Infrastructure · Folkestone (Cheriton) / Coquelles, United Kingdom · 1987–1994
Channel Tunnel
Planned at £2.6 billion and due in 1993, the Channel Tunnel opened on 6 May 1994 at £4.65 billion in 1985 prices, an 80 percent real overrun.
Channel Tunnel as a Gantt chart: planned vs actual
- Planned
- Actual
- Forecast
- Milestones (planned, actual)
- ↳ Dependency
- Today
| Phase | Planned | Actual |
|---|---|---|
| Concession, treaty and legislation | not published | Jan 1986 – Jul 1987 |
| Mobilization and site works | Dec 1, 1987 – ? | Dec 1, 1987 – Jun 1988 |
| Tunnel boring | 1988 – ? | Jun 1988 – 1991 |
| Fit-out, systems and rolling stock | ? – May 1993 | 1991 – May 1994 |
| Opening and phased start of services | May 1993 – May 1993 | May 6, 1994 – Nov 1994 |
Open in the explorer of 100 projects · Compare with Seikan Tunnel (the other great undersea rail tunnel, with a far longer delay)
The plan
In January 1986 the British and French governments chose the rail scheme put forward by Channel Tunnel Group and France-Manche, and in February 1986 they signed the Treaty of Canterbury1. The Channel Tunnel Act received Royal Assent in July 1987, and Eurotunnel was granted a 55-year concession to build, own and operate the link before handing it back1. No public money was to be spent.
The project consisted of two rail tunnels and a central service tunnel, about 50 km long with 37.9 km under the sea1. Eurotunnel financed it through equity, a public share offer and a syndicated bank loan of about £5 billion, and hired TransManche Link (TML), an Anglo-French consortium of contractors, to design and build it14.
The investment cost was estimated at £2.6 billion in 1985 prices1. Works began on 1 December 1987, and the tunnel was due to open in mid-199315. At the share offer, Eurotunnel told investors that 10 percent would be a reasonable allowance for unforeseen construction costs3.
What actually happened
Mobilization and site works, 1987–1988
TML began work for Eurotunnel at the end of 1987, preparing sites at Folkestone and Coquelles1. Relations between client and contractor deteriorated early, with public rows over cost, delay and program management starting in 19874.
Tunnel boring, 1988–1991
French boring started in June 1988 and the British machines started in December 19881. Eleven tunnel boring machines cut through chalk marl1. Early hold-ups in the boring program put the June 1993 target at risk5.
On 1 December 1990 Graham Fagg and Philippe Cozette broke through the service tunnel. The two drives met about 30 cm apart horizontally and 8 cm vertically1. The running tunnels followed in 1991. Ten workers, eight of them British, died during construction, most of them in the first months of boring1.
Fit-out, systems and the cost dispute, 1991–1994
Once the bores were finished, TML had to install track, signaling, cooling and power, and the shuttle trains had to be built and tested. The intergovernmental commission and its safety authority, which controlled engineering and safety decisions, required enhanced safety, security and environmental measures that added cost12.
In September 1990 TML formally claimed extra payments, and by May 1992 its claims totaled $2.6 billion4. That June, Eurotunnel's chief Sir Alastair Morton warned that the argument over who would pay threatened the completion date, and the target had already slipped to October 19935.
Opening and phased services, 1994
Queen Elizabeth II and President François Mitterrand opened the tunnel on 6 May 1994, one year later than originally planned1. Freight services started on 1 June 1994 and passenger trains in November 19941. The construction cost at completion was £4.65 billion in 1985 prices, 80 percent above the estimate, and financing costs ended 140 percent above forecast13.
Revenue and restructuring, 1994–2007
Revenues came in at about half of forecast3. Carrying the debt, Eurotunnel went through repeated restructurings, and on 2 August 2006 a French court placed it under bankruptcy protection2. A restructuring approved in May 2007 exchanged much of the remaining debt for equity2.
Why it went the way it did
Requirements changed after the contract was signed
The overrun has been attributed in part to enhanced safety, security and environmental demands imposed after the contract was let12. Under the 1986 treaty, final engineering and safety decisions sat with the intergovernmental commission and its safety authority, not with the client or the builder1.
Split governance and a long dispute
Eurotunnel paid, TML built, and the governments approved. Each change passed through three parties with different interests, and Eurotunnel's claims of poor workmanship and TML's counterclaims produced a dispute that lasted for the rest of the project4. The Bank of England had to intervene in the project's finances twice4.
Late tasks held up everything after them
The schedule was a chain. Systems could not be installed until boring was complete, and the tunnel could not open until systems and trains were commissioned. Delays in boring pushed fit-out to the right, and the funding dispute threatened fit-out again5. This is the pattern described in our piece on task dependencies: one late link moves every date after it.
Debt that grew with delay
Because the project was privately financed, every month of delay added interest with no revenue to pay it. Flyvbjerg calls this the debt trap and names the Channel Tunnel as an example3.
Lessons for project managers
- Fix safety requirements before pricing the contract. Safety and environmental demands added after award were a named cause of the overrun. Agree them with regulators first, then sign the price.
- Map the critical path across organizations. Boring, fit-out, trains and approvals sat with different parties. A shared project schedule that shows who owns each link makes the cost of a slip visible to everyone.
- Model financing cost as a schedule risk. Construction ran 80 percent over, but financing ran 140 percent over. On debt-funded projects, a year of delay is a cost item in its own right.
- Doubt traffic forecasts as much as cost estimates. Revenues of about half the forecast did more damage than the construction overrun. Treat demand with the same skepticism about optimism bias as cost.
Channel Tunnel by the numbers
| Planned | Actual | Source | |
|---|---|---|---|
| Construction cost (1985 prices) | £2.6 billion | £4.65 billion | [1] |
| Real cost overrun | 10% allowance for the unforeseen | 80% | [3] |
| Financing cost overrun | 0% | 140% | [3] |
| Works start | 1 December 1987 | 1 December 1987 | [1] |
| Official opening | Mid-1993 | 6 May 1994 | [1] |
| Length | About 50 km | 50.46 km, 37.9 km under the sea | [1] |
| Revenue | 1985 forecast | About half of forecast | [3] |
From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979).
Frequently asked questions about Channel Tunnel
- How much over budget was the Channel Tunnel?
- Measured in constant 1985 prices, construction cost £4.65 billion against an estimate of £2.6 billion, an 80 percent overrun1. Financing costs ended 140 percent above forecast3. Figures in circulation vary because they use different bases: TML's original estimate was about £4.7 billion, and the nominal final cost including financing is usually given as about £9.5 billion2.
- How long did the Channel Tunnel take to build?
- Works started on 1 December 1987 and the tunnel was officially opened on 6 May 1994, about six and a half years later1. Boring took from 1988 to 1991, and the rest of the time went on track, systems and trains. Freight started in June 1994 and passenger trains in November 19941.
- Was the Channel Tunnel finished on time?
- No. It opened one year later than originally planned1. The original target was mid-1993; by June 1992 it had slipped to October 1993, after delays in boring and a dispute between Eurotunnel and its contractor over who would pay for cost overruns5.
- Who built the Channel Tunnel?
- TransManche Link, a bi-national design-and-build organization joining a French contractors' group and a British joint venture, built it for Eurotunnel, which financed and operates it under a government concession41. The British and French governments oversaw engineering and safety through an intergovernmental commission set up by the 1986 Treaty of Canterbury1.
- Did the Channel Tunnel make money?
- Not for its original investors. Revenues were about half of forecast, and Flyvbjerg cites an evaluation that found the British economy would have been better off without it3. Eurotunnel entered bankruptcy protection in 2006 and was restructured in 2007, when it reported its first net profit2.
Sources
- Channel Tunnel, Wikipedia (accessed October 25, 2026)
- Getlink (Eurotunnel), Wikipedia (accessed October 25, 2026)
- What You Should Know About Megaprojects, and Why: An Overview, Bent Flyvbjerg, Project Management Journal (arXiv preprint) (accessed October 25, 2026)
- TransManche Link, Wikipedia (accessed October 25, 2026)
- Project Hits Steep Overruns (10 June 1992), The Christian Science Monitor (accessed October 25, 2026)
Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.