Infrastructure · Culebra Cut (Gaillard Cut), near Panama City, Panama · 1904–1914

Panama Canal

The United States opened the Panama Canal on 15 August 1914, ahead of every schedule it had set, at about $375 million all-in against a 1906 construction-only estimate of $139.7 million.

+168%cost overrun
4 years earlyagainst the first plan
$12.1 billionactual cost in 2025 dollars
Over budgetconfidence: disputed

Panama Canal as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
French attempt (Compagnie universelle, de Lesseps)not publishedJan 1, 1881 – May 15, 1889
US takeover, sanitation and preparation (Wallace, Stevens)May 4, 1904 – ?May 4, 1904 – Apr 1, 1907
Lock canal design adoptednot publishedJan 1, 1906 – Jun 29, 1906
Main construction under Goethals (Culebra Cut, Gatun Dam, locks)Apr 1, 1907 – 1918Apr 1, 1907 – Oct 10, 1913
Opening to traffic? – 1918Aug 15, 1914 – Aug 15, 1914

The plan

The American canal was built on the ruins of a French one. Ferdinand de Lesseps, fresh from Suez, began a sea-level canal on 1 January 1881; his company went bankrupt in 1889 after spending a reported US$287 million, and an estimated 22,000 workers died of disease and accidents1. The United States took formal control of the property on 4 May 19041.

The design question took two more years. A consulting board recommended a sea-level canal in January 1906, but chief engineer John Stevens argued for locks and a large artificial lake and persuaded President Roosevelt1. When the lock design was chosen, its construction estimate was $139,705,200, a figure that excluded interest during construction, sanitation, the cost of governing the Canal Zone, and the $50 million paid to Panama and the French company2. The time estimate cited at that decision was twelve or fifteen years2.

By 1909 the plan had been rebaselined. President Taft wrote that the current estimate was $297,766,000 on the same narrow basis, or $375 million in total, and that the canal would be finished on or before 1 January 19152.

Official rebaseline: 1908-09 revised estimate and fixed completion date (Taft, 1909), $298 million (outturn +26% against it), revised finish Jan 1, 1915.

What actually happened

The French attempt, 1881–1889

The French tried to cut a sea-level channel through the mountains and jungle of the isthmus and were defeated by landslides, yellow fever and malaria, and money1. Their work was not wasted: the Panama Canal Authority counts some 30 million cubic yards of French excavation toward the canal's total3.

Takeover, sanitation and preparation, 1904–1907

The first American chief engineer, John Findley Wallace, was appointed on 6 May 1904 and resigned in June 19051. His successor, Stevens, spent his two years on the unglamorous parts: rebuilding the railroad, housing workers and backing Colonel William Gorgas's campaign against mosquitoes. After two years the mosquito-spread diseases were nearly eliminated1.

The lock-and-lake decision, 1906

Choosing locks meant damming the Chagres River at Gatun to create a lake 85 feet above sea level, at the time the largest dam and largest artificial lake in the world1. It also meant far less digging than a sea-level channel, which is what made the schedule achievable.

Main construction under Goethals, 1907–1913

Army engineer George Washington Goethals replaced Stevens in 19071. The hardest work was the Culebra Cut through the continental divide, where slides kept refilling the excavation; the first and largest major slide came at Cucaracha in 19074. Of more than 100 million cubic yards removed from the cut, roughly a quarter had slid in from the sides4. Steam shovels broke through the cut on 20 May 19134.

Opening, August 1914

The cement boat Ancon made the first official transit on 15 August 19143. The planned celebration was scaled down because the First World War had begun3. By 1 July 1914 the Americans had excavated 238,845,587 cubic yards3. According to hospital records, 5,609 lives were lost to disease and accidents in the American era, most of them West Indian laborers31.

Why it went the way it did

An estimate built on thin surveys

Taft admitted in 1909 that the excavation yardage had been underestimated by 50 percent because the surveys were insufficient and the design had changed2. Ground expected to be easy to dredge turned out to be rock, raising the average cost of excavation by about 20 percent, and wages ran higher than assumed2. This is the pattern described in project time estimation vs reality: the first number was made before anyone knew the ground.

Scope grew after approval

The canal got bigger after the estimate was set. The bottom of the Culebra Cut was widened from 200 to 300 feet, usable lock length went from 900 to 1,000 feet, and the Pacific dams were moved back to Miraflores and Pedro Miguel2. Each change was defensible, and each added cost.

An estimate that left things out

Part of the apparent overrun is accounting. The $139.7 million figure covered construction only, while the $375 million outturn includes sanitation, Zone government and the $50 million in purchase payments23. Measured against Taft's 1909 rebaseline of $297.8 million on the narrow basis, the result was close to plan, and the Panama Canal Authority says the final figure came in about $23 million below the 1907 estimate3.

Health and control came first

The schedule was beaten because the Americans fixed what had broken the French. Gorgas's sanitation removed the disease that had killed the earlier workforce, and the switch to locks cut the volume of digging1. Goethals then ran the work under centralized control until the cut was through14.

Lessons for project managers

  1. Survey the ground before you fix the number. Panama's excavation was underestimated by half because the surveys were thin2. Money spent on site investigation is cheap next to a 50% error in quantities.
  2. Say what the estimate leaves out. The 1906 figure excluded sanitation, government and land, which made the later total look like a doubling2. Publishing the exclusions next to the number avoids that argument.
  3. Change the concept before you build it. Switching from sea level to locks and a lake rescued a project that had already failed once1. The cheapest time to change a design is in the planning stage, before excavation begins.
  4. Remove the hazard that stopped the last team. The French were beaten largely by disease. Sanitation was the Americans' first major work package, and it made everything after it possible1.

Panama Canal by the numbers

PlannedActualSource
Cost$139,705,200 (1906, construction only)about $375 million (1914, all-in)[2]
Rebaselined cost$297,766,000 (1909, construction only)about $23 million below the 1907 estimate[3]
Cost in 2025 US dollarsabout $5.0 billionabout $12.1 billion[3]
Start of US work4 May 19044 May 1904[1]
Completionabout 1918 (12–15 years from 1906); rebaselined to 1 January 191515 August 1914[2]
Excavation (US era)underestimated by 50%238,845,587 cubic yards[3]
Deaths (US era)not applicable5,609 (hospital records)[3]

From the history of managing work: The Principles of Scientific Management (1911), Henry Gantt charts work against time (c. 1910–1915).

Frequently asked questions about Panama Canal

How much did the Panama Canal cost?
The Panama Canal Authority puts the American cost at around $375 million, including the $10 million paid to Panama and the $40 million paid to the French company; fortifications added about $12 million more3. The 1906 construction-only estimate was $139,705,2002. The French had already spent a reported $287 million before giving up in 18891.
Was the Panama Canal over budget?
It depends on the baseline. Against the 1906 estimate of $139.7 million the final $375 million looks like a large overrun, but that estimate excluded sanitation, Zone government and the $50 million in purchase payments2. On a like-for-like basis Taft's 1909 estimate was $297.8 million, and the canal finished about $23 million below the 1907 estimate23.
How long did it take to build the Panama Canal?
The American project took about ten years and three months, from the takeover on 4 May 1904 to the first official transit on 15 August 191413. Counting the French attempt that began in 1881, the effort spanned 33 years with a long gap in the 1890s1.
Was the Panama Canal finished on time?
Yes, early. The estimate at the 1906 lock-canal decision was twelve to fifteen years, and in 1909 the target was fixed at 1 January 19152. The canal opened on 15 August 1914, months ahead of that date and years ahead of the original estimate3.
How many people died building the Panama Canal?
Hospital records list 5,609 deaths from disease and accidents during the American construction era3. Most were West Indian laborers, particularly from Barbados, and about 350 were Americans1. An estimated 22,000 workers died during the French attempt1. The Panama Canal Authority puts the total for both eras at about 25,000, while noting that the true number is unknown3.

Sources

  1. Panama Canal, Wikipedia (accessed October 25, 2026)
  2. Article by the President in McClure's Magazine: An Answer to the Panama Canal Critics (1 May 1909), The American Presidency Project, UC Santa Barbara (accessed October 25, 2026)
  3. End of the Construction, Panama Canal Authority (accessed October 25, 2026)
  4. Culebra Cut, Wikipedia (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart

The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.

See Kanbanchi’s Gantt chart Start your free trial Back to all 100 great projects