Historic · Barcelona, Spain · 1882–ongoing
Basílica de la Sagrada Família
The 2026 Gaudí-centenary target was met for the 172.5 m central tower, but the full basilica is now expected around 2035, 153 years after work began.
Sagrada Família as a Gantt chart: planned vs actual
- Planned
- Actual
- Forecast
- Milestones (planned, actual)
- ↳ Dependency
- Today
| Phase | Planned | Actual |
|---|---|---|
| Del Villar's neo-Gothic start | Mar 19, 1882 – ? | Mar 19, 1882 – Mar 1883 |
| Gaudí's direction | not published | Mar 1883 – Jun 10, 1926 |
| Slow progress and wartime damage | not published | Jun 10, 1926 – Nov 7, 2010 |
| Central towers | ? – 2026 | Nov 7, 2010 – Feb 20, 2026 |
| Interior finishes and Glory façade (forecast) | ? – 2026 | Feb 20, 2026 – 2035 |
Open in the explorer of 100 projects · Compare with Cologne Cathedral (another cathedral that took centuries to finish)
The plan
The Sagrada Família never had a completion date at the start. Construction began on 19 March 1882 under the architect Francisco de Paula del Villar, who resigned a year later; Antoni Gaudí took over in 1883, was formally named Architect Director in March 1884 and redesigned the church far beyond the original neo-Gothic scheme.1 As an expiatory temple it is paid for by donations and, since 2010, by visitor tickets, so it has never had an overall budget, and its total cost is not public.13
The first real schedule baseline came more than 130 years in. In 2014 completion was expected by 2026, the centenary of Gaudí's death, and in October 2015 the chief architect Jordi Faulí said construction was 70 percent complete, with most of the structure planned for 2026.1 That target is the planned finish used in the chart.
The current forecast is about 2035. In February 2025 the construction board said the basilica could be finished in about ten years, but only if all schedules were confirmed and deadlines met.2 It is a conditional statement rather than an official date, but by June 2026 Reuters was reporting completion as pushed back to 2035, and Euronews described full completion as expected in the next decade.45 The chart treats 2035 as a forecast.
What actually happened
Del Villar's neo-Gothic start, 1882–1883
Work began on 19 March 1882 on a conventional neo-Gothic design by del Villar, who resigned on 18 March 1883.1 Gaudí's appointment changed the scope of the project completely, which is the first reason no early schedule means much: the building that was started is not the building being finished.1
Gaudí's direction, 1883–1926
Gaudí led the work for more than four decades.5 At his death in June 1926 the project was, depending on the estimate, between 15 and 25 percent complete; Wikipedia's own sections give both that range and "less than a quarter".1 Progress was slow because the work depended on private donations.1
Lost plans and slow progress, 1926–2010
In July 1936 the crypt was set on fire and the workshop broken into, and Gaudí's plans were partially destroyed.1 Later architects had to reconstruct his intentions from surviving fragments. Income grew with tourism, to about 3 million visitors a year by 1990, and Pope Benedict XVI consecrated the church as a basilica on 7 November 2010.1 In the 20th century the stone was still carved by hand; later, computer-aided design and CNC milling let stone be shaped off-site.1
The central towers, 2010–2026
The 21st century brought speed. Post-tensioned stone panels were pre-assembled before installation, and the annual budget reached about EUR 25 million, largely from entrance fees.1 In October 2018 the trustees agreed to pay the city EUR 36 million for a building permit, issued on 7 June 2019, after more than 130 years without one.1
Then the schedule took a hit. Construction stopped on 11 March 2020 for Covid-19, the first halt since the Spanish Civil War, and resumed on 4 July 2020, while ticket income collapsed.13 The Tower of Jesus Christ was still structurally completed on 20 February 2026 at 172.5 m, and Pope Leo XIV inaugurated it on 10 June 2026, 100 years to the day after Gaudí's death, before a crowd of about 120,000.135 Crowned with a five-story ceramic cross, it made the basilica the tallest church in the world.4
Interior finishes and the Glory façade, 2026–c. 2035 (forecast)
The tower interior is expected to be finished in 2028.13 The remaining main element is the Glory façade, the intended main entrance, planned with about 100 sculptures.2 Its four towers are already built, but the board says Gaudí's design includes a monumental staircase over Carrer de Mallorca that would require demolishing buildings opposite and could displace around 3,000 residents, who oppose it.12 No completion date for the basilica as a whole has been published.3
Why it went the way it did
Pay-as-you-go funding
The basilica is built only as fast as donations and tickets allow. That explains the slow 20th century and the fast 21st: visitors rose to a record of about 4.9 million in 2025, according to Reuters, and in 2024 the foundation reported EUR 133.9 million of income and EUR 86.2 million of spending, more than half of it on construction.24 It also explains the Covid setback, when ticket sales fell sharply.3
A design that had to be reconstructed
The 1936 fire partially destroyed Gaudí's plans, leaving later architects to work from what survived.1 Every later phase began with interpretation before construction, which is slow work that no funding model can fully accelerate.
Final scope outside the builders' control
The last piece of the project depends on the city, not the construction board. The Glory staircase needs agreement on land now occupied by homes, and residents say they lack a clear timeline.23 A target set before that agreement exists is, in effect, an optimistic estimate of the kind discussed in project time estimation versus reality.
Lessons for project managers
- Model income shocks in self-funded projects. Revenue-funded work avoids debt but ties the schedule to ticket sales. The 2020 closure stopped both the site and the money that paid for it.
- Archive the design outside the workshop. Losing plans and models in 1936 turned decades of work into reconstruction. Keep copies of design intent somewhere a single event cannot reach.
- Split a milestone from the finish date. The 2026 centenary was met for the central tower but not the building. Publishing milestones and completion separately on the project schedule keeps a symbolic date from being read as the end.
- Secure consent for final scope early. The Glory façade now waits on the city and on residents. Treat third-party approvals as dependencies that can hold up everything after them, and clear them before committing to a date.
Sagrada Família by the numbers
| Planned | Actual | Source | |
|---|---|---|---|
| Overall cost | No overall budget | Not public; annual budget about EUR 25 million | [1] |
| 2024 income and spending | n/a | EUR 133.9m income, EUR 86.2m spending | [2] |
| Start | 19 March 1882 | 19 March 1882 | [1] |
| Completion | 2026 (Gaudí centenary, set in 2014) | About 2035 (forecast, Feb 2025) | [4] |
| Tower of Jesus Christ | 2026 | Topped out 20 Feb 2026, inaugurated 10 Jun 2026 | [1] |
| Central tower height | 172.5 m | 172.5 m | [1] |
| Delay vs 2026 target | 0 | About 9 years (forecast) | [2] |
| Visitors | n/a | About 4.9 million (2025, record) | [4] |
Frequently asked questions about Sagrada Família
- When will the Sagrada Família be finished?
- There is no official date. In February 2025 the construction board said the basilica could be finished in about ten years if schedules and deadlines held, which points to around 2035, the date Reuters reported in June 2026.24 The central Tower of Jesus Christ was inaugurated on 10 June 2026, its interior is expected by 2028, and the Glory façade still depends on an agreement with the city.13
- Did the Sagrada Família meet its 2026 deadline?
- Partly. The 2026 target, set in 2014 for the centenary of Gaudí's death, was met for the 172.5 m Tower of Jesus Christ, which topped out in February 2026 and was inaugurated on 10 June 2026.13 The basilica as a whole was not finished, and Reuters reported that the overall completion date had been pushed back to 2035.34
- Why is the Sagrada Família taking so long?
- Three reasons stand out. It is funded only by donations and tickets, so progress has always tracked income.1 Gaudí's plans were partially destroyed in 1936 and had to be reconstructed.1 And the final Glory façade needs a staircase that would require demolishing nearby homes, which awaits agreement with the city.2
- How much does the Sagrada Família cost?
- No overall budget or total cost has been published. The annual construction budget is about EUR 25 million, financed largely by entrance fees.1 In 2024 the foundation reported EUR 133.9 million of income and EUR 86.2 million of spending, more than half of it on construction, and it paid the city EUR 36 million for its building permit.12
Sources
- Sagrada Família, Wikipedia (accessed October 25, 2026)
- Sagrada Família could finish construction in ten years, Catalan News (accessed October 25, 2026)
- Sagrada Família's 144-year journey nears its end with the Tower of Jesus Christ (CNN Style), KEYT / CNN (accessed October 25, 2026)
- With Pope Leo's blessing, Barcelona's Sagrada Familia reaches new heights (Reuters), Chronicle.lu / Reuters (accessed October 25, 2026)
- Sagrada Familia opens new tower before 120,000 people, Euronews (accessed October 25, 2026)
Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.