SurvivalBook by Andy Weir, 2011 Mars

The Martian as a project: Kanban board and Gantt chart

On sol 6 of the Ares 3 mission, a dust storm forces the crew off Mars and Mark Watney is left behind, presumed dead. He has to stay alive until a rescue can reach him, and the rescue has to be invented on Earth.

  • 1team
  • 549 solsduration (approximate)
  • Deliveredoutcome
  • 5handoffs, our count
  • 4re-plans, our count

Start your free trial7 days, every feature, on your Google or Microsoft account.

The Martian as a Kanban board

The board is frozen at one moment, during the drive to the other landing site. 2 cards wait in To do, 1 is in progress, 1 is blocked and 4 are done. The card on the critical path is "Drive to the other site", owned by Mark. Blocked: "Talk to Earth directly", which the team cannot move on its own.

To do

  • Launch the ascent vehicle
  • Meet the ship

In progress

  • Drive to the other site

Blocked

  • Talk to Earth directly

Done

  • Survive the storm
  • Grow food
  • Contact Earth
  • Agree the rescue

Purple label: on the critical path. Letter: the card owner, and a question mark means nobody owns it. Blocked: stopped by something outside the team.

Run your own project on a board like this

Lists, owners, due dates and subcards, inside the Google Drive or Microsoft account your team already uses.

Start your free trial

The Martian: the timeline as a Gantt chart

The same work on a timeline: 7 cards, 4 dependencies and the today line at Sol 480. 3 cards are milestones, drawn as diamonds. No arrow is red: every card waits for the one before it, as planned.

Dates are approximate: the book does not give a full timeline, so the chart uses relative steps.

Cards on the timeline
CardStartDue
Left behindSol 6Milestone
Grow foodSol 10Sol 200
Earth plans a rescueSol 60Sol 250
Crew turns backSol 250Milestone
Drive to the other siteSol 449Sol 505
Modify the vehicleSol 505Sol 545
RescueSol 549Milestone

What happened, in project terms

One person on Mars kept a log, fixed one problem at a time and made his status visible to the people who could help. The rescue plan came from a junior analyst and was carried out by a crew that voted to go back. Good projects let anyone propose the reroute.

By our count the quest has 5 handoffs, moments where work changes hands, and 4 re-plans: more re-plans than most books on this page.

Lessons for project managers

  1. Solve one problem at a time, in public

    In Kanbanchi, keep a short Blocked list and review it every day. Survival plans fail when a blocker sits unnoticed, not when the team lacks ideas.

  2. Skipping tests to save time can cost the date

    The rushed probe was meant to save weeks and lost them. Cut scope before you cut testing.

  3. Make status visible

    Watney's log and his messages let hundreds of people help. The more visible the work, the more people can spot the fix.

Draw the dependencies before they bite

The Gantt chart uses the same cards your team already moves on the board.

Start your free trial

What went wrong: the risk register

Most of what went wrong was visible early. Here are three risks a project manager could have written down at the start. Switch between the plan and what actually happened.

  • The habitat is a single point of failure

    Likelihood: mediumImpact: severe

    Mitigation: Keep backups of anything you cannot replace, outside the main habitat.

    What happened: The Hab's airlock blew out and the potato farm died, which cut his food supply. Materialised

  • Skipping tests to hit the date

    Likelihood: highImpact: severe

    Mitigation: Keep the tests that protect the critical path, even when time is short.

    What happened: NASA rushed the resupply probe and skipped inspections. It failed at launch. Materialised

  • Losing the only link to Earth

    Likelihood: mediumImpact: high

    Mitigation: Plan a second channel, however slow.

    What happened: Watney broke the Pathfinder radio by accident and had to work with short messages through the rover. Absorbed

The Martian by the numbers

BookThe Martian
AuthorAndy Weir
First published2011
SettingMars
Quest typeSurvival
Team1 on Mars, a planet's worth of help
Duration549 sols
OutcomeDelivered
Handoffs (our count)5
Re-plans (our count)4
Dates on this pageApproximate: the book gives no full timeline, so the Gantt chart uses relative steps

Questions about The Martian as a project

What does The Martian teach about project management?

Solve one problem at a time, in public. Skipping tests to save time can cost the date, and make status visible. The full reasoning is in the lessons above.

How long does the quest in The Martian take?

549 sols. The book gives no full timeline, so the Gantt chart on this page uses approximate, relative steps.

How would you set up The Martian as a Kanban board?

Four lists: To do, In progress, Blocked and Done. At the moment shown above there are 2 cards to do, 1 in progress, 1 blocked and 4 done. The card to watch is "Drive to the other site", on the critical path. Give it two owners, and link it to the cards it waits on so the Gantt chart shows the order.

Plan your own quest on one board and one timeline

Lists for the work, two names on every critical card and the dependencies drawn before anything goes wrong, inside the Google or Microsoft account you already use.