Buildings · Dubai, United Arab Emirates · 2004–2010

Burj Khalifa

The world's tallest building opened on 4 January 2010, about 13 months after its end-2008 target, at roughly $1.5 billion against early press figures of $900 million; Emaar never published an official budget.

+67%cost overrun
13 months lateagainst the first plan
$2.21 billionactual cost in 2025 dollars
Over budget and lateconfidence: disputed

Burj Khalifa as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Excavation and foundationsJan 2004 – ?Jan 6, 2004 – Sep 20, 2004
Superstructure (Samsung C&T, BESIX, Arabtec JV)Sep 21, 2004 – ?Sep 21, 2004 – Jan 17, 2009
Facade claddingnot published? – Oct 1, 2009
Interior fit-out and commissioning? – Dec 2008? – Jan 4, 2010
Remaining facilitiesnot publishedJan 4, 2010 – Jan 23, 2011

The plan

Emaar Properties launched Burj Dubai as the centerpiece of its Downtown Burj Dubai district, a development Gulf News valued at $20 billion in 2007.2 Skidmore, Owings & Merrill designed the tower, with Adrian Smith as chief architect and Bill Baker as chief structural engineer.1 Site work began in January 2004; Wikipedia gives both 6 and 12 January as the start.1

Emaar never published a formal budget or a baseline schedule, so the planned figures on this page come from the press. In February 2007 Gulf News gave the tower's cost as $900 million and reported a completion target in the fourth quarter of 2008, which Emaar said was unchanged.2 In March 2008 the Associated Press put the cost at $1 billion.3 The chart uses the end of 2008 as the planned finish, about 59 months after the start.

Those press figures may not cover the same scope as the final number. Emaar chairman Mohamed Alabbar estimated the cost at about $1.5 billion in March 2009, and that figure was repeated at the opening.14 If the earlier figures described the structure alone and the later one included fit-out, part of the apparent 67% overrun is a change in what was counted rather than in what was spent.

What actually happened

Excavation and foundations, 2004

Excavation started in January 2004, and the foundation alone took more than 45,000 cubic meters of concrete.1 The main construction contract began in September 2004.1

Superstructure, 2004–2009

A joint venture of Samsung C&T, BESIX and Arabtec built the tower, with Turner as project manager on the main contract.1 By February 2007 it had reached 103 floors, and Emaar kept the final floor count and height confidential as it rose.2

The tower topped out on 17 January 2009 at 829.8 meters. In total it used about 330,000 cubic meters of concrete, 55,000 tonnes of reinforcing steel and 22 million hours of labor.1

Facade cladding, 2006–2009

The curtain wall was the first problem. Swiss cladding firm Schmidlin went bankrupt in 2006, and its local subsidiary had been contracted to install the exterior. Gulf News blamed it for most of a delay of a couple of months reported in early 2007, and said a new cladding contractor was working to catch up.2

Far East Aluminium of Hong Kong supplied the exterior cladding, and the exterior was complete on 1 October 2009.1

Fit-out and opening, 2008–2010

In March 2008 the tower was reported four months behind, with completion moved into 2009. Alabbar said quality was the first priority and that several interior designs had been rejected at various stages.3 Dubai's property market crashed at the end of 2008 while fit-out was under way.4

The tower opened on 4 January 2010 and was renamed Burj Khalifa in honor of Khalifa bin Zayed Al Nahyan, recognizing federal financial support during Dubai's debt crisis.1 The last major planned facility in the building became operational on 23 January 2011.1

Why it went the way it did

A facade subcontractor's insolvency

A supertall tower cannot be fitted out until it is closed in. When the cladding contractor's parent went bankrupt, the replacement had to catch up on work that sat on the critical path, and Gulf News attributed most of the early delay to it.2 The exterior was not complete until October 2009, nine months after topping out.1

Interior designs changed during fit-out

Emaar's chairman said several interior designs were rejected at various stages, and the four-month slip announced in March 2008 came with that explanation.3 Rejecting designs late means redoing work that other trades depend on.

No published baseline

Because Emaar never published a budget, the cost overrun can only be estimated from press figures of uncertain scope: $900 million in 2007, $1 billion in 2008 and about $1.5 billion in 2009.231 The schedule baseline is clearer, since Emaar itself stated the fourth-quarter 2008 target.2

Lessons for project managers

  1. Check specialty subcontractors' finances before award. One facade firm's bankruptcy set the pace for the whole building.2 Mapping task dependencies shows which subcontractors sit on the critical path and deserve the closest scrutiny.
  2. Freeze interior design before fit-out starts. Rejected interior designs were the stated reason for the 2008 slip.3 Good project planning fixes design decisions before the trades that depend on them begin.
  3. Track completion, not just height. The tower topped out in January 2009 but opened a year later.1 A planned versus actual schedule that shows cladding and fit-out separately reveals that gap early.
  4. Publish a baseline budget with a fixed scope. Without one, nobody can say how much of the rise from $900 million to $1.5 billion was overrun and how much was added scope.21

Burj Khalifa by the numbers

PlannedActualSource
Cost$900 million (press, 2007); $1 billion (press, 2008)About $1.5 billion (Emaar estimate, 2009)[1]
Cost in 2025 US dollarsAbout $1.4 billionAbout $2.2 billion[1]
StartJanuary 2004January 2004[1]
CompletionEnd of 20084 January 2010 (opening)[2]
DurationAbout 59 monthsAbout 72 months[1]
DelayNoneAbout 13 months[3]
HeightNot disclosed during construction829.8 m[1]

From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979).

Frequently asked questions about Burj Khalifa

How much did the Burj Khalifa cost?
About $1.5 billion, according to an estimate by Emaar chairman Mohamed Alabbar in March 2009, repeated when the tower opened in January 2010.14 Emaar never published an official budget, and the figure covers the tower, not the wider Downtown development that Gulf News valued at $20 billion in 2007.2
Was the Burj Khalifa over budget?
Probably, but by how much is unclear. Press reports gave the cost as $900 million in 2007 and $1 billion in 2008, against about $1.5 billion at completion.231 That would be a rise of about 67% from the earliest figure, but the early numbers may have excluded fit-out, and Emaar never published a baseline to check them against.
How long did the Burj Khalifa take to build?
About six years. Excavation began in January 2004, the tower topped out on 17 January 2009, the exterior was finished on 1 October 2009 and the building opened on 4 January 2010.1 Emaar had targeted completion in the fourth quarter of 2008, so it opened about 13 months late.2
Why was the Burj Khalifa delayed?
Two causes were reported at the time. The bankruptcy of Schmidlin, whose subsidiary was contracted to install the exterior cladding, accounted for most of an early delay.2 In March 2008 Emaar's chairman said several interior designs had been rejected because quality came first, and the project was reported four months behind.3
Who built the Burj Khalifa?
Emaar Properties developed it. Skidmore, Owings & Merrill designed it, with Adrian Smith as chief architect and Bill Baker as chief structural engineer. A joint venture of Samsung C&T of South Korea, BESIX of Belgium and Arabtec of the UAE was the main contractor, Turner was project manager, and Far East Aluminium supplied the cladding.1

Sources

  1. Burj Khalifa, Wikipedia (accessed October 25, 2026)
  2. Burj Dubai hits snags, Gulf News (accessed October 25, 2026)
  3. World's Tallest Building Completion Delayed by Four Months, Developer Says, Construction Equipment Guide (AP) (accessed October 25, 2026)
  4. Dubai opens world's tallest tower, Al Jazeera (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart

The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.

See Kanbanchi’s Gantt chart Start your free trial Back to all 100 great projects