value. Twelve supporting principles followed. The short text gave a common name to iterative, team-based methods and helped them spread from software into many other kinds of work.
Why it mattered: The manifesto shifted the measure of progress from documents and plans to working results delivered in short cycles. It reframed the plan as something to revise often rather than defend.
Projects from this era on the map: Universal Credit HealthCare.gov
Sources: agilemanifesto.org, agilemanifesto.org
2002–2006
Bent Flyvbjerg; COWI; UK Department for Transport
In 2002 Bent Flyvbjerg, Mette Skamris Holm and Søren Buhl studied 258 transport projects worth US$90 billion and found that the cost estimates used to approve them were systematically too low, with actual costs averaging 28 percent above plan. Building on Kahneman and Tversky's work, Flyvbjerg proposed reference class forecasting: rather than building a forecast up from the details of one project, take the actual outcomes of a class of similar past projects and use their spread to set budgets and contingencies. With the consultancy COWI he turned this into guidance published by the UK Department for Transport in June 2004. Its first use, that October, was a review of the Edinburgh Tram business case, described in a 2006 paper.
Why it mattered: Reference class forecasting turned the planning fallacy into a practical correction that governments could require. It has since been applied to projects such as Crossrail and adopted in several European countries.
Projects from this era on the map: Crossrail Channel Tunnel Sydney Opera House
2006
In 2006 Google brought office documents into the web browser. On March 9 it acquired Upstartle, maker of the Writely web word processor; on August 28 it launched Google Apps for Your Domain for organizations; and on October 10 it released its web-based document editor, offered with spreadsheets as Google Docs & Spreadsheets. Several people could now work on the same document or spreadsheet at once, with no files to email back and forth and a revision history kept online. For project work, a schedule, a task list or a status report could live in one shared place that every team member saw in its current state. Google Apps became G Suite in 2016 and Google Workspace in 2020.
Why it mattered: Browser-based collaboration ended the era of emailing plan files and reconciling versions. It set the expectation that project information is shared and current by default.
2010
David J. Anderson
David J. Anderson adapted Toyota's pull system to software and IT work. At Microsoft in 2004 he applied theory-of-constraints ideas to a team in the company's IT department, and at Corbis in 2006 and 2007 the approach took recognizable form as the Kanban Method. In 2010 Blue Hole Press published his book Kanban: Successful Evolutionary Change for Your Technology Business. The method starts from a team's current process rather than replacing it. Its two primary practices are to visualize work, usually on a board with a column for each stage, and to limit work in progress, so the team pulls new items only when it has capacity. Measuring flow then exposes bottlenecks and long waits.
Why it mattered: The book gave knowledge workers a way to manage flow without adopting a whole new process. Kanban boards with work-in-progress limits became a standard view in modern task tools.
Sources: Wikipedia
2011
Fog Creek Software; Joel Spolsky
Fog Creek Software, the New York company co-founded by Joel Spolsky, unveiled Trello at a TechCrunch event in 2011. Trello put a simple kanban-style board in the browser: lists as columns, cards for tasks, and drag and drop to move work from one stage to the next. It was free to start and needed little training, which helped it spread well beyond software teams. Trello became a separate company in 2014, reported 1.1 million daily active users and 14 million signups in May 2016, and was acquired by Atlassian in January 2017 for $425 million. Its growth showed that a visual board could work as a project tool for people who had never used one.
Why it mattered: Trello made the kanban board a mainstream, everyday way to organize work. It showed that simple visual tools could reach far more people than traditional scheduling software.
Sources: Wikipedia
2013–2016
Kanbanchi
Kanbanchi began in 2013 as an internal tool at a software development studio: a kanban board built for Google Apps, the suite now called Google Workspace. It went live on the Chrome Web Store in 2014, and in 2016 a separate company was set up to run it. Instead of keeping projects in a separate system, it saves each board as a file in Google Drive, so boards are shared and permissioned like any other Drive document. Later it added a Gantt chart that turns a board into a timeline with dependencies and milestones. It reflects a wider shift of planning tools into the workspace where teams already write, email and meet.
Why it mattered: Kanbanchi combined the two oldest visual planning formats, the kanban board and the Gantt chart, inside the tools many teams already used every day. Storing boards in Google Drive kept project data under the organization's own file permissions.
A look at modern Gantt chart tools.
2023
Bent Flyvbjerg; Dan Gardner
On February 7, 2023, Crown Currency published How Big Things Get Done by Bent Flyvbjerg, an Oxford economist, and the writer Dan Gardner. Drawing on a database of more than 16,000 projects, they report that 92 percent of megaprojects come in over budget, over schedule or both, and that only a small fraction deliver on budget, schedule and benefits together. The book contrasts troubled projects, such as the Sydney Opera House and California's high-speed rail, whose cost estimate rose from $33 billion to $100 billion, with fast ones, such as the Empire State Building, built from sketch to completion in 21 months. Its advice centers on planning slowly and thoroughly, then acting fast.
Why it mattered: The book brought decades of research on project overruns to a general audience. It argued that careful, iterative planning and reference class forecasting are the cheapest risk controls a project has.
Projects from this era on the map: Sydney Opera House Empire State Building California HSR
Sources: Penguin Random House, Dan Gardner
2023
Software vendors across the industry; Project Management Institute
The public release of ChatGPT on November 30, 2022, and of GPT-4 in March 2023, put large language models in front of millions of office workers. During 2023 the major productivity suites announced assistants built on such models; Google, for example, introduced Duet AI for Google Workspace at its I/O conference in May and opened enterprise preorders in June. Project management tools followed with features that draft task lists from a short description, summarize status updates and comment threads, and suggest schedules. PMI's research on generative AI argues that fluency in AI basics is now essential for project professionals, and that the more complex a task, the more human judgment it requires. Estimates and commitments still rest with people.
Why it mattered: AI assistants cut the time spent drafting plans, summaries and reports. They also raised new questions about checking machine-generated estimates against real project data.
Sources: Wikipedia, Google Workspace Blog, Project Management Institute
2024–2025
Software vendors and AI labs; Gartner; Anthropic and Andon Labs
In 2024 and 2025 AI moved from drafting text to taking actions. Gartner describes agentic AI as systems that plan and act on their own to reach goals a user sets. In project work that meant agents that break a goal into tasks, update the board, chase overdue items and write the weekly status report, with a person approving each step. Anthropic tested how far this could go: for about a month in 2025 its Claude model ran a small office shop, choosing suppliers, setting prices and answering customers, while staff restocked the shelves. It lost money and made odd mistakes. The researchers still concluded that AI middle managers were plausible with better tools.
Why it mattered: For the first time software did project work rather than just recording it. It also met the oldest problem on this page: in June 2025 Gartner predicted that over 40% of agentic AI projects would be canceled by the end of 2027, citing costs, unclear value and weak risk controls.
2026
Organizations adopting AI agents; Gartner
By 2026 an AI assistant is a standard part of most project tools, and planning with one has become routine rather than an experiment. A growing group of projects, mostly in software, research and operations, now runs with AI agents doing the planning, scheduling, tracking and reporting, while people set the goals, approve the decisions and supervise the result. Gartner's 2026 survey of chief information officers found that 17% of organizations had already deployed AI agents and more than 60% expected to within two years, the steepest adoption curve of any technology it measured. In 2019 Gartner had forecast that AI would take over 80% of the tracking and reporting work of project management by 2030.
Why it mattered: The project manager's job shifts from keeping the plan up to date to deciding what the plan should be and checking the agents that run it. The questions on this page do not change: was the first estimate realistic, and who notices when the critical path slips?
Each row is a phase of the project. The thin grey bar is what was planned; the thicker purple bar is what happened. Where a project is still running, the purple turns to hatching after today’s date, which is drawn as a dashed line. The gap between the two bars is the story: read more about planned versus actual project schedules.
Diamonds mark milestones: hollow for the planned date, filled for the actual one. Kanbanchi’s own Gantt chart added milestones for the same reason. Small arrows join phases that ran one after another, the dependencies on a Gantt chart that turn one late phase into a late project; we explain how they work in task dependencies explained.
A Gantt chart shows tasks against time and how they depend on each other, which is what separates it from a simple timeline, a roadmap and a calendar. See Gantt chart vs timeline, Gantt chart vs roadmap and Gantt chart vs calendar, or start with how a Gantt chart works and what a Gantt chart tool helps with.
Want to reproduce one of these charts yourself? You can build a Gantt chart in Google Sheets from the CSV below; this step-by-step guide covers the formulas.
The full record for every project: numbers, story, lessons, phases and sources. Open any project for details.
Beijing, China · Infrastructure (airport) · On time and on budget · Confidence: medium
Beijing Daxing opened on 25 September 2019, five days ahead of plan, against an approved investment of CNY 79.98 billion.
Cost: planned CN¥80 billion (2014), actual CN¥80 billion (2019) ($17.7 billion planned and $14.6 billion actual in 2025 dollars). Start: planned Dec 2014, actual Dec 26, 2014. Finish: planned Sep 30, 2019, actual Sep 25, 2019.
Cost overrun: 0% ($3.65 million over in 2025 dollars), in money of the day. Delay: none.
Beijing Daxing International Airport, south of the capital on the Beijing-Hebei border, was approved by the National Development and Reform Commission in December 2014 and opened on 25 September 2019. Its starfish-shaped terminal, designed by Zaha Hadid Architects with ADP Ingénierie and executed by the Beijing Institute of Architectural Design, covers about 700,000 m². The first phase has four runways and is planned for 72 million passengers a year by 2025.
Daxing is a schedule story: about 57 months from groundbreaking on 26 December 2014 to opening on 25 September 2019, five days before the planned 30 September date recorded by Chinese Wikipedia. The terminal concrete frame was done by March 2017 and construction was declared complete on 30 June 2019, leaving nearly three months for operational trials before the switchover. The approved feasibility study put total investment at CNY 79.98 billion, and the commonly reported outturn is about CNY 80 billion, which would mean the project held its budget. Cost reporting is not clean, though. English Wikipedia also cites an earlier estimate of at least CNY 70 billion that included the Beijing section of an intercity railway, and a separate report of CNY 120 billion for the airport itself within CNY 450 billion including surrounding infrastructure. No audited final account was found, so the on-budget result rests on reported, not audited, figures. The client throughout was a single body, the Beijing New Airport Construction Headquarters, and the master plan was prepared by NACO.
Daxing was the first airport in China built with two control towers and four runways.
Approvals: planned not published; actual Dec 22, 2012 – Dec 22, 2014. Terminal structure: planned Dec 2014 – ?; actual Dec 26, 2014 – Mar 2017. Roof, fit-out, airfield and systems: planned not published; actual Mar 2017 – Jun 30, 2019. Operational readiness trials: planned not published; actual Jun 30, 2019 – Sep 25, 2019. Opening: planned Sep 30, 2019 – Sep 30, 2019; actual Sep 25, 2019 – Sep 26, 2019.
From the history of managing work: How Big Things Get Done (2023)
Schönefeld, near Berlin, Germany · Infrastructure (airport) · Over budget and late · Confidence: disputed
Berlin's BER airport opened nine years late, in October 2020, after its cost rose from about €2 billion to roughly €6.5 to 7.3 billion.
Cost: planned €2 billion (2006), actual €6.9 billion (2020) ($4.01 billion planned and $9.79 billion actual in 2025 dollars). Start: planned Sep 5, 2006, actual Sep 5, 2006. Finish: planned Oct 2011, actual Oct 31, 2020.
Cost overrun: +245% ($6.96 billion over in 2025 dollars), in money of the day. Delay: 9 years (177% of the planned duration).
Official rebaseline: 2009 budget; opening moved to June 2012: €2.83 billion (2009), so the outturn is +144% against it; a revised finish of Jun 2012, 8 years late against it.
BER was built at Schönefeld to replace Berlin's Tegel and Schönefeld airports with a single hub owned by Berlin, Brandenburg and the federal government. Construction began in 2006 for an October 2011 opening. Weeks before the rescheduled June 2012 opening the fire protection system failed inspection, and the terminal stood unused for years while technical systems were reworked. The airport opened on 31 October 2020, during the COVID-19 pandemic, with Tegel closing days later.
The core failure was technical systems design and integration. The fire alarm and smoke-extraction system was not built to the construction permit and failed the mandatory acceptance test; its design required smoke to be pulled downward against its natural rise, and inspectors found wiring, programming and implementation faults. Alfredo di Mauro, who designed it, was dismissed in May 2014 and was reported not to be a qualified engineer. The planning team also broke down: the general planner pg bbi became insolvent and the architects Gerkan, Marg and Partners were dismissed. Inspectors reported poor workmanship, including about 60 km of cooling pipes allegedly installed without insulation, and corruption cases added to delays. Wikipedia also cites a 2015 assessment that the financial plan was flawed because it assumed BER would become a major international hub.
The airport opened on 31 October 2020, during the pandemic, eight and a half years after a fully marketed June 2012 opening was called off.
Construction of terminal and airfield: planned 2006 – Oct 2011; actual 2006 – May 2012. Opening cancelled; fire-protection failure: planned ? – Jun 2, 2012; actual May 2012 – May 2014. Remediation and rework: planned not published; actual 2014 – 2019. Acceptance, licensing and trial operations: planned not published; actual 2019 – Oct 2020. Opening and transfer from Tegel: planned Oct 2011 – Oct 2011; actual Oct 31, 2020 – Nov 8, 2020.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
New York City, United States · Infrastructure (bridge) · Over budget and late · Confidence: disputed
John Roebling expected five years and about $10.8 million; the Brooklyn Bridge took 13 years and about $15.5 million.
Cost: planned $10.8 million (1867), actual $15.5 million (1883) ($249 million planned and $536 million actual in 2025 dollars). Start: planned 1870, actual Jan 2, 1870. Finish: planned 1875, actual May 24, 1883.
Cost overrun: +44% ($162 million over in 2025 dollars), in money of the day. Delay: 8 years (158% of the planned duration).
The Brooklyn Bridge, designed by John A. Roebling and completed by his son Washington Roebling and Emily Warren Roebling, was the first steel-wire suspension bridge across the East River and, at opening, the longest suspension span in the world. Work started in January 1870 with pneumatic caissons sunk into the riverbed. Towers, cables and the deck followed, and the bridge opened on 24 May 1883. An estimated 27 men died during construction.
Leadership was lost before work started: John Roebling died in July 1869 from an injury sustained while surveying, and Washington Roebling was paralyzed by caisson disease during the foundation work, directing the job from his room with Emily Roebling carrying much of the chief engineer's daily work for about 11 years. The caissons were a technical frontier; physician Andrew Smith treated 110 cases of decompression sickness in the first half of 1872. Scope also grew. According to an 1883 account in The Illustrated Carpenter and Builder, the approaches were changed from light iron trusses to massive masonry and the tower foundations were altered, which swelled the cost. Procurement fraud added work: contractor J. Lloyd Haigh supplied substandard wire, and only five of 80 tested wire rings met standards. Governance changed too, when the private company was converted into a public work in 1874, with Brooklyn paying two-thirds. The structure itself proved sound and is still in use.
Contractor J. Lloyd Haigh was estimated to have made about $300,000 by substituting inferior wire in the cables.
Design and approvals: planned not published; actual 1867 – Jul 1869. Caisson foundations: planned 1870 – ?; actual Mar 19, 1870 – Jul 1872. Masonry towers: planned not published; actual 1871 – Jul 1876. Cable spinning: planned not published; actual Aug 15, 1876 – Oct 5, 1878. Deck, approaches and opening: planned ? – 1875; actual Oct 1878 – May 24, 1883.
From the history of managing work: Karol Adamiecki draws the harmonogram (1896)
Fresno (Central Valley), United States · Infrastructure (high-speed rail) · Over budget and late · Confidence: disputed
California voters were told in 2008 that high-speed rail from San Francisco to Anaheim would cost $33.6 billion by 2020; the 2026 plan says about $126 billion and 2040.
Cost: planned $33.6 billion (2008), actual $126 billion (2026) (forecast) ($50.2 billion planned and $126 billion actual in 2025 dollars). Start: planned not published, actual Jan 6, 2015. Finish: planned 2020, actual 2040 (forecast).
Cost overrun: +275% ($92.4 billion over in 2025 dollars), in money of the day. Delay: 20 years.
The California High-Speed Rail Authority is building an electrified high-speed line meant to link San Francisco and Los Angeles in 2 hours 40 minutes, as Proposition 1A required. Voters approved $9 billion in bonds in November 2008. Construction began in Fresno in January 2015 on the Central Valley segment. No track had been laid for passenger service by 2026; the 2026 Business Plan targets first service between Merced and Bakersfield in 2033 and Phase 1 in 2040.
The 2008 estimate was produced before engineering and alignment work, in constant 2008 dollars, while the $9 billion state bond was fixed, so inflation alone widened the gap; it also assumed $12-16 billion in federal funds and $6.7-7.5 billion in private investment that did not materialize at that scale (Eno Center). Converting to year-of-expenditure dollars raised the figure to $42.6 billion in 2009, and fuller design raised it to $65-75 billion in 2011. Funding came in pieces, and construction began in the Central Valley in 2015 without full funding for a usable segment; by 2018 the Authority was publishing cost ranges ($63.3-98.1 billion) rather than a single figure. In 2025 the federal government withdrew about $4 billion in grants, cutting available funding to $39 billion (LAO). The state Inspector General's July 2026 review found that recent cost reductions in the Merced-Bakersfield estimate came from planning to build less, not from efficiency, and that omitted financing and contingency would add billions.
The Authority's 2026 plan says Phase I would cost about $231 billion without the scope optimizations it proposes.
Prop 1A and 2008 business plan: planned not published; actual Nov 2008 – Nov 2008. Re-estimates and environmental clearance: planned not published; actual Dec 2009 – 2014. Central Valley civil construction: planned not published; actual Jan 6, 2015 – ?. Track, systems and Merced-Bakersfield service (forecast): planned ? – 2020; actual ? – 2033. Full Phase 1 San Francisco-Los Angeles/Anaheim (forecast): planned ? – 2020; actual ? – 2040.
From the history of managing work: Reference class forecasting (2002–2006), Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Boston, United States · Infrastructure (highway tunnel) · Over budget and late · Confidence: medium
Boston's Big Dig was planned at $2.8 billion for 1998 and finished in December 2007 at $14.6 billion, before interest.
Cost: planned $2.8 billion (1982), actual $14.6 billion (2007) ($9.34 billion planned and $22.7 billion actual in 2025 dollars). Start: planned not published, actual 1991. Finish: planned 1998, actual Dec 2007.
Cost overrun: +421% ($18.3 billion over in 2025 dollars), in money of the day. Delay: 10 years.
The Central Artery/Tunnel Project replaced Boston's elevated Interstate 93 with tunnels under downtown, extended I-90 to Logan Airport through the Ted Williams Tunnel, and added the Leonard P. Zakim Bunker Hill Memorial Bridge. Managed by a Bechtel and Parsons Brinckerhoff joint venture under the Massachusetts Highway Department and later the Turnpike Authority, it was the most expensive US highway project. Construction ran from 1991 to December 2007, nine years later than first planned.
The first estimate was made before the scope was set. The 1982 figure of $2.8 billion covered a project that was then enlarged, with the harbor tunnel, interchanges and environmental mitigation for the city, and it was later reported in year-of-expenditure dollars as inflation accumulated over a 25-year program. GAO's July 1996 testimony found that the official $7.8 billion estimate left out more than $1 billion of costs counted in previous estimates and did not account for inflation; GAO's own figure was $10.4 billion. Its 1997 report traced a further rise to $10.8 billion mainly to construction bids above projections and design-phase estimates over budget, and found contract cost growth at 17.4 percent against a 10.7 percent containment goal. Underground tunneling under a working city, which FHWA called inherently risky, added further growth. After the 2006 ceiling collapse and leaks, the Bechtel/Parsons Brinckerhoff consortium agreed to pay $407 million in restitution. The project did deliver its traffic goals and reclaimed surface land for the Rose Kennedy Greenway.
Including borrowing costs, the project's cost was reported at about $21.93 billion, with bonds being repaid for decades after opening.
Planning and environmental review: planned not published; actual 1982 – 1991. Ted Williams Tunnel (I-90 harbor crossing): planned not published; actual 1991 – Dec 1995. Cost growth and federal scrutiny: planned not published; actual 1996 – 1997. Central Artery tunnels (I-93) and Zakim Bridge: planned ? – 1998; actual 1991 – Mar 2005. Surface restoration and close-out: planned ? – 1998; actual 2005 – Dec 2007.
From the history of managing work: Reference class forecasting (2002–2006), Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Folkestone (Cheriton) / Coquelles, United Kingdom · Infrastructure (tunnel) · Over budget and late · Confidence: medium
The Channel Tunnel opened a year late with an 80 percent real-terms construction overrun, £4.65 billion against £2.6 billion at 1985 prices.
Cost: planned £2.6 billion (1985), actual £4.65 billion (1985) ($10.1 billion planned and $18.1 billion actual in 2025 dollars). Start: planned Dec 1, 1987, actual Dec 1, 1987. Finish: planned May 1993, actual May 6, 1994.
Cost overrun: +79% ($7.96 billion over in 2025 dollars), in constant prices. Delay: 12 months (18% of the planned duration).
The 50 km rail tunnel under the Strait of Dover was the third serious attempt after abandoned starts in the 1880s and 1974-75. Built without public money as a build-own-operate-transfer concession, it was financed by Eurotunnel and designed and built by the Anglo-French TransManche Link consortium. Boring started in 1988, the service tunnel broke through on 1 December 1990, and Queen Elizabeth II and President Mitterrand opened the tunnel on 6 May 1994. Ten workers died during construction.
The overrun came from three named sources. First, the scope grew after contract award: the intergovernmental commission and safety authority that controlled engineering and safety decisions imposed enhanced safety, security and environmental requirements, which Getlink's own history cites as part of the cause. Second, governance was split: Eurotunnel financed the work, TML designed and built it under a construction contract, and the two governments kept control of final engineering and safety decisions, so changes passed through three parties with different incentives. Third, financing: as costs and delay grew, interest accumulated and financing costs ended about 140 percent above forecast. The engineering itself was a success. The UK and French tunnelling teams met with an error of about 30 cm horizontally and 8 cm vertically. Traffic forecasts were the larger failure: the 1985 forecast of passenger numbers was not reached, and Eurotunnel went through repeated restructurings, entering bankruptcy protection in 2006.
When the service tunnels met on 1 December 1990, the two bores were misaligned by only about 30 cm horizontally and 8 cm vertically.
Concession, treaty and legislation: planned not published; actual Jan 1986 – Jul 1987. Mobilization and site works: planned Dec 1, 1987 – ?; actual Dec 1, 1987 – Jun 1988. Tunnel boring: planned 1988 – ?; actual Jun 1988 – 1991. Fit-out, systems and rolling stock: planned ? – May 1993; actual 1991 – May 1994. Opening and phased start of services: planned May 1993 – May 1993; actual May 6, 1994 – Nov 1994.
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979)
Brasília, Brazil · Infrastructure (new capital city) · Incomplete data · Confidence: disputed
Brazil built a new capital in 41 months and inaugurated it on 21 April 1960, the date set by law, at an estimated cost of about US$1.5 billion.
Cost: planned cost not public, actual $1.5 billion (1960) (n/a planned and $16.3 billion actual in 2025 dollars). Start: planned 1956, actual 1956. Finish: planned Apr 21, 1960, actual Apr 21, 1960.
Cost overrun: cost not public. Delay: none.
Brasília was built on Brazil's central plateau to move the capital inland from Rio de Janeiro, a transfer required by the 1946 constitution. President Juscelino Kubitschek made it the centerpiece of his 'Fifty Years in Five' program. Lúcio Costa's airplane-shaped pilot plan was chosen in 1957 and Oscar Niemeyer designed the main buildings. A 1957 law fixed the inauguration for 21 April 1960, and the city was inaugurated that day after 41 months of construction.
The schedule was met because the date was fixed by law and treated as immovable. Law 3,273 of October 1957 set 21 April 1960 for the transfer, Kubitschek's term ran to 1961, and NOVACAP drove construction with tens of thousands of workers brought in from elsewhere. Cost control was the casualty. No published construction budget exists, records were poor and bureaucratic steps were cut for speed, according to JSTOR Daily. The most cited figure is economist Eugênio Gudin's estimate of about US$1.5 billion, roughly 10 to 12 percent of Brazil's GDP; Poder360 quotes Marcelo Paiva Abreu calling it the only known total, while Ipea's Rodrigo Orair says it is probably an underestimate because it omits roads such as the Belém-Brasília highway and later works. A 1996 recalculation by Ib Teixeira was far higher. The government financed the work partly by printing money and issuing debt, which JSTOR Daily links to a legacy of inflation. The city opened incomplete, and embassies moved only in the early 1970s.
The village where the first construction workers lived, Vila Amaury, now lies under the artificial Lake Paranoá.
Launch under 'Fifty Years in Five': planned 1956 – ?; actual Jan 1956 – 1956. Pilot plan: planned not published; actual 1957 – 1957. Date fixed by law: planned not published; actual Oct 1, 1957 – Oct 1, 1957. Main construction: planned 1956 – Apr 21, 1960; actual 1956 – Apr 21, 1960. Inauguration and continued build-out: planned Apr 21, 1960 – ?; actual Apr 21, 1960 – 1975.
From the history of managing work: The Critical Path Method (1956–1959), Kahneman and Tversky name the planning fallacy (1977–1979)
London, United Kingdom · Infrastructure (metro / regional rail) · Over budget and late · Confidence: high
Crossrail's central section opened three and a half years late, in May 2022, with costs at £18.9 billion against £15.9 billion first announced in 2007.
Cost: planned £15.9 billion (2007), actual £18.9 billion (2022) ($49.4 billion planned and $25.7 billion actual in 2025 dollars). Start: planned 2009, actual May 15, 2009. Finish: planned May 2018, actual May 21, 2023.
Cost overrun: +19% ($4.08 billion over in 2025 dollars), in money of the day. Delay: 5 years (57% of the planned duration).
Official rebaseline: 2010 Crossrail funding settlement: £14.8 billion (2010), so the outturn is +28% against it; a revised finish of Dec 2019, 3 years late against it.
Crossrail built twin-bore tunnels under central London linking the Great Western line at Paddington with lines to Shenfield and Abbey Wood, with new central stations. Sponsored by the Department for Transport and Transport for London and delivered by Crossrail Ltd, construction started in May 2009. Branded the Elizabeth line, the central section opened on 24 May 2022, and the full timetable began on 21 May 2023.
Civil engineering went well: tunnelling finished on schedule in 2015. The failure came in systems integration and governance. The NAO's May 2019 report found that the programme was dominated by a fixed December 2018 opening date, set in 2010, which forced many activities to run in parallel. Design and contract changes raised contract costs by about GBP 2.5 billion between 2013 and 2018, the contractual model removed downward pressure on costs, and there was no detailed, achievable delivery plan until late 2018. The NAO also described an optimistic 'can do' culture that became unrealistic. Crossrail itself cited the difficulty of writing and testing software to integrate trains with three different signalling systems, plus late installation of tunnel equipment. Sponsors learned of the delay only weeks before the planned opening, announcing it in August 2018. Funding was raised to GBP 17.6 billion in December 2018 and later to GBP 18.8 billion. COVID-19 added several months in 2020.
The 2007 cost estimates were set at a level the government judged had a 95 percent probability of not being exceeded.
Funding and powers: planned not published; actual 2007 – Jul 2008. Enabling works and re-baseline: planned 2009 – ?; actual May 15, 2009 – Dec 2010. Tunnelling: planned not published; actual 2012 – Jun 4, 2015. Stations, track and systems fit-out: planned ? – Dec 2018; actual 2015 – 2021. Trial running and trial operations: planned not published; actual May 2021 – May 2022. Phased opening: planned Dec 2018 – Dec 2019; actual May 24, 2022 – May 21, 2023.
From the history of managing work: Reference class forecasting (2002–2006), Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Dubai, United Arab Emirates · Infrastructure (metro) · Over budget · Confidence: medium
Dubai's Red Line opened on its fixed date of 9 September 2009, but the two-line metro's budget rose from AED 15.5 billion to about AED 28 billion.
Cost: planned AED 15.5 billion (2005), actual AED 28 billion (2010) ($6.96 billion planned and $11.3 billion actual in 2025 dollars). Start: planned 2006, actual Mar 21, 2006. Finish: planned Sep 9, 2009, actual Sep 9, 2009.
Cost overrun: +81% ($5.03 billion over in 2025 dollars), in money of the day. Delay: none.
The Dubai Metro Red Line is a driverless rail line running mostly on viaduct from Rashidiya through the city center and along Sheikh Zayed Road to Jebel Ali. The Roads and Transport Authority (RTA) awarded a design-and-build contract to the Dubai Rail Link consortium in May 2005, and work started on 21 March 2006. The line opened on schedule on 9 September 2009 with 10 stations; the rest opened through March 2011, and the Green Line followed in September 2011.
The opening date was met. The RTA fixed the launch for 9/9/09 and opened the line at 9:09:09 pm that day, after telling the press in February 2009 that the financial crisis would not delay it. The method was to open a working core and finish the rest later: only 10 of 29 stations opened at launch, and the remainder followed over the next 18 months rather than by the February 2010 date the RTA had forecast. Cost grew sharply. RTA chairman Mattar Al Tayer said in 2009 that the two lines would cost about AED 28 billion against an original budget of AED 15.5 billion; The National put the rise at 75 percent over original estimates. The RTA said this was not an overrun but the result of scope changes it chose to make: a 4.5 km extension to Emirates Road with extra stations and a new depot, an added Mall of the Emirates station, more than 3 km of extra Green Line track at Al Jadaf, and substantially redesigned stations and footbridges.
The Red Line opened at 9 minutes and 9 seconds past 9 pm on 9 September 2009, or 9:09:09 on 09/09/09.
Design-and-build contract award: planned not published; actual 2005 – May 2005. Red Line construction: planned 2006 – Sep 2009; actual Mar 21, 2006 – Sep 2009. Red Line opening (first 10 stations): planned Sep 9, 2009 – Sep 9, 2009; actual Sep 9, 2009 – Sep 9, 2009. Remaining Red Line stations: planned Sep 2009 – Feb 2010; actual Apr 30, 2010 – Mar 11, 2011. Green Line (same budget envelope): planned ? – 2010; actual ? – Sep 9, 2011.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Nationwide (completed at Glenwood Canyon, Colorado), United States · Infrastructure (highway network) · Over budget and late · Confidence: medium
The Interstate System's cost estimate rose from $37.6 billion in 1958 to $128.9 billion in 1991, and it took 36 years instead of about 12.
Cost: planned $37.6 billion (1958), actual $129 billion (1991) ($420 billion planned and $305 billion actual in 2025 dollars). Start: planned 1956, actual Jun 29, 1956. Finish: planned 1969, actual Oct 14, 1992.
Cost overrun: +243% ($216 billion over in 2025 dollars), in money of the day. Delay: 23 years (179% of the planned duration).
The Interstate System is a network of about 41,000 miles of limited-access highways authorized by the Federal-Aid Highway Act of 1956, signed by President Eisenhower on 29 June 1956. The federal government paid most of the cost from a dedicated Highway Trust Fund. Congress required periodic cost estimates, the first in 1958 and the last in 1991. The original system was proclaimed complete when I-70 through Glenwood Canyon, Colorado, opened on 14 October 1992.
The network was delivered, but at more than three times the first mandated estimate and almost three times the planned duration. FHWA's table of the 15 legislatively required estimates shows the total rising from $37.622 billion in 1958 to $128.9 billion in January 1991, with the federal share going from $33.952 billion to $114.3 billion. FHWA attributes the changes to system adjustments, new eligibility rules and legislation, unit price changes, social, economic and environmental requirements, right-of-way and design changes, extra interchanges and construction overruns. Much of the growth is inflation, since the estimates are in current dollars. The schedule slipped as urban routes met resistance and the 1969 National Environmental Policy Act added review; Glenwood Canyon alone was planned from 1960 and finished in 1992 at $490 million for 12.5 miles. Wikipedia reports that the initial estimate was $25 billion over 12 years. The approach that worked was a dedicated trust fund and uniform national standards, which kept money flowing for decades.
In 1986, I-80 became the world's first continuous freeway to span from the Atlantic to the Pacific.
Federal-Aid Highway Act and early contracts: planned 1956 – ?; actual Jun 29, 1956 – 1958. Main network construction: planned 1958 – 1969; actual 1958 – 1974. Environmental review era and redefinition: planned not published; actual 1969 – 1986. Last links: I-70 Glenwood Canyon: planned not published; actual 1980 – Oct 14, 1992.
From the history of managing work: The Critical Path Method (1956–1959), PERT puts uncertainty into the schedule (1957–1958), Kahneman and Tversky name the planning fallacy (1977–1979)
Rome, New York (Albany to Buffalo), United States · Infrastructure (canal) · Over budget · Confidence: medium
New York built the 363-mile Erie Canal in eight years for $7.14 million, about 43 percent above the 1817 estimate of $5 million.
Cost: planned $5 million (1817), actual $7.14 million (1825) ($101 million planned and $203 million actual in 2025 dollars). Start: planned Jul 4, 1817, actual Jul 4, 1817. Finish: planned not published, actual Oct 26, 1825.
Cost overrun: +43% ($61 million over in 2025 dollars), in money of the day. Delay: not known.
The Erie Canal linked the Hudson River at Albany with Lake Erie at Buffalo, opening a water route from New York City to the Great Lakes. Championed by De Witt Clinton and paid for by New York State, it was authorized in April 1817, begun at Rome on 4 July 1817 and opened in sections from 1819. The full canal opened on 26 October 1825 at a recorded cost of $7,143,789, and tolls soon repaid the state's construction debt.
The canal overran its 1817 estimate by roughly 43 percent in nominal terms, but delivered on its economic case. The commissioners' revised March 1817 estimate was $5 million, close to the $5 million figures of 1810-1811 surveys; the State Engineer's 1878 report records a final cost of $7,143,789. Opening in sections was the key decision. Building the middle section first, Rome to Utica in 1819 and on to Salina in 1820, produced early toll revenue and public support before the eastern section to Albany (1823) and the western section to Buffalo were finished. Opponents had called it 'Clinton's Folly', and in 1819 critics estimated that at that pace it would take 30 years; instead it was finished in eight. Toll revenue covered the construction debt quickly, and through 1883 tolls brought in $121 million against $78 million of total costs, according to a 1961 New York legislative report.
At the 1825 'Wedding of the Waters', Clinton poured Lake Erie water into New York Harbor.
Authorization: planned not published; actual Mar 1817 – Apr 15, 1817. Middle section, Rome to Utica and Salina: planned Jul 4, 1817 – ?; actual Jul 4, 1817 – 1820. Eastern section to Albany: planned not published; actual 1820 – Sep 10, 1823. Western section to Buffalo: planned not published; actual 1823 – Oct 26, 1825.
From the history of managing work: Karol Adamiecki draws the harmonogram (1896)
Promontory Summit, Utah, United States · Infrastructure (railway) · Incomplete data · Confidence: medium
The first US transcontinental railroad was joined at Promontory Summit on 10 May 1869, seven years ahead of the 1 July 1876 deadline set by Congress.
Cost: planned cost not public, actual $99.5 million (1869) (n/a planned and $2.41 billion actual in 2025 dollars). Start: planned not published, actual Jan 8, 1863. Finish: planned Jul 1, 1876, actual May 10, 1869.
Cost overrun: cost not public. Delay: 7 years early.
The first transcontinental railroad linked the existing eastern network at Council Bluffs and Omaha with Sacramento, California. Authorized by the Pacific Railroad Act of 1862, it was built by the Central Pacific from the west starting in January 1863 and the Union Pacific from the east, with federal bonds and land grants paid per mile of track. The lines met at Promontory Summit, Utah, on 10 May 1869. The NPS puts construction costs at about $63.5 million for the Union Pacific and $36 million for the Central Pacific.
Measured against the schedule Congress set, the railroad was early. Section 17 of the 1862 Act required a continuous line by 1 July 1876; it was joined in May 1869. The financing design drove the pace: federal bonds were issued per mile completed, at $16,000 on level ground, double in foothills and treble in the mountains, which rewarded speed and length of track more than quality or route efficiency. The Central Pacific struggled to find labor until it hired Chinese workers, who became the core of its Sierra Nevada workforce. The Union Pacific started slowly and did not begin real construction until July 1865. The incentive also invited abuse. Union Pacific insiders ran construction through Crédit Mobilier, which billed far more than the work cost; Wikipedia cites roughly $94 million billed against about $50 million in actual building cost. No official construction budget was set at authorization, so a planned-versus-actual cost comparison is not possible.
Mormon workers signed a lone tree beside the track 1,000 miles from Omaha, now known as the Thousand Mile Tree.
Pacific Railroad Act and financing: planned not published; actual Jul 1, 1862 – Jan 8, 1863. Central Pacific builds east from Sacramento: planned ? – Jul 1, 1876; actual Jan 8, 1863 – May 10, 1869. Union Pacific builds west from Omaha: planned ? – Jul 1, 1876; actual Jul 1865 – May 10, 1869. Junction at Promontory Summit: planned ? – Jul 1, 1876; actual May 10, 1869 – May 10, 1869.
From the history of managing work: Karol Adamiecki draws the harmonogram (1896), The Principles of Scientific Management (1911)
San Francisco, United States · Infrastructure (bridge) · Incomplete data · Confidence: disputed
The Golden Gate Bridge was built for about $35 million, the size of its bond issue, and finished ahead of schedule and $1.3 million under budget.
Cost: planned $35 million (1930), actual $33.7 million (1937) ($675 million planned and $754 million actual in 2025 dollars). Start: planned Jan 5, 1933, actual Jan 5, 1933. Finish: planned not published, actual May 27, 1937.
Cost overrun: -4% ($29.9 million under in 2025 dollars), in money of the day. Delay: not known.
Chief engineer Joseph Strauss's Golden Gate Bridge spans the Golden Gate strait between San Francisco and Marin County. Financed by a $35 million bond issue of the Golden Gate Bridge and Highway District, backed by Bank of America, it was built between January 1933 and April 1937 and opened on 27 May 1937. Its 1,280 m main span was the world's longest at the time. Eleven men died during construction; a safety net saved 19 others.
The project is a rare case of a megaproject landing on budget during the Depression. The district fixed the financing first: voters approved bonds in November 1930, and contracts for the main work, totaling $23.8 million, were awarded in November 1932 before construction began. Strauss replaced his early hybrid cantilever-suspension design, estimated at $17 million, with a pure suspension bridge; the FHWA notes the $35 million bond was well below early construction estimates of up to $100 million. The hardest technical task was the San Francisco pier, built in open water within a fender wall against strong tidal currents. Safety practice was unusually strict for the period: hard hats, glare-free goggles, special diets against dizziness and a net under the deck. The one catastrophic failure came on 17 February 1937, when a scaffold fell through the net and ten men died. The bonds were retired in 1971 with $35 million principal and nearly $39 million interest paid from tolls.
The 19 workers whose falls were caught by the safety net called themselves the Half Way to Hell Club.
Bond approval and contract award: planned not published; actual Nov 1930 – Nov 1932. Marin tower: planned not published; actual Nov 7, 1933 – Jun 28, 1934. San Francisco pier, fender and tower: planned not published; actual 1933 – Jun 28, 1935. Cable spinning: planned not published; actual Aug 2, 1935 – May 1936. Suspended structure and roadway: planned not published; actual Jul 1936 – Apr 19, 1937. Opening: planned not published; actual May 27, 1937 – May 27, 1937.
From the history of managing work: Scheduling the Hoover Dam (1931–1936), Henry Gantt charts work against time (c. 1910–1915)
Erstfeld / Bodio, Switzerland · Infrastructure (tunnel) · Over budget · Confidence: medium
The 57 km Gotthard Base Tunnel opened about a year early in 2016, but at CHF 9.56 billion it cost 51 percent more than the 1998 estimate in constant prices.
Cost: planned CHF 6.32 billion (1998), actual CHF 9.56 billion (1998) ($8.61 billion planned and $13 billion actual in 2025 dollars). Start: planned 1999, actual Nov 4, 1999. Finish: planned 2017, actual Dec 11, 2016.
Cost overrun: +51% ($4.41 billion over in 2025 dollars), in constant prices. Delay: 7 months early.
The Gotthard Base Tunnel is the world's longest railway tunnel, two single-track bores of 57 km under the Swiss Alps between Erstfeld and Bodio. It is the centerpiece of the New Railway Link through the Alps (NRLA), approved by referendum in 1992. Excavation started in 1999 and ended in 2011, with up to 2,450 m of rock overhead. AlpTransit Gotthard handed the tunnel over on 31 May 2016 and timetabled service began on 11 December 2016.
Schedule went better than cost. Swiss federal figures put the 1998 projected cost of the tunnel at CHF 6.323 billion and the December 2015 projection at CHF 9.560 billion, both on a 1998 price base without inflation, a real increase of about 51 percent. Swissinfo reported in 2005 that extra costs came from geology and from rail equipment that proved more complex than foreseen. The parliamentary NEAT supervisory delegation tracked forecasts against a fixed 1998 price base, which kept real increases visible and separate from inflation. Excavation finished in March 2011 and fit-out progressed well enough that in August 2011 the Federal Office of Transport moved timetabled operation forward to the end of 2016, a year earlier than planned. Nine workers died during construction. The line was disrupted again in August 2023 when a freight derailment closed one bore until September 2024.
Excavation removed about 28.2 million tonnes of rock, described as equal to five Great Pyramids of Giza.
Referendum and exploration: planned not published; actual Sep 27, 1992 – 1996. Funding vote and preparatory works: planned not published; actual 1996 – Nov 4, 1999. Excavation: planned 1999 – ?; actual Nov 4, 1999 – Mar 23, 2011. Rail systems installation: planned not published; actual Sep 2, 2011 – May 2016. Handover, trial operation and service start: planned ? – 2017; actual May 31, 2016 – Dec 11, 2016.
From the history of managing work: The Critical Path Method (1956–1959), Reference class forecasting (2002–2006)
London, United Kingdom · Infrastructure (airport terminal) · On time and on budget · Confidence: medium
BAA delivered the £4.3 billion Heathrow Terminal 5 on time and within budget, then lost more than 500 flights in its first ten days.
Cost: planned £4.3 billion (2002), actual £4.3 billion (2008) ($11.6 billion planned and $11.9 billion actual in 2025 dollars). Start: planned Sep 2002, actual Sep 2002. Finish: planned Mar 2008, actual Mar 27, 2008.
Cost overrun: 0% ($0 over in 2025 dollars), in money of the day. Delay: none.
Heathrow Terminal 5 is a terminal complex for British Airways at London's busiest airport, designed by the Richard Rogers Partnership with Arup and Mott MacDonald. After a public inquiry from 1995 to 1999 and approval in November 2001, construction began in September 2002 under BAA's T5 Agreement, a relational contract in which the client held the major risks. The terminal opened to passengers on 27 March 2008. Its main building is the largest free-standing building in the UK.
Construction was a recognized success; the handover was not. BAA's pre-project study of UK projects over £1 billion and international airports found none delivered on time, on budget and to standard, and predicted T5 would be about £1 billion over budget, a year late and cause at least two deaths if run conventionally. BAA responded with the T5 Agreement: a cost-plus contract with a fixed fee and incentive fund, in which BAA retained the major risks, removed contractors' risk contingencies and pooled contingency centrally. GIHub and Designing Buildings Wiki both report that the project was finished on time and within its £4.3 billion budget. Operational readiness was the weak point. On opening day, 27 March 2008, British Airways cancelled 34 flights and suspended check-in; over ten days about 42,000 bags were delayed and more than 500 flights cancelled, blamed on IT problems and car parking. The case shows that integration and trial operations belong inside the project plan, not after it.
Archaeologists working on the T5 site recovered more than 80,000 artefacts.
Public planning inquiry: planned not published; actual May 16, 1995 – Mar 17, 1999. Government decision: planned not published; actual Mar 17, 1999 – Nov 20, 2001. Construction under the T5 Agreement: planned Sep 2002 – Mar 2008; actual Sep 2002 – Mar 14, 2008. Opening and operational start: planned Mar 2008 – Mar 2008; actual Mar 14, 2008 – Mar 27, 2008.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
London to Birmingham, United Kingdom · Infrastructure (high-speed rail) · Over budget and late · Confidence: disputed
HS2's first phase was costed at about £16 billion and due in 2026; the May 2026 reset puts it at £87.7 to 102.7 billion and opening by 2036 to 2039.
Cost: planned £16.6 billion (2010), actual £95.2 billion (2025) (forecast) ($37.9 billion planned and $126 billion actual in 2025 dollars). Start: planned 2017, actual Sep 4, 2020. Finish: planned Dec 2026, actual Oct 2039 (forecast).
Cost overrun: +474% ($104 billion over in 2025 dollars), in money of the day. Delay: 13 years (136% of the planned duration).
High Speed 2 is a new high-speed railway from London to the West Midlands, originally the first phase of a Y-shaped network to Manchester and Leeds. Promoted by the Department for Transport and built by HS2 Ltd, Phase 1 received Royal Assent in 2017 and main construction began in 2020. The northern legs were cancelled in 2023. After reviews by James Stewart and Stephen Lovegrove, the government in May 2026 set a cost range of £87.7 to 102.7 billion and opening windows from 2036.
Costs were set before design maturity and then repeatedly re-based. The 2010 Phase 1 estimate of GBP 15.8-17.4 billion was followed by a June 2013 network package of GBP 42.6 billion and the 2015 package of GBP 55.7 billion, and by 2016 the NAO found the Phase 1 forecast already exceeded available funding with less contingency than planned. The 2019 Oakervee review put the full programme at up to GBP 87.7 billion. Specification was a named cause: the May 2026 Lovegrove review cited 'gold plating', including the pursuit of the highest possible speeds, and the government cut the design speed from 360 km/h to 320 km/h. Political change disrupted scope, with Phase 2 north of Birmingham cancelled in October 2023 after sunk design work. Delivery control was weak: in March 2025 chief executive Mark Wild wrote that HS2 had 'failed in its mission to control costs and deliver to schedule' and estimated the programme was about one-third complete against a planned three-quarters. About GBP 44 billion had been spent by 2026.
An internal review found that cancelling HS2 outright would cost at least as much as completing it.
Proposal, route and funding envelopes: planned not published; actual 2010 – Jun 2016. Hybrid bill and Royal Assent: planned ? – Dec 2016; actual Nov 2013 – Feb 2017. Enabling works and Oakervee review: planned 2017 – ?; actual 2017 – Apr 15, 2020. Main civil works (tunnels, viaducts): planned not published; actual Sep 4, 2020 – ?. Reset: Stewart and Lovegrove reviews: planned not published; actual Mar 2025 – May 19, 2026. Rail systems, testing and opening (forecast): planned ? – Dec 2026; actual ? – Oct 2039.
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979)
Chek Lap Kok, Lantau Island, Hong Kong · Infrastructure (airport) · Late · Confidence: medium
Hong Kong's Airport Core Programme finished at HK$155.3 billion, HK$8.4 billion below its 1992-93 budget, though the airport itself opened about a year after its mid-1997 target.
Cost: planned HK$164 billion (1992), actual HK$155 billion (1998) ($48.1 billion planned and $39.3 billion actual in 2025 dollars). Start: planned 1992, actual 1992. Finish: planned Jun 1997, actual Jul 6, 1998.
Cost overrun: -5% ($2.13 billion under in 2025 dollars), in money of the day. Delay: 13 months (21% of the planned duration).
Official rebaseline: January 1998 official opening date: a revised finish of Jul 6, 1998, met.
The Airport Core Programme comprised 10 projects built to replace Kai Tak with a new airport on a reclaimed platform at Chek Lap Kok, off Lantau Island: the airport, the Airport Railway, the Lantau Link bridges, the Western Harbour Crossing, expressways, and reclamation and new-town works. Construction began in 1992 under the Airport Authority, MTR Corporation and government departments, coordinated by the New Airport Projects Co-ordination Office. Kai Tak closed and the new airport began commercial operations on 6 July 1998.
On cost, the programme is a rare success. The government's 1997 Yearbook records that the ACP budget was cut three times, by a total of HK$8.4 billion, from HK$163.7 billion projected in 1992-93 to HK$155.3 billion in money-of-the-day prices, and that eight of the 10 projects were substantially complete ahead of schedule and below budget during 1997. A 2006 government reply to the Legislative Council reported final spending below estimate for all three delivery bodies: the Airport Authority spent HK$49.3 billion against HK$49.8 billion, and MTR's Airport Railway HK$33.5 billion against HK$34.0 billion. Savings came partly from scope cuts, such as building the Airport Railway with two tracks rather than four. Schedule was weaker: the airport was targeted for mid-1997, ahead of the handover, then for April 1998, and opened on 6 July 1998. Opening day was marred by failures of the flight information display system and the cargo handling system, which disrupted freight for months and forced the reuse of Kai Tak's cargo terminal.
Guinness World Records lists the Chek Lap Kok airport as the most expensive airport project ever.
Strategy and Sino-British agreement: planned not published; actual Oct 11, 1989 – Sep 3, 1991. Airport site formation and construction: planned 1992 – Jun 1997; actual 1992 – Jul 2, 1998. Airport Railway, Lantau Link and other core projects: planned 1992 – Jun 1997; actual 1992 – Jun 1998. Relocation from Kai Tak: planned not published; actual May 6, 1998 – Aug 5, 1998. Opening and operational recovery: planned Apr 1998 – ?; actual Jul 6, 1998 – Dec 1998.
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Hong Kong / Zhuhai / Macau, China · Infrastructure (bridge-tunnel) · Over budget and late · Confidence: medium
The 55 km Hong Kong–Zhuhai–Macau crossing opened in October 2018, about two years late, and its Main Bridge budget rose from CNY 38 billion to CNY 48.07 billion.
Cost: planned CN¥38 billion (2009), actual CN¥48.1 billion (2017) ($8.35 billion planned and $9.34 billion actual in 2025 dollars). Start: planned Dec 2009, actual Dec 15, 2009. Finish: planned 2016, actual Oct 24, 2018.
Cost overrun: +27% ($1.96 billion over in 2025 dollars), in money of the day. Delay: 2 years (35% of the planned duration).
Official rebaseline: revised budget approved by the Ministry of Transport: CN¥48.1 billion, so the outturn is 0% against it.
The Hong Kong–Zhuhai–Macau Bridge is a 55 km system of bridges, four artificial islands and a 6.7 km immersed tunnel across the Pearl River estuary, the world's longest open-sea fixed link. Construction began on 15 December 2009 with opening planned for late 2016. The Main Bridge was completed in July 2017 and the crossing opened on 24 October 2018. Total spending including link roads and border facilities is reported at about CNY 127 billion.
The project ran about two years past its late-2016 target and over budget. Caixin reported in December 2017 that the Ministry of Transport approved a revised Main Bridge budget of CNY 48.07 billion against an original plan of CNY 38 billion, after contractors sought more money for complicated construction conditions, rising labor and material costs and changes to construction plans. The governments had to find an extra CNY 4.6 billion, of which Hong Kong paid CNY 2 billion and Macau CNY 590 million. In Hong Kong, a judicial review of the environmental assessment held up the start of the Hong Kong section until December 2011, and parts of the reclaimed border-crossing island moved by up to six or seven metres, according to the Highways Department. Building the deep immersed-tube tunnel in open sea was technically novel and difficult. Safety was a serious problem: Wikipedia, citing official and press figures, reports 19 worker deaths, nine on the mainland side and more than ten on the Hong Kong side.
Hong Kong and Macau drive on the left, but traffic on the bridge itself drives on the right.
Main Bridge construction start and island reclamation: planned Dec 2009 – ?; actual Dec 15, 2009 – Dec 2011. Bridges, artificial islands and immersed tunnel: planned not published; actual Dec 2011 – May 2, 2017. Main Bridge completion: planned ? – 2016; actual May 2, 2017 – Jul 6, 2017. Link roads, ports and systems: planned ? – 2016; actual Jul 6, 2017 – Feb 6, 2018. Opening: planned 2016 – 2016; actual Oct 23, 2018 – Oct 24, 2018.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Millau, France · Infrastructure (bridge) · Over budget · Confidence: medium
Eiffage built the 343 m tall Millau Viaduct in about three years and opened it on 16 December 2004, 25 days ahead of plan.
Cost: planned €320 million (2001), actual €394 million (2004) ($521 million planned and $835 million actual in 2025 dollars). Start: planned Oct 2001, actual Oct 16, 2001. Finish: planned Jan 10, 2005, actual Dec 16, 2004.
Cost overrun: +23% ($157 million over in 2025 dollars), in money of the day. Delay: none.
The Millau Viaduct carries the A75 autoroute 270 m above the Tarn valley in southern France. Designed by engineer Michel Virlogeux with architect Norman Foster, it was financed and built by Eiffage under a 75-year toll concession, with no public subsidy. Work began in October 2001 and the bridge opened on 16 December 2004, ahead of its planned January 2005 date. At 343 m it was the world's tallest bridge structure for about two decades.
The viaduct is a schedule success built on a strong contractual incentive. Under the concession, Eiffage carried construction and traffic risk, financed the work privately and, according to Batiweb's 2002 report, had 39 months to finish under penalties of up to EUR 25,000 per day of delay. That structure rewarded speed. Eiffage launched the steel deck incrementally, pushing it out in 600 mm cycles, so the deck could be assembled on land while the piers rose with sliding formwork at about 4 m every three days. The halves met in May 2004 and traffic began on 16 December 2004, about three weeks before the 10 January 2005 target. Cost reporting is less tidy: the EUR 320 million figure reported in 2002 covers the viaduct alone, while French Wikipedia says the whole works were valued at close to EUR 400 million and English Wikipedia gives EUR 394 million plus EUR 20 million for the toll plaza. The apparent gap is mostly a difference in scope, not a documented overrun.
Pier P2 is about 13 m taller than the Eiffel Tower.
Concession award and approval: planned not published; actual May 20, 1998 – Oct 8, 2001. Foundations: planned Oct 2001 – ?; actual Oct 16, 2001 – Mar 2002. Piers: planned not published; actual Mar 2002 – Nov 2003. Deck launching: planned not published; actual Feb 25, 2003 – May 28, 2004. Masts, stays, load tests: planned ? – Jan 10, 2005; actual Jun 2004 – Dec 14, 2004. Opening to traffic: planned Jan 10, 2005 – Jan 10, 2005; actual Dec 16, 2004 – Dec 16, 2004.
From the history of managing work: The Critical Path Method (1956–1959), How Big Things Get Done (2023)
Copenhagen / Malmö, Denmark · Infrastructure (bridge-tunnel) · Over budget · Confidence: disputed
The 16 km Øresund road-rail link opened on its planned date, 1 July 2000, for DKK 14.8 billion in 1990 prices.
Cost: planned DKK 13.9 billion (1990), actual DKK 14.8 billion (1990) ($5.55 billion planned and $5.89 billion actual in 2025 dollars). Start: planned 1995, actual 1995. Finish: planned Jul 1, 2000, actual Jul 1, 2000.
Cost overrun: +6% ($348 million over in 2025 dollars), in constant prices. Delay: none.
Official rebaseline: May 1997 revised budget, 1990 prices: DKK 14.8 billion (1990), so the outturn is +0% against it.
The Øresund Fixed Link joins Copenhagen and Malmö with a 4 km immersed tunnel, the artificial island of Peberholm and a 7.8 km cable-stayed bridge carrying a motorway above a double-track railway. It was agreed by Denmark and Sweden in 1991, built from 1995 by the Sundlink consortium and opened on 1 July 2000. The coast-to-coast link is financed by state-guaranteed loans repaid from tolls and rail fees, with full repayment now expected around 2050.
On delivery the project performed well: the Swedish government reported in 1999/2000 that construction would close within the consortium budget of DKK 14,750 million in July 1990 prices, and the operator now states final construction cost at DKK 14.8 billion in 1990 prices. The opening date of 1 July 2000 was held despite setbacks, including a skewed tunnel element and 16 unexploded Second World War bombs found on the seabed. The weaker part is the front end. Aalborg University researcher Mette Skamris and Rigsrevisionen (the Danish auditor-general) criticised how the 1991 financial case was built: the discount rate was cut from the 7 percent government guideline to 5 percent and traffic forecasts were raised until a projected DKK 400 million deficit became a small surplus before the construction act passed. Flyvbjerg, Bruzelius and Rothengatter argue that overruns should be measured from the 1991 decision, while link management argued that politically approved environmental design changes should be excluded. Repayment has also stretched, from 30 years in 2000 to about 50 years today.
Construction crews found 16 unexploded Second World War bombs on the Øresund seabed.
Treaty and parliamentary approval: planned not published; actual Mar 23, 1991 – Aug 14, 1991. Consortium set-up, design and contracts: planned not published; actual Jan 1992 – Nov 1995. Construction of tunnel, Peberholm and bridge: planned 1995 – ?; actual 1995 – Aug 14, 1999. Systems installation and testing: planned ? – Jul 1, 2000; actual Aug 14, 1999 – Jun 30, 2000. Opening: planned Jul 1, 2000 – Jul 1, 2000; actual Jul 1, 2000 – Jul 1, 2000.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Culebra Cut (Gaillard Cut), near Panama City, Panama · Infrastructure (canal) · Over budget · Confidence: disputed
The US opened the Panama Canal in August 1914, ahead of its revised 1915 target, at about $375 million against a 1906 construction estimate of $139.7 million.
Cost: planned $140 million (1906), actual $375 million (1914) ($5.01 billion planned and $12.1 billion actual in 2025 dollars). Start: planned May 4, 1904, actual May 4, 1904. Finish: planned 1918, actual Aug 15, 1914.
Cost overrun: +168% ($7.56 billion over in 2025 dollars), in money of the day. Delay: 4 years early.
Official rebaseline: 1908-09 revised estimate and fixed completion date (Taft, 1909): $298 million (1909), so the outturn is +26% against it; a revised finish of Jan 1, 1915, met.
After the French company of Ferdinand de Lesseps abandoned a sea-level canal in 1889, the United States took over the works in May 1904. Congress chose a lock-and-lake design in June 1906. Under George Goethals the Army-led Isthmian Canal Commission dug the Culebra Cut, dammed the Chagres River to form Gatun Lake and built three flights of locks. The canal opened on 15 August 1914. About 5,600 workers died during the American era, according to hospital records.
The schedule was met; the budget was not, though the comparison is not like-for-like. In 1909 President Taft wrote that the original 1906 estimate of $139,705,200 excluded interest, sanitation, Zone government and the $50 million paid to Panama and the French company. On the same basis the estimate had already risen to $297,766,000, or $375 million including everything. Taft listed the causes: excavation yardage underestimated by 50 percent because of inadequate surveys, a wider canal and larger locks requested by the Navy, dams moved to Miraflores and Pedro Miguel, harder rock that raised average excavation cost about 20 percent, and higher wages and housing costs. Landslides in the Culebra Cut kept adding spoil. What went right was the decision to drop the sea-level plan for locks and a lake, the sanitation campaign led by William Gorgas, and Goethals's centralized control. The Panama Canal Authority says the final cost came in about $23 million below the 1907 estimate.
By 1 July 1914 the Americans had excavated 238,845,587 cubic yards of material, according to the Panama Canal Authority.
French attempt (Compagnie universelle, de Lesseps): planned not published; actual Jan 1, 1881 – May 15, 1889. US takeover, sanitation and preparation (Wallace, Stevens): planned May 4, 1904 – ?; actual May 4, 1904 – Apr 1, 1907. Lock canal design adopted: planned not published; actual Jan 1, 1906 – Jun 29, 1906. Main construction under Goethals (Culebra Cut, Gatun Dam, locks): planned Apr 1, 1907 – 1918; actual Apr 1, 1907 – Oct 10, 1913. Opening to traffic: planned ? – 1918; actual Aug 15, 1914 – Aug 15, 1914.
From the history of managing work: The Principles of Scientific Management (1911), Henry Gantt charts work against time (c. 1910–1915)
New York City, United States · Infrastructure (metro) · Over budget and late · Confidence: disputed
The first 2.9 km of the Second Avenue Subway opened three years late on 1 January 2017, at $4.45 billion for three new stations.
Cost: planned $4.05 billion (2007), actual $4.45 billion (2017) ($6.29 billion planned and $5.84 billion actual in 2025 dollars). Start: planned Apr 2007, actual Apr 12, 2007. Finish: planned Dec 2013, actual Jan 1, 2017.
Cost overrun: +10% ($526 million over in 2025 dollars), in money of the day. Delay: 3 years (46% of the planned duration).
Official rebaseline: MTA Phase 1 budget raised after the FFGA: $4.45 billion (2008), so the outturn is 0% against it.
Phase 1 of the Second Avenue Subway extended the Q train from 63rd Street up Second Avenue to 96th Street on Manhattan's Upper East Side, with new stations at 72nd, 86th and 96th Streets. Work on the line had stopped in the 1970s. The Metropolitan Transportation Authority broke ground in April 2007, bored the tunnels in 2010-2011, mined two station caverns, and opened the line on 1 January 2017, three years after the end-2013 date promised in 2007.
Phase 1 stayed within its $4.45 billion budget as reported by the MTA, but the budget was protected partly by cutting scope: after cost increases from materials and diesel prices in 2008, features were scaled back. The 72nd Street station was cut from three tracks and two island platforms to two tracks and one platform, its width reduced from 100 to 70 feet, and platform screen doors were dropped in 2012. Schedule slipped repeatedly, from 2012 (2005 statement) to end-2013 (2007 promise) and then 2014, 2015 and 2016. Named causes: utility relocation took 14 months instead of eight; launch-box excavation delayed the start of tunnel boring to May 2010; controlled blasting was delayed when two buildings were evacuated in June 2009; and in 2016 testing of systems ran at about 14 tests a week against roughly 40 needed, with elevators, escalators and fire alarms unfinished. Federal monitors projected in June 2015 that the line would not open until February 2018. The December 2016 opening came after Governor Andrew Cuomo intervened and the MTA added $66 million to accelerate work. A construction manager summed up the result as four and a half billion dollars for three stations.
The April 2007 groundbreaking was held in a tunnel segment at 99th Street that had been built in the 1970s for an earlier, abandoned attempt at the line.
Funding and groundbreaking: planned not published; actual Nov 2005 – Nov 2007. Utility relocation and launch box: planned Apr 2007 – Dec 2007; actual Apr 23, 2007 – May 2010. Tunnel boring: planned not published; actual May 14, 2010 – Sep 22, 2011. Station caverns (72nd and 86th Streets): planned not published; actual Oct 2010 – Nov 2013. Fit-out, systems and testing: planned ? – Dec 2013; actual Jun 2013 – Dec 31, 2016. Opening: planned Dec 2013 – Dec 2013; actual Jan 1, 2017 – Jan 1, 2017.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Tsugaru Strait (Aomori / Hokkaido), Japan · Infrastructure (tunnel) · Over budget · Confidence: disputed
The Seikan Tunnel was planned as an eight-year, ¥201.4 billion job; it took 24 years from the start of works and cost about ¥690 billion.
Cost: planned ¥201 billion (1971), actual ¥690 billion (1988) ($4.6 billion planned and $14.7 billion actual in 2025 dollars). Start: planned not published, actual Sep 28, 1971. Finish: planned not published, actual Mar 13, 1988.
Cost overrun: +243% ($10.4 billion over in 2025 dollars), in money of the day. Delay: not known.
Official rebaseline: later 'planning stage' estimate (year not stated): ¥538 billion, so the outturn is +28% against it.
The Seikan Tunnel carries rail traffic under the Tsugaru Strait between Honshu and Hokkaido, reaching about 240 m below sea level. Surveys began in 1946 and main works in September 1971. Crews fought repeated floods in volcanic, faulted rock before the pilot tunnel broke through in 1983 and the main bore in 1985. It opened on 13 March 1988 and has carried Hokkaido Shinkansen trains since 2016. It was the world's longest undersea tunnel by total length.
Geology was the main cause of cost growth and delay. Japanese Wikipedia records that planners originally expected to finish close to schedule using tunnel boring machines, but the TBM was abandoned after less than 2 km in the fractured, water-bearing rock beneath the strait. Crews switched to dynamite and mechanical picking, driving a pilot tunnel, then a service tunnel, then the main bore under the sea. Major inflows hit in 1969, 1974 and, worst of all, at the Yoshioka shaft on 6 May 1976, at a peak of 85 tonnes of water per minute. Thirty-four workers died over the project. The tunnel body cost ¥745.5 billion against ¥538.4 billion at the planning stage, about 38 percent more in nominal yen, and the whole Kaikyo line cost about ¥900 billion against ¥689 billion. Toyo Keizai reports that the original plan was to finish in eight years for ¥201.4 billion; the works took 24 years to opening and cost ¥690 billion.1 trillion was almost twelve times the original budget, which implies a much smaller earliest baseline that is not documented in sources opened. Meanwhile air travel overtook the ferries the tunnel was meant to replace; about 90 percent of passenger travel between the islands is still by plane.
Its two undersea stations were the first railway stations in the world built under the sea.
Geological surveys: planned not published; actual 1946 – 1964. Investigative and pilot excavation: planned not published; actual 1964 – Sep 28, 1971. Main construction and pilot tunnel: planned not published; actual Sep 28, 1971 – Jan 27, 1983. Main bore completion: planned not published; actual Jan 27, 1983 – Mar 10, 1985. Track, systems and opening: planned not published; actual Mar 10, 1985 – Mar 13, 1988.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Stuttgart, Germany · Infrastructure (railway station and rail node) · Over budget and late · Confidence: medium
Stuttgart 21 was agreed in 2009 at about €3.1 billion for 2019; Deutsche Bahn now forecasts €14.5 billion and December 2031.
Cost: planned €3.08 billion (2009), actual €14.5 billion (2026) (forecast) ($6.43 billion planned and $16.8 billion actual in 2025 dollars). Start: planned Feb 2, 2010, actual Feb 2, 2010. Finish: planned 2019, actual Dec 2031 (forecast).
Cost overrun: +371% ($13.2 billion over in 2025 dollars), in money of the day. Delay: 13 years (132% of the planned duration).
Official rebaseline: March 2013 official cost estimate: €6.5 billion (2013), so the outturn is +123% against it.
Stuttgart 21 replaces Stuttgart's terminus station with an underground through station and new approach tunnels, integrated with the Wendlingen-Ulm high-speed line and a new airport station. Deutsche Bahn, the federal government, Baden-Württemberg and the city signed the financing agreement in April 2009, and construction began in February 2010 amid large protests. After nine postponements the main station is forecast to open in December 2031, with related works phased to 2033.
The 2009 financing agreement fixed costs at EUR 2.81 billion at 2004 prices, EUR 3.076 billion with general price increases, plus a EUR 1.45 billion risk budget, a cap of EUR 4.526 billion. Internal DB calculations reported in late 2009 already pointed higher, and the cost frame rose through EUR 6.5 billion (2013), 8.2 billion (2018) and about 11 billion (2023). In June 2026 DB added about EUR 3 billion more, to EUR 14.5 billion. Named causes in that re-plan: digitalisation of the rail node was much harder than planned, planning processes were not mature enough, cables were laid incorrectly (DB cites about 100 km to be redone), a technical building built in 2013 no longer fits current needs, and the emergency power concept had to be redesigned because new requirements were addressed too late. Funding disputes followed: Baden-Württemberg refused to contribute beyond its share, and in 2025 the courts upheld the ruling that DB must bear overruns above the cap alone. Political conflict, including the 2010 protests and a 2011 referendum, shaped the early years.
Some S-Bahn trains upgraded for the digital node are due to be retired shortly after the new station opens, which a state politician called a misinvestment.
Concept and planning: planned not published; actual Apr 1994 – Apr 2, 2009. Start of works and protests: planned Feb 2, 2010 – ?; actual Feb 2, 2010 – Nov 2011. Tunnels and underground through station: planned 2010 – 2019; actual 2010 – ?. Digital rail node (ETCS) and systems: planned not published; actual ? – Dec 2031. Opening of new main station (forecast): planned 2019 – 2019; actual Dec 2031 – Dec 2031.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Ismailia, Egypt · Infrastructure (canal) · Over budget and late · Confidence: medium
The Suez Canal took ten years instead of the six announced and cost 433 million francs against a 200-million-franc estimate.
Cost: planned FRF 200 million (1858), actual FRF 433 million (1869) ($1.44 billion planned and $2.02 billion actual in 2025 dollars). Start: planned Apr 25, 1859, actual Apr 25, 1859. Finish: planned 1865, actual Nov 17, 1869.
Cost overrun: +116% ($1.09 billion over in 2025 dollars), in money of the day. Delay: 4 years (71% of the planned duration).
Ferdinand de Lesseps won a concession from Egypt's ruler Sa'id Pasha and floated the Suez Canal Company in 1858 with 200 million francs of capital, the cost estimated by an international commission. Digging began at Port Said in April 1859, first by tens of thousands of conscripted Egyptian laborers. After forced labor was ended in 1864, steam dredgers took over. The sea-level canal opened on 17 November 1869, linking the Mediterranean and the Red Sea.
The estimate rested on a construction method that was later withdrawn. Early excavation relied on the corvee, a system of unpaid forced labor supplied by the Egyptian government. Pressure from Britain and the Ottoman court led to Napoleon III's arbitration in July 1864, which ended forced labor, returned land grants to Egypt and required Egypt to pay the company 84 million francs. The company then had to mechanize, buying and designing large steam dredgers and excavators, which added cost and time. Financing was also fragile: shares sold well in France but poorly abroad, and Sa'id Pasha had to take up 177,000 of the 400,000 shares to complete the capital. A further 100 million francs of bonds had to be sold in 1867, partly through lotteries approved by the French government. The final bill of 432,807,882 francs (Fondation Napoleon) was more than double the estimate, and Egypt bore about half of the total. The works themselves succeeded: the flat desert route and sea-level design avoided locks.
The Mediterranean and Red Sea waters first met in the Bitter Lakes on 15 August 1869, three months before the official inauguration.
Concession and company formation: planned not published; actual 1854 – Dec 15, 1858. Excavation with corvee labor: planned Apr 25, 1859 – ?; actual Apr 25, 1859 – Jul 6, 1864. Arbitration and switch to mechanical dredging: planned not published; actual Jul 6, 1864 – Dec 31, 1864. Mechanized excavation to the Red Sea: planned ? – 1865; actual 1865 – Aug 15, 1869. Inauguration: planned ? – 1865; actual Nov 17, 1869 – Nov 17, 1869.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
Sydney, Australia · Infrastructure (bridge) · Over budget · Confidence: disputed
The Sydney Harbour Bridge cost about AU£6.25 million against a 1922 statutory estimate of £5.75 million, and was paid off only in 1988.
Cost: planned £A5.75 million (1922), actual £A6.25 million (1932) ($490 million planned and $413 million actual in 2025 dollars). Start: planned 1923, actual Jul 28, 1923. Finish: planned not published, actual Mar 19, 1932.
Cost overrun: +9% ($33 million over in 2025 dollars), in money of the day. Delay: not known.
The steel arch bridge across Sydney Harbour, championed by chief engineer John Bradfield of the New South Wales Department of Public Works, was built by Dorman Long & Co of Middlesbrough under a 1924 contract. Work began with clearance at Milsons Point in July 1923. The two half-arches met on 19 August 1930 and the bridge opened on 19 March 1932. It carries rail, road and footways. Sixteen workers died during construction.
The core structure was delivered close to the design concept, and the cantilevered arch erection, with each half held back by cables anchored in rock tunnels until the two met, worked as planned. Costs grew mainly outside the steel contract. The Sydney Harbour Bridge Act 1922 set the estimated cost, including land resumptions, at £5,750,000, not to be exceeded by more than 10 percent. The final figure of about £6.25 million (Wikipedia) breaches that limit, and other accounts that include wider works and charges put the total at £10,057,170, about double the original quote. Delays came from industrial action and coordination: a 1932 Dorman Long statement attributed higher costs to the 1926 strike and other troubles, and the 1930 Public Works Department annual report noted that work was held up until anchorage cables were attached and because final approved plans were not complete. Clearing the north shore approach required demolishing about 800 homes, a social cost not captured in the budget.
The loan for the bridge was not fully paid off until 1988.
Legislation and tendering: planned not published; actual 1922 – Mar 24, 1924. Site clearance and approaches: planned 1923 – ?; actual Jul 28, 1923 – Sep 1928. Steel arch erection: planned not published; actual Oct 26, 1928 – Aug 19, 1930. Deck, pylons and finishing: planned not published; actual Aug 1930 – Jan 21, 1932. Load testing and opening: planned not published; actual Jan 19, 1932 – Mar 19, 1932.
From the history of managing work: Henry Gantt charts work against time (c. 1910–1915), The Principles of Scientific Management (1911)
Dubai, United Arab Emirates · Buildings (skyscraper) · Over budget and late · Confidence: disputed
The world's tallest building opened 13 months after its end-2008 target, at about US$1.5 billion against early reports of US$900 million.
Cost: planned $900 million (2007), actual $1.5 billion (2010) ($1.4 billion planned and $2.21 billion actual in 2025 dollars). Start: planned Jan 2004, actual Jan 6, 2004. Finish: planned Dec 2008, actual Jan 4, 2010.
Cost overrun: +67% ($886 million over in 2025 dollars), in money of the day. Delay: 13 months (21% of the planned duration).
Emaar Properties began work on Burj Dubai in January 2004 as the centerpiece of its Downtown development. A joint venture of Samsung C&T, BESIX and Arabtec built the concrete core, with Turner as project manager, and the tower topped out at 829.8 m on 17 January 2009. Cladding problems and interior redesigns pushed completion from the end of 2008 to January 2010. The tower was renamed Burj Khalifa at its opening on 4 January 2010, after Abu Dhabi's ruler.
The structure itself went largely to plan: the buttressed core allowed fast, repetitive floor cycles, and the main contractor reached the top in just over four years. Delays came from the envelope and the interiors. In early 2007 Gulf News reported the tower two months behind after Swiss curtain-wall contractor Schmidlin went bankrupt, forcing Emaar to bring in a replacement (Far East Aluminium). In March 2008 Emaar admitted a four-month slip, and chairman Mohamed Alabbar said several interior designs had been rejected because quality came first. A labor strike at subcontractor Arabtec was also reported. The 2008 financial crisis hit Dubai while fit-out was under way, and Abu Dhabi's support during the crisis led to the renaming. Emaar never published a formal baseline budget; press reports moved from US$900 million (2007) and US$1 billion (2008) to Alabbar's estimate of about US$1.5 billion at completion.
Emaar kept the final height secret during construction, saying it would not be announced until completion, and topped out at 829.8 m in January 2009.
Excavation and foundations: planned Jan 2004 – ?; actual Jan 6, 2004 – Sep 20, 2004. Superstructure (Samsung C&T, BESIX, Arabtec JV): planned Sep 21, 2004 – ?; actual Sep 21, 2004 – Jan 17, 2009. Facade cladding: planned not published; actual ? – Oct 1, 2009. Interior fit-out and commissioning: planned ? – Dec 2008; actual ? – Jan 4, 2010. Remaining facilities: planned not published; actual Jan 4, 2010 – Jan 23, 2011.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
Paris, France · Buildings (tower) · Over budget · Confidence: medium
Built in about 26 months for the 1889 World's Fair, the Eiffel Tower cost 7.8 million francs against an estimate of 6.5 million.
Cost: planned FRF 6.5 million (1887), actual FRF 7.8 million (1889) ($45 million planned and $53.9 million actual in 2025 dollars). Start: planned Jan 1887, actual Jan 28, 1887. Finish: planned May 6, 1889, actual Mar 31, 1889.
Cost overrun: +20% ($8.99 million over in 2025 dollars), in money of the day. Delay: 1 month early.
Gustave Eiffel's company won the contest for a centerpiece of the 1889 Exposition Universelle, marking the centenary of the French Revolution. The contract of 8 January 1887 gave Eiffel 1.5 million francs toward an estimated 6.5 million and the right to run the tower for 20 years. Foundations started on 28 January 1887, ironwork on 1 July 1887, and the 300-meter structure was finished on 31 March 1889, before the fair opened. Final cost was 7,799,401.31 francs.
The schedule held because the work was industrialized off site. Eiffel's drawing office produced more than 5,000 drawings, and 18,038 wrought-iron parts were prefabricated at his Levallois-Perret works to tight tolerances, then joined on site with 2.5 million rivets by about 300 on-site workers. Erection used creeper cranes climbing the legs, and the most difficult step, joining the four legs at the first level, was finished by the end of March 1888. Only one worker died. The financial structure shifted risk to the builder: the state and city contributed 1.5 million francs, less than a quarter of the 6.5 million estimate, and Eiffel raised the rest through a company in which he put up half the capital, in exchange for 20 years of operating income. Cost still rose to about 7.8 million francs, roughly 20% above the 1887 estimate. A public protest by artists, published in Le Temps on 14 February 1887, did not stop the work.
The lifts were not finished when the tower opened, so nearly 30,000 visitors climbed the stairs before the lifts entered service on 26 May 1889.
Design and contract: planned not published; actual May 1884 – Jan 8, 1887. Foundations: planned Jan 1887 – ?; actual Jan 28, 1887 – Jun 30, 1887. Ironwork to first level: planned not published; actual Jul 1, 1887 – Mar 1888. Second level: planned not published; actual Apr 1888 – Aug 21, 1888. Upper tower to summit: planned ? – May 6, 1889; actual Aug 21, 1888 – Mar 31, 1889. Opening to the public: planned May 6, 1889 – May 6, 1889; actual May 15, 1889 – May 15, 1889.
From the history of managing work: Karol Adamiecki draws the harmonogram (1896)
Hamburg, Germany · Buildings (concert hall) · Over budget and late · Confidence: medium
Hamburg taxpayers were told the Elbphilharmonie would cost them EUR 77 million; the bill reached EUR 789 million and the hall opened seven years late.
Cost: planned €77 million (2005), actual €789 million (2016) ($158 million planned and $1.17 billion actual in 2025 dollars). Start: planned 2007, actual Apr 2, 2007. Finish: planned 2010, actual Oct 31, 2016.
Cost overrun: +925% ($1.06 billion over in 2025 dollars), in money of the day. Delay: 6 years (211% of the planned duration).
Official rebaseline: 2006 revised budget (city share): €114 million (2006), so the outturn is +590% against it.
Hamburg commissioned Herzog & de Meuron to place a glass concert hall on top of the Kaispeicher A warehouse in HafenCity. A 2005 feasibility study estimated EUR 186 million in total, of which EUR 77 million from the city, with opening in 2010. Hochtief started in April 2007. Contract amendments, design disputes and a halt from 2011 over the roof drove costs up until a 2013 settlement shifted risk to the contractor. The building was handed over on 31 October 2016 and opened on 11 January 2017.
The Hamburg parliament's inquiry committee, which reported in 2014, blamed an unfinished plan, weak political oversight and supervision, and disorder on the construction site, and named the city's project company ReGe and its head Hartmut Wegener among those responsible (SRF; Karlsruhe city council summary). The city tendered and signed the construction contract with Hochtief before the design was complete, so every later design detail became a claim. Costs rose to EUR 241.3 million in total in 2006 and to an estimated EUR 450 million after the contract was amended in November 2008. Unclear division of responsibility between the city, the architects and the contractor led to prolonged disputes, and in November 2011 work stopped over the safety of the 2,000-tonne roof. The turnaround came in a settlement at the end of 2012 and in 2013: the city paid about EUR 200 million extra and Hochtief took on all construction risk, after which the project finished on the new date of October 2016.
The Grand Hall is lined with about 10,000 individually microshaped drywall plates that disperse sound waves, according to Wikipedia.
Concept and feasibility: planned not published; actual 2003 – 2005. Contract and early construction: planned 2007 – ?; actual Apr 2, 2007 – Nov 2008. Main construction: planned 2007 – 2010; actual Apr 2, 2007 – Nov 2011. Construction halt over roof safety: planned not published; actual Nov 2011 – 2013. Restart under new agreement and completion: planned ? – Oct 2016; actual 2013 – Oct 31, 2016. Opening: planned 2010 – 2010; actual Jan 11, 2017 – Jan 11, 2017.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
London, United Kingdom · Buildings (clock tower) · Over budget and late · Confidence: medium
The repair of Big Ben's tower, priced at £29 million in 2016, ended up costing about £80 million and finished more than a year after its 2021 target.
Cost: planned £29 million (2016), actual £79.7 million (2020) ($52.7 million planned and $127 million actual in 2025 dollars). Start: planned 2017, actual Aug 21, 2017. Finish: planned 2021, actual Nov 13, 2022.
Cost overrun: +175% ($80.9 million over in 2025 dollars), in money of the day. Delay: 16 months (34% of the planned duration).
Official rebaseline: February 2020 budget approved by the Commons and Lords Commissions: £79.7 million (2020), so the outturn is 0% against it.
The Elizabeth Tower conservation project was the largest repair of the Palace of Westminster clock tower in its history. Commissioned by the House of Commons and House of Lords Commissions, designed by Purcell and built by Sir Robert McAlpine, it stripped and repaired the cast-iron roof, stonework, clock dials and the Great Clock mechanism. The bells fell silent on 21 August 2017 for a planned four-year programme and returned to regular service on 13 November 2022.
The cost grew in two big steps because the condition of the tower was not known when the first price was set. The spring 2016 estimate of GBP 29m rose to GBP 61.1m in 2017 after 16 months of detailed design and survey work. Construction Management reported that further stone surveys, slower than expected re-glazing and repainting, unrecorded utilities under Speaker's Green and New Palace Yard, and a risk allowance raised from GBP 5.8m to GBP 17.2m drove that rise, and parliamentary officials admitted estimating failures, saying early estimates had been set low to avoid market-driven escalation. In February 2020 the budget rose again to GBP 79.7m: Second World War bomb damage was worse than thought, asbestos turned up in unexpected places, lead paint was widespread, and about 700 stone repairs were needed, nearly double the estimate. A failed in-house attempt to restore the clock mechanism added almost GBP 2m. COVID-19 then stopped work in March 2020 and pushed completion into 2022.
All 1,296 pieces of glass in the clock dials were replaced, and the dial frames were repainted in their original Prussian blue.
Survey, design and procurement: planned 2016 – 2017; actual 2016 – Aug 2017. Scaffolding and conservation works: planned Aug 2017 – 2021; actual Aug 21, 2017 – Dec 2021. COVID-19 site stoppage and recovery: planned not published; actual Mar 25, 2020 – 2021. Scaffold and gantry removal: planned ? – 2021; actual Dec 2021 – Apr 2022. Clock reinstatement and return to service: planned ? – 2021; actual Apr 2022 – Nov 13, 2022.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006)
New York City, United States · Buildings (skyscraper) · On time and on budget · Confidence: disputed
The Empire State Building rose in 410 days and cost $40.9 million including land and demolition, against a $50 million budget.
Cost: planned $50 million (1929), actual $40.9 million (1931) ($938 million planned and $867 million actual in 2025 dollars). Start: planned Oct 1, 1929, actual Oct 1, 1929. Finish: planned May 1, 1931, actual Apr 11, 1931.
Cost overrun: -18% ($192 million under in 2025 dollars), in money of the day. Delay: none.
Developers John J. Raskob and Pierre du Pont, with Al Smith as the public face, set a fixed programme: occupancy by 1 May 1931 and a budget of $50 million including land. Demolition of the Waldorf-Astoria began in October 1929, steel rose from April 1930, and the frame topped out in September 1930. Contractor Starrett Brothers and Eken finished the structure on 11 April 1931, twelve days early, and the tower opened on schedule. The Depression cut labor and material prices, and the total came to about $40.9 million, below the estimate.
Most things went right, for identifiable reasons. Architects Shreve, Lamb and Harmon worked from a fixed brief and a fixed opening date, and the design was frozen early after fifteen iterations. Starrett Brothers and Eken ran the site like a production line: trades followed each other floor by floor on a tight schedule, and up to 3,500 workers built four and a half stories a week. Demolition, excavation and erection overlapped, an early form of fast-track construction, according to Jacobsson and Wilson (Business Horizons, 2018). The steel topped out twelve days ahead of schedule and the structure was finished in 410 days. Context mattered as much as method: the Depression lowered wages and material costs after the October 1929 crash, which Jacobsson and Wilson cite as a main reason the building cost $24.7 million instead of the estimated $43 million. The downside was commercial: the building opened into a collapsed office market and was largely empty for years.
On 14 August 1930, 3,439 workers were on site in a single day, according to Wikipedia's construction history.
Demolition of the Waldorf-Astoria: planned not published; actual Oct 1, 1929 – Mar 1930. Excavation and foundations: planned not published; actual Jan 22, 1930 – Mar 1930. Steel frame erection: planned ? – Oct 1, 1930; actual Apr 1, 1930 – Sep 19, 1930. Enclosure and fit-out: planned ? – Apr 23, 1931; actual Jun 1930 – Apr 11, 1931. Opening: planned May 1, 1931 – May 1, 1931; actual May 1, 1931 – May 1, 1931.
From the history of managing work: Henry Gantt charts work against time (c. 1910–1915), The Principles of Scientific Management (1911), Scheduling the Hoover Dam (1931–1936)
St. Louis, United States · Buildings (monument) · Over budget and late · Confidence: medium
Expected to finish for St. Louis's 1964 bicentennial, the Gateway Arch topped out in October 1965 and cost about $13 million against an $11.4 million contract.
Cost: planned $11.4 million (1962), actual $13 million (1967) ($122 million planned and $126 million actual in 2025 dollars). Start: planned Jun 1959, actual Jun 23, 1959. Finish: planned 1964, actual Jul 24, 1967.
Cost overrun: +14% ($15 million over in 2025 dollars), in money of the day. Delay: 3 years (61% of the planned duration).
The Gateway Arch, designed by Eero Saarinen after a 1947-48 competition, is the centerpiece of the Jefferson National Expansion Memorial on the St. Louis riverfront, managed by the National Park Service. After site clearance and railroad relocation from 1959, MacDonald Construction signed the arch and visitor center contract in March 1962. The first steel section was set in February 1963, and the two legs were joined on October 28, 1965. The tram to the top opened in July 1967, and the memorial was dedicated in May 1968.
The National Park Service administrative history records a project driven by funding as much as engineering. Congress repeatedly approved less than the Park Service requested, so work proceeded in separately funded phases. When arch bids were opened in January 1962 they ranged from $11.9 million to $12.8 million against an engineers' estimate of $8,067,000, and the contract was signed at $11,442,418 after scope reductions. Construction then met several named delays: a stop order for plan changes after the first foundation pour in 1962, a strike by hoisting and operating engineers in May 1963, problems with post-tensioning bars in the south leg in 1963-64, and a June 1964 stop order over design concerns raised by consultants to the steel subcontractor. Welding heat distorted some stainless steel sections, and workers in the narrow legs competed for space. The administrative history states that arch construction costs ran $4 million above estimate. Completion slipped from the 1964 bicentennial to October 1965. Congress did not appropriate the remaining funds in 1966 and 1967, which delayed the tram and dedication.
On the day the arch was closed, workers sprayed the south leg with water to cool the steel so the final section would fit the gap.
Site clearance and railroad relocation: planned Jun 1959 – ?; actual Jun 23, 1959 – Nov 17, 1961. Arch foundations and visitor center shell: planned Mar 1962 – ?; actual Mar 14, 1962 – Feb 12, 1963. Stainless steel arch erection: planned Feb 1963 – 1964; actual Feb 12, 1963 – Oct 28, 1965. Tram system and visitor center completion: planned ? – Dec 2, 1964; actual Oct 28, 1965 – Jul 24, 1967.
Bilbao, Spain · Buildings (art museum) · Late · Confidence: medium
Frank Gehry's titanium museum opened in October 1997 on time and on its roughly $100 million budget, a rare result for a landmark building.
Cost: planned $100 million (1991), actual $100 million (1997) ($236 million planned and $201 million actual in 2025 dollars). Start: planned 1991, actual 1991. Finish: planned 1997, actual Oct 18, 1997.
Cost overrun: 0% ($0 over in 2025 dollars), in money of the day. Delay: 4 months (5% of the planned duration).
The Guggenheim Museum Bilbao was a partnership between the Basque Government, which paid for the building, and the Solomon R. Guggenheim Foundation, which ran the program. Frank Gehry designed it on a former port site on the Nervion river, using CATIA software from aerospace to model and cost its curved titanium forms. Ground was broken on October 22, 1993, Ferrovial built it, and King Juan Carlos I opened it on October 18, 1997. It is widely cited as delivered on time and on budget.
Most sources agree the building was delivered on time and on budget. The Association for Project Management, drawing on Bent Flyvbjerg's analysis, names specific reasons. The objectives were clear from the start. Three tiers of government backed a single consortium and kept their support steady for the five years of the project. Once the outline was agreed, politicians did not interfere with the design, a model Flyvbjerg calls the organization of the artist. Gehry identified which items on his wish list were essential and protected those. Wikipedia, citing Paul Goldberger and Dassault Systemes, credits Gehry's method of a detailed cost estimate, CATIA visualizations and close work with the building trades, which let complex geometry be priced and fabricated with confidence. The APM also notes that titanium was unusually cheap in the mid-1990s, which helped the cladding fit the budget. Partners included the engineering firm IDOM and the Guggenheim Foundation.
The museum's skin uses about 33,000 titanium plates, rolled in Pittsburgh to a thickness of about 0.4 mm.
Agreement and architect selection: planned not published; actual 1991 – 1991. Design and digital modeling: planned not published; actual 1991 – Oct 1993. Construction: planned ? – 1997; actual Oct 22, 1993 – 1997. Opening: planned ? – 1997; actual Oct 1997 – Oct 18, 1997.
From the history of managing work: How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979)
Singapore, Singapore · Buildings (integrated resort) · Over budget and late · Confidence: medium
Marina Bay Sands was pitched at S$3.85 billion plus land and opened in stages from 2010 at about S$8 billion.
Cost: planned S$5.05 billion (2006), actual S$8 billion (2010) ($5.08 billion planned and $8.67 billion actual in 2025 dollars). Start: planned Dec 2006, actual Feb 2007. Finish: planned Dec 2009, actual Feb 17, 2011.
Cost overrun: +58% ($3.2 billion over in 2025 dollars), in money of the day. Delay: 14 months (39% of the planned duration).
Singapore awarded the Marina Bay integrated resort to Las Vegas Sands on 27 May 2006, at a fixed land price of S$1.2 billion. The company committed S$3.85 billion of investment, excluding land, and planned to open in a single phase in 2009. Ssangyong Engineering and Construction built Moshe Safdie's three 55-story towers joined by a rooftop SkyPark. Rising material costs and labor shortages, then the 2008 financial crisis, forced a phased opening from April 2010 to February 2011, with total cost put at S$8 billion.
The cost growth came mainly from market conditions during a regional construction boom. Wikipedia attributes the delays to escalating material costs and labor shortages from the outset, worsened by the 2008 financial crisis. By January 2008, an SEC filing reported by the Las Vegas Review-Journal said the project could cost as much as US$4.6 billion against an original US$3.6 billion, citing a weaker US dollar and higher building and material costs in Singapore. Engineering novelty added risk: a 340-meter skyway joins the tops of the three towers and overhangs the north tower by 66.5 meters. Las Vegas Sands responded by splitting the single 2009 opening into phases, opening the casino and part of the hotel on 27 April 2010 so revenue could start, followed by the SkyPark in June 2010 and the grand opening on 17 February 2011. Sheldon Adelson put the total at S$8.0 billion, including land, as of July 2009. The government's fixed land price and tender terms limited public exposure to the overrun.
The SkyPark platform overhangs the north hotel tower by 66.5 meters, according to Wikipedia.
Tender award and design: planned May 2006 – Dec 2006; actual May 27, 2006 – Feb 2007. Site preparation and foundations: planned Dec 2006 – ?; actual Feb 2007 – ?. Hotel towers, podium and SkyPark (Ssangyong E&C): planned ? – Dec 2009; actual Feb 2007 – Jun 23, 2010. Phased opening: planned Dec 2009 – Dec 2009; actual Apr 27, 2010 – Feb 17, 2011.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
London (Greenwich Peninsula), United Kingdom · Buildings (exhibition) · On time and on budget · Confidence: high
The Dome opened on time and spent GBP 789 million against a GBP 758 million budget, but visitor income came in at about half the plan and Lottery grants rose from GBP 399 million to GBP 628 million.
Cost: planned £758 million (1997), actual £789 million (2001) ($2.49 billion planned and $2.07 billion actual in 2025 dollars). Start: planned Jun 1997, actual Jun 1997. Finish: planned Dec 31, 2000, actual Dec 31, 2000.
Cost overrun: +4% ($81.2 million over in 2025 dollars), in money of the day. Delay: none.
The Millennium Experience was a one-year national exhibition in a purpose-built tent structure on the Greenwich Peninsula, run by the New Millennium Experience Company and funded largely by the Millennium Commission from National Lottery money. The government confirmed it in June 1997, the Dome was finished in June 1999, and it opened on December 31, 1999. It closed as planned on December 31, 2000. The National Audit Office found spending close to budget but income far below it, because the 12 million visitor target was missed.
Delivery to the fixed date went well: the National Audit Office (NAO) called opening on time a major achievement, and spending of GBP 789 million was close to the May 1997 budget of GBP 758 million. The failure was on the revenue side. The business plan assumed 12 million paying visitors; by September 2000 the company was planning on 4.5 million paying visitors, and about 6.5 million people visited in the year. Income forecast at GBP 359 million in May 1997 was expected to be about GBP 189 million by December 2001. The NAO's 2000 report found the visitor and income targets highly ambitious and inherently risky, said the complex organizational arrangements set up at the start made the project harder to manage, and said financial management was not sufficiently robust. The Millennium Commission's grant rose from GBP 399 million to GBP 628 million, an increase of 57 percent, including four extra grants totaling GBP 179 million during 2000. The NAO also found the company's contract records inadequate.
Despite poor press coverage, 87 percent of visitors surveyed by August 2000 said they were satisfied with their visit.
Dome construction: planned Jun 1997 – ?; actual Jun 1997 – Jun 22, 1999. Exhibition installation and opening: planned ? – Dec 31, 1999; actual Jun 22, 1999 – Dec 31, 1999. Millennium Experience operation: planned Jan 1, 2000 – Dec 31, 2000; actual Jan 1, 2000 – Dec 31, 2000. Wind-up of the operating company: planned Jan 2001 – ?; actual Jan 2001 – Dec 18, 2001.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006)
Keystone, South Dakota, United States · Buildings (monument (mountain sculpture)) · Over budget and late · Confidence: medium
Expected to take five years and $500,000, the carving of Mount Rushmore took 14 years and cost $989,992.32, and the figures were never finished below the chest.
Cost: planned $500,000 (1927), actual $989,992 (1941) ($9.27 million planned and $21.7 million actual in 2025 dollars). Start: planned 1927, actual Oct 4, 1927. Finish: planned 1932, actual Oct 31, 1941.
Cost overrun: +98% ($10.7 million over in 2025 dollars), in money of the day. Delay: 9 years (187% of the planned duration).
Mount Rushmore National Memorial in the Black Hills of South Dakota was promoted by state historian Doane Robinson and Senator Peter Norbeck to draw tourists, and carved by sculptor Gutzon Borglum with about 400 workers. Carving ran from October 4, 1927 to October 31, 1941, removing about 450,000 tons of rock, about 90 percent of it by dynamite. Federal matching funds paid most of the cost. The planned waist-length figures, a Hall of Records and an inscription panel were dropped when money ran out.
The early projection of about five years and $500,000 assumed steady funding and sound rock, and neither held. Funding was the main constraint. South Dakota's 1925 enabling law allocated no money; the 1929 federal act authorized matching funds of up to $250,000, but the first federal payment was only $54,670.56, matching what the private association had spent. Money became scarce during the Great Depression and work halted for a time. Geology forced rework: the first Jefferson figure, carved to Washington's right, had to be blasted away because the rock was poor, losing about 18 months of work. Management also changed hands: an executive order placed the project under the National Park Service in 1933, and Borglum regained control through a commission in 1938. After Borglum died in March 1941 and with U.S. entry into World War II approaching, the memorial was declared complete on October 31, 1941 with reduced scope. The National Park Service records that no worker died during the 14 years of carving.
Nearly 400 men and women worked on the mountain for 14 years, and not one fatality occurred.
Washington figure: planned 1927 – ?; actual Oct 4, 1927 – Jul 4, 1934. Jefferson, Lincoln and Roosevelt figures: planned ? – 1932; actual 1934 – Jul 2, 1939. Hall of Records: planned not published; actual 1938 – 1939. Final work under Lincoln Borglum: planned not published; actual Mar 1941 – Oct 31, 1941.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
New York City, United States · Buildings (skyscraper) · Over budget and late · Confidence: medium
The tallest building in the Western Hemisphere opened three years late, with its estimated cost up from $3 billion to $3.9 billion.
Cost: planned $3 billion (2007), actual $3.9 billion (2014) ($4.66 billion planned and $5.3 billion actual in 2025 dollars). Start: planned Apr 2006, actual Apr 27, 2006. Finish: planned 2011, actual Nov 3, 2014.
Cost overrun: +30% ($1.22 billion over in 2025 dollars), in money of the day. Delay: 3 years (64% of the planned duration).
One World Trade Center is a 1,776-ft (541 m) office tower in Lower Manhattan, designed by David Childs of Skidmore, Owings & Merrill and developed by the Port Authority of New York and New Jersey, with the Durst Organization joining in 2010. The cornerstone was laid in 2004, but disputes over money, security and design held main construction back until April 2006. The tower had been due in 2011 and opened on November 3, 2014.
The schedule slipped before construction began. Wikipedia, citing contemporary reporting, records that disputes over money, security and design delayed work from the 2004 cornerstone until 2006. In April 2005 the design was reworked to add a 187-ft concrete base for security, and the final design was not unveiled until June 28, 2005, so the design was not frozen until a year before groundbreaking. In July 2008 the Port Authority's reassessment found that the 2011 completion target was not realistic. Construction Briefing reported at the time that rising commodity prices were pushing costs up and that disagreements among the 19 federal, state and city agencies involved had left issues unresolved. Once the base was finished, the steel frame went up steadily at about one floor per week in 2010. The February 2007 estimate of about $3 billion rose to $3.9 billion by 2012. The observatory opened in May 2015, one day ahead of its own revised schedule.
The final section of the spire, lifted on May 10, 2013, brought the tower to exactly 1,776 ft, a figure chosen to reference the year 1776.
Foundations and below-grade works: planned Apr 2006 – ?; actual Apr 27, 2006 – May 17, 2008. Concrete base and lower floors: planned not published; actual May 17, 2008 – 2010. Steel superstructure: planned not published; actual 2010 – Aug 2012. Spire installation: planned not published; actual Dec 12, 2012 – May 10, 2013. Fit-out and opening: planned ? – 2011; actual May 2013 – Nov 3, 2014.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
London, United Kingdom · Buildings (parliament building) · Over budget and late · Confidence: disputed
Charles Barry estimated six years and about GBP 725,000 to rebuild Parliament; it took 30 years and about GBP 2.4 million.
Cost: planned £724,986 (1836), actual £2.4 million (1870) ($102 million planned and $341 million actual in 2025 dollars). Start: planned 1840, actual Apr 27, 1840. Finish: planned 1846, actual 1870.
Cost overrun: +231% ($238 million over in 2025 dollars), in money of the day. Delay: 24 years (400% of the planned duration).
Official rebaseline: July 1854 estimate: £2.17 million (1854), so the outturn is +11% against it.
After fire destroyed most of the old Palace of Westminster on October 16, 1834, a competition with 97 entries was won in January 1836 by Charles Barry's Perpendicular Gothic design, with interiors by Augustus Pugin. Barry estimated six years and GBP 724,986. The foundation stone was laid in 1840, the Lords chamber opened in 1847, the Commons in 1852, and the Clock Tower housing Big Ben was finished in 1859. Barry died in 1860 and his son completed the building around 1870.
Barry's 1836 estimate of GBP 724,986 excluded the site, the river embankment and furnishings, so the baseline was incomplete from the start. By July 1854 the estimate had reached GBP 2,166,846, and the final cost is usually given as about GBP 2.4 million. The Oxford University Press blog, summarizing a history of the project, lists named causes: an unclear client, with Barry taking conflicting instructions from government, Parliament and contractors; weak governance, as the Office of Woods could not cope and was replaced by the Office of Works in 1851, while a Royal Commission set up to control the budget gave up after three years; difficult ground of gravel, quicksand and riverbed; contractor problems, with the first firm dismissed for slow progress and a strike under the second; select committee inquiries that suspended work; disputes with specialists such as the ventilation engineer David Boswell Reid and the clock designer Edmund Beckett Denison; and quantity surveying still in its infancy. The Great Bell cracked in testing and again in 1859, adding further delay.
The first Great Bell, cast in 1856, cracked beyond repair during testing; its 13.5-ton replacement, recast at Whitechapel in 1858, cracked again in September 1859.
Foundations and House of Lords: planned 1840 – 1846; actual Apr 27, 1840 – 1847. Clock Tower and Great Clock: planned not published; actual Sep 28, 1843 – May 31, 1859. House of Commons: planned ? – 1846; actual 1847 – 1852. Victoria Tower and main works: planned ? – 1846; actual 1852 – May 12, 1860. Completion under E. M. Barry: planned not published; actual May 1860 – 1870.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Paris, France · Buildings (cathedral restoration) · Late · Confidence: medium
Rebuilt in five years and eight months for about EUR 703 million, Notre-Dame reopened in December 2024 within budget, according to France's Court of Audit.
Cost: planned €717 million (2019), actual €703 million (2024) ($1.01 billion planned and $781 million actual in 2025 dollars). Start: planned Apr 16, 2019, actual Apr 16, 2019. Finish: planned Apr 2024, actual Dec 7, 2024.
Cost overrun: -2% ($15.5 million under in 2025 dollars), in money of the day. Delay: 8 months (13% of the planned duration).
On April 15, 2019, a fire destroyed the roof and spire of Notre-Dame de Paris. President Emmanuel Macron set a five-year target the next day, and a July 2019 law created a dedicated public body, led first by General Jean-Louis Georgelin and, after his death in August 2023, by Philippe Jost. More than EUR 843 million in donations paid for the work. After a securing phase to September 2021, the roof and spire were rebuilt largely in their original form, and the cathedral reopened on December 7, 2024.
France's Court of Audit (Cour des comptes), in its third and final report in September 2025, described the restoration as a success with budget and timetable rigorously respected and no extra cost. The securing phase used EUR 151 million of a EUR 165 million budget, and the restoration phase had a EUR 552 million budget, leaving about EUR 140 million of donations for pre-fire defects and the sacristy. The court's president, Pierre Moscovici, praised the creation of a single public body to run the project. Several factors helped: a fixed public deadline, a special law passed 95 days after the fire, and donations that removed the usual funding uncertainty. The decision to rebuild the spire and roof largely as before ended the design debate opened by an international competition. Setbacks included a site shutdown after failed lead inspections and pandemic slowdowns in 2020. Measured against the five-year target of April 2024, the reopening came about eight months later. Earlier court reports asked for more transparency on how donations covered the public body's running costs.
The golden rooster returned to the top of the new spire in December 2023 was redesigned as a phoenix, and a time capsule of relics was placed inside it.
Emergency securing and consolidation: planned Apr 16, 2019 – ?; actual Apr 16, 2019 – Sep 2021. Restoration: timber roof and spire: planned Sep 2021 – Apr 2024; actual Sep 2021 – Mar 6, 2024. Restoration: interior, windows and organ: planned ? – Apr 2024; actual Mar 2022 – Nov 29, 2024. Reopening: planned ? – Apr 2024; actual Dec 7, 2024 – Dec 8, 2024.
From the history of managing work: How Big Things Get Done (2023)
Amsterdam, Netherlands · Buildings (museum) · Over budget and late · Confidence: medium
Planned in 2000 as a 202-million-guilder (about EUR 92 million) job finishing in 2005, the Rijksmuseum renovation reopened in April 2013 at about EUR 370 million.
Cost: planned €91.7 million (2000), actual €370 million (2013) ($158 million planned and $679 million actual in 2025 dollars). Start: planned 2003, actual Dec 7, 2003. Finish: planned 2005, actual Apr 13, 2013.
Cost overrun: +304% ($511 million over in 2025 dollars), in money of the day. Delay: 8 years (389% of the planned duration).
Official rebaseline: 2003 budget at closure (State Secretary Van der Laan): €272 million (2003), so the outturn is +36% against it; a revised finish of 2008, 5 years late against it.
The Dutch state renovated and partly rebuilt Pierre Cuypers's 1885 Rijksmuseum in Amsterdam to a design by Spanish architects Cruz y Ortiz, restoring decorated interiors, opening up the courtyards as an atrium entrance and keeping the cycle passage through the building. The client was the Rijksgebouwendienst with the museum and the culture ministry. The main building closed on 7 December 2003, with a small selection, including The Night Watch, shown in the Philips Wing. It reopened on 13 April 2013.
Fragmented governance and a failed tender caused most of the delay. Binnenlands Bestuur listed more than 80 required permits, a long dispute with the cycling lobby over keeping the public passage through the building, and a failed tender. In 2007-08 BAM was the only bidder for the main building and offered EUR 222m against a ministry cap of EUR 134m set by an independent advisory bureau; work stopped in summer 2007, and in February 2008 culture minister Ronald Plasterk rejected the bid and moved reopening to 2013. MPs complained in 2009 that responsibility was always passed between the museum management, the city, the contractor, the project office, the cycling union and the architects, and that the Spanish architects were left to manage Dutch permit and consultation procedures. Re-tendering the work as seven lots during the construction slump brought the main-building price down to EUR 158m. The overall envelope rose from EUR 272m (2003) to EUR 333m and then EUR 366m (2013 prices), funded partly by rent that was not paid while the museum stayed shut.
A public cycle path runs through the middle of the Rijksmuseum, and the dispute over keeping it was one cause of the delay.
Decision, budget and design: planned not published; actual 1999 – 2003. Closure and first works: planned Dec 2003 – ?; actual Dec 7, 2003 – Jun 2007. Failed tender and re-tender in seven lots: planned not published; actual Jun 2007 – May 2009. Main reconstruction: planned ? – 2005; actual 2009 – Jul 16, 2012. Fit-out, rehang and reopening: planned ? – 2005; actual Jul 16, 2012 – Apr 13, 2013.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Edinburgh, United Kingdom · Buildings (parliament building) · Over budget and late · Confidence: disputed
Holyrood was first priced at GBP 10-40 million and finished three years late at GBP 414 million.
Cost: planned £40 million (1997), actual £414 million (2004) ($131 million planned and $1.29 billion actual in 2025 dollars). Start: planned Jun 1999, actual Jun 1999. Finish: planned Jul 2001, actual Sep 7, 2004.
Cost overrun: +936% ($1.17 billion over in 2025 dollars), in money of the day. Delay: 3 years (151% of the planned duration).
Official rebaseline: April 2000 Parliament-approved budget: £195 million (2000), so the outturn is +113% against it.
After the 1997 devolution referendum, the Scottish Office estimated a new parliament building at GBP 10-40 million. Enric Miralles won the design in July 1998 and work began at Holyrood in June 1999, with completion due in July 2001. Under construction management procurement, with the design still developing and the brief growing, the forecast cost rose to GBP 431 million. MSPs held their first debate there in September 2004. Both Audit Scotland and the Fraser Inquiry examined why.
Lord Fraser's inquiry (reported September 2004) named the choice of construction management as the single factor behind most of the project's misfortunes. The method leaves cost risk with the client, and civil servants adopted it to save time without properly assessing the risk or asking ministers to approve it. Audit Scotland (June 2004) found that forecast costs more than doubled from GBP 195 million in September 2000 to GBP 431 million in February 2004, and cited weak leadership, poor cost control and more than 2,000 design changes. Earlier, its 2000 report showed that almost half of the construction cost increase came from a 47% rise in floor area, plus a complex design, higher quality, security needs and Queensberry House. Estimates were kept low: the January 1998 budget of GBP 50 million for construction excluded about GBP 40 million of fees, VAT and other costs. The deaths of architect Enric Miralles (July 2000) and First Minister Donald Dewar (October 2000) removed the project's two main champions. Fraser concluded the building could never have cost under GBP 50 million and estimated GBP 150 million was lost to delays.
Flyvbjerg's table of large-project overruns ranks Holyrood second at 1,600%, behind only the Suez Canal.
Site choice and architect selection: planned Jul 1997 – Jul 1998; actual Jul 1997 – Jul 6, 1998. Design development: planned Jul 1998 – Jun 1999; actual Jul 1998 – 2003. Demolition and enabling works: planned Jun 1999 – ?; actual Jun 1999 – 2000. Main construction (construction management, Bovis Lend Lease): planned Jun 1999 – Jul 2001; actual Jun 1999 – Aug 2004. Occupation and opening: planned Jul 2001 – Jul 2001; actual Sep 7, 2004 – Oct 9, 2004.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
New York City (Liberty Island), United States · Buildings (monument) · Over budget and late · Confidence: disputed
Meant for the 1876 centennial, the statue was dedicated ten years late, and its pedestal cost about twice the $125,000 first estimated.
Cost: planned $125,000 (1877), actual $282,000 (1886) ($3.78 million planned and $10.1 million actual in 2025 dollars). Start: planned 1875, actual Nov 1875. Finish: planned 1876, actual Oct 28, 1886.
Cost overrun: +126% ($5.63 million over in 2025 dollars), in money of the day. Delay: 10 years (1032% of the planned duration).
Frederic-Auguste Bartholdi's copper statue was financed by the French public and built in Paris, with an iron framework engineered by Gustave Eiffel. Americans paid for Richard Morris Hunt's granite-faced pedestal on Bedloe's Island. Conceived to mark the 1876 centennial of U.S. independence, only the arm and torch were ready that year. The statue was finished in Paris in 1884, shipped in 1885, and dedicated on October 28, 1886, after a newspaper campaign rescued the pedestal fund.
The project was split by funding source, and both halves ran short. In France, the National Park Service history records that the statue cost much more than anticipated (about $250,000 in the end), and the money was not fully subscribed until July 1882 despite a lottery added in 1878. In the United States, the American Committee calculated in 1877 that the pedestal and erection would cost $125,000, then found it had to double that estimate. Hunt's pedestal was cut from 114 ft to 89 ft for cost reasons. By January 1885 the committee had no money left; its treasurer reported $182,000 raised and spent and said $100,000 more was needed or work would be abandoned. Joseph Pulitzer's New York World then raised $102,000 from about 120,000 donors by August 11, 1885. Technical design also changed mid-stream: after Viollet-le-Duc died in 1879, Eiffel replaced the planned masonry core with a flexible iron truss, which is still in use.
About 80 percent of the $102,000 raised by Pulitzer's New York World for the pedestal came in gifts of less than one dollar.
Fundraising in France: planned 1875 – 1876; actual Nov 1875 – Jul 1882. Arm and torch fabrication: planned ? – 1876; actual 1876 – 1876. Head fabrication: planned not published; actual 1877 – 1878. Iron framework and assembly in Paris: planned ? – 1883; actual 1881 – Jul 4, 1884. Pedestal construction: planned not published; actual 1883 – Apr 22, 1886. Shipping and reassembly: planned not published; actual Jan 1885 – Oct 28, 1886.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
Sydney, Australia · Buildings (opera house) · Over budget and late · Confidence: high
Estimated at A$7 million and due on Australia Day 1963, the Opera House opened ten years late at A$102 million.
Cost: planned A$7 million (1957), actual A$102 million (1973) ($89.4 million planned and $1.05 billion actual in 2025 dollars). Start: planned Mar 2, 1959, actual Mar 2, 1959. Finish: planned Jan 26, 1963, actual Oct 20, 1973.
Cost overrun: +1357% ($978 million over in 2025 dollars), in money of the day. Delay: 11 years (275% of the planned duration).
The New South Wales government picked Jorn Utzon's sail-roofed design in January 1957 and started building on Bennelong Point in March 1959, aiming to open on 26 January 1963. Construction began before the shells could be engineered, the podium had to be partly rebuilt, and Utzon resigned in 1966 after a dispute with the works minister. A local team finished the interiors, and Queen Elizabeth II opened the building on 20 October 1973. Lotteries paid for almost all of it.
The main cause was a design that was not frozen. Premier Joe Cahill pushed for an early start in 1959, before anyone knew how to build Utzon's shells, so Stage I (the podium, contractor Civil & Civic) went ahead without final loads. By January 1961 it was 47 weeks late, and the columns later had to be rebuilt to carry the roof. Finding a buildable geometry for the shells took Utzon and Ove Arup & Partners years. After a change of government, works minister Davis Hughes withheld payments and Utzon left on 28 February 1966, which forced a redesign of the interiors by Peter Hall's team. The NSW Treasury puts the result at A$102 million, 1,357% over the original A$7 million estimate and about ten years late, and Flyvbjerg lists a 1,400% overrun. The outcome was a building that became a national symbol, financed almost entirely by 496 Opera House lotteries rather than tax revenue.
The NSW Treasury records that 496 Opera House lotteries, selling 86.7 million tickets between 1957 and 1986, raised the A$102 million the building cost.
Design competition and planning: planned Jan 29, 1957 – Mar 1, 1959; actual Jan 29, 1957 – Mar 1, 1959. Stage I: podium (Civil & Civic): planned Mar 2, 1959 – ?; actual Mar 2, 1959 – Feb 1963. Stage II: roof shells (MR Hornibrook): planned not published; actual 1963 – 1967. Utzon resignation and design handover: planned not published; actual Feb 28, 1966 – Apr 1966. Stage III: interiors and fit-out: planned not published; actual 1967 – Sep 1973. Opening: planned Jan 26, 1963 – Jan 26, 1963; actual Oct 20, 1973 – Oct 20, 1973.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Los Angeles, United States · Buildings (concert hall) · Over budget and late · Confidence: medium
Planned to open in 1997 for about $210 million, Frank Gehry's hall opened six years late in 2003 at $274 million.
Cost: planned $210 million (1991), actual $274 million (2003) ($496 million planned and $480 million actual in 2025 dollars). Start: planned 1992, actual Dec 1992. Finish: planned 1997, actual Oct 23, 2003.
Cost overrun: +31% ($112 million over in 2025 dollars), in money of the day. Delay: 6 years (126% of the planned duration).
Walt Disney Concert Hall, home of the Los Angeles Philharmonic, began with Lillian Disney's $50 million gift in 1987. Frank Gehry delivered designs in 1991, and a garage was started under the site in December 1992, with the hall due to open in 1997. Rising costs and a fundraising shortfall stalled the hall itself for about five years. After renewed fundraising, construction restarted in December 1999, and the stainless-steel-clad hall opened on October 23, 2003, at a total project cost of $274 million including the $110 million garage.
Newsweek, writing in the mid-1990s, traced a cost rise of roughly $50 million mainly to a 1992 decision to fast-track the project by bidding contracts before the design drawings were finished. It also cited five years of negotiation with county and city officials after the 1987 gift, design changes such as a hotel added and then dropped and an atrium removed, leases still unsigned at the 1992 ceremony, and a fundraising shortfall during a California recession: the Music Center had pledged $22.5 million and was $20.5 million short. MousePlanet adds that estimates reached $265 million by 1995, when Los Angeles County threatened to withdraw unless $52.3 million more was raised within two years, and that work on the hall halted. Fundraising led by Eli Broad and Mayor Richard Riordan resumed in 1996, and a $25 million Walt Disney Company gift followed in 1997. To save money, the planned stone skin was replaced with stainless steel. The garage was built on its own schedule from 1992 to 1996.
The hall's signature stainless steel skin was a cost-cutting change; the original design called for a stone exterior.
Underground parking garage: planned 1992 – ?; actual Dec 1992 – 1996. Construction halt and fundraising: planned not published; actual 1994 – Dec 1999. Concert hall construction: planned 1993 – 1997; actual Dec 1999 – Oct 2003. Dedication and opening: planned ? – 1997; actual Oct 20, 2003 – Oct 23, 2003.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
London, United Kingdom · Buildings (stadium) · Over budget and late · Confidence: medium
The new Wembley opened a year late, and contractor Multiplex lost about A$251 million on its GBP 445 million fixed-price deal.
Cost: planned £757 million (2003), actual £798 million (2007) ($2.17 billion planned and $2.48 billion actual in 2025 dollars). Start: planned Sep 30, 2002, actual Sep 30, 2002. Finish: planned May 13, 2006, actual Mar 9, 2007.
Cost overrun: +5% ($127 million over in 2025 dollars), in money of the day. Delay: 10 months (23% of the planned duration).
Wembley National Stadium Limited, a Football Association subsidiary, rebuilt England's national stadium with a 90,000-seat bowl under a 133-meter arch. Demolition began on 30 September 2002, and in June 2003 the National Audit Office reported an expected cost of GBP 757 million with completion in early 2006. Australian contractor Multiplex agreed a fixed construction price of GBP 445 million. Steelwork disputes and delays pushed the 2006 FA Cup Final to Cardiff. The stadium was handed over on 9 March 2007 at a reported cost of GBP 798 million.
The client's budget was largely protected by a fixed-price contract, so most of the overrun fell on the contractor. Multiplex had agreed to build for GBP 445 million and in April 2008 reported an expected loss of about A$251 million on the job (KHL). The roof and arch were the main technical risk. Multiplex's dispute with steel subcontractor Cleveland Bridge, which held a GBP 60 million subcontract including the arch, went to court; in 2008 the court ruled that Cleveland Bridge owed Multiplex GBP 6.15 million. In December 2005 the builders admitted a material risk of missing the 2006 FA Cup Final, which the FA moved to Cardiff in February 2006, and in March 2006 the opening slipped to 2007. On the client side, the NAO had earlier criticized the procurement for meeting Multiplex before the formal process. Total client cost rose from the NAO's GBP 757 million to GBP 798 million, about 5% in nominal terms.
The arch spans 315 meters and supports all the weight of the north roof and 60% of the retractable south roof.
Financing and approvals: planned ? – Dec 2000; actual 2000 – Sep 2002. Demolition of the old stadium: planned Sep 30, 2002 – ?; actual Sep 30, 2002 – 2003. Main construction (Multiplex, fixed price): planned 2003 – Mar 2006; actual 2003 – Mar 9, 2007. Test events: planned not published; actual Mar 17, 2007 – Mar 24, 2007. Official opening: planned May 13, 2006 – May 13, 2006; actual May 19, 2007 – May 19, 2007.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
Cape Canaveral (Kennedy Space Center), United States · Space and science (crewed lunar program) · Over budget · Confidence: disputed
NASA met Kennedy's end-of-decade deadline with five months to spare, for $25.4 billion against an early estimate of $20 billion.
Cost: planned $20 billion (1961), actual $25.4 billion (1973) ($215 billion planned and $184 billion actual in 2025 dollars). Start: planned May 25, 1961, actual May 25, 1961. Finish: planned Dec 31, 1969, actual Jul 24, 1969.
Cost overrun: +27% ($39.2 billion over in 2025 dollars), in money of the day. Delay: 5 months early.
Apollo was NASA's civil program to land astronauts on the Moon and return them safely, a goal President Kennedy set on May 25, 1961. After the Saturn I and Saturn V rockets were developed and the 1967 Apollo 1 fire forced a spacecraft redesign, Apollo 11 landed on July 20, 1969. Six landings followed through Apollo 17 in December 1972. NASA reported a total cost of $25.4 billion in 1973, about 27 percent above the $20 billion figure James Webb gave in 1961.
The program had a single fixed goal and a hard deadline, which kept scope stable for most of the decade. Cost estimating began low: preliminary NASA analysis put a lunar landing at $7 billion to $12 billion, and Administrator James Webb raised the figure to $20 billion before reporting it to Vice President Johnson in April 1961. Funding pressure appeared early. In 1962 Apollo chief Brainerd Holmes sought more than $400 million in supplemental funds to prevent schedule slippage, which Webb initially refused, and the Bureau of the Budget projected $16.4 billion in costs through 1967 alone. The worst setback was technical and human: the January 27, 1967 cabin fire killed three astronauts and halted crewed flights for 20 months while the command module was redesigned. At its peak the effort employed about 400,000 people across more than 20,000 firms and universities. NASA's 1973 report to Congress put the total at $25.4 billion; a 2019 reconstruction by Casey Dreier of the Planetary Society found $25.8 billion, within 1.6 percent.
The Apollo missions brought back 382 kilograms (842 pounds) of lunar rock and soil.
Concept and goal-setting: planned not published; actual 1960 – May 25, 1961. Launch vehicle and spacecraft development: planned May 1961 – ?; actual Oct 27, 1961 – Jan 27, 1967. Apollo 1 fire and spacecraft redesign: planned not published; actual Jan 27, 1967 – Oct 11, 1968. Crewed flights to the first landing: planned ? – Dec 31, 1969; actual Oct 11, 1968 – Jul 24, 1969.
From the history of managing work: Apollo and systems management (1961–1969), PERT puts uncertainty into the schedule (1957–1958), The work breakdown structure (1962)
Pasadena (Jet Propulsion Laboratory), United States · Space and science (planetary orbiter and probe) · Incomplete data · Confidence: medium
Cassini–Huygens cost about $3.26 billion and survived the cancellation of its twin mission CRAF, then flew to Saturn and operated for 13 years.
Cost: planned cost not public, actual $3.26 billion (2000) (n/a planned and $6.09 billion actual in 2025 dollars). Start: planned 1990, actual 1990. Finish: planned not published, actual Sep 15, 2017.
Cost overrun: cost not public. Delay: not known.
Cassini–Huygens was a joint mission of NASA, the European Space Agency and the Italian Space Agency to study Saturn, its rings and its moon Titan. Congress approved it in 1990 alongside the CRAF comet mission; budget cuts led NASA to cancel CRAF and restructure Cassini. The spacecraft launched on October 15, 1997, entered Saturn orbit on July 1, 2004 and delivered ESA's Huygens probe to Titan's surface on January 14, 2005. After two extensions it ended in Saturn's atmosphere on September 15, 2017.
Cassini began as half of a two-spacecraft program. Congress approved CRAF and Cassini together on the promise that a shared spacecraft design would save money, with the condition that one would be dropped if costs passed $1.6 billion. The comet penetrator instrument on CRAF grew from an estimated $22 million to as much as $120 million, Congress cut the program's budgets in FY1992 and FY1993, and the schedule stretched by two years. NASA cancelled CRAF; GAO later found little documented analysis behind that decision. Cassini itself was restructured to reduce costs, partly by moving about $94 million of development work into the operations account, which GAO flagged as a concern. After restructuring, the project met its new cost and schedule goals and launched in its October 1997 window. One design error surfaced in flight: the Huygens radio receiver's bandwidth was too narrow for the expected Doppler shift, and engineers solved it by redesigning Cassini's orbits. The mission returned data until 2017. Including launch, the total cost was about $3.26 billion, of which NASA paid about $2.6 billion, ESA $500 million and the Italian agency $160 million.
Cassini carried a DVD with more than 616,400 signatures from people in 81 countries.
Joint CRAF/Cassini program: planned 1990 – ?; actual 1990 – 1992. Restructured Cassini development: planned ? – Oct 1997; actual 1992 – Oct 15, 1997. Cruise to Saturn: planned not published; actual Oct 15, 1997 – Jul 1, 2004. Prime mission and Huygens landing: planned Jun 2004 – May 2008; actual Jul 1, 2004 – Apr 16, 2008. Equinox and Solstice extended missions: planned not published; actual Apr 16, 2008 – Sep 15, 2017.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
Greenbelt, Maryland (Goddard Space Flight Center), United States · Space and science (space telescope) · Over budget and late · Confidence: medium
Hubble reached orbit seven years late at about $1.5 billion, more than double its original $600 million estimate, then needed a 1993 repair mission to see clearly.
Cost: planned $600 million (1977), actual $1.5 billion (1990) ($3.19 billion planned and $3.7 billion actual in 2025 dollars). Start: planned 1977, actual 1977. Finish: planned 1983, actual Dec 13, 1993.
Cost overrun: +150% ($2.22 billion over in 2025 dollars), in money of the day. Delay: 10 years (174% of the planned duration).
The Hubble Space Telescope was approved in 1977 for a 1983 Shuttle launch, with the European Space Agency contributing hardware in return for at least 15 percent of observing time. Funding cuts, technical problems and the 1986 Challenger accident pushed the launch to April 24, 1990, by which time the telescope had cost about $1.5 billion. Weeks later its primary mirror was found to be ground to the wrong shape. Astronauts on STS-61 installed corrective optics in December 1993, and Hubble then reached its intended performance.
Hubble's early years show how budget pressure, a concurrent schedule and weak oversight compound. From 1977 to the planned 1983 launch the project faced repeated funding and schedule crises; by 1980 a launch before 1986 was ruled out, and by 1985 construction cost had roughly doubled from the original $600 million to about $1.2 billion. GAO warned in 1977 and 1980 that NASA's estimates left out major cost items. The Challenger accident in January 1986 then grounded the Shuttle, leaving the finished telescope in a clean room for four years at about $6 million a month. The biggest failure was in the optics: Perkin-Elmer, the low bidder at $64.2 million against Kodak-Itek's $99.8 million, polished the primary mirror too flat at the edge by about 2.2 micrometers because a lens in its reflective null corrector was 1.3 mm out of position. The November 1990 Allen report also blamed poor communication and oversight by NASA and the contractor. What went right was the design for servicing: the telescope could be repaired in orbit, and the 1993 STS-61 crew restored its vision in five spacewalks.
Kodak's backup primary mirror for Hubble is on permanent display at the Smithsonian's National Air and Space Museum.
Approval and design: planned 1977 – 1979; actual 1977 – 1979. Primary mirror grinding and polishing: planned not published; actual 1979 – May 1981. Assembly, testing and launch slips: planned 1981 – 1983; actual 1981 – Jan 28, 1986. Storage after the Challenger accident: planned not published; actual Jan 28, 1986 – Apr 24, 1990. Mirror flaw discovery and investigation: planned not published; actual Apr 24, 1990 – Nov 1990. Corrective optics and first servicing mission: planned not published; actual Oct 1991 – Dec 13, 1993.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), PMI publishes the Project Management Body of Knowledge (1987)
Bethesda, Maryland (National Institutes of Health), United States · Space and science (genomics research program) · On time and on budget · Confidence: medium
The Human Genome Project finished in April 2003, more than two years early, at about $2.7 billion against a $3 billion estimate.
Cost: planned $3 billion (1991), actual $2.7 billion (1991) ($7.09 billion planned and $6.38 billion actual in 2025 dollars). Start: planned 1990, actual 1990. Finish: planned 2005, actual Apr 14, 2003.
Cost overrun: -10% ($709 million under in 2025 dollars), in constant prices. Delay: 2 years early.
The Human Genome Project, led in the United States by the National Institutes of Health and the Department of Energy, set out to sequence the 3 billion base pairs of human DNA. Congress funded it in 1990 with a 2005 target and a projected cost of about $3 billion. With partners in the UK, France, Germany, Japan and China, the consortium announced a draft in June 2000 and an essentially complete sequence on April 14, 2003. NHGRI says the project cost NIH about $2.7 billion in FY1991 dollars.
The project is a rare large program that finished early and below its estimate. It was planned in successive five-year phases, with mapping and technology development first, so the costly sequencing work was scaled up only after methods and automated sequencers had matured. Sequencing technology improved quickly during the 1990s, which lowered the unit cost of the main deliverable. Competition also mattered: Celera Genomics launched a privately funded effort in 1998, and the public consortium accelerated production, announcing a working draft with Celera in June 2000. Governance choices helped keep the effort coherent. The 1996 Bermuda Principles required rapid public release of sequence data, and from 1990 a fixed share of the budget funded research on ethical, legal and social issues. Some caveats apply: NHGRI notes that precise cost accounting is difficult, the $3 billion figure covered a broad range of genomics work beyond sequencing, and the 2003 sequence still had gaps that were not fully closed until the Telomere-to-Telomere consortium's work in 2022.
Most of the DNA sequenced came from volunteers in Buffalo, New York, recruited through newspaper advertisements.
Planning and first funding: planned not published; actual 1988 – 1990. Mapping and technology development: planned 1990 – ?; actual 1990 – 1998. Large-scale sequencing: planned not published; actual 1998 – Jun 26, 2000. Draft analysis and publication: planned not published; actual Jun 26, 2000 – Feb 2001. Finishing the reference sequence: planned ? – 2005; actual Feb 2001 – Apr 14, 2003.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006)
Houston (Johnson Space Center), United States · Space and science (space station) · Over budget and late · Confidence: disputed
Approved in 1984 as an $8 billion station to be finished by 1994, the US-led space station was completed in 2011 at a construction cost NASA put at $31 billion.
Cost: planned $8 billion (1984), actual $31 billion (2008) ($24.8 billion planned and $46.4 billion actual in 2025 dollars). Start: planned 1984, actual 1984. Finish: planned 1994, actual May 2011.
Cost overrun: +288% ($34.4 billion over in 2025 dollars), in money of the day. Delay: 17 years (169% of the planned duration).
Official rebaseline: 1993 redesign estimate: $17.4 billion (1993), so the outturn is +78% against it; a revised finish of Jun 2002, 9 years late against it.
NASA began the space station program in 1984 as Space Station Freedom, estimating $8 billion in FY1984 dollars for research and development through assembly and a 1994 completion. After years of cost growth the design was reworked in 1993 into the International Space Station with partner agencies. Assembly in orbit began in 1998, paused after the 2003 Columbia accident, and the US segment was completed in 2011. GAO reported in 2008 that NASA expected construction to cost $31 billion, excluding Shuttle launches.
The station's cost history is a series of baselines that did not hold. The 1984 estimate of $8 billion excluded launch costs and assumed completion within a decade. By 1993 NASA's estimate for Freedom was $30 billion to build and $90 billion including 30 years of operations, and the program was redesigned. The 1993 redesign promised construction for $17.4 billion and no more than $2.1 billion a year; NASA exceeded the annual cap in FY1998, an independent task force put the cost at $24.7 billion in April 1998, and in 2001 NASA found about $4.8 billion of further growth, more than 72 percent above the 1993 figure. GAO counted about $35 billion appropriated by 2006, and estimates of the total US cost to develop, assemble and operate the station reached about $100 billion. The schedule depended on the Shuttle: the planned June 2002 completion moved to 2006 and then beyond, and the Columbia accident in February 2003 stopped assembly for two and a half years. The modular design allowed the station to operate and host crews while still being built.
Building the complete station took more than 40 assembly flights, 36 of them by the Space Shuttle, for a mass of about 410,000 kilograms.
Space Station Freedom design: planned 1984 – 1994; actual 1984 – 1993. Redesign as the International Space Station: planned not published; actual 1993 – Dec 4, 1998. Initial assembly: planned not published; actual Dec 4, 1998 – Feb 7, 2001. Core assembly: planned not published; actual Feb 7, 2001 – Feb 1, 2003. Stand-down after the Columbia accident: planned not published; actual Feb 1, 2003 – Jul 26, 2005. Completion of the US segment: planned ? – Jun 2002; actual Jul 26, 2005 – May 2011.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), The work breakdown structure (1962)
Greenbelt, Maryland (Goddard Space Flight Center), United States · Space and science (space telescope) · Over budget and late · Confidence: high
Webb was pitched in the late 1990s as a roughly $1 billion telescope launching in 2007; it launched on Christmas Day 2021 at a life-cycle cost of $9.7 billion.
Cost: planned $1 billion (1999), actual $9.7 billion (2021) ($1.93 billion planned and $11.5 billion actual in 2025 dollars). Start: planned 1996, actual 1996. Finish: planned 2007, actual Dec 25, 2021.
Cost overrun: +870% ($10.3 billion over in 2025 dollars), in money of the day. Delay: 15 years (132% of the planned duration).
Official rebaseline: FY2009 baseline commitment: $4.96 billion (2009), so the outturn is +95% against it; a revised finish of Jun 2014, 8 years late against it.
The James Webb Space Telescope, NASA's infrared successor to Hubble built with the European and Canadian space agencies, was proposed in 1996 for about $500 million. NASA committed to a formal baseline in FY2009: $4.964 billion life-cycle cost and a June 2014 launch. Repeated technical problems led to replans in 2011 and 2018 and a near-cancellation by a House subcommittee. Webb launched on December 25, 2021 at a life-cycle cost of about $9.7 billion and released its first full-color images in July 2022.
Webb's estimates were unrealistic from the start. The National Academy of Sciences endorsed it in 2001 at about $1 billion, and the 2009 baseline of $4.964 billion was judged unachievable within a year by the Independent Comprehensive Review Panel chaired by John Casani, which in 2010 put the life-cycle cost at $6.5 billion and the earliest launch in late 2015. In July 2011 the House Appropriations Committee recommended cancelling the project; Congress instead funded a revised $8.835 billion plan with an $8 billion cap on development. Integration and testing then exposed further problems. The May 2018 Independent Review Board named five causes: human errors such as applying the wrong voltage in a wiring test, embedded problems such as sunshield fasteners that loosened under vibration, inexperience with novel technologies like the sunshield, excessive optimism, and system complexity. The board found 344 potential single-point failures. NASA reported a breach of the cap in March 2018, and GAO later said the launch had slipped more than seven years since 2009. Once launched, deployment worked as designed.
Mechanical integration of the telescope with its spacecraft and sunshield, first scheduled for 2007, was completed in August 2019.
Next Generation Space Telescope concept studies: planned not published; actual 1996 – Mar 2003. Formulation and prime contract: planned not published; actual Mar 2003 – 2008. Development under the 2009 baseline: planned 2008 – Jun 2014; actual 2008 – Nov 2011. Telescope and instrument build: planned not published; actual Nov 2011 – Nov 2016. Observatory integration and test: planned not published; actual Nov 2016 – Aug 2019. Final testing and launch campaign: planned not published; actual Aug 2019 – Dec 25, 2021.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Geneva (CERN, Meyrin), Switzerland · Space and science (particle accelerator) · Over budget and late · Confidence: disputed
CERN's collider started physics five years after its 2005 target, and its construction cost to CERN rose from an allotted 2.6 billion Swiss francs to 4.3 billion.
Cost: planned CHF 2.6 billion (1996), actual CHF 4.33 billion (2008) ($4.32 billion planned and $5.99 billion actual in 2025 dollars). Start: planned Dec 1994, actual Dec 1994. Finish: planned 2005, actual Mar 30, 2010.
Cost overrun: +67% ($2.39 billion over in 2025 dollars), in money of the day. Delay: 5 years (45% of the planned duration).
The Large Hadron Collider is a 27-kilometer superconducting proton collider straddling the Swiss-French border near Geneva. CERN Council approved it in December 1994 and in 1996 chose a single-stage build aimed at commissioning in 2005. A 2001 budget crisis, magnet and civil engineering problems, and a September 2008 magnet-connection failure nine days after first beam delayed operations. Physics at 7 TeV began on March 30, 2010. CERN puts its construction cost at 4,332 million Swiss francs, plus about 1.5 billion for the detectors.
The cost crisis became public in September 2001, when CERN management told Council that costs had risen 850 million Swiss francs above the 2.6 billion allotted. About 480 million of this, roughly 18 percent, fell on items in the original LHC budget. Physics Today listed the causes: 150 million francs for unplanned magnet prototypes, magnet assembly about 180 million over expectations, 120 million for a computing grid, 70 million for problems excavating the CMS cavern, 150 million for outside contractors, and a shortfall in non-member contributions. Council members said management had not taken the tight budget seriously. The funding model added risk: the 1996 decision to build in one stage depended on non-member states, while member contributions were cut by up to 9.3 percent against the 1994 level. The schedule slipped from 2005 to first beam on September 10, 2008, and a faulty electrical connection between two magnets then damaged a sector on September 19, costing more than a year before physics. Once running, the machine delivered its main goal, the Higgs boson discovery announced in July 2012.
CERN's 4,332 million franc figure excludes most detector costs: the four main detectors cost about 1.5 billion francs more, mostly paid by the experimental collaborations.
Approval and funding plan: planned Dec 1994 – Dec 1996; actual Dec 1994 – Dec 20, 1996. Construction and installation: planned Dec 1996 – 2005; actual Dec 1996 – Sep 10, 2008. First beam and magnet incident: planned not published; actual Sep 10, 2008 – Sep 19, 2008. Repair and consolidation: planned not published; actual Sep 19, 2008 – Nov 23, 2009. Ramp-up to physics operation: planned not published; actual Nov 23, 2009 – Mar 30, 2010.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Pasadena (Jet Propulsion Laboratory), United States · Space and science (planetary lander and rover) · Late · Confidence: medium
Mars Pathfinder was built in about three years for $150 million plus $25 million for its rover, and Sojourner worked 83 days on a planned seven-day mission.
Cost: planned $175 million (1993), actual $175 million (1997) ($390 million planned and $351 million actual in 2025 dollars). Start: planned 1993, actual 1993. Finish: planned Jul 1997, actual Sep 27, 1997.
Cost overrun: 0% ($0 over in 2025 dollars), in money of the day. Delay: 2 months (5% of the planned duration).
Mars Pathfinder was an early NASA Discovery mission, built at the Jet Propulsion Laboratory to show that a lander and rover could reach Mars quickly and cheaply. The goals were about three years of development, under $150 million for the lander and $25 million for the Sojourner rover. It launched on December 4, 1996, landed on July 4, 1997 using airbags, and returned data until September 27, 1997. Including launch and operations, NASA put the total at about $265 million.
Pathfinder was the model for NASA's 'faster, better, cheaper' approach of the 1990s: a hard cost cap, a short schedule and a fixed planetary launch window. The team met its targets, with NASA reporting $150 million for the lander's development and construction and about $25 million for the rover. Its entry, descent and landing system combined a parachute, retrorockets and airbags that inflated about 355 meters above the surface; the lander hit at 14 meters per second and bounced at least 15 times before stopping. The mission exceeded its goals, with Sojourner operating 83 days against a planned seven and the lander returning data until late September 1997. Not everything was clean. A priority inversion bug in the flight software, seen in preflight testing but given low priority, caused four computer resets in July 1997 before engineers patched it on July 21. The mission was also deliberately narrow: a technology demonstration with a small instrument set, which made the tight cap achievable.
Pathfinder cost about one-fifteenth as much as a Viking mission to Mars.
Design and development: planned 1993 – Dec 1996; actual 1993 – Dec 4, 1996. Cruise to Mars: planned Dec 1996 – Jul 1997; actual Dec 4, 1996 – Jul 4, 1997. Surface operations: planned Jul 1997 – Jul 1997; actual Jul 4, 1997 – Sep 27, 1997.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), The Agile Manifesto (2001)
Pasadena (Jet Propulsion Laboratory), United States · Space and science (planetary rover) · Over budget and late · Confidence: medium
Curiosity missed its 2009 launch window by two years, and its life-cycle cost rose 56 percent to about $2.5 billion.
Cost: planned $1.6 billion (2006), actual $2.5 billion (2011) ($2.56 billion planned and $3.58 billion actual in 2025 dollars). Start: planned 2004, actual 2004. Finish: planned Oct 2009, actual Nov 26, 2011.
Cost overrun: +56% ($1.29 billion over in 2025 dollars), in money of the day. Delay: 2 years (40% of the planned duration).
The Mars Science Laboratory is NASA's car-sized Curiosity rover, built at the Jet Propulsion Laboratory. Confirmed in 2006 at a life-cycle cost of about $1.6 billion, it was due to launch in fall 2009. Problems with actuators, the heat shield and late deliveries of components forced NASA in December 2008 to slip the launch to the next Mars window, 26 months later. Curiosity launched on November 26, 2011 and landed in Gale Crater on August 6, 2012. The Inspector General put the life-cycle cost at about $2.5 billion.
MSL grew in scope and novelty faster than its budget. Its large rover required a new heat shield and a new landing system, and the team's choice of dry-lubricant actuators for the rover's joints proved very hard to make work, forcing a late switch to conventional actuators. Contractors also delivered critical components and instruments late. On December 4, 2008 NASA concluded the work could not be finished for the fall 2009 launch window; because Mars windows open only every 26 months, the slip was two years and added hundreds of millions of dollars. The NASA Inspector General reported in June 2011 that development cost had risen 86 percent, from $969 million to $1.8 billion, and life-cycle cost 56 percent, from $1.6 billion to $2.5 billion. It found managers may have been overly optimistic about the time and money needed, with more than three times the planned number of critical tasks still open and about 1,200 unresolved problem reports. A missed 2011 window would have cost about $570 million more. The rover launched on time in 2011 and landed successfully.
Missing the November 2011 launch window would have delayed the mission another 26 months and, the Inspector General estimated, cost about $570 million.
Formulation: planned not published; actual 2004 – 2006. Development toward the 2009 launch window: planned 2006 – Oct 2009; actual 2006 – Dec 4, 2008. Two-year slip and completion: planned not published; actual Dec 4, 2008 – Jun 2011. Final testing and launch campaign: planned not published; actual Jun 2011 – Nov 26, 2011.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Goldratt's Critical Chain (1997)
Laurel, Maryland (Johns Hopkins Applied Physics Laboratory), United States · Space and science (planetary flyby probe) · On time and on budget · Confidence: medium
New Horizons made its 2006 launch window and reached Pluto in July 2015, the earliest date planned, within a total budget of about $700 million.
Cost: planned $700 million (2001), actual $700 million (2016) ($1.27 billion planned and $939 million actual in 2025 dollars). Start: planned Nov 29, 2001, actual Nov 29, 2001. Finish: planned Jul 14, 2015, actual Jul 14, 2015.
Cost overrun: 0% ($0 over in 2025 dollars), in money of the day. Delay: none.
New Horizons was the first mission to Pluto, selected by NASA on November 29, 2001 and run by Southwest Research Institute and the Johns Hopkins Applied Physics Laboratory. It survived an early funding cut, launched on January 19, 2006 within a 35-day window, used Jupiter's gravity in February 2007, and flew past Pluto on July 14, 2015, the earliest arrival the plan allowed. NASA put the mission's cost at about $700 million for 2001-2016, the ceiling for its program class.
New Horizons was a principal-investigator mission under NASA's New Frontiers rules, which made the PI responsible for cost, schedule and performance and set a total cost limit of $700 million. Its predecessor concept, Pluto-Kuiper Express, had been cancelled in 2000 when estimates exceeded available funds, so the team had a clear cost ceiling from the start. The schedule was driven by physics: only launches between January 11 and February 2, 2006 could use a Jupiter gravity assist that cut three to five years off the trip. NASA's launch planning showed that later departures meant later arrivals, with Pluto-direct launches in February reaching Pluto as late as 2020. Political risk was the biggest early threat: NASA left the mission out of its 2003 budget, and it was restored after the 2002 Decadal Survey ranked it first among medium-size missions. One shortfall was outside the team's control: delays at the Department of Energy reduced plutonium production, so the power source carried 9.75 kg of fuel instead of 10.9 kg, and instruments could not all run at once.
The New Horizons power source was originally a spare built for the Cassini mission.
Proposal competition and selection: planned Jan 20, 2001 – Nov 2001; actual Jan 20, 2001 – Nov 29, 2001. Funding fight and design: planned not published; actual Nov 29, 2001 – 2002. Spacecraft build and test: planned not published; actual 2002 – Sep 24, 2005. Launch campaign: planned Sep 2005 – Feb 14, 2006; actual Sep 24, 2005 – Jan 19, 2006. Cruise to Jupiter and Pluto: planned Jan 2006 – Jul 14, 2015; actual Jan 19, 2006 – Jul 14, 2015.
From the history of managing work: The Critical Path Method (1956–1959), Kahneman and Tversky name the planning fallacy (1977–1979)
Darmstadt (ESA European Space Operations Centre), Germany · Space and science (comet orbiter and lander) · Over budget and late · Confidence: disputed
A launcher failure cost Rosetta its January 2003 window and its original comet, but ESA's about 1.4 billion euro mission still became the first to orbit a comet.
Cost: planned €1 billion (2003), actual €1.4 billion (2014) ($1.98 billion planned and $2.53 billion actual in 2025 dollars). Start: planned Nov 1993, actual Nov 1993. Finish: planned Nov 2011, actual Aug 6, 2014.
Cost overrun: +40% ($724 million over in 2025 dollars), in money of the day. Delay: 3 years (15% of the planned duration).
Rosetta was a European Space Agency mission, approved in November 1993, to orbit a comet and place a lander on its nucleus. It was due to launch in January 2003 to comet 46P/Wirtanen, but the December 2002 failure of a new Ariane 5 variant grounded the launcher. ESA retargeted the spacecraft to comet 67P/Churyumov-Gerasimenko, launched it on March 2, 2004 and reached the comet on August 6, 2014. The Philae lander touched down on November 12, 2014. ESA puts the total cost close to 1.4 billion euros.
Rosetta's main setback came from outside the project. The spacecraft was ready for a January 12, 2003 launch to comet Wirtanen when the first Ariane 5 ECA failed on December 11, 2002, carrying a commercial satellite. With the launcher grounded, Rosetta missed its window. ESA chose a new target, comet 67P/Churyumov-Gerasimenko, because it could be reached using the same Ariane 5 version, while a 2004 Wirtanen mission would have needed a more powerful rocket. The switch kept the spacecraft design but stretched the cruise to ten years; arrival moved from 2011 to 2014. ESA reports the Philae lander alone cost 220 million euros in 2014 economic conditions, including the expenses of the one-year delay. During the cruise, Rosetta was put into hibernation from June 2011 to January 2014, with almost all electronics switched off, and woke on schedule. At the comet, Philae bounced on landing on November 12, 2014 and came to rest about two hours later, while the orbiter worked until it was set down on the comet on September 30, 2016.
Rosetta was the first spacecraft to orbit a comet, entering orbit around 67P on August 6, 2014.
Approval and mission definition: planned Nov 1993 – ?; actual Nov 1993 – 1996. Spacecraft and lander development: planned 1996 – Jan 12, 2003; actual 1996 – Dec 11, 2002. Postponement and retargeting: planned not published; actual Dec 11, 2002 – Mar 2, 2004. Cruise and hibernation: planned Jan 2003 – Nov 2011; actual Mar 2, 2004 – Jan 20, 2014. Approach and arrival at the comet: planned not published; actual Jan 20, 2014 – Aug 6, 2014.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
Cape Canaveral (Kennedy Space Center), United States · Space and science (reusable launch system) · Over budget and late · Confidence: medium
The Shuttle first flew in April 1981, about two years after its March 1979 target, after NASA had sold it on a $5.15 billion development estimate.
Cost: planned $5.15 billion (1971), actual $6.74 billion (1971) ($40.9 billion planned and $53.6 billion actual in 2025 dollars). Start: planned Jan 5, 1972, actual Jan 5, 1972. Finish: planned Mar 1979, actual Apr 14, 1981.
Cost overrun: +31% ($12.7 billion over in 2025 dollars), in constant prices. Delay: 2 years (29% of the planned duration).
President Nixon approved the Space Shuttle on January 5, 1972 as a partly reusable vehicle meant to cut the cost of reaching orbit. NASA's estimate for development was $5.15 billion, under a $5.5 billion ceiling set by the White House budget office. Main engine failures in testing and the slow installation of about 30,000 heat-shield tiles delayed the first orbital flight from March 1979 to April 12, 1981, when Columbia flew STS-1. The program flew 135 missions through 2011.
The Shuttle's design was a product of budget negotiation. NASA initially proposed a fully reusable system costing about $10 billion to develop; under pressure from the Office of Management and Budget it cut the figure roughly in half within six months by accepting higher costs per flight. OMB insisted that development stay within $5.5 billion, and NASA budget officer William Lilly produced an estimate of $5.15 billion, which included $260 million for an abort system that was later dropped. Even then, reviewers inside government expected overruns; one 1971 analysis warned the full nonrecurring cost could approach $15 billion. Promised economics rested on optimistic flight rates of about 50 flights a year and early per-flight cost estimates below $10 million. Development then ran into two hard technical problems: the high-pressure main engines suffered nozzle failures and broken turbine blades in testing, and the ceramic thermal tiles were slow to install and often had to be replaced. Columbia arrived at Kennedy Space Center in March 1979 with 6,000 tiles still missing. The first flight slipped about two years, and the program never came close to the promised flight rate, peaking at nine flights in a year.
Columbia's cockpit on STS-1 had 2,214 switches and displays, about three times as many as the Apollo command module.
Approval and configuration choices: planned Jan 5, 1972 – ?; actual Jan 5, 1972 – Aug 1972. Design, engine and orbiter development: planned Aug 1972 – ?; actual Aug 1972 – Sep 17, 1976. Approach and landing tests: planned not published; actual Feb 1977 – 1977. Columbia completion and tile installation: planned ? – Mar 1979; actual Mar 25, 1979 – Dec 29, 1980. First orbital flight, STS-1: planned Mar 1979 – Mar 1979; actual Apr 12, 1981 – Apr 14, 1981.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Apollo and systems management (1961–1969), The work breakdown structure (1962)
Warsaw, Poland · Software and IT (video game) · Late · Confidence: medium
Cyberpunk 2077 slipped three times from April to December 2020 on a PLN 1.2 billion budget, then was pulled from the PlayStation Store eight days after launch.
Cost: planned cost not public, actual PLN 1.2 billion (2020) (n/a planned and $383 million actual in 2025 dollars). Start: planned not published, actual May 2012. Finish: planned Apr 16, 2020, actual Dec 10, 2020.
Cost overrun: cost not public. Delay: 8 months.
CD Projekt announced Cyberpunk 2077 in May 2012 and began full production after The Witcher 3. At E3 2019 it set a release date of 16 April 2020. The game slipped three times, to 10 December 2020, as the studio prepared versions for nine platforms. It launched with serious bugs on older consoles, and Sony suspended PlayStation Store sales on 18 December 2020. CD Projekt reported more than 13 million copies sold by 20 December and later disclosed total development and marketing costs of about PLN 1.2 billion.
The studio committed to a public date at E3 2019 and then announced three delays, each close to the previous date: in January 2020 to September, in June to November, and on 27 October to December, after the game had reportedly gone gold. CD Projekt said it had to prepare and test nine versions across current-generation, next-generation and PC platforms while working from home during the pandemic. The plan to ship on PlayStation 4 and Xbox One alongside more powerful hardware was the central technical risk; those versions launched with poor performance, and Sony removed the game from its store from 18 December 2020 until June 2021. Staff had been asked to work six-day weeks in the final months. Commercially the launch succeeded: CD Projekt said on 11 December 2020 that pre-order royalties alone exceeded total development and marketing costs incurred or expected for 2020, and it reported over 13 million copies sold, net of refunds, by 20 December. Investor suits ended in a $1.85 million settlement.
CD Projekt said pre-order royalties exceeded the game's total development and marketing costs a day after launch (current report no. 65/2020, 11 December 2020).
Announcement and pre-production: planned not published; actual May 2012 – 2016. Full production: planned 2016 – Apr 2020; actual 2016 – Oct 2020. Delays and final testing: planned not published; actual Jan 2020 – Dec 2020. Launch: planned Apr 16, 2020 – Apr 16, 2020; actual Dec 10, 2020 – Dec 10, 2020. Remediation: planned not published; actual Dec 18, 2020 – Sep 2023.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Scrum is presented at OOPSLA (1995), How Big Things Get Done (2023)
Denver, United States · Software and IT (airport automation) · Over budget and late · Confidence: disputed
A baggage system signed at $175.6 million delayed Denver's new airport by 16 months and was scrapped by United in 2005.
Cost: planned $176 million (1992), actual $250 million (1995) ($403 million planned and $528 million actual in 2025 dollars). Start: planned Apr 1992, actual Apr 1992. Finish: planned Oct 1993, actual Feb 28, 1995.
Cost overrun: +42% ($157 million over in 2025 dollars), in money of the day. Delay: 16 months (91% of the planned duration).
Denver International Airport planned an airport-wide automated baggage system in which computer-controlled telecarts would move bags along tracks under the terminals. BAE Automated Systems signed a $175.6 million contract in 1992, after airport construction had started. Tests failed repeatedly, the airport opening slipped four times from October 1993, and the city built a conventional backup system for over $51 million. DIA opened on 28 February 1995 with only part of the system working. United abandoned it in 2005.
The system was added late: the airport was already under construction when Denver sought bids for an airport-wide system in 1992, and none of the three bidders' proposals was judged suitable, so the city went directly to BAE. Scope grew after signing, including Continental's requested sorter and extra maintenance tracks. The schedule left little time for a technology never built at this scale. GAO's 1994 briefing documented specific failures: a photo eye that could not detect piled bags, software that lost track of which telecarts were loaded after a jam, and conveyors not synchronized with telecarts, so bags fell between them. A failed demonstration for reporters in April 1994 forced an indefinite delay. GAO estimated the total cost of the delayed opening at about $360 million and the monthly deficit at $18 million to $19 million. The decision to build a $51 million conventional backup allowed the airport to open.
United kept paying about $60 million a year under its lease for the system even after deciding in 2005 to abandon it (NBC News).
Contract and design: planned Apr 1992 – ?; actual Apr 1992 – Dec 1992. Build and installation: planned Apr 1992 – Oct 1993; actual Apr 1992 – Apr 1994. Testing and failed demonstration: planned not published; actual Apr 1994 – Aug 1994. Backup conventional system: planned Aug 1994 – Jan 15, 1995; actual Aug 1994 – Feb 1995. Airport opening: planned Oct 1993 – Oct 1993; actual Feb 28, 1995 – Feb 28, 1995. Limited operation and abandonment: planned not published; actual Feb 28, 1995 – Jun 7, 2005.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Washington, D.C., United States · Software and IT (case management software) · Cancelled · Confidence: high
The FBI's Virtual Case File grew from a $119.2 million plan to $170 million and was abandoned in 2005 without going into service.
Cost: planned $119 million (2001), actual $170 million (2005) ($217 million planned and $280 million actual in 2025 dollars). Start: planned Jun 2001, actual Jun 2001. Finish: planned Jun 2004, actual Apr 2005.
Cost overrun: +43% ($83.7 million over in 2025 dollars), in money of the day. Delay: not known.
Official rebaseline: revised UAC plan (DOJ OIG audit 05-07): $170 million, so the outturn is 0% against it; a revised finish of Dec 2003, 16 months late against it.
The Virtual Case File was the software part of the FBI's Trilogy modernization, meant to replace the paper-heavy Automated Case Support system with electronic case files. SAIC began work in June 2001 under a cost-plus contract. After the September 2001 attacks the FBI expanded the scope and pulled the deadline forward to December 2003. The first delivery that month was rejected as non-functional. After a negative independent review, the FBI abandoned VCF in April 2005, having allocated $170 million, and started the Sentinel program.
The Justice Department Inspector General attributed the failure to poorly defined and slowly evolving design requirements, design changes after the FBI refocused on terrorism prevention, a lack of management continuity and oversight, weak contracting, weak IT investment management, and the absence of an enterprise architecture. The program changed scope late: in December 2001 VCF was expanded to replace all existing applications while the deadline was moved earlier, to December 2003. SAIC worked under a cost-plus contract, which gave the contractor little incentive to resist scope changes. The December 2003 delivery did not meet the FBI's requirements, and an Aerospace Corporation review in 2004 was largely negative. The OIG concluded that the successor system was unlikely to benefit substantially from the three years and $170 million spent on VCF. The infrastructure parts of Trilogy, by contrast, were completed in April 2004, close to their May 2004 target.
The Trilogy infrastructure upgrades, delivered by a separate contractor, finished in April 2004, slightly ahead of their May 2004 target, while the VCF software never went live (DOJ OIG).
Contract award and requirements: planned Jun 2001 – ?; actual Jun 2001 – Dec 2002. Design and build: planned Jun 2001 – Jun 2004; actual 2002 – Dec 2003. Delivery 1 and acceptance testing: planned not published; actual Dec 2003 – Jun 2004. Initial Operational Capability pilot and review: planned Jun 2004 – Mar 2005; actual Jun 2004 – Jan 2005. Cancellation and replacement: planned not published; actual Mar 2005 – Apr 2005.
From the history of managing work: Royce describes, and warns against, the waterfall (1970), The Agile Manifesto (2001), Kahneman and Tversky name the planning fallacy (1977–1979)
Baltimore (CMS headquarters, Woodlawn, Maryland), United States · Software and IT (e-government) · Over budget and late · Confidence: medium
A federal marketplace contract estimated at $93.7 million had $209 million obligated by February 2014, and the site crashed on launch day.
Cost: planned $93.7 million (2011), actual $209 million (2014) ($134 million planned and $284 million actual in 2025 dollars). Start: planned Sep 2011, actual Sep 2011. Finish: planned Oct 1, 2013, actual Dec 2013.
Cost overrun: +123% ($157 million over in 2025 dollars), in money of the day. Delay: 3 months (10% of the planned duration).
HealthCare.gov is the federal health insurance marketplace that the Affordable Care Act required by January 2014. CMS hired CGI Federal in 2011 to build the Federally Facilitated Marketplace (FFM), with an estimated contract value of $93.7 million. The site opened on 1 October 2013 as planned but suffered outages and errors that blocked most users. A two-month tech surge made it usable by December 2013. By February 2014, more than $209 million had been obligated for the FFM alone.
GAO found that CMS issued the FFM and data hub task orders when key technical requirements were unknown, including the number of states that would use the federal marketplace and the number of likely enrollees. It used cost-reimbursement contracts, so it paid allowable costs whether or not the system was finished. Requirements kept changing, governance reviews were postponed, the readiness assessment moved from March to September 2013, and required approvals were not obtained before launch. CMS also chose not to withhold fees, putting the launch date first. The HHS Inspector General named the absence of clear leadership as the most critical problem, along with too much focus on policy and too little on technology, poor contract management, and staying on a failing course despite warnings. The recovery worked because CMS and contractors formed one team without status distinctions and applied ruthless prioritization to the most important fixes.
CMS paid the FFM contractor only $12.5 million in fees and withheld about $267,000, roughly 2 percent, despite the troubled launch (GAO-14-694).
Requirements and contracting: planned Mar 2010 – Sep 2011; actual Mar 2010 – Dec 2011. Design and build: planned Sep 2011 – Mar 2013; actual Sep 2011 – Sep 2013. Readiness testing: planned Mar 2013 – Mar 2013; actual Sep 2013 – Sep 2013. Launch: planned Oct 1, 2013 – Oct 1, 2013; actual Oct 1, 2013 – Oct 1, 2013. Remediation (tech surge): planned not published; actual Oct 2013 – Dec 2013. Re-procurement of FFM: planned not published; actual Jan 2014 – Jun 2014.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), The Agile Manifesto (2001), How Big Things Get Done (2023)
Leeds (NHS Connecting for Health), United Kingdom · Software and IT (health records / e-government) · Cancelled · Confidence: disputed
England's NHS IT programme started with a £2.3 billion three-year budget and was dismantled in 2011 with a forecast cost of £9.8 billion.
Cost: planned £2.3 billion (2002), actual £9.8 billion (2013) ($6.18 billion planned and $21.2 billion actual in 2025 dollars). Start: planned Oct 2002, actual Oct 2002. Finish: planned 2010, actual Sep 9, 2011.
Cost overrun: +326% ($16.2 billion over in 2025 dollars), in money of the day. Delay: not known.
Official rebaseline: June 2006 NAO ten-year estimate: £12.4 billion (2006), so the outturn is -21% against it.
The National Programme for IT was launched in 2002 to give every NHS patient in England an electronic care record by 2010, linked through a national Spine. The Department of Health let large regional contracts to Accenture, BT, CSC and Fujitsu in 2003 and 2004. Local systems arrived late and in small numbers, two of the main suppliers left, and the government announced the programme's dismantling in September 2011. The Public Accounts Committee reported in 2013 that the Department's forecast cost was £9.8 billion.
The programme tried to replace hospital and GP systems across England through a few very large, centrally negotiated regional contracts, with local NHS trusts having little say in the systems they would receive. The care records software, notably iSoft's Lorenzo in the North, Midlands and East, ran years late; the NAO found in 2011 that only 4 of 97 planned systems had reached acute trusts there in seven years, and that the number of systems was cut sharply without a matching cut in cost. Supplier failure followed: Accenture withdrew in 2006 and Fujitsu's contract was terminated in 2008, with the termination dispute generating £31.5 million of legal costs. Benefits were thin; the Department reported £3.7 billion of benefits to March 2012, about half the costs incurred. The PAC said the £9.8 billion forecast omitted future Lorenzo costs and Fujitsu termination costs. National infrastructure such as the Spine was delivered and continued in use.
The PAC reported in 2013 that terminating Fujitsu's contract had produced £31.5 million in legal costs over four years (The Register).
Strategy and procurement: planned Jun 2002 – Jan 2004; actual Jun 2002 – Jan 2004. National systems (Spine and services): planned Jan 2004 – ?; actual Jan 2004 – Sep 2011. Local care records deployment: planned Jan 2004 – 2010; actual Jan 2004 – Sep 2011. Supplier exits and contract resets: planned not published; actual Sep 2006 – May 2008. Dismantling and residual contracts: planned not published; actual Sep 9, 2011 – 2016.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), PRINCE2 opens the method to any project (1996), How Big Things Get Done (2023)
Miramichi, New Brunswick (Public Service Pay Centre), Canada · Software and IT (public-sector payroll) · Over budget and late · Confidence: disputed
Approved at about C$309 million to save money on federal pay, Phoenix has cost an estimated C$5.1 billion to launch and fix.
Cost: planned C$309 million (2009), actual C$5.1 billion (2025) ($406 million planned and $3.65 billion actual in 2025 dollars). Start: planned Jul 2009, actual Jul 2009. Finish: planned 2015, actual Apr 21, 2016.
Cost overrun: +1551% ($3.43 billion over in 2025 dollars), in money of the day. Delay: 10 months (14% of the planned duration).
Phoenix was meant to modernize pay for Canada's federal public service by replacing a 40-year-old system and centralizing pay staff in Miramichi, New Brunswick. Cabinet approved about $309 million in 2009, expecting savings of about $70 million a year. IBM configured PeopleSoft software, and the system went live in two waves in February and April 2016. Hundreds of thousands of employees were then overpaid, underpaid or not paid. A federal official put total spending at about $5.1 billion in 2025, and a replacement is being procured.
The Auditor General called Phoenix an incomprehensible failure of project management and oversight. The 2018 audit found that Phoenix executives put schedule and budget ahead of functionality and security, and that their decision to launch was unreasonable given the information available. The system went live without critical pay processing functions, without full testing, with significant security weaknesses and without an adequate contingency plan. Warnings from the Miramichi pay centre and from departments were not heeded. The project had a detailed management structure but no independent oversight, and appeared set up to avoid responsibility. Contract scope also proved badly underestimated: IBM's original contract was $5.7 million but it was eventually paid $185 million. Costs then moved from building to repairing: about $400 million by May 2017, $954 million spent by July 2018, and an estimated $5.1 billion by 2025, against planned savings of about $70 million a year.
IBM's original Phoenix contract was worth $5.7 million; it was eventually paid $185 million (Wikipedia, citing government figures).
Business case and approval: planned Jul 2009 – Jul 2009; actual Jul 2009 – Jun 2011. Contract and build: planned Jun 2011 – 2015; actual Jun 2011 – Feb 2016. Go-live wave 1: planned ? – 2015; actual Feb 24, 2016 – Feb 24, 2016. Go-live wave 2: planned ? – 2015; actual Apr 21, 2016 – Apr 21, 2016. Stabilization and backlog remediation: planned not published; actual Apr 2016 – Mar 2025. Replacement (Dayforce): planned Jun 2025 – ?; actual Jun 2025 – ?.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Brisbane, Australia · Software and IT (public-sector payroll) · Over budget · Confidence: disputed
A $98 million IBM contract produced a payroll that mispaid 78,000 health workers and was estimated in 2012 to cost at least $1.25 billion to fix.
Cost: planned A$98 million (2007), actual A$1.25 billion (2012) ($128 million planned and $1.82 billion actual in 2025 dollars). Start: planned Dec 5, 2007, actual Dec 5, 2007. Finish: planned not published, actual Mar 14, 2010.
Cost overrun: +1176% ($1.67 billion over in 2025 dollars), in money of the day. Delay: not known.
Queensland's shared services program planned a common payroll and HR system for state agencies. IBM won a $98 million prime contract in December 2007; the scope was narrowed in 2008 to an urgent replacement for Queensland Health's unsupported LATTICE payroll. The SAP and Workbrain system went live on 14 March 2010 after more than ten delays and incomplete testing. Thousands of the department's roughly 78,000 staff were overpaid, underpaid or unpaid. KPMG estimated in 2012 that fixing and running it would cost at least $1.25 billion.
The project grew out of a struggling whole-of-government Shared Services Initiative; a March 2007 report found CorpTech had made little progress while using many contractors. The prime contractor model failed within a year: by October 2008 IBM said it needed $181 million, almost twice the contract value, and the state cut the scope to an interim Queensland Health payroll while LATTICE was already out of vendor support, creating deadline pressure. The system went live in March 2010 although the vendor and the department knew it was unlikely to pay staff accurately. KPMG's review found that no full parallel pay run had been done, the technical infrastructure failed, staff were unfamiliar with the processes, and bottlenecks were not anticipated. Payroll staff were making about 200,000 manual entries a pay period by 2012. Commissioner Richard Chesterman's 2013 inquiry placed the project in the front rank of failures in public administration.
By mid-2012, payroll staff were making about 200,000 manual entries each pay period to correct the system (ABC News).
Shared Services Initiative: planned Jul 1, 2003 – ?; actual Jul 1, 2003 – Sep 2007. Procurement: planned Sep 12, 2007 – Dec 2007; actual Sep 12, 2007 – Dec 5, 2007. Rescoping to interim Queensland Health payroll: planned not published; actual Jul 2008 – Oct 2008. Build and testing: planned not published; actual Oct 2008 – Mar 2010. Go-live: planned not published; actual Mar 14, 2010 – Mar 14, 2010. Remediation and inquiry: planned not published; actual Mar 2010 – Jul 31, 2013.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Cupertino, California, United States · Software and IT (consumer device and operating system) · Incomplete data · Confidence: disputed
Apple met its own June 2007 launch promise for the iPhone, at a development cost an insider later put at about $150 million.
Cost: planned cost not public, actual $150 million (2007) (n/a planned and $233 million actual in 2025 dollars). Start: planned 2004, actual 2004. Finish: planned Jun 2007, actual Jun 29, 2007.
Cost overrun: cost not public. Delay: none.
Apple began building a confidential smartphone team in 2004, a project known internally as Purple. Working with Cingular Wireless, later AT&T Mobility, a team of about 1,000 people developed the hardware and a touch interface based on Mac OS X. Steve Jobs unveiled the iPhone on 9 January 2007 and promised US availability in June. It went on sale on 29 June 2007, and Apple sold its one millionth iPhone 74 days later. Apple has never disclosed the budget.
The schedule held where it was public: Apple announced a June 2007 ship date in January and launched on 29 June. Several decisions helped. Apple kept the work secret and inside a small group of senior staff, so plans could change without public cost. The Cingular deal let Apple design hardware and software in-house, a rare concession in the US carrier market at the time, in exchange for four years of exclusive US sales and a share of monthly service revenue. Leadership was concentrated in three named owners for hardware, software and design. The risks were real: Wired's 2008 account, summarized by Fortune, described a demo a few months before Macworld that went badly enough for Jobs to say the company did not yet have a product. Apple did not announce internal dates before January 2007, so slippage in the earlier phases, if any, is not public.
Only about 30 of Apple's most senior people had seen the iPhone before Jobs unveiled it, according to Wired's 2008 account as summarized by Fortune.
Team assembly and concept: planned not published; actual 2004 – 2005. Hardware and software development with Cingular: planned not published; actual 2005 – Dec 2006. Public announcement: planned Jan 9, 2007 – Jan 9, 2007; actual Jan 9, 2007 – Jan 9, 2007. Final engineering and production ramp: planned Jan 2007 – Jun 2007; actual Jan 2007 – Jun 2007. US launch and early sales: planned Jun 2007 – Jun 2007; actual Jun 29, 2007 – Sep 9, 2007.
From the history of managing work: The Agile Manifesto (2001), Planning moves into the browser (2006)
London (Department for Work and Pensions), United Kingdom · Software and IT (e-government / welfare system) · Over budget and late · Confidence: medium
Universal Credit was due by 2017 for £2.4 billion; the latest forecast is £2.9 billion and legacy benefits ending in March 2026.
Cost: planned £2.4 billion (2012), actual £2.93 billion (2023) (forecast) ($5.33 billion planned and $3.85 billion actual in 2025 dollars). Start: planned 2010, actual 2010. Finish: planned 2017, actual Mar 31, 2026 (forecast).
Cost overrun: +22% ($694 million over in 2025 dollars), in money of the day. Delay: 9 years (125% of the planned duration).
Official rebaseline: 2018 full business case: £2.02 billion (2018), so the outturn is +45% against it.
Universal Credit merges six means-tested benefits for working-age people into one monthly payment. The Department for Work and Pensions planned in 2010 to move eight million households onto it by 2017, and its December 2012 business case put implementation at £2.4 billion. Early IT failed, the programme was reset in 2013, and a new digital system was built. UC reached all new claims in 2018. Moving existing claimants took far longer; the end of legacy benefits is set for 31 March 2026 at a forecast £2.9 billion.
The NAO's 2013 review found that DWP had set an October 2013 national rollout date without being able to explain how it chose that date, that the pathfinder systems had limited function and needed manual intervention, and that £34 million of new IT assets had to be written off. DWP had tried an agile approach while policy was still being defined and struggled to fit it into existing contracts, governance and assurance; reviews in 2012 found a 'fortress' culture, and financial control over supplier spending was inadequate. IT costs were forecast at £637 million by April 2015, 60% above the original £396 million. After the 2013 reset DWP built a new full service system, which reached all new claims nationwide by 2018. Later delays came mainly from the managed migration of existing claimants. Since the 2018 business case, the NAO reported, completion slipped by at least six years and costs rose by £912 million, driven by inflation, fraud and error measures, timetable extensions and the decision to postpone moving ESA claimants to 2028 to save money. That date was later brought forward to March 2026.
By July 2013 the Universal Credit pathfinder had taken only about 1,000 new claims across four sites (NAO, 2013).
Design and early IT build: planned 2010 – Apr 2013; actual 2010 – Apr 2013. Pathfinder and programme reset: planned Apr 2013 – Oct 2013; actual Apr 2013 – 2016. National rollout for new claims: planned Oct 2013 – 2017; actual 2016 – Dec 2018. Managed migration of legacy claimants: planned ? – Mar 2022; actual Apr 2023 – Mar 31, 2026.
From the history of managing work: The Agile Manifesto (2001), Scrum is presented at OOPSLA (1995), PRINCE2 opens the method to any project (1996)
Redmond, Washington, United States · Software and IT (operating system) · Late · Confidence: medium
Planned as a minor 2003 update, Windows Vista shipped to consumers in January 2007 after a reported $6 billion and a full development reset.
Cost: planned cost not public, actual $6 billion (2007) (n/a planned and $9.32 billion actual in 2025 dollars). Start: planned May 2001, actual May 2001. Finish: planned 2003, actual Jan 30, 2007.
Cost overrun: cost not public. Delay: 4 years (168% of the planned duration).
Official rebaseline: August 2004 Longhorn development reset: a revised finish of 2006, 7 months late against it.
Longhorn began in May 2001 as a modest Windows release planned for late 2003, between Windows XP and a larger future release. Features accumulated, including the WinFS storage system, and the code base became unstable. In August 2004 Microsoft restarted development from the Windows Server 2003 code base and dropped WinFS. Renamed Windows Vista in July 2005, it was released to manufacturing on 8 November 2006 and reached consumers on 30 January 2007. Press reports put development at more than five years and about $6 billion.
The main cause was scope growth on an unstable base. A release intended as a small interim update absorbed ambitious technologies, including the WinFS file system, the Avalon presentation layer and the Indigo communications system. By 2004 the Windows team faced serious problems with Longhorn, and Microsoft also diverted effort to Windows XP Service Pack 2, a security release. On 27 August 2004 group vice president Jim Allchin told employees that development would restart from Windows Server 2003 SP1, that WinFS would be removed, and that Avalon and Indigo would also be offered for older Windows versions, so that Vista could still ship in 2006. The reset worked in schedule terms: Vista reached manufacturing in November 2006. Critics nicknamed the reduced plan Shorthorn. A Windows developer's 2006 blog post described roughly 2,000 developers and about 50 million lines of code, scale that slowed integration.
Development of Vista restarted in 2004 from the code of Windows Server 2003 SP1, not from the Longhorn code written since 2001 (Thurrott).
Original Longhorn development: planned May 2001 – 2003; actual May 2001 – Aug 27, 2004. Development reset: planned not published; actual Aug 27, 2004 – Jul 27, 2005. Beta testing: planned not published; actual Jul 27, 2005 – Nov 8, 2006. Release to manufacturing and business launch: planned ? – 2006; actual Nov 8, 2006 – Nov 30, 2006. Consumer launch: planned ? – 2006; actual Jan 30, 2007 – Jan 30, 2007.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Scrum is presented at OOPSLA (1995)
Washington, D.C., United States · Software and IT (systems remediation) · Over budget and late · Confidence: high
The federal Y2K fix was first estimated at $2.3 billion in 1997 and ended at about $8.4 billion, with 99.9% of critical systems ready.
Cost: planned $2.29 billion (1997), actual $8.38 billion (2000) ($4.6 billion planned and $15.7 billion actual in 2025 dollars). Start: planned 1996, actual 1996. Finish: planned Nov 1999, actual Dec 31, 1999.
Cost overrun: +266% ($11.4 billion over in 2025 dollars), in money of the day. Delay: 2 months (4% of the planned duration).
Official rebaseline: OMB accelerated implementation deadline: a revised finish of Mar 31, 1999, 9 months late against it.
Many federal computer systems stored years as two digits and risked failing on 1 January 2000. In February 1997 the Office of Management and Budget published a government-wide plan and a preliminary cost estimate of $2.3 billion for fiscal 1996 to 2000. Agencies inventoried thousands of mission-critical systems, then renovated, validated and implemented fixes. The estimate rose quarter after quarter, to $8.38 billion by late 1999. OMB reported 92% of mission-critical systems compliant at its 31 March 1999 goal and 99.9% in December 1999.
The cost grew mainly because the first estimate was preliminary and made before agencies knew the size of the problem. The February 1997 figure of $2,292.4 million excluded normal lifecycle replacements and was criticized by Congress and outside experts as too low. As agencies completed inventories, the estimate rose to $3.9 billion in November 1997, $4.7 billion in February 1998, more than $5 billion in May 1998, $8.05 billion in June 1999, and $8.38 billion by late 1999. What went right was the fixed, non-negotiable deadline, phased milestones reported quarterly to Congress, a public grading of agencies, and emergency funding of $2.25 billion for non-defense work. OMB pulled the implementation target from November 1999 forward to March 1999 to leave time for testing; 92% of systems met it. GAO later recommended a federal chief information officer to keep this central leadership, which the E-Government Act of 2002 largely addressed.
Agencies' count of mission-critical systems fell from 8,589 to 7,850 between November 1997 and February 1998 as they refined what counted as critical (OMB).
Awareness and assessment: planned 1996 – Jun 1997; actual 1996 – 1998. Renovation: planned 1997 – Sep 1998; actual 1997 – Mar 1999. Validation: planned 1998 – Jan 1999; actual 1998 – Mar 1999. Implementation: planned 1998 – Nov 1999; actual 1998 – Dec 1999. Rollover: planned Dec 31, 1999 – Jan 1, 2000; actual Dec 31, 1999 – Jan 1, 2000.
From the history of managing work: PMI publishes the Project Management Body of Knowledge (1987), Kahneman and Tversky name the planning fallacy (1977–1979), PRINCE2 opens the method to any project (1996)
Toulouse, France · Vehicles and aircraft (airliner) · Over budget and late · Confidence: disputed
Airbus launched the A380 at a projected €9.5 billion in 2000; wiring problems made the first delivery 18 months late and Airbus put total development at about €18 billion by 2006.
Cost: planned €9.5 billion (2000), actual €18 billion (2006) ($16.4 billion planned and $36.1 billion actual in 2025 dollars). Start: planned Dec 19, 2000, actual Dec 19, 2000. Finish: planned Apr 2006, actual Oct 15, 2007.
Cost overrun: +90% ($17.1 billion over in 2025 dollars), in money of the day. Delay: 18 months (28% of the planned duration).
Airbus's board approved the A380 superjumbo on 19 December 2000 at a projected cost of €9.5 billion. The first aircraft was unveiled in Toulouse on 18 January 2005 and flew on 27 April 2005, and type certificates followed on 12 December 2006. Problems installing customized electrical wiring forced three delivery delays in 2006. Singapore Airlines received the first aircraft on 15 October 2007, about 18 months behind schedule, and flew it commercially ten days later.
The airframe itself progressed steadily: the A380 first flew on 27 April 2005 and EASA and the FAA certified it on 12 December 2006. The failure was in production. Each aircraft carried about 530 km of wiring, customized for each airline's cabin, and Wikipedia and NBC News report that the installation problems drove the delays announced on 13 June and 3 October 2006. Airbus said in June 2006 that the complexity of customizing wiring for each customer would push back deliveries and add cost, and airlines sought an estimated €2 billion in compensation. Cost estimates grew from €9.5 billion in 2000 to €10.3 billion by 2004 and about €18 billion in 2006, with later estimates of $25 billion (2014). Reports in 2006 said the delays would cut €4.8 billion from parent company EADS's profits over four years. The Mail & Guardian reported that break-even rose from 270 aircraft at launch to 420 at list price, a figure the program never approached.
Each A380 carried about 530 km (330 miles) of wiring, the detail at the center of the 2006 delays.
Design and component manufacture: planned Dec 2000 – ?; actual Dec 19, 2000 – Jan 18, 2005. Flight test and certification: planned not published; actual Apr 27, 2005 – Dec 12, 2006. Wiring rework and production recovery: planned not published; actual Jun 13, 2006 – Oct 2007. First delivery and service entry: planned Apr 2006 – Apr 2006; actual Oct 15, 2007 – Oct 25, 2007.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Everett, United States · Vehicles and aircraft (airliner) · Incomplete data · Confidence: disputed
Boeing promised Pan Am a 747 by the end of 1969, about 28 months after the order, and delivered on time, but development passed $1 billion and the company's debt exceeded $2 billion.
Cost: planned cost not public, actual $1 billion (1969) (n/a planned and $8.78 billion actual in 2025 dollars). Start: planned Apr 1966, actual Apr 1966. Finish: planned Dec 1969, actual Dec 1969.
Cost overrun: cost not public. Delay: none.
In April 1966 Pan Am ordered 25 Boeing 747s for about $525-550 million, with deliveries due by the end of 1969. Boeing had to design the aircraft and build a new factory at Everett, Washington, at the same time. The first 747 rolled out on 30 September 1968, flew on 9 February 1969 and was certified in December 1969, in time for delivery to Pan Am. Service began on 22 January 1970. Development cost about $1 billion, excluding the $200 million plant.
The schedule was met because Boeing ran design, factory construction and tooling in parallel. HistoryLink notes that work on the 747 mockup began before the walls of the mockup building were complete and that factory construction was barely fast enough to keep up. The price was financial exposure. CEO Bill Allen's decision is often described as betting the company: Wikipedia reports that Boeing's debt exceeded $2 billion, including $1.2 billion owed to banks, a record for any company at the time. The weakest link was the new Pratt & Whitney JT9D high-bypass engine, which suffered stalls and turbine casing distortion. According to the Centennial of Flight Commission, the engine problem was not solved when the aircraft entered service, and around 20 to 30 finished aircraft sat at Everett waiting for engines. The 747 went on to stay in production for more than five decades.
The Everett assembly plant built for the 747 enclosed about 200 million cubic feet (5.7 million cubic meters).
Launch order and design definition: planned Apr 1966 – Jul 1966; actual Apr 1966 – Jul 1966. Everett plant construction: planned Jun 1966 – ?; actual Jun 1966 – Sep 1968. Detailed design and first aircraft assembly: planned Jul 1966 – ?; actual Jul 1966 – Sep 30, 1968. Flight test and certification: planned ? – Dec 1969; actual Feb 9, 1969 – Dec 1969. Delivery and entry into service: planned Dec 1969 – Dec 1969; actual Dec 1969 – Jan 22, 1970.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
Everett, United States · Vehicles and aircraft (airliner) · Over budget · Confidence: disputed
Boeing designed the 777 almost entirely on computer with 238 design-build teams and delivered the first aircraft to United on time in May 1995, for a reported $4-5 billion.
Cost: planned $4 billion (1990), actual $5 billion (1995) ($9.86 billion planned and $10.6 billion actual in 2025 dollars). Start: planned Oct 15, 1990, actual Oct 15, 1990. Finish: planned May 1995, actual May 15, 1995.
Cost overrun: +25% ($2.11 billion over in 2025 dollars), in money of the day. Delay: none.
In January 1990 Boeing invited eight airlines to help define a new twin-engine widebody, and on 15 October 1990 United launched the program. The 777 was the first Boeing airliner designed entirely in 3D on CATIA, with cross-functional design-build teams replacing sequential hand-offs. Major assembly began on 4 January 1993, the first flight was on 12 June 1994, and certification came on 19 April 1995. United took the first aircraft on 15 May 1995 and flew the first service on 7 June.
The 777 is a standard case of a program that kept its date. IEEE Spectrum described the change: jetliners had been developed in a linear fashion, with structure designed first and systems fitted later, which caused late rework. Boeing replaced that with up to 238 design-build teams combining design, manufacturing and supplier staff, and with digital pre-assembly on CATIA, which let it skip physical mockups except for the nose. Airline engineers from United, ANA, British Airways and Japan Airlines sat in Seattle with full access to the design. When the first wing and center fuselage were joined, the section was out of alignment by only 0.69 mm. Boeing also set the goal of 'ETOPS out of the box', and the FAA granted 180-minute ETOPS on 30 May 1995. The approach was not cheap: Boeing's investment was put at over $4 billion, with $2 billion more from suppliers, and the Everett plant was doubled in size for almost $1.5 billion.
Boeing built only one physical mockup of the 777, of the nose, partly to confirm that real crews could move in the cockpit as easily as 'Catia-man', a computer human model engineers nicknamed 'Robocop'.
Airline consultation (Working Together): planned Jan 1990 – Oct 1990; actual Jan 1990 – Oct 15, 1990. Digital design (CATIA, design-build teams): planned Oct 1990 – ?; actual Oct 15, 1990 – Apr 9, 1994. Major assembly of first aircraft: planned not published; actual Jan 4, 1993 – Apr 9, 1994. Flight test and certification: planned not published; actual Jun 12, 1994 – May 30, 1995. Delivery and entry into service: planned May 1995 – Jun 1995; actual May 15, 1995 – Jun 7, 1995.
From the history of managing work: The New New Product Development Game (1986)
Everett, United States · Vehicles and aircraft (airliner) · Over budget and late · Confidence: medium
Boeing's board approved a $7 billion development budget for the 787; the program reportedly cost $32 billion and the first jet reached ANA more than three years late.
Cost: planned $7 billion (2003), actual $32 billion (2011) ($12.3 billion planned and $45.8 billion actual in 2025 dollars). Start: planned Apr 26, 2004, actual Apr 26, 2004. Finish: planned May 2008, actual Sep 26, 2011.
Cost overrun: +357% ($35.8 billion over in 2025 dollars), in money of the day. Delay: 3 years (83% of the planned duration).
Boeing launched the 787 on 26 April 2004 with an All Nippon Airways order for 50 aircraft, promising a composite-fuselage, fuel-efficient midsize jet. The board had approved a development budget of about $7 billion, and the first delivery to ANA was expected in May 2008. After seven delays the first flight came on 15 December 2009 and ANA took delivery on 25-26 September 2011. Press reports put total program cost at about $32 billion.
The 787 combined two novelties at once: a mostly carbon-composite airframe and a supply chain in which partners in Japan, Italy and the United States designed and built whole fuselage and wing sections. The first aircraft was rolled out on 8 July 2007 without its major operating systems, and the first flight planned for late August 2007 slipped repeatedly. Wikipedia lists five announced delays between September 2007 and November 2008, citing incorrect fastener installation, supplier shortfalls and a machinists' strike; CAPA counts seven delays and a 58-day labor strike in 2008. On 23 June 2009 Boeing postponed the first flight again for structural reasons. Airlines including United and Air India sought compensation. The $32 billion figure reported in the press includes deferred production costs, and Wikipedia notes original development investment was estimated at a further $20 billion or more. The aircraft itself sold well, which let Boeing recover the program over time.
When Boeing handed the first 787 to ANA in September 2011, executive Scott Fancher told reporters, 'This is not plastic,' referring to the composite airframe.
Design and supplier development: planned Apr 2004 – Jul 2007; actual Apr 26, 2004 – Jul 8, 2007. Rollout to first flight: planned Jul 8, 2007 – Aug 2007; actual Jul 8, 2007 – Dec 15, 2009. Flight test and certification: planned Aug 2007 – May 2008; actual Dec 15, 2009 – Aug 26, 2011. First delivery and service entry: planned May 2008 – May 2008; actual Sep 25, 2011 – Oct 26, 2011.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Toulouse, France · Vehicles and aircraft (airliner) · Over budget and late · Confidence: disputed
Concorde's development estimate rose from £150-170 million at the 1962 treaty to an estimated £1.5-2.1 billion, and passenger service began six years late, in 1976.
Cost: planned £160 million (1962), actual £1.8 billion (1976) ($4.78 billion planned and $18.4 billion actual in 2025 dollars). Start: planned Nov 29, 1962, actual Nov 29, 1962. Finish: planned 1970, actual Jan 21, 1976.
Cost overrun: +1025% ($16.7 billion over in 2025 dollars), in money of the day. Delay: 6 years (73% of the planned duration).
Official rebaseline: 1970 government estimate (June 1970 prices): £825 million (1970), so the outturn is +118% against it.
Britain and France signed a treaty on 29 November 1962 to jointly develop a supersonic airliner and share the cost equally. At signing, the British government put development at £150-170 million, with a first flight in 1966 and service in 1970. Prototype 001 flew from Toulouse on 2 March 1969, certification came in late 1975, and Air France and British Airways opened service on 21 January 1976. Through March 1976 the program had cost an estimated £1.5-2.1 billion in 1976 pounds.
Hansard records the estimate climbing in steps as the design matured: £150-170 million in November 1962, £450 million plus a £50 million contingency by early 1967, £730 million at October 1969 prices and £825 million at June 1970 prices. Ministers said later figures also covered work needed after certification, so part of the growth was scope that the first estimate omitted. Technical novelty was the main driver: Concorde was a Mach 2 airliner with no precedent, and the prototypes flew three years after the 1966 target. A binding intergovernmental treaty made cancellation diplomatically costly, so the program continued as costs rose. Inflation in the late 1960s and 1970s added to nominal totals, which is why the 1976 figure is several times larger in money terms than the real-terms growth alone. The BBC's Timewatch, cited by Wikipedia, said estimates had already gone from £70 million to £150 million by 1962. Engineering results were strong: the aircraft met its Mach 2 transatlantic mission and flew until 2003.
Prototype 001 made Concorde's first flight from Toulouse on 2 March 1969 with test pilot André Turcat at the controls.
Treaty and design definition: planned Nov 1962 – ?; actual Nov 29, 1962 – Feb 1965. Prototype construction: planned ? – 1966; actual Feb 1965 – Dec 1967. Prototype flight testing: planned 1966 – ?; actual Mar 2, 1969 – Oct 9, 1975. Certification: planned not published; actual Oct 9, 1975 – Dec 5, 1975. Entry into service: planned 1970 – 1970; actual Jan 21, 1976 – Jan 21, 1976.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006)
Saint-Nazaire, France · Vehicles and aircraft (ocean liner) · Over budget · Confidence: disputed
Chantiers de l'Atlantique built Queen Mary 2, the largest ocean liner ever, on schedule in about three years after a contract worth about $780 million.
Cost: planned $780 million (2000), actual $840 million (2003) ($1.46 billion planned and $1.47 billion actual in 2025 dollars). Start: planned Nov 6, 2000, actual Nov 6, 2000. Finish: planned Dec 2003, actual Dec 22, 2003.
Cost overrun: +8% ($105 million over in 2025 dollars), in money of the day. Delay: none.
Cunard, owned by Carnival Corporation, signed a contract with Alstom Chantiers de l'Atlantique on 6 November 2000 to build Queen Mary 2 at Saint-Nazaire for about $780 million, with service expected in late 2003. The keel was laid on 4 July 2002, the hull floated out on 21 March 2003 and sea trials ran that autumn. The ship left the yard on 22 December 2003 and sailed her maiden voyage from Southampton on 12 January 2004. Wikipedia states construction was completed on schedule.
The build met the late-2003 service date set at contract signing, and Wikipedia records that construction was completed on schedule. Hull assembly took under nine months from keel laying to float-out, leaving about nine months for fitting out and trials. The program's worst event was not a schedule or budget failure but a safety one: on 15 November 2003 a gangway to the ship collapsed into the dry dock, killing 16 people and injuring 32. Cost reporting is less clear than schedule. Carnival announced a cost of approximately $780 million in 2000; Travel Weekly reported £538 million at signing; a UK National Audit Office document gives about £550 million; and an earlier Wikipedia version listed £460 million (about $900 million). Wikipedia now gives a final cost of about $300,000 per berth. These figures suggest the final cost stayed close to the contract.
Queen Mary 2 remains the largest ocean liner ever built, as distinct from cruise ships.
Concept and tendering (Project Queen Mary): planned not published; actual Dec 1998 – Nov 6, 2000. Detailed design and block fabrication: planned Nov 2000 – ?; actual Nov 6, 2000 – Jul 4, 2002. Hull assembly in the building dock: planned not published; actual Jul 4, 2002 – Mar 21, 2003. Fitting out and sea trials: planned not published; actual Mar 21, 2003 – Dec 22, 2003. Delivery and maiden voyage: planned Dec 2003 – Jan 2004; actual Dec 22, 2003 – Jan 12, 2004.
From the history of managing work: Gantt charts at the Emergency Fleet Corporation (1917–1918)
Belfast, United Kingdom · Vehicles and aircraft (ocean liner) · Incomplete data · Confidence: medium
Harland & Wolff built Titanic for about £1.5 million, but repairs to her sister ship Olympic pushed the maiden voyage back three weeks, from 20 March to 10 April 1912.
Cost: planned £1.5 million (1908), actual cost not public. Start: planned Mar 31, 1909, actual Mar 31, 1909. Finish: planned Mar 20, 1912, actual Apr 10, 1912.
Cost overrun: cost not public. Delay: none.
White Star Line ordered Titanic from Harland & Wolff in Belfast as the second of three Olympic-class liners. Her keel was laid on 31 March 1909 beside Olympic under the Arrol Gantry, and she was launched on 31 May 1911. Fitting out took about a year. Work was slowed twice when the yard diverted labor and parts to repair Olympic, moving the maiden voyage from 20 March to 10 April 1912. A price of £3 million was agreed for the first two ships, about £1.5 million each; no separate final cost for Titanic was published.
The yard delivered two of the largest ships of their day almost in parallel, which required rebuilding its slipways: Harland & Wolff demolished three slipways to make two larger ones and built the Arrol Gantry, more than 6,000 tonnes of steel, over them. The contract was cost-plus: the builder was authorized to spend what it needed, plus extras and a five percent fee, which removed price pressure but also budget discipline. The schedule slipped because of resource sharing between sister ships. After HMS Hawke struck Olympic on 20 September 1911, the yard replaced Olympic's damaged propeller shaft with one made for Titanic; when Olympic lost a propeller blade on 24 February 1912, Titanic was moved out of the graving dock on 6 March to make room. Together these delayed the maiden voyage by three weeks. Wikipedia records eight deaths during construction and fitting out and 246 injuries. Four days into her maiden voyage, on 15 April 1912, Titanic sank after striking an iceberg.
The Arrol Gantry built over Titanic's slipway stood 228 feet (69 m) high and was 840 feet (260 m) long.
Design and agreement: planned not published; actual Jul 31, 1908 – Mar 31, 1909. Hull construction on the slipway: planned Mar 31, 1909 – ?; actual Mar 31, 1909 – May 31, 1911. Fitting out: planned May 31, 1911 – ?; actual May 31, 1911 – Mar 31, 1912. Graving dock work: planned not published; actual Feb 3, 1912 – Mar 6, 1912. Sea trials and maiden voyage: planned ? – Mar 20, 1912; actual Apr 2, 1912 – Apr 10, 1912.
From the history of managing work: Henry Gantt charts work against time (c. 1910–1915), The Principles of Scientific Management (1911), Gantt charts at the Emergency Fleet Corporation (1917–1918)
Fremont, United States · Vehicles and aircraft (car production line) · Late · Confidence: medium
Tesla planned to build 5,000 Model 3s a week by December 2017; it built 2,425 in the whole fourth quarter and reached 5,031 in a week only at the end of June 2018.
Cost: planned $2.25 billion (2017), actual cost not public. Start: planned Jul 2017, actual Jul 2017. Finish: planned Dec 2017, actual Jun 30, 2018.
Cost overrun: cost not public. Delay: 7 months (130% of the planned duration).
Tesla unveiled the Model 3 on 31 March 2016 and began limited production in July 2017, handing over the first cars on 28 July. In its Q2 2017 letter the company said it would reach a run rate of 5,000 vehicles a week by the end of 2017, after spending an expected $2-2.5 billion in capital before production. Output in Q4 2017 was 2,425 cars. Tesla pushed the target to the end of Q2 2018 and produced 5,031 Model 3s in the last seven days of that quarter.
Tesla chose in 2016 to accelerate the build plan, a decision Wikipedia notes led to the predicted 'production bottlenecks' and 'production hell'. The plan assumed that a new car, new battery module lines at the Nevada Gigafactory and a new assembly process would all ramp together. They did not: CNBC reported in February 2018 that battery-line constraints at the Gigafactory were holding back output, and Q3 2017 production fell far short of the 1,500-car guidance. In January 2018 Tesla reset the schedule to about 2,500 a week by the end of Q1 and 5,000 by the end of Q2. To hit the second target it added a new general assembly line, GA4, which its 2 July 2018 release said built about 20% of Model 3s in the final week. The goal was met six months late, and Tesla then guided to 6,000 a week.
In Q2 2018 Tesla built more Model 3s (28,578) than Model S and Model X combined (24,761) for the first time.
Unveiling and pre-production: planned Mar 31, 2016 – Jul 2017; actual Mar 31, 2016 – Jul 2017. Production launch: planned Jul 2017 – Sep 2017; actual Jul 2017 – Sep 2017. Ramp to 5,000 per week (original plan): planned Oct 2017 – Dec 2017; actual Oct 2017 – Dec 31, 2017. Revised ramp and GA4 line: planned Jan 2018 – Jun 30, 2018; actual Jan 2018 – Jun 30, 2018.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Toyota's kanban and the pull system (1948–1953)
Tokyo, Japan · Vehicles and aircraft (high-speed rail) · Over budget · Confidence: medium
The Tōkaidō Shinkansen opened on time for the 1964 Tokyo Olympics, but cost about ¥380 billion against a ¥194.8 billion estimate, and its two leaders resigned.
Cost: planned ¥195 billion (1958), actual ¥380 billion (1964) ($6.04 billion planned and $10.9 billion actual in 2025 dollars). Start: planned Apr 20, 1959, actual Apr 20, 1959. Finish: planned Oct 1964, actual Oct 1, 1964.
Cost overrun: +95% ($5.31 billion over in 2025 dollars), in money of the day. Delay: none.
Japanese National Railways began building a new standard-gauge line between Tokyo and Osaka on 20 April 1959 under president Shinji Sogō and chief engineer Hideo Shima. The 1958 estimate was ¥172.5 billion, or ¥194.8 billion including interest, and a World Bank loan of $80 million covered about 15 percent. The line opened on 1 October 1964, ahead of the Tokyo Olympics, after about five and a half years. Final cost was about ¥380 billion, almost double the estimate.
The schedule held because the Olympic opening on 10 October 1964 was a fixed, public deadline and JNR proved the technology early on a 37 km model line, where a train reached 256 km/h in March 1963. The budget did not hold. Wikipedia's biography of Sogō, citing Christopher Hood's history of the Shinkansen, says he kept estimated costs 'deliberately low' because he feared a realistic figure would lose government and World Bank support. When the shortfall appeared, he diverted resources from other JNR projects; once that became a political issue, he resigned in 1963 and Shima left with him. The World Bank loan also had conditions: it could not be used for experimental technology, which pushed JNR to present the line as proven engineering. The cost overrun did not prevent the line from becoming commercially successful, and the model was copied by high-speed networks worldwide.
On 30 March 1963 a test train on the Kamonomiya model line reached 256 km/h, a Japanese rail speed record at the time.
Approval and authorization: planned Dec 1958 – Apr 1959; actual Dec 1958 – Apr 13, 1959. Civil construction: planned Apr 20, 1959 – 1964; actual Apr 20, 1959 – Jul 1, 1964. World Bank financing: planned May 1960 – ?; actual May 1960 – May 1961. Model line testing: planned not published; actual Jun 1962 – Jul 1964. Opening: planned Oct 1964 – Oct 1964; actual Oct 1, 1964 – Oct 1, 1964.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Toyota City, Japan · Vehicles and aircraft (hybrid car) · Incomplete data · Confidence: medium
Toyota's management pulled the Prius launch forward by a year, from the end of 1998 to December 1997, and the world's first mass-produced hybrid went on sale on 10 December 1997.
Cost: planned cost not public, actual cost not public. Start: planned Sep 1993, actual Sep 1993. Finish: planned Dec 1998, actual Dec 10, 1997.
Cost overrun: cost not public. Delay: 12 months early.
Toyota's G21 project began as a study group in September 1993 to define a car for the 21st century, led from 1994 by chief engineer Takeshi Uchiyamada. The team chose a hybrid drivetrain and showed a concept at the October 1995 Tokyo Motor Show. The original target was sales and production by the end of 1998, but management accelerated the program by a year. The NHW10 Prius went on sale in Japan on 10 December 1997, built at the Takaoka plant.
The Prius is a rare case of a program that finished earlier than its plan. Toyota's own 2017 history says management decided to bring the launch forward by a year to December 1997, the month of the COP3 climate conference in Kyoto, which gave the target a fixed external date. The engineering risk was high: the first production-hybrid prototype, assembled in early November 1995, took 49 days to get running and then stopped after about 500 meters. Toyota reorganized, naming veteran engineer Takehisa Yaegashi to lead the hybrid system team in March 1996, and worked with production engineering in parallel through simultaneous engineering. Wikipedia says the team reviewed more than 100 hybrid layouts before choosing one. President Hiroshi Okuda committed publicly at a 25 March 1997 briefing. The trade-off was financial: Wikipedia reports Toyota executives said the company lost money on each first-generation car and broke even only with the NHW11 that followed.
Launch orders for the first Prius reached 3,500 cars in the first month, three times Toyota's target.
G21 study and concept definition: planned Sep 1993 – ?; actual Sep 1993 – Dec 1994. Concept car and first prototype: planned ? – Oct 1995; actual Jan 1995 – Dec 1995. Hybrid system engineering and test driving: planned not published; actual Mar 1996 – Oct 1997. Public announcement and production preparation: planned ? – Dec 1998; actual Mar 25, 1997 – Dec 1997. Japan launch: planned Dec 1998 – Dec 1998; actual Dec 10, 1997 – Dec 10, 1997.
From the history of managing work: Toyota's kanban and the pull system (1948–1953), The New New Product Development Game (1986)
Flamanville, Manche, Normandy, France · Energy (nuclear plant) · Over budget and late · Confidence: medium
France's first EPR was budgeted at EUR 3.3bn for 2012; the Cour des comptes puts its full cost at EUR 23.7bn and it reached the grid 12 years late.
Cost: planned €3.3 billion (2006), actual €23.7 billion (2023) ($6.62 billion planned and $27.1 billion actual in 2025 dollars). Start: planned Dec 2007, actual Dec 4, 2007. Finish: planned 2012, actual Dec 21, 2024.
Cost overrun: +618% ($23.3 billion over in 2025 dollars), in money of the day. Delay: 13 years (274% of the planned duration).
Flamanville 3 is a 1,650 MW EPR reactor built by EDF on the Normandy coast. Construction began in December 2007 with an initial budget of EUR 3.3 billion and commercial operation planned for 2012. After vessel steel anomalies, weld defects and repeated re-baselining, it was connected to the grid on 21 December 2024 and reached full power in December 2025. France's audit court, the Cour des comptes, estimated the full cost at EUR 19.1 billion (2015 euros) in 2020 and EUR 23.7 billion (2023 euros) in January 2025.
The Cour des comptes' 2020 report on the EPR program and its January 2025 follow-up describe a first-of-a-kind project started before French industry had built a reactor for about 15 years, with loss of skills in the supply chain and design work not mature when construction began. Quality failures then drove most of the delay. In April 2015 Areva disclosed that steel in the reactor vessel head and bottom had lower-than-expected mechanical toughness, triggering a long regulatory review. In June 2019 the regulator required eight welds on the main steam lines, which pass through the containment, to be repaired before start-up, and more than 100 defective welds were eventually identified. Each problem forced a new schedule and budget. The audit court's 2025 figure of EUR 20.4bn in 2015 euros, or EUR 23.7bn in 2023 euros, includes financing costs and is EUR 1.3bn above its 2020 estimate; EDF's own figure is EUR 19.3bn (2015 euros). The court calculated that a 4% return would require selling power at more than EUR 122/MWh.
Fuel loading took just two weeks in May 2024, after more than 16 years of construction.
Civil works and reactor building: planned Dec 2007 – ?; actual Dec 4, 2007 – Apr 2015. Component anomalies and repairs: planned not published; actual Apr 2015 – May 2024. Fuel loading and start-up: planned ? – 2012; actual May 8, 2024 – Sep 2024. Grid connection and power ascension: planned not published; actual Dec 21, 2024 – Dec 14, 2025. Commercial operation: planned ? – 2012; actual Dec 14, 2025 – May 5, 2026.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Bridgwater, Somerset, United Kingdom · Energy (nuclear plant) · Over budget and late · Confidence: medium
Hinkley Point C was presented in 2012 as a GBP 16bn plant generating by 2023; EDF now expects about GBP 35bn in 2015 prices and Unit 1 in 2030.
Cost: planned £16 billion (2012), actual £35 billion (2015) (forecast) ($35.6 billion planned and $72.6 billion actual in 2025 dollars). Start: planned Sep 2016, actual Mar 2017. Finish: planned 2023, actual 2030 (forecast).
Cost overrun: +119% ($39.4 billion over in 2025 dollars), in money of the day. Delay: 7 years (103% of the planned duration).
Official rebaseline: 2016 final investment decision: £18 billion (2015), so the outturn is +94% against it; a revised finish of Dec 2025, 5 years late against it.
Hinkley Point C is a two-reactor, 3.2 GW EPR nuclear station being built by EDF with China General Nuclear in Somerset, England. At the September 2016 go-ahead it was priced at GBP 18 billion in 2015 money, with first power from Unit 1 expected at the end of 2025. Successive updates raised the estimate to GBP 22-23bn (2021), GBP 25-26bn (2022), GBP 31-35bn (2024) and GBP 35bn (February 2026), with Unit 1 now forecast for 2030. Construction costs are borne by EDF and CGN, not taxpayers.
Hinkley Point C is the UK's first new nuclear station in a generation and uses the EPR design, which had already overrun at Olkiluoto 3 and Flamanville 3. EDF has attributed the increases to first-of-a-kind engineering in a UK regulatory context, the scale of design adaptation, Covid-19 disruption to labor and supply chains, and inflation in materials and labor. In September 2019 EDF said ground conditions and the cost of reaching design maturity would add up to GBP 2.9bn. A 15-month risk to Unit 1 followed in 2023. The National Audit Office concluded in June 2017 that the government had locked consumers into 'a high cost and risky deal', with expected top-up payments under the contract for difference rising from GBP 6bn to GBP 30bn as wholesale price forecasts fell; it could not say the department had maximized value for money. Because construction risk sits with EDF and CGN, the overruns have hit EDF's balance sheet, including a EUR 2.5bn write-down announced in February 2026. Progress milestones have still been met: both reactor domes are in place.
Once running, the two reactors are expected to supply about 7% of the UK's electricity consumption.
Commercial deal and final investment decision: planned not published; actual Oct 2013 – Sep 15, 2016. Site works and nuclear island foundations: planned Sep 2016 – ?; actual Mar 2017 – Jun 2020. Reactor buildings and dome lifts: planned not published; actual Jun 2020 – Jul 17, 2025. Mechanical, electrical and commissioning (Unit 1): planned ? – 2023; actual Dec 15, 2023 – 2030.
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979)
Boulder City, Nevada / Black Canyon, United States · Energy (hydroelectric dam) · On time and on budget · Confidence: medium
Six Companies had seven years to build Hoover Dam and handed it over in under five, about two years early.
Cost: planned $165 million (1928), actual $140 million (1939) ($3.09 billion planned and $3.24 billion actual in 2025 dollars). Start: planned Apr 20, 1931, actual Apr 20, 1931. Finish: planned Apr 20, 1938, actual Mar 1, 1936.
Cost overrun: -15% ($579 million under in 2025 dollars), in money of the day. Delay: 2 years early.
Hoover Dam, built in Black Canyon on the Colorado River between Nevada and Arizona, was authorized by the Boulder Canyon Project Act of December 1928 with a $165 million appropriation. The Six Companies consortium won the dam contract in 1931 with a bid of about $48.9 million and seven years to finish. The river was diverted in November 1932, concrete placement ran from June 1933 to May 1935, and the government accepted the completed works on 1 March 1936, roughly two years ahead of the contract deadline.
The schedule was beaten mainly through contractor incentives and an aggressive, highly organized work plan. The contract gave Six Companies seven years from 20 April 1931 and imposed penalties for delay, so every month saved reduced the consortium's overhead and raised its margin. The Great Depression supplied an abundant labor pool: about 21,000 people worked on the job in total, with an average of 3,500 a day and a peak of 5,218 in June 1934. Construction was also accelerated deliberately to create jobs. The river was diverted almost a year before the contractual date of October 1933, which let foundation work and concrete placement start early. Concrete was poured in interlocking columns cooled by embedded pipes, allowing placement rates of up to 275,000 cubic yards in a month. The speed came at a human cost: 112 deaths were reported in connection with the project, and the camp conditions in 1931 led to a strike. Cost comparisons are approximate because the $165 million appropriation covered the wider Boulder Canyon Project, including the All-American Canal.
On its busiest day the project placed 10,462 cubic yards of concrete, according to the US Bureau of Reclamation.
Authorization and contract award: planned Dec 21, 1928 – ?; actual Dec 21, 1928 – Mar 1931. River diversion tunnels: planned Apr 20, 1931 – Oct 1, 1933; actual 1931 – Nov 13, 1932. Cofferdams and foundation excavation: planned not published; actual Sep 1932 – Jun 6, 1933. Concrete placement: planned not published; actual Jun 6, 1933 – May 29, 1935. Dedication and completion of all features: planned ? – Apr 20, 1938; actual Sep 30, 1935 – Mar 1, 1936. Power generation start: planned not published; actual Mar 1, 1936 – Sep 11, 1936.
From the history of managing work: Scheduling the Hoover Dam (1931–1936), Henry Gantt charts work against time (c. 1910–1915), The Principles of Scientific Management (1911)
Foz do Iguaçu / Hernandarias, Brazil · Energy (hydroelectric dam) · Over budget · Confidence: disputed
Itaipu was first costed at about US$2.7bn; it ended up at roughly US$19.6bn, and its debt took 50 years and US$63.5bn to repay.
Cost: planned $2.7 billion (1973), actual $19.6 billion (1991) ($19.6 billion planned and $46.3 billion actual in 2025 dollars). Start: planned 1975, actual Jan 1975. Finish: planned not published, actual 1991.
Cost overrun: +626% ($39.9 billion over in 2025 dollars), in money of the day. Delay: not known.
Itaipu is a 14 GW hydroelectric dam on the Paraná River, owned equally by Brazil and Paraguay through Itaipu Binacional under a treaty signed in April 1973. Construction started in 1975, the river was diverted in 1978, the reservoir filled in October 1982 and the first unit ran in May 1984. The 18th unit entered service in 1991 and two more followed in 2006-2007. An early estimate of about US$2.7 billion grew to a reported US$19.6 billion; debt service totaled US$63.5 billion by February 2023.
The main driver of cost growth was scope change. According to former Itaipu director Jorge Ayala Kunzle, the pre-1973 estimate of about US$2.7bn assumed 14 smaller turbines; the design grew to 18 large units with provision for two reserves, because planners judged that water, materials and energy demand justified it, and the plant finished with 20 units. Financing was the second driver: the binational entity was built almost entirely on borrowed money, raised through more than 300 financing contracts with about 70 creditors and guaranteed by Brazil's Treasury, during the high-interest, high-inflation 1970s and 1980s. Of the US$63.5bn eventually paid, about US$27.9bn was financial charges. The scheme was technically successful: units were commissioned at two to three per year and the plant became one of the world's largest producers of electricity. The debt calculations were never officially audited, and some Paraguayan groups dispute part of it. Resettlement of about 10,000 families and the flooding of the Guaíra falls were part of the project scope.
Itaipu made its final construction-debt payment, US$115 million, in February 2023, almost 50 years after the treaty was signed.
Treaty and binational entity: planned not published; actual Apr 26, 1973 – Jan 1975. River diversion and excavation: planned 1975 – ?; actual Jan 1975 – Oct 14, 1978. Main dam and powerhouse construction: planned not published; actual Oct 14, 1978 – Oct 13, 1982. Reservoir filling: planned not published; actual Oct 13, 1982 – Oct 27, 1982. Installation of first 18 generating units: planned not published; actual May 5, 1984 – 1991. Units 19 and 20: planned not published; actual Sep 2006 – Mar 2007.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979)
Saint-Paul-lès-Durance, France · Energy (fusion reactor) · Over budget and late · Confidence: disputed
Signed in 2006 at an estimated EUR 5.9bn with first plasma due in 2016, ITER now expects research operation in 2034 after cost estimates passed EUR 20bn.
Cost: planned €5.9 billion (2008), actual €20 billion (2016) (forecast) ($13 billion planned and $29.7 billion actual in 2025 dollars). Start: planned 2007, actual Oct 24, 2007. Finish: planned 2016, actual 2034 (forecast).
Cost overrun: +239% ($20.9 billion over in 2025 dollars), in money of the day. Delay: 18 years (200% of the planned duration).
Official rebaseline: April 2016 ITER Council cost assessment: €20 billion (2016), so the outturn is 0% against it.
ITER is a seven-member international fusion experiment under construction at Saint-Paul-lès-Durance in southern France, hosted by the EU and funded largely through in-kind component contributions. The 2006 agreement was based on an estimated EUR 5.9 billion (2008 prices) over ten years and first plasma in 2016. The 2016 re-baseline put the cost at about EUR 20 billion and first plasma at December 2025. The 2024 baseline moved start of research operation to 2034 and deuterium-tritium operation to 2039, adding about EUR 5 billion.
The European Parliament's research service records three resets: a 2008 design review raised the estimate to about EUR 19bn and moved first plasma to 2019; the April 2016 Council baseline set about EUR 20bn and December 2025; and Baseline 2024, presented by Director-General Pietro Barabaschi, moved research operation to 2034. Causes include technical novelty, since ITER is a first-of-a-kind machine; an immature design at the time of the agreement; and a procurement model in which members supply components in kind from factories in many countries, making integration and quality control hard and total cost difficult to state. In 2022, cracks were found in cooling pipes of the thermal shields and dimensional problems in vacuum vessel sectors, requiring repairs, and the French nuclear safety authority briefly halted assembly over radiological shielding. Covid-19 disrupted supply chains. The European Court of Auditors found the EU's post-2020 construction funding need was EUR 5.4bn above the amount already committed. Barabaschi declined in 2024 to give a total cost because of the in-kind funding structure.
Europe, as host, pays almost half of ITER's construction cost; the other six members share the rest equally.
Agreement and organization set-up: planned not published; actual Nov 21, 2006 – Oct 24, 2007. Site preparation and excavation: planned 2007 – ?; actual 2008 – 2013. Tokamak complex construction and component manufacturing: planned not published; actual 2013 – Jul 28, 2020. Machine assembly: planned ? – 2016; actual Jul 28, 2020 – 2033. Start of research operation (forecast): planned 2016 – ?; actual 2034 – ?. Deuterium-tritium operation (forecast): planned not published; actual 2039 – ?.
From the history of managing work: The work breakdown structure (1962), Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Eurajoki, Finland · Energy (nuclear plant) · Over budget and late · Confidence: medium
Finland's first EPR was sold as a EUR 3bn fixed-price turnkey job due in 2009; it entered commercial operation in 2023 at an estimated EUR 11bn.
Cost: planned €3 billion (2003), actual €11 billion (2023) ($5.94 billion planned and $12.6 billion actual in 2025 dollars). Start: planned 2005, actual Aug 12, 2005. Finish: planned May 2009, actual May 1, 2023.
Cost overrun: +267% ($9.15 billion over in 2025 dollars), in money of the day. Delay: 14 years (361% of the planned duration).
Olkiluoto 3 is a 1,600 MWe EPR reactor at Eurajoki on Finland's west coast, ordered by utility TVO from an Areva-Siemens consortium under a fixed-price turnkey contract of about EUR 3 billion signed in December 2003. Construction began in August 2005 with commercial operation planned for May 2009. First criticality came in December 2021, grid connection in March 2022, and commercial operation on 1 May 2023, 14 years late. Total cost is estimated at about EUR 11 billion, split roughly equally between TVO's investment and Areva's losses.
Olkiluoto 3 was the first EPR to start construction anywhere, and Finland's nuclear regulator STUK identified the core causes in a 2010 review. The original schedule was overly ambitious for a first-of-a-kind plant larger than any previous reactor; design and engineering were not sufficiently complete when construction began; there was a shortage of experienced designers; the parties lacked experience managing a project of this size; and there was a worldwide shortage of qualified nuclear equipment suppliers. The fixed-price turnkey contract did not stop the delays but moved most of the overrun onto the vendor: Areva is reported to have absorbed about EUR 5.5bn in losses while TVO invested about EUR 5.5bn. Years of disputes ended in a 2018 settlement under which Areva paid TVO EUR 450m in compensation. Late-stage commissioning added further slippage, including foreign material found in the turbine steam reheater in May 2022. Regular production finally began on 16 April 2023, about 18 years after construction started.
Regular electricity production began on 16 April 2023, almost exactly 14 years after the original May 2009 target.
Contract and licensing: planned not published; actual Dec 19, 2003 – Feb 7, 2005. Civil construction and installation: planned 2005 – May 2009; actual Aug 12, 2005 – Mar 2021. Fuel loading and first criticality: planned not published; actual Mar 2021 – Dec 21, 2021. Test production: planned not published; actual Mar 12, 2022 – Apr 16, 2023. Regular and commercial operation: planned ? – May 2009; actual Apr 16, 2023 – May 1, 2023.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Kosciuszko National Park, Snowy Mountains, NSW, Australia · Energy (pumped hydro storage) · Over budget and late · Confidence: medium
Snowy 2.0 was floated at about A$2bn in 2017; the official cost to complete is now A$12bn and full operation has slipped to at least December 2028.
Cost: planned A$2 billion (2017), actual A$12 billion (2023) (forecast) ($2.02 billion planned and $8.42 billion actual in 2025 dollars). Start: planned 2018, actual 2019. Finish: planned 2024, actual Dec 2028 (forecast).
Cost overrun: +500% ($7.02 billion over in 2025 dollars), in money of the day. Delay: 5 years (74% of the planned duration).
Official rebaseline: August 2023 Snowy Hydro project reset: A$12 billion (2023), so the outturn is 0% against it; a revised finish of Dec 2028, met.
Snowy 2.0 links the Tantangara and Talbingo reservoirs in Kosciuszko National Park with tunnels and an underground power station to create a 2,200 MW pumped-storage scheme. Announced in early 2017 at a rough A$2 billion, it was costed at A$3.8-4.5 billion in the December 2017 feasibility study and awarded as a A$5.1 billion main contract. Snowy Hydro's August 2023 reset set a A$12 billion cost to complete, first power in late 2027 and all units operating by December 2028. Transmission is extra.
Snowy Hydro itself named the causes when it reset the project on 31 August 2023. Project-specific: the design was immature at final investment decision, complex elements cost more to build than estimated, and site and geological conditions varied, most notably the soft ground that trapped tunnel boring machine Florence near Tantangara for about 19 months and opened a sinkhole above the tunnel in December 2022. External: pandemic disruption, labor shortages worsened by quarantine and movement restrictions, shipping and supply-chain delays, and rising material and labor costs. The initial A$2bn figure was a political estimate made before a feasibility study; that study, released in December 2017, already put the cost at A$3.8-4.5bn, and the main contract alone came in about 35 percent above the top of that range, partly because it included escalation over eight years. The completion date has been reset several times. By October 2025 the scheme was reported to be about 67 percent complete and unlikely to finish within the A$12bn forecast.
Tunnel boring machine Florence, named after Florence Violet McKenzie, spent about 19 months stuck in soft ground near Tantangara.
Announcement and feasibility study: planned not published; actual Mar 2017 – Dec 21, 2017. Contract award and approvals: planned 2018 – ?; actual 2018 – 2019. Early works and tunneling: planned not published; actual 2019 – Jul 11, 2024. Project reset: planned not published; actual May 2023 – Aug 31, 2023. Power station, waterways and first power (forecast): planned ? – 2024; actual Aug 31, 2023 – Dec 2027. Commercial operation of all units (forecast): planned ? – 2024; actual Dec 2027 – Dec 2028.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Sandouping, Yichang, Hubei, China · Energy (hydroelectric dam) · Late · Confidence: disputed
The world's largest power station came in at about 203 billion yuan against an initial budget of 203.9 billion, but full operation slipped three years to 2012.
Cost: planned CN¥204 billion (1994), actual CN¥203 billion (2012) ($51.2 billion planned and $45.1 billion actual in 2025 dollars). Start: planned Dec 14, 1994, actual Dec 14, 1994. Finish: planned 2009, actual Jul 2012.
Cost overrun: 0% ($200 million under in 2025 dollars), in money of the day. Delay: 3 years (21% of the planned duration).
Official rebaseline: revised official estimate (cited 2000-2001): CN¥180 billion, so the outturn is +13% against it.
The Three Gorges Dam on the Yangtze at Sandouping, Hubei, was approved by the National People's Congress in 1992 and officially started on 14 December 1994. Its 2003 reservoir filling and first generator were followed by dam-body completion in 2006 and full operation of all main units in July 2012, three years after the 2009 target. The initial budget was 203.9 billion yuan; reported final cost is about 203 billion yuan. Relocation of roughly 1.24 million or more residents was a major cost and scope item.
On cost, official figures show the project close to or under its initial budget. Xinhua reported in 2000 that the original 203.9 billion yuan budget assumed price inflation of 5 to 10 percent a year; when prices fell in the late 1990s, low inflation alone saved more than 14 billion yuan, and low interest rates also helped, so the developer said the dam would cost no more than 180 billion yuan. By the end of 2008, dynamic investment stood at 181.5 billion yuan. Later reported totals, around 203 billion yuan, include later works. On schedule, the main dam and first power in 2003 kept broadly to plan, but full operation of all generating units slipped from 2009 to 2012, and the ship lift was not complete until 2016. Resettlement was the largest non-engineering scope item: about 1.24 million people had been relocated by 2008, and a 2001 report noted 310 cases of misuse of relocation funds. Because official figures mix static and dynamic bases and several budgets were published, the true overrun is disputed, especially by foreign analysts who estimated much higher totals.
At the 1992 National People's Congress vote, 664 delegates abstained and 177 voted against, an unusually large dissent for that body.
Approval and preparation: planned not published; actual Apr 3, 1992 – Dec 14, 1994. Main works to first power: planned Dec 14, 1994 – ?; actual Dec 14, 1994 – Jul 10, 2003. Dam body completion: planned not published; actual Jul 10, 2003 – May 20, 2006. Remaining generating units: planned ? – 2009; actual May 20, 2006 – Jul 2012. Ship lift: planned not published; actual Oct 2007 – Jan 2016. Resettlement and final acceptance: planned not published; actual 1993 – Nov 1, 2020.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Johannesburg (Soccer City), South Africa · Events (football world cup) · Over budget · Confidence: medium
South Africa's World Cup stadiums cost the state about R11.7 billion, some 39 percent more than the R8.4 billion expected in 2006.
Cost: planned R8.4 billion (2006), actual R11.7 billion (2010) ($1.98 billion planned and $2.36 billion actual in 2025 dollars). Start: planned May 15, 2004, actual May 15, 2004. Finish: planned Jun 11, 2010, actual Jun 11, 2010.
Cost overrun: +39% ($667 million over in 2025 dollars), in money of the day. Delay: none.
South Africa won the 2010 FIFA World Cup in May 2004, the first held in Africa. Five stadiums were built and five upgraded in nine host cities, including Soccer City in Johannesburg, Moses Mabhida in Durban and Cape Town Stadium at Green Point. All were ready by December 2009, despite a national construction strike in July 2009. National Treasury data put public stadium spending at R11.7 billion for 2005-2010, against an R8.4 billion estimate in 2006.
The stadium programme met FIFA's fixed deadline. Soccer City's upgrade was finished on October 21, 2009, Moses Mabhida opened on November 28, 2009 and Cape Town Stadium on December 14, 2009, six months before kick-off. Cost was another matter. In October 2006 stadium construction was expected to cost R8.4 billion. National Treasury figures compiled by du Plessis and Venter (Stellenbosch University, 2010) show public stadium expenditure of R11.7 billion between 2005 and 2010, out of R33.7 billion of public spending directly tied to the tournament. Individual venues escalated faster. Nelson Mandela Bay Stadium in Port Elizabeth rose from an estimated R711 million in June 2006 to R1.5 billion by May 2008 and a completed cost of about R2.065 billion, leaving local ratepayers to cover a shortfall under the national-provincial-municipal cost split. A strike by about 70,000 stadium workers on July 8, 2009 added schedule pressure late in the programme. Treasury data show that stadium spending was only R0.7 billion by the end of 2006 and peaked at R4.4 billion in 2008, so nearly all of the cost was committed after the 2006 estimate.
The Nelson Mandela Bay Stadium's cost rose from an estimated R711 million in June 2006 to about R2.065 billion on completion (Wikipedia, citing The Herald, July 14, 2010).
Bid and award: planned ? – May 15, 2004; actual 2003 – May 15, 2004. Stadium planning and budgeting: planned not published; actual 2005 – Oct 2006. Stadium construction (5 new, 5 upgraded): planned ? – Dec 2009; actual Jan 2007 – Dec 14, 2009. Test event (Confederations Cup): planned Jun 2009 – Jun 2009; actual Jun 2009 – Jun 2009. Tournament: planned Jun 11, 2010 – Jul 11, 2010; actual Jun 11, 2010 – Jul 11, 2010.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023)
Athens, Greece · Events (olympics) · Over budget · Confidence: disputed
Athens 2004 opened on time, but government and organizing costs grew from about EUR 3 billion to near EUR 9 billion.
Cost: planned €3 billion (2000), actual €9 billion (2004) ($5.18 billion planned and $19.1 billion actual in 2025 dollars). Start: planned Sep 5, 1997, actual Sep 5, 1997. Finish: planned Aug 13, 2004, actual Aug 13, 2004.
Cost overrun: +200% ($12.7 billion over in 2025 dollars), in money of the day. Delay: none.
Athens won the 2004 Games in September 1997, seven years after losing the centenary Games to Atlanta. Preparation was slow, and venues were finished in a rush: the main stadium, with Santiago Calatrava's roof, was completed two months before the August 13 opening. According to PwC figures reported by the BBC, the government budget rose from EUR 2.5 billion to EUR 4.6 billion and operating costs from EUR 0.5 billion to EUR 2 billion. The state put the total near EUR 9 billion.
The Games were delivered on time, but the final years became a race against the opening date. By late March 2004 several projects were behind schedule, and the planned roof over the Aquatics Centre was dropped. The Olympic Stadium, refurbished from 2002 to 2004 with Calatrava's steel-and-glass roof, was completed only about two months before the opening. In June 2004 the BBC, citing PricewaterhouseCoopers, reported that the government's Games budget had grown from EUR 2.5 billion to EUR 4.6 billion and organizing costs from EUR 0.5 billion to EUR 2 billion. It added that the new government accused its predecessor of 'losing control' of spending, and that items such as EUR 1.3 billion of transport work and the EUR 600 million athletes' village were not counted. The state later put the total near EUR 9 billion, and a 2013 Finance Ministry report put it at EUR 8.5 billion, of which about EUR 2 billion was covered by ATHOC revenue. On sports-related costs alone, Oxford researchers measured a 49 percent real overrun, low by Olympic standards. The large gap between that figure and the headline totals is mostly a question of scope.
The Athens organizing committee (ATHOC) wound up in 2005 with a surplus of EUR 130.6 million, even as the state's Games bill neared EUR 9 billion (Wikipedia, citing ATHOC and the Greek government).
Bid and award: planned ? – Sep 5, 1997; actual 1996 – Sep 5, 1997. Venue and infrastructure construction: planned ? – Aug 13, 2004; actual 2000 – Aug 2004. Olympic Stadium renovation (Calatrava roof): planned not published; actual 2002 – Jun 2004. Games: planned Aug 13, 2004 – Aug 29, 2004; actual Aug 13, 2004 – Aug 29, 2004. Wind-up and cost accounting: planned not published; actual Aug 30, 2004 – Jan 18, 2013.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Barcelona, Spain · Events (olympics) · Over budget · Confidence: medium
Barcelona's sports-related Olympic costs ran 266 percent over the bid in real terms, to US$9.7 billion in 2015 dollars, but the Games are widely seen as a model of urban regeneration.
Cost: planned $2.65 billion (2015), actual $9.69 billion (2015) ($3.6 billion planned and $13.2 billion actual in 2025 dollars). Start: planned Oct 17, 1986, actual Oct 17, 1986. Finish: planned Jul 25, 1992, actual Jul 25, 1992.
Cost overrun: +266% ($9.56 billion over in 2025 dollars), in constant prices. Delay: none.
Barcelona, home city of IOC president Juan Antonio Samaranch, won the 1992 Games in October 1986 and used them to drive a wider renewal of the city. The Games opened on time on July 25, 1992. The Oxford Olympics Study puts sports-related costs at US$9.7 billion in 2015 dollars, 266 percent over the bid in real terms and the second-highest Summer Games total before London. Spending on general infrastructure was about eight times the sports spending.
Barcelona is the standard example of a costly Games that most observers still count as a success. On cost, Oxford researchers measured a 266 percent real overrun on sports-related costs against the bid, second only to Montreal among the Summer Games in their 2016 dataset, with an outturn of US$9.7 billion in 2015 dollars. Part of the explanation is scope: the city treated the Games as a lever for long-planned urban renewal, so the Olympic program grew well beyond the venues. Baade and Matheson, cited by Flyvbjerg, Budzier and Lunn, found that Barcelona's general infrastructure spending, on roads, the waterfront and similar works, was about eight times its sports infrastructure spending. Those wider costs fall outside the overrun figure. On benefits, the infrastructure investment is credited with improving quality of life and raising the city's attraction for tourism and investment, and Barcelona is often cited as a case of hosting transforming a city. For a project manager the record is mixed. The schedule held to a fixed date, but the bid budget was not a reliable forecast, and the 'success' judgment rests on benefits that the original estimate never priced.
For Barcelona 1992, general infrastructure cost about eight times as much as sports infrastructure (Baade and Matheson, cited in Flyvbjerg, Budzier & Lunn 2020).
Bid and award: planned ? – Oct 17, 1986; actual 1981 – Oct 17, 1986. Venue construction (Montjuic and other areas): planned ? – Jul 25, 1992; actual 1986 – Jul 1992. Games: planned Jul 25, 1992 – Aug 9, 1992; actual Jul 25, 1992 – Aug 9, 1992.
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Milan (Rho-Pero), Italy · Events (world's fair) · On time and on budget · Confidence: disputed
Expo 2015 opened on its fixed date of May 1, 2015, and its organizing company spent EUR 2.25 billion from 2009 to 2015.
Cost: planned €3.2 billion (2008), actual €2.25 billion (2015) ($7.05 billion planned and $3.4 billion actual in 2025 dollars). Start: planned Mar 31, 2008, actual Mar 31, 2008. Finish: planned May 1, 2015, actual May 1, 2015.
Cost overrun: -29% ($1.43 billion under in 2025 dollars), in money of the day. Delay: none.
Official rebaseline: September 2012 revised plan: €3.02 billion (2012), so the outturn is -25% against it.
Milan won the right to host the 2015 World Expo in March 2008, beating Izmir, with the theme 'Feeding the Planet, Energy for Life'. A public company, Expo 2015 S.p.A., led by Giuseppe Sala, built a 1.1 square km site at Rho-Pero, north-west of Milan. Delivery was slowed by land disputes and disrupted by 2014 corruption arrests, but the Expo opened on May 1, 2015 and drew about 22.2 million visits. The company's costs totalled EUR 2.2547 billion.
Expo 2015 met its immovable deadline, but the run-up was difficult. The site land was privately owned, split between Fondazione Fiera Milano and the Cabassi family, and a long dispute between institutions ended only with the creation of the public land company Arexpo from 2011. That shortened the time left for construction. In 2014 a Milan anti-corruption investigation into Expo contracts led to several arrests, and the government put procurement under the oversight of anti-corruption commissioner Raffaele Cantone. Some countries pulled out, Canada and Australia citing budget limits, and Bulgaria cited delays. On the delivery side, the master plan was simplified from a 'classical' site of pavilions to a lighter layout along two axes modeled on a Roman cardo and decumanus, which reduced roofing. Attendance reached the 20 million target. According to the final accounts reported by Corriere della Sera, the company cost EUR 2,254.7 million from 2009 to 2015. Funding came from EUR 1,258.7 million of public contributions and EUR 944 million of operating revenue, including EUR 421.3 million from tickets, and the company closed with positive net equity of EUR 30.7 million.
Expo 2015 sold 21,476,957 tickets at an average of EUR 17.4 each (Italian Wikipedia, citing Expo data).
Candidacy and award: planned ? – Mar 31, 2008; actual Nov 3, 2006 – Mar 31, 2008. Registration and master plan: planned not published; actual 2009 – Oct 20, 2010. Land acquisition and site construction: planned ? – May 1, 2015; actual Jun 2011 – May 1, 2015. Exposition: planned May 1, 2015 – Oct 31, 2015; actual May 1, 2015 – Oct 31, 2015. Liquidation and final accounts: planned not published; actual Nov 2015 – May 12, 2016.
From the history of managing work: How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979)
London (Stratford), United Kingdom · Events (olympics) · Over budget · Confidence: disputed
London 2012 finished GBP 377 million under its 2007 budget of GBP 9.3 billion, but that budget was more than double the 2005 bid.
Cost: planned £4 billion (2005), actual £8.92 billion (2012) ($12 billion planned and $19.8 billion actual in 2025 dollars). Start: planned Jul 6, 2005, actual Jul 6, 2005. Finish: planned Jul 27, 2012, actual Jul 27, 2012.
Cost overrun: +123% ($10.9 billion over in 2025 dollars), in money of the day. Delay: none.
Official rebaseline: March 2007 public sector funding package: £9.32 billion (2007), so the outturn is -4% against it.
London won the 2012 Games on July 6, 2005 with a gross cost estimate of just over GBP 4 billion. In March 2007 the government reset the public budget at about GBP 9.3 billion, including a GBP 2.7 billion contingency. The Olympic Delivery Authority built the Stratford park on schedule, and the Games opened on July 27, 2012. The National Audit Office forecast a final cost of GBP 8.921 billion, within the 2007 package but well above the bid.
London is two stories, depending on the baseline. Against the March 2007 Public Sector Funding Package of about GBP 9.3 billion, delivery was disciplined. The NAO reported in December 2012 that the construction programme was completed on time and within budget, with the Olympic Delivery Authority's venues and infrastructure expected to cost about GBP 6.7 billion against GBP 8.1 billion available, and an overall forecast underspend of GBP 377 million. Venue security added about GBP 500 million late, which the package absorbed. Against the 2005 bid, the picture is different. The NAO's July 2007 report explains that the bid's estimated gross cost of just over GBP 4 billion omitted or underestimated items that the new budget added: ODA programme management, a GBP 2.7 billion contingency, tax, and security. Public funding rose by about GBP 6 billion, and expected private funding fell to GBP 165 million. Flyvbjerg, Budzier and Lunn measure a 76 percent real overrun on sports-related costs against the bid, and describe the 'under budget' claim as misleading because it used the reset baseline. The bid's 4.3 percent contingency was roughly one-eighteenth of the overrun that followed.
London's bid carried a 4.3 percent contingency, about 18 times smaller than the 76 percent real overrun that followed (Flyvbjerg, Budzier & Lunn 2020).
Bid and award: planned ? – Jul 6, 2005; actual 2003 – Jul 6, 2005. Delivery set-up and rebudgeting: planned not published; actual Apr 2006 – Mar 15, 2007. Olympic Park construction: planned ? – 2011; actual Dec 2006 – Dec 2011. Test events: planned not published; actual 2011 – Jul 2012. Games: planned Jul 27, 2012 – Aug 12, 2012; actual Jul 27, 2012 – Aug 12, 2012. Post-Games review and legacy transfer: planned not published; actual Aug 13, 2012 – Dec 5, 2012.
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979)
Montreal, Canada · Events (olympics) · Over budget · Confidence: disputed
Estimated at C$120 million in 1970, the Montreal Games ended at about C$1.6 billion and took Quebec 30 years to pay off.
Cost: planned C$120 million (1970), actual C$1.6 billion (2006) ($953 million planned and $2.25 billion actual in 2025 dollars). Start: planned May 12, 1970, actual May 12, 1970. Finish: planned Jul 17, 1976, actual Jul 17, 1976.
Cost overrun: +1233% ($2.08 billion over in 2025 dollars), in money of the day. Delay: none.
Official rebaseline: 1973 revised estimate: C$310 million (1973), so the outturn is +416% against it.
Montreal won the 1976 Summer Olympics in 1970 on a promise of a modest, self-financing Games. The original estimate was C$120 million, revised to C$310 million in 1973. Construction of the Taillibert-designed Olympic Park began late, in April 1973, and was hit by strikes, inflation and corruption. The Games opened on time on July 17, 1976, but the stadium tower and roof were finished only in 1987, and the debt was cleared in November 2006.
Oxford researchers rank Montreal as the largest cost overrun of any Summer Games, 720 percent in real terms against the bid estimate (Flyvbjerg, Budzier & Lunn 2020). The causes are well documented. Design ambition: Roger Taillibert's stadium, with a 175-metre inclined tower and retractable roof, was technically novel and was not finished until 1987. A late start: ground was broken on April 28, 1973, under three years before the opening. Labor disruption: unions called major strikes in 1974 and 1975, delaying the stadium, pool and velodrome. Inflation: steel rose from $200 to $1,200 a tonne during construction, according to the McCord Stewart Museum. Weak governance: the Malouf commission criticized the organizing committee and Mayor Jean Drapeau for mismanagement and for the absence of an overall budget and project oversight, and corruption charges followed. In November 1975 the Quebec government took control of the project. The fixed opening date turned the remaining work into an acceleration exercise at any price. Repayment, mainly through a tobacco tax introduced in May 1976, ran until November 2006.
In 1973 Mayor Jean Drapeau said the Olympics could no more have a deficit "than a man can have a baby" (quoted in Flyvbjerg, Budzier & Lunn 2020, citing CBC).
Bid and award: planned ? – May 12, 1970; actual 1969 – May 12, 1970. Olympic Park and stadium construction: planned ? – Jul 17, 1976; actual Apr 28, 1973 – Jul 17, 1976. Quebec government takeover: planned not published; actual Nov 1975 – Jul 17, 1976. Games: planned Jul 17, 1976 – Aug 1, 1976; actual Jul 17, 1976 – Aug 1, 1976. Tower and roof completion: planned ? – Jul 17, 1976; actual Aug 1976 – Apr 1987. Debt repayment: planned not published; actual May 11, 1976 – Nov 2006.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023)
Rio de Janeiro, Brazil · Events (olympics) · Over budget · Confidence: disputed
Rio 2016's sports-related costs came in 352 percent over the bid in real terms, the second-largest Summer Games overrun on Oxford's list.
Cost: planned $3.03 billion (2015), actual $13.7 billion (2015) ($4.11 billion planned and $18.6 billion actual in 2025 dollars). Start: planned Oct 2, 2009, actual Oct 2, 2009. Finish: planned Aug 5, 2016, actual Aug 5, 2016.
Cost overrun: +352% ($14.5 billion over in 2025 dollars), in constant prices. Delay: none.
Rio de Janeiro won the 2016 Games in October 2009, the first awarded to South America. Venues were split across four clusters, with the main park at Barra da Tijuca. Brazil's recession and political crisis hit during delivery, and in June 2016 the state governor declared a financial emergency to fund the Games. The Games opened on time on August 5, 2016. Oxford researchers later put sports-related costs at US$13.7 billion in 2015 dollars, 352 percent above the bid.
Rio shows how much an Olympic cost estimate can move even after the Games. In 2016, using the January 2016 budget forecast, the Oxford Olympics Study put Rio's sports-related cost at US$4.6 billion with a 51 percent overrun and described the Games as on track to reverse the trend of rising costs. The 2020 follow-up by Flyvbjerg, Budzier and Lunn, using the sixth and final update of the responsibility matrix published in June 2017, put the cost at US$13.7 billion and the overrun at 352 percent in real terms. The authors add that the matrix was criticized for leaving out some sports-related costs. The period of delivery coincided with a deep recession and political crisis in Brazil. In June 2016 the Rio state governor declared a state of emergency to secure extra funding. The researchers cite Rio, together with Athens, as an example of the financial risk faced by hosts with fragile economies. Corruption allegations later reached venue contracts, including claims against former mayor Eduardo Paes. On the delivery side, temporary and modular venues such as the handball Future Arena, designed to be rebuilt as schools, were an attempt to limit stranded assets.
The handball venue, the Future Arena, was designed as a temporary modular structure that could be dismantled and rebuilt as four schools (Wikipedia, citing Dezeen).
Bid and award: planned ? – Oct 2, 2009; actual 2007 – Oct 2, 2009. Venue construction (Barra, Deodoro, Maracana, Copacabana clusters): planned ? – Aug 5, 2016; actual 2012 – Aug 2016. Test events: planned not published; actual Aug 2015 – May 2016. State financial emergency: planned not published; actual Jun 2016 – Aug 2016. Games: planned Aug 5, 2016 – Aug 21, 2016; actual Aug 5, 2016 – Aug 21, 2016.
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979)
Tokyo, Japan · Events (olympics) · Over budget and late · Confidence: medium
Tokyo's Games cost 1.42 trillion yen, nearly double the 734 billion yen in the 2013 bid, and opened a year late because of the pandemic.
Cost: planned ¥734 billion (2013), actual ¥1.42 trillion (2021) ($10.4 billion planned and $15.4 billion actual in 2025 dollars). Start: planned Sep 7, 2013, actual Sep 7, 2013. Finish: planned Jul 24, 2020, actual Jul 23, 2021.
Cost overrun: +94% ($7.42 billion over in 2025 dollars), in money of the day. Delay: 12 months (15% of the planned duration).
Official rebaseline: March 2020 postponement to 2021: a revised finish of Jul 23, 2021, met.
Tokyo won the 2020 Summer Olympics in September 2013 with a bid-file cost of 734 billion yen. Delivery ran into trouble early, when Zaha Hadid's National Stadium design was scrapped in July 2015 over cost. The replacement stadium was finished in November 2019, but COVID-19 forced a one-year postponement in March 2020. The Games ran from July 23 to August 8, 2021, mostly without spectators. In June 2022 the organizers reported a final cost of 1.42 trillion yen.
Tokyo's overrun has two layers: ordinary megaproject escalation and a one-off pandemic shock. Cost pressure showed early. By June 2015 the estimated cost of Zaha Hadid's National Stadium had reached about 250 billion yen. On July 17, 2015 Prime Minister Shinzo Abe scrapped the design and ordered a new competition. The replacement was finished in November 2019 at about 157 billion yen, too late for its original role as a Rugby World Cup venue. In October 2018 the Board of Audit warned that total Olympic-related spending could exceed US$25 billion once government outlays outside the organizers' budget were counted. Then on March 24, 2020, the IOC and Japan postponed the Games by a year because of COVID-19. Flyvbjerg, Budzier and Lunn cite this as an example of a 'black swan' adding billions to costs already incurred. The Games went ahead in July 2021 under a state of emergency, with spectators barred. The organizers' June 2022 final report gave a total of 1.42 trillion yen, against 734 billion yen in the 2013 bid file (Kyodo). On time, the event slipped 364 days; the scope delivered was essentially as planned.
Tokyo 2020 was the only Olympic Games held without official spectators, after overseas fans were barred in March 2021 and local fans in July 2021 (Wikipedia).
Bid and award: planned ? – Sep 7, 2013; actual 2011 – Sep 7, 2013. National Stadium redesign: planned not published; actual Jul 17, 2015 – Dec 2015. Venue construction (National Stadium): planned ? – Mar 2019; actual Dec 2016 – Nov 30, 2019. Postponement: planned not published; actual Mar 24, 2020 – Jul 23, 2021. Games: planned Jul 24, 2020 – Aug 9, 2020; actual Jul 23, 2021 – Aug 8, 2021. Final accounts: planned not published; actual Aug 9, 2021 – Jun 21, 2022.
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979)
Barcelona, Spain · Historic (basilica) · Late · Confidence: medium
The 2026 Gaudí-centenary target was met for the 172.5 m central tower, but the full basilica is now expected around 2035, 153 years after work began.
Cost: planned cost not public, actual cost not public (forecast). Start: planned Mar 19, 1882, actual Mar 19, 1882. Finish: planned 2026, actual 2035 (forecast).
Cost overrun: cost not public. Delay: 9 years (6% of the planned duration).
The Sagrada Família in Barcelona has been under construction since 19 March 1882. Antoni Gaudí took over in 1883 and worked on it until his death in 1926, when it was roughly a fifth complete. Funded by donations and tickets, it was consecrated in 2010. In 2014 the target was set for 2026, the centenary of Gaudí's death. The Tower of Jesus Christ topped out in February 2026 at 172.5 m and was inaugurated on 10 June 2026, but interior work and the Glory façade continue, with completion now projected around 2035.
The basilica has no fixed budget because, as an expiatory temple, it is built only as fast as donations and ticket income allow. That funding model explains both the slow 20th century and the rapid 21st: visitor numbers grew to about 3 million a year by 1990 and about 5 million in 2025, and in 2024 the foundation reported EUR 133.9m of income and EUR 86.2m of spending, more than half on construction. Design continuity was the second challenge. Gaudí left few complete drawings, and in July 1936 the crypt was set on fire and his workshop and plaster models were partly destroyed, so later architects reconstructed his intentions from fragments. Computer-aided design and off-site prefabrication of stone panels later accelerated the towers. The 2026 target was hit for the central tower but not for the whole building, partly because the Covid-19 closure from March to July 2020 cut both work and ticket revenue. The remaining Glory façade depends on a proposed monumental staircase that may require demolishing homes opposite the church, a decision outside the builders' control.
The Sagrada Família obtained its building permit only on 7 June 2019, 137 years after construction began, after agreeing to pay the city EUR 36 million.
Del Villar's neo-Gothic start: planned Mar 19, 1882 – ?; actual Mar 19, 1882 – Mar 1883. Gaudí's direction: planned not published; actual Mar 1883 – Jun 10, 1926. Slow progress and wartime damage: planned not published; actual Jun 10, 1926 – Nov 7, 2010. Central towers: planned ? – 2026; actual Nov 7, 2010 – Feb 20, 2026. Interior finishes and Glory façade (forecast): planned ? – 2026; actual Feb 20, 2026 – 2035.
Cologne, Germany · Historic (cathedral) · Incomplete data · Confidence: disputed
Cologne Cathedral took 632 years to finish, including more than three centuries when no one worked on it at all.
Cost: planned cost not public, actual Thaler 6.6 million (1880). Start: planned not published, actual Aug 15, 1248. Finish: planned not published, actual Oct 15, 1880.
Cost overrun: cost not public. Delay: not known.
Cologne Cathedral was begun on 15 August 1248 to house the relics of the Three Kings. Its choir was consecrated in 1322, but work slowed and stopped in the early 16th century, leaving the south tower stump crowned by a medieval crane for about 400 years. In 1842 King Frederick William IV of Prussia relaunched it, and builders finished it in 38 years. The completion ceremony on 15 October 1880 produced the world's tallest building at about 157 m. The 1842-1880 campaign raised more than 6.6 million thalers.
The medieval phase failed for reasons of funding and fashion rather than engineering. Planet Wissen attributes the stop, around 1520 to 1530, to lack of money and fading interest in the Gothic style. With no sponsor willing to finance the remaining nave and towers, the site was left with a temporary roof and a crane on the south tower. The 19th-century restart succeeded because it combined a frozen design with a reliable funding model. The surviving medieval drawing of the west front, Plan F, gave the architects Ernst Friedrich Zwirner and Richard Voigtel an approved design to execute, so no design competition or redesign was needed. Funding came from a public-private partnership: the Zentral-Dombauverein, founded under a royal order of December 1841, raised about two-thirds of the cost through membership and a lottery that sold more than 320,000 tickets in its first draw, and the Prussian state paid the rest. Completion was also a matter of national symbolism in the decades around German unification, which kept political backing in place until 1880.
The first draw of the Dombaulotterie sold more than 320,000 tickets and netted 177,000 thalers for the building fund.
Gothic choir (Master Gerhard): planned not published; actual Aug 15, 1248 – 1322. Nave and south tower (medieval): planned not published; actual 1322 – 1473. Medieval works wind down: planned not published; actual 1473 – 1520. Unfinished period: planned not published; actual 1520 – Sep 4, 1842. 19th-century completion (Zwirner, Voigtel): planned Sep 4, 1842 – ?; actual Sep 4, 1842 – Oct 15, 1880.
Giza, Egypt · Historic (pyramid / royal tomb) · Incomplete data · Confidence: disputed
About 2.3 million stone blocks were set in place in roughly 20 to 27 years, the length of one pharaoh's reign.
Cost: planned cost not public, actual cost not public. Start: planned not published, actual 2600 BC. Finish: planned not published, actual 2574 BC.
Cost overrun: cost not public. Delay: not known.
The Great Pyramid was built at Giza for the Fourth Dynasty king Khufu around 2600 BC. Originally 146.6 m tall with a base of about 230 m per side, it contains about 2.3 million blocks weighing roughly 6 million tonnes. Herodotus said it took 20 years; modern estimates are about 26 to 27 years, bounded by Khufu's reign of about 23 to 29 years. The Diary of Merer, a papyrus logbook found in 2013, documents limestone deliveries from Tura in the king's 26th or 27th year.
There is no record of a planned budget or schedule, but the project had a hard deadline: the tomb had to be usable when the king died, and Khufu's reign lasted about 23 to 29 years according to the Turin King List and dated graffiti. The builders met it. Organization rather than technology explains the result. A 1999 construction-management study with Egyptologist Mark Lehner estimated an average workforce of about 13,200 and a peak near 40,000, far fewer than Herodotus's 100,000. Excavations of workers' settlements point to organized, fed and housed crews, largely conscripted rather than enslaved. Logistics were planned across Egypt: local limestone for the core, fine limestone ferried from Tura across the Nile, and granite shipped from Aswan. The Diary of Merer shows a crew of boatmen making round trips between Tura and Giza on a regular cycle under the oversight of Ankhhaf, Khufu's half-brother. Precision was high: the base is level to about 21 mm and aligned to the cardinal points within a fraction of a degree.
The pyramid was the tallest human-made structure in the world for more than 3,700 years.
Site survey, leveling and alignment: planned not published; actual 2600 BC – 2598 BC. Quarrying and core courses: planned not published; actual 2598 BC – 2585 BC. Upper structure and granite chambers: planned not published; actual 2585 BC – 2578 BC. Casing with Tura limestone: planned not published; actual 2580 BC – 2574 BC. Completion and capstone: planned not published; actual 2576 BC – 2574 BC.
Badaling, Beijing, China · Historic (wall / frontier fortification) · Incomplete data · Confidence: disputed
Over 276 years the Ming dynasty built a system of walls that a 2009 survey measured at 8,850 km, including 6,259 km of actual wall.
Cost: planned cost not public, actual cost not public. Start: planned not published, actual 1368. Finish: planned not published, actual 1644.
Cost overrun: cost not public. Delay: not known.
Most of the Great Wall that visitors see today was built under the Ming dynasty between 1368 and 1644. Rather than one project, it was a long series of campaigns: Yu Zijun's Ordos wall in the 1470s, the Xuanfu-Datong program of the 1540s, the replacement of dry-stone walls near Beijing with brick and mortar from 1550, and Qi Jiguang's hollow watchtowers from 1569. A two-year government survey reported in 2009 measured the Ming wall at about 8,850 km, of which 6,259 km is built wall.
The Ming wall was never a single planned project with a budget and end date; it grew in bursts driven by funding, court politics and changing threats along the northern frontier. Sources record recurring gaps between ambition and resources. Yu Zijun's Ordos wall of the 1470s, about 1,100 km with 800 strong points, cost over one million silver taels. In 1548 a project linked to Jizhou requested 436,000 liang of silver but was allotted only about one-sixth. Qi Jiguang and Tan Lun's watchtower plan of 1569 called for 3,000 hollow brick towers and was cut to 1,200. Materials technology changed during the program: early walls of rammed earth and dry stone were progressively rebuilt in fired brick and mortar, especially in the sections guarding Beijing. Work paused in the 1590s when resources were diverted elsewhere and continued until the dynasty fell in 1644. The 2009 survey by the State Administration of Cultural Heritage and the State Bureau of Surveying and Mapping found the Ming system nearly 3,000 km longer than earlier estimates based on historical records.
The 2009 survey counted 2,232 km of natural barriers such as hills and rivers as part of the 8,850 km Ming wall system.
Early Ming walls of earth and stone: planned not published; actual 1368 – 1470. Ordos wall (Yu Zijun): planned Dec 1472 – ?; actual Dec 1472 – 1474. Xuanfu-Datong program: planned not published; actual 1544 – 1549. Ji-Chang stone and brick rebuild: planned not published; actual 1550 – 1571. Closing gaps and final works: planned not published; actual 1577 – 1644.
Agra, India · Historic (mausoleum) · Incomplete data · Confidence: disputed
More than 20,000 workers spent about 22 years on the Taj Mahal complex, at a reported cost of 32 million rupees.
Cost: planned cost not public, actual Rs 32 million (1653). Start: planned not published, actual Jan 1632. Finish: planned not published, actual 1653.
Cost overrun: cost not public. Delay: not known.
The Taj Mahal in Agra was commissioned by the Mughal emperor Shah Jahan as a tomb for his wife Mumtaz Mahal, who died in June 1631. Foundation work began in January 1632. The white marble mausoleum is dated complete in 1648, and the surrounding complex of red sandstone mosque, guest house, gateway and charbagh garden in about 1653. More than 20,000 workers and artisans took part, and the reported cost was about 32 million rupees. It became a UNESCO World Heritage Site in 1983.
No planned budget or schedule survives, so performance can only be judged from outcomes. The work was delivered as a phased imperial program: the court held the first ceremony at the tomb on the 12th anniversary of Mumtaz Mahal's death in 1643, while the mausoleum was still being finished, and the subsidiary buildings and gardens followed until about 1653. Workers and specialist artisans were recruited from across the Mughal empire and beyond; one account cites craftsmen from Persia and the Ottoman Empire. The design is commonly credited to Ustad Ahmad Lahori, but Shah Jahan's official histories name only the supervisors, Makramat Khan and Mir Abd al-Karim, and the attribution rests largely on a poem by Ahmad's son written years later. Completion dates are themselves disputed: the court chronicler Abdul Hamid Lahori placed completion of the main work around 1643-1644, the entrance inscription gives 1648, and other accounts extend to 1653 or 1654. The 32 million rupee figure is the commonly cited contemporary estimate and cannot be checked against accounts.
The tomb was first used for a ceremony in 1643, on the 12th anniversary of Mumtaz Mahal's death, five years before the mausoleum was dated complete.
Commission and site acquisition: planned not published; actual Jun 1631 – Jan 1632. Foundations and plinth: planned not published; actual Jan 1632 – 1635. Mausoleum: planned not published; actual Jan 1632 – 1648. Mosque, guest house, gateway and gardens: planned not published; actual 1640 – 1653.
Redmond, Washington, United States · Software and IT (operating system) · Late · Confidence: medium
Announced in 1993 for a mid-1994 release, Windows 95 reached stores on 24 August 1995, about 14 months late.
Cost: planned cost not public, actual cost not public. Start: planned Mar 1992, actual Mar 1992. Finish: planned Jun 1994, actual Aug 24, 1995.
Cost overrun: cost not public. Delay: 14 months (53% of the planned duration).
Official rebaseline: early-1995 target set in summer 1994: a revised finish of Feb 1995, 6 months late against it.
Chicago, the successor to Windows 3.1 and MS-DOS, began around March 1992. An internal plan targeted June 1993, and the product was publicly announced in 1993 for release in mid-1994. In summer 1994 Microsoft moved the date to early 1995, and around the end of 1994 it slipped again by about six months to August 1995. After builds and betas starting in 1993, Windows 95 was released to manufacturing on 14 July 1995 and went on sale on 24 August 1995.
Chicago combined several technical goals in one release: a 32-bit protected-mode kernel, a new 32-bit Windows subsystem, a new user interface, and compatibility with existing DOS and Windows 3.1 software. A 1992 Microsoft product plan scheduled several of these components for June 1993, which proved far too optimistic. The public mid-1994 date also slipped. In July 1994 executive vice president Steve Ballmer told analysts the product would not go on sale before January 1995 and might not produce revenue until April 1995. TidBITS reported in January 1995 that Microsoft had pushed the release a further six months, to August 1995. The final schedule held: RTM came on 14 July 1995 and retail launch on 24 August. A long public beta and a paid preview program tested compatibility on a wide range of hardware.
Microsoft paid for 1.5 million free copies of The Times in the UK on launch day, according to Wikipedia citing CNET.
Design and early development: planned Mar 1992 – ?; actual Mar 1992 – Aug 10, 1993. Developer preview builds: planned not published; actual Aug 10, 1993 – Jun 9, 1994. Beta testing: planned not published; actual Jun 9, 1994 – Mar 17, 1995. Release candidates and preview program: planned not published; actual Mar 17, 1995 – Jul 14, 1995. Release to manufacturing and retail launch: planned ? – Jun 1994; actual Jul 14, 1995 – Aug 24, 1995.
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Scrum is presented at OOPSLA (1995), Microsoft Project for DOS (1984)
This dataset compares what was promised with what was delivered. Every figure comes from an open public source listed with its project: audit offices such as the US Government Accountability Office, the UK National Audit Office and France’s Cour des comptes; official project reports; peer-reviewed research, including Bent Flyvbjerg’s megaproject studies and the Oxford Olympics Study; reputable press; and Wikipedia where it cites its references. We never fill a gap with an invented number: a missing figure is shown as missing.
Known disputes. 42 records are marked disputed, usually because no audited final account exists or because sources measure different scopes. Olympic Games are the clearest example: bid budgets, public funding packages and organizing-committee accounts cover different things, and we say which one we used. The notes inside each record give the details.
Found an error? Tell us through the Kanbanchi contact page with the project name and a source, and we will correct it.
Download CSV Download JSON Timeline JSON
Licence: Creative Commons Attribution 4.0. Attribution: “Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects”. Last updated .
The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.
Kanbanchi turns a kanban board into a Gantt chart with dependencies and milestones, stored in your own Google Drive. Compare options in apps for project timelines, see what teams need from project management software with a Gantt chart, or read how it works as a Gantt chart for Google Workspace. Already using it? Learn to export a Gantt chart to PDF, change dates in the Gantt view or create a clean Gantt chart.
See Kanbanchi’s Gantt chart Start your free trial Everything about Gantt chart tools