  "meta": {
    "title": "The World's Great Projects as Gantt Charts",
    "publisher": "Kanbanchi",
    "url": "https://www.kanbanchi.com/gantt-chart-tool/great-projects/",
    "license": "CC BY 4.0",
    "attribution": "Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects",
    "generated": "2026-10-25",
    "count": 100,
    "inflation_method": "Costs converted to US dollars at the exchange rate of the cost year (rate and source in each record), then inflated to 2025 dollars with the US CPI (Federal Reserve Bank of Minneapolis, Consumer Price Index 1800- (1967=100; pre-1913 BLS historical estimates; CPI-U from 1978), https://www.minneapolisfed.org/about-us/monetary-policy/inflation-calculator/consumer-price-index-1800-). overrun_pct is computed as actual_cost / planned_cost - 1 in the project's own currency; overrun_basis says whether both figures are in the same price base (real) or in money of different years (nominal).",
    "outcome_rules": "over budget = more than 5% above planned cost; late = finished more than 1 month after planned end; ongoing projects use the latest official forecast (actual_is_forecast = true); year-only dates are placed at mid-year.",
    "baseline_rule": "Planned = the first publicly approved or announced budget and schedule. Where the owner later set an official revised budget or schedule, it is kept as rebaseline_* and compared separately.",
    "eras": [
      "ancient",
      "pre-1800",
      "1800s",
      "1900-1945",
      "1946-1979",
      "1980-1999",
      "2000-2014",
      "2015-now"
    ],
    "cost_not_public_rule": "cost_not_public = true when the planned or actual cost was never published; the page shows \"cost not public\" instead of an overrun."
  },
  "projects": [
    {
      "id": 1,
      "slug": "beijing-daxing-airport",
      "name": "Beijing Daxing International Airport",
      "short_name": "Beijing Daxing Airport",
      "category": "infrastructure",
      "subcategory": "airport",
      "country": "China",
      "country_code": "CN",
      "countries": [
        "China"
      ],
      "continent": "Asia",
      "city": "Beijing",
      "lat": 39.5092,
      "lng": 116.4106,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "on_time_on_budget",
      "planned_start": "2014-12",
      "planned_end": "2019-09-30",
      "actual_start": "2014-12-26",
      "actual_end": "2019-09-25",
      "actual_is_forecast": false,
      "planned_duration_months": 57.5,
      "actual_duration_months": 57,
      "delay_months": -0.2,
      "delay_pct": -0.3,
      "planned_cost": 79980000000,
      "actual_cost": 80000000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        80000000000,
        120000000000
      ],
      "cost_currency": "CNY",
      "planned_cost_year": 2014,
      "cost_year": 2019,
      "planned_fx_to_usd": 0.1623,
      "actual_fx_to_usd": 0.1448,
      "planned_cost_usd_nominal": 12980754000,
      "cost_usd_nominal": 11584000000,
      "planned_cost_usd_today": 17653752453,
      "cost_usd_today": 14587426786,
      "overrun_usd_today": 3646857,
      "overrun_pct": 0,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Approvals",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2012-12-22",
          "actual_end": "2014-12-22",
          "note": "State Council approved the new airport on 22 December 2012; NDRC approved the feasibility study (total investment CNY 79.98bn) in late 2014 (Chinese Wikipedia gives 22 November, English Wikipedia 22 December)."
        },
        {
          "name": "Terminal structure",
          "planned_start": "2014-12",
          "planned_end": null,
          "actual_start": "2014-12-26",
          "actual_end": "2017-03",
          "note": "Work began 26 December 2014; terminal concrete structure complete by March 2017."
        },
        {
          "name": "Roof, fit-out, airfield and systems",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2017-03",
          "actual_end": "2019-06-30",
          "note": "Construction officially finished 30 June 2019."
        },
        {
          "name": "Operational readiness trials",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2019-06-30",
          "actual_end": "2019-09-25",
          "note": "Preparation period between completion and opening."
        },
        {
          "name": "Opening",
          "planned_start": "2019-09-30",
          "planned_end": "2019-09-30",
          "actual_start": "2019-09-25",
          "actual_end": "2019-09-26",
          "note": "Opening ceremony 25 September 2019, five days ahead of the planned 30 September; first commercial flights 26 September 2019. Nanyuan Airport closed the same day."
        }
      ],
      "milestones": [
        {
          "name": "NDRC feasibility approval",
          "planned_date": null,
          "actual_date": "2014-12-22"
        },
        {
          "name": "Construction complete",
          "planned_date": null,
          "actual_date": "2019-06-30"
        },
        {
          "name": "Opening",
          "planned_date": "2019-09-30",
          "actual_date": "2019-09-25"
        }
      ],
      "headline": "Beijing Daxing opened on 25 September 2019, five days ahead of plan, against an approved investment of CNY 79.98 billion.",
      "summary": "Beijing Daxing International Airport, south of the capital on the Beijing-Hebei border, was approved by the National Development and Reform Commission in December 2014 and opened on 25 September 2019. Its starfish-shaped terminal, designed by Zaha Hadid Architects with ADP Ingénierie and executed by the Beijing Institute of Architectural Design, covers about 700,000 m². The first phase has four runways and is planned for 72 million passengers a year by 2025.",
      "what_went_wrong_or_right": "Daxing is a schedule story: about 57 months from groundbreaking on 26 December 2014 to opening on 25 September 2019, five days before the planned 30 September date recorded by Chinese Wikipedia. The terminal concrete frame was done by March 2017 and construction was declared complete on 30 June 2019, leaving nearly three months for operational trials before the switchover. The approved feasibility study put total investment at CNY 79.98 billion, and the commonly reported outturn is about CNY 80 billion, which would mean the project held its budget. Cost reporting is not clean, though. English Wikipedia also cites an earlier estimate of at least CNY 70 billion that included the Beijing section of an intercity railway, and a separate report of CNY 120 billion for the airport itself within CNY 450 billion including surrounding infrastructure. No audited final account was found, so the on-budget result rests on reported, not audited, figures. The client throughout was a single body, the Beijing New Airport Construction Headquarters, and the master plan was prepared by NACO.",
      "lessons": [
        "Leave months between construction completion and opening for operational trials.",
        "Publish costs with a fixed scope; mixing airport, rail and surrounding works makes outturn unreadable.",
        "A single client body with clear authority can compress approvals and handoffs."
      ],
      "fun_fact": "Daxing was the first airport in China built with two control towers and four runways.",
      "method_tags": [
        "fast_track",
        "phased_delivery",
        "design_build"
      ],
      "related_history_ids": [
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Beijing Daxing International Airport",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Beijing_Daxing_International_Airport",
          "accessed": "2026-10-25"
        },
        {
          "title": "Beijing Daxing International Airport",
          "publisher": "Zaha Hadid Architects",
          "url": "https://www.zha.com/architecture/beijing-new-airport-terminal-building/?disclaimer=true",
          "accessed": "2026-10-25"
        },
        {
          "title": "北京大兴国际机场 (Beijing Daxing International Airport)",
          "publisher": "Wikipedia (Chinese)",
          "url": "https://zh.wikipedia.org/wiki/北京大兴国际机场",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: total investment of CNY 79.98bn in the NDRC-approved feasibility study (Chinese Wikipedia); approval date given as 22 November 2014 (Chinese Wikipedia) or 22 December 2014 (English Wikipedia). Planned opening 30 September 2019 (Chinese Wikipedia). Actual: about CNY 80bn (English Wikipedia lead); English Wikipedia also reports CNY 120bn for the airport itself and CNY 450bn including peripheral projects, hence the range, and an earlier estimate of at least CNY 70bn including intercity rail. No audited outturn found. FX: approximate annual averages, 2014 about 6.16 and 2019 about 6.91 CNY per USD (Federal Reserve H.10), not re-checked in this session.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 2,
      "slug": "berlin-brandenburg-airport",
      "name": "Berlin Brandenburg Airport Willy Brandt (BER)",
      "short_name": "Berlin BER Airport",
      "category": "infrastructure",
      "subcategory": "airport",
      "country": "Germany",
      "country_code": "DE",
      "countries": [
        "Germany"
      ],
      "continent": "Europe",
      "city": "Schönefeld, near Berlin",
      "lat": 52.3667,
      "lng": 13.5033,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2006-09-05",
      "planned_end": "2011-10",
      "actual_start": "2006-09-05",
      "actual_end": "2020-10-31",
      "actual_is_forecast": false,
      "planned_duration_months": 61.3,
      "actual_duration_months": 169.9,
      "delay_months": 108.5,
      "delay_pct": 177,
      "planned_cost": 2000000000,
      "actual_cost": 6900000000,
      "planned_cost_range": [
        2000000000,
        2830000000
      ],
      "actual_cost_range": [
        6500000000,
        7300000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2006,
      "cost_year": 2020,
      "planned_fx_to_usd": 1.2556,
      "actual_fx_to_usd": 1.1413,
      "planned_cost_usd_nominal": 2512000000,
      "cost_usd_nominal": 7872900000,
      "planned_cost_usd_today": 4011819082,
      "cost_usd_today": 9794304680,
      "overrun_usd_today": 6955375788,
      "overrun_pct": 245,
      "overrun_basis": "nominal",
      "rebaseline_cost": 2830000000,
      "rebaseline_cost_year": 2009,
      "rebaseline_end": "2012-06",
      "rebaseline_label": "2009 budget; opening moved to June 2012",
      "rebaseline_overrun_pct": 143.8,
      "rebaseline_delay_months": 100.5,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Construction of terminal and airfield",
          "planned_start": "2006",
          "planned_end": "2011-10",
          "actual_start": "2006",
          "actual_end": "2012-05",
          "note": "Construction began in 2006 for an October 2011 opening, later moved to 2 June 2012."
        },
        {
          "name": "Opening cancelled; fire-protection failure",
          "planned_start": null,
          "planned_end": "2012-06-02",
          "actual_start": "2012-05",
          "actual_end": "2014-05",
          "note": "The fire alarm and smoke-extraction system failed acceptance. The general planner pg bbi was dismissed and the fire-system designer was dismissed in May 2014."
        },
        {
          "name": "Remediation and rework",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2014",
          "actual_end": "2019",
          "note": "Rewiring, reprogramming and rebuilding of technical systems; cost estimates rose to EUR 5.4 billion (2015) and higher."
        },
        {
          "name": "Acceptance, licensing and trial operations",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2019",
          "actual_end": "2020-10",
          "note": "Operating licence granted in May 2020; trial operations followed."
        },
        {
          "name": "Opening and transfer from Tegel",
          "planned_start": "2011-10",
          "planned_end": "2011-10",
          "actual_start": "2020-10-31",
          "actual_end": "2020-11-08",
          "note": "Commercial operations began 31 October 2020; airlines completed the move from Tegel by 8 November 2020."
        }
      ],
      "milestones": [
        {
          "name": "Construction begins",
          "planned_date": "2006",
          "actual_date": "2006"
        },
        {
          "name": "First planned opening",
          "planned_date": "2011-10",
          "actual_date": null
        },
        {
          "name": "Opening of June 2012 cancelled",
          "planned_date": "2012-06-02",
          "actual_date": null
        },
        {
          "name": "Operating licence granted",
          "planned_date": null,
          "actual_date": "2020-05"
        },
        {
          "name": "Airport opens",
          "planned_date": "2011-10",
          "actual_date": "2020-10-31"
        }
      ],
      "headline": "Berlin's BER airport opened nine years late, in October 2020, after its cost rose from about €2 billion to roughly €6.5 to 7.3 billion.",
      "summary": "BER was built at Schönefeld to replace Berlin's Tegel and Schönefeld airports with a single hub owned by Berlin, Brandenburg and the federal government. Construction began in 2006 for an October 2011 opening. Weeks before the rescheduled June 2012 opening the fire protection system failed inspection, and the terminal stood unused for years while technical systems were reworked. The airport opened on 31 October 2020, during the COVID-19 pandemic, with Tegel closing days later.",
      "what_went_wrong_or_right": "The core failure was technical systems design and integration. The fire alarm and smoke-extraction system was not built to the construction permit and failed the mandatory acceptance test; its design required smoke to be pulled downward against its natural rise, and inspectors found wiring, programming and implementation faults. Alfredo di Mauro, who designed it, was dismissed in May 2014 and was reported not to be a qualified engineer. The planning team also broke down: the general planner pg bbi became insolvent and the architects Gerkan, Marg and Partners were dismissed. Inspectors reported poor workmanship, including about 60 km of cooling pipes allegedly installed without insulation, and corruption cases added to delays. Wikipedia also cites a 2015 assessment that the financial plan was flawed because it assumed BER would become a major international hub.",
      "lessons": [
        "Have life-safety systems designed and checked by qualified, independent engineers.",
        "Plan for the loss of a general planner; BER's insolvency left design without an owner.",
        "Test life-safety systems against the permit early, not weeks before opening."
      ],
      "fun_fact": "The airport opened on 31 October 2020, during the pandemic, eight and a half years after a fully marketed June 2012 opening was called off.",
      "method_tags": [
        "big_bang"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Berlin Brandenburg Airport",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Berlin_Brandenburg_Airport",
          "accessed": "2026-10-25"
        },
        {
          "title": "Endlich - BER geht in Betrieb",
          "publisher": "Bund der Steuerzahler Deutschland",
          "url": "https://steuerzahler.de/aktuelles/detail/endlich-ber-geht-in-betrieb/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Flughafen Berlin Brandenburg",
          "publisher": "Wikipedia (German)",
          "url": "https://de.wikipedia.org/wiki/Flughafen_Berlin_Brandenburg",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: about EUR 2 billion at the start of construction (Bund der Steuerzahler); Wikipedia gives the budget as EUR 2.83 billion as of 2009, hence planned_cost_range. Planned opening: October 2011 (Wikipedia); the 3 June 2012 date was the later, cancelled opening. Actual cost: the Bund der Steuerzahler reports about EUR 6.5 to 7 billion up to opening; German Wikipedia gives total project cost of about EUR 7.3 billion. Stored as the midpoint of EUR 6.5-7.3 billion, EUR 6.9 billion. German Wikipedia dates the first groundbreaking to 5 September 2006, when an October 2011 opening was expected, and gives a 1995 first calculation of DM 1.1 billion (pre-approval, not used) and EUR 2.4 billion in 2008. Wikipedia reports a 2018 estimate of EUR 9.4 billion, or EUR 10.3 billion including overhead, which uses a wider scope (financing, noise protection, expansion) and is not used. Figures nominal. FX: Fed H.10 annual averages, about $1.256 per euro (2006) and $1.141 (2020). The record would benefit from a Brandenburg Landesrechnungshof or FBB annual report citation. Baseline audit 2026-10-25: Planned figures unchanged: EUR 2bn at the 2006 start of construction with October 2011 opening; the 1995 DM 1.1bn first calculation predates approval, so it is not used. Added the EUR 2.83bn budget as of 2009 and the later June 2012 opening date (cancelled) as the rebaseline (Wikipedia); these come from two separate decisions, so the label is approximate.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 3,
      "slug": "brooklyn-bridge",
      "name": "Brooklyn Bridge",
      "short_name": "Brooklyn Bridge",
      "category": "infrastructure",
      "subcategory": "bridge",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "New York City",
      "lat": 40.7058,
      "lng": -73.9964,
      "era": "1800s",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1870",
      "planned_end": "1875",
      "actual_start": "1870-01-02",
      "actual_end": "1883-05-24",
      "actual_is_forecast": false,
      "planned_duration_months": 60,
      "actual_duration_months": 160.7,
      "delay_months": 94.8,
      "delay_pct": 157.9,
      "planned_cost": 10800000,
      "actual_cost": 15500000,
      "planned_cost_range": [
        6675357,
        10800000
      ],
      "actual_cost_range": [
        15100000,
        15552878
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1867,
      "cost_year": 1883,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 10800000,
      "cost_usd_nominal": 15500000,
      "planned_cost_usd_today": 248785714,
      "cost_usd_today": 535580357,
      "overrun_usd_today": 162401786,
      "overrun_pct": 43.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Design and approvals",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1867",
          "actual_end": "1869-07",
          "note": "New York Bridge Company incorporated 1867; John A. Roebling's report of September 1867. Roebling died in July 1869 after a survey accident; his son Washington took over."
        },
        {
          "name": "Caisson foundations",
          "planned_start": "1870",
          "planned_end": null,
          "actual_start": "1870-03-19",
          "actual_end": "1872-07",
          "note": "Brooklyn caisson launched March 1870 and filled March 1871; Manhattan caisson launched May 1871 and filled July 1872. Caisson disease paralyzed Washington Roebling."
        },
        {
          "name": "Masonry towers",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1871",
          "actual_end": "1876-07",
          "note": "Brooklyn tower topped out June 1875; Manhattan tower completed July 1876."
        },
        {
          "name": "Cable spinning",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1876-08-15",
          "actual_end": "1878-10-05",
          "note": "First main-cable wire May 1877; last wire 5 October 1878. Contractor J. Lloyd Haigh supplied fraudulent wire."
        },
        {
          "name": "Deck, approaches and opening",
          "planned_start": null,
          "planned_end": "1875",
          "actual_start": "1878-10",
          "actual_end": "1883-05-24",
          "note": "Suspended deck and masonry approaches built; bridge opened on 24 May 1883."
        }
      ],
      "milestones": [
        {
          "name": "Roebling submits plan and estimate",
          "planned_date": null,
          "actual_date": "1867-09"
        },
        {
          "name": "Construction starts",
          "planned_date": "1870",
          "actual_date": "1870-01-02"
        },
        {
          "name": "Manhattan tower completed",
          "planned_date": null,
          "actual_date": "1876-07"
        },
        {
          "name": "Last main-cable wire run",
          "planned_date": null,
          "actual_date": "1878-10-05"
        },
        {
          "name": "Bridge opens",
          "planned_date": "1875",
          "actual_date": "1883-05-24"
        }
      ],
      "headline": "John Roebling expected five years and about $10.8 million; the Brooklyn Bridge took 13 years and about $15.5 million.",
      "summary": "The Brooklyn Bridge, designed by John A. Roebling and completed by his son Washington Roebling and Emily Warren Roebling, was the first steel-wire suspension bridge across the East River and, at opening, the longest suspension span in the world. Work started in January 1870 with pneumatic caissons sunk into the riverbed. Towers, cables and the deck followed, and the bridge opened on 24 May 1883. An estimated 27 men died during construction.",
      "what_went_wrong_or_right": "Leadership was lost before work started: John Roebling died in July 1869 from an injury sustained while surveying, and Washington Roebling was paralyzed by caisson disease during the foundation work, directing the job from his room with Emily Roebling carrying much of the chief engineer's daily work for about 11 years. The caissons were a technical frontier; physician Andrew Smith treated 110 cases of decompression sickness in the first half of 1872. Scope also grew. According to an 1883 account in The Illustrated Carpenter and Builder, the approaches were changed from light iron trusses to massive masonry and the tower foundations were altered, which swelled the cost. Procurement fraud added work: contractor J. Lloyd Haigh supplied substandard wire, and only five of 80 tested wire rings met standards. Governance changed too, when the private company was converted into a public work in 1874, with Brooklyn paying two-thirds. The structure itself proved sound and is still in use.",
      "lessons": [
        "Plan for key-person risk on long projects; Brooklyn lost two chief engineers to injury.",
        "Test supplier materials independently; wire fraud was caught only by inspection.",
        "Record scope changes against the original estimate so growth can be explained."
      ],
      "fun_fact": "Contractor J. Lloyd Haigh was estimated to have made about $300,000 by substituting inferior wire in the cables.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "adamiecki-1896"
      ],
      "sources": [
        {
          "title": "Brooklyn Bridge",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Brooklyn_Bridge",
          "accessed": "2026-10-25"
        },
        {
          "title": "Brooklyn Bridge, Part 1",
          "publisher": "STRUCTURE magazine",
          "url": "https://www.structuremag.org/article/brooklyn-bridge-part-1/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Chapter 04: Bridges to Brooklyn",
          "publisher": "nycsubway.org",
          "url": "https://nycsubway.org/wiki/Chapter_04:_Bridges_to_Brooklyn",
          "accessed": "2026-10-25"
        },
        {
          "title": "The Brooklyn Bridge (reprint of The Illustrated Carpenter and Builder, 8 June 1883)",
          "publisher": "studfile.net",
          "url": "https://studfile.net/preview/539461/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: John A. Roebling's 1867 plan, which gave the bridge proper at $7,000,000 and the approaches at $3,800,000 ($10.8 million total) and expected completion in five years (The Illustrated Carpenter and Builder, 8 June 1883, via a student-uploaded copy). STRUCTURE magazine cites the Brooklyn Eagle's summary of the September 1867 report as $6,675,357, hence planned_cost_range. Planned_end 1875 is derived from five years after the 1870 start (year precision). Actual: $15.5 million in 1883 dollars (Wikipedia), including land; nycsubway.org's financial statement gives $15,337,056.66 to 31 March 1883; other sources give $15.1 million and $15,552,878 through April 1884, hence actual_cost_range. The baseline may exclude land, so the overrun is partly a scope difference. Nominal USD (greenback era); fx = 1.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 4,
      "slug": "california-high-speed-rail",
      "name": "California High-Speed Rail (Phase 1)",
      "short_name": "California HSR",
      "category": "infrastructure",
      "subcategory": "high-speed rail",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Fresno (Central Valley)",
      "lat": 36.7378,
      "lng": -119.7871,
      "era": "2015-now",
      "status": "ongoing",
      "outcome": "over_budget_and_late",
      "planned_start": null,
      "planned_end": "2020",
      "actual_start": "2015-01-06",
      "actual_end": "2040",
      "actual_is_forecast": true,
      "planned_duration_months": null,
      "actual_duration_months": 305.8,
      "delay_months": 240,
      "delay_pct": null,
      "planned_cost": 33600000000,
      "actual_cost": 126000000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        126000000000,
        231000000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 2008,
      "cost_year": 2026,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 33600000000,
      "cost_usd_nominal": 126000000000,
      "planned_cost_usd_today": 50244204019,
      "cost_usd_today": 126000000000,
      "overrun_usd_today": 92400000000,
      "overrun_pct": 275,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Prop 1A and 2008 business plan",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2008-11",
          "actual_end": "2008-11",
          "note": "Voters approved Proposition 1A in November 2008: $9 billion in bonds for high-speed rail plus $950 million for connecting rail. The 2008 plan costed Phase 1 San Francisco-Anaheim at $33.6 billion (2008 dollars)."
        },
        {
          "name": "Re-estimates and environmental clearance",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2009-12",
          "actual_end": "2014",
          "note": "Estimate rose to $42.6 billion (YOE) in 2009, $65.4-74.5 billion in the 2012 draft, $68.4 billion with a blended approach in April 2012."
        },
        {
          "name": "Central Valley civil construction",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2015-01-06",
          "actual_end": null,
          "note": "Groundbreaking in Fresno on 6 January 2015. Structures and guideway in the Central Valley; about $4 billion in federal grants withdrawn in 2025."
        },
        {
          "name": "Track, systems and Merced-Bakersfield service (forecast)",
          "planned_start": null,
          "planned_end": "2020",
          "actual_start": null,
          "actual_end": "2033",
          "note": "2026 Business Plan targets first service on a shortened Merced-Bakersfield segment in 2033; LAO describes this as an unconstrained schedule."
        },
        {
          "name": "Full Phase 1 San Francisco-Los Angeles/Anaheim (forecast)",
          "planned_start": null,
          "planned_end": "2020",
          "actual_start": null,
          "actual_end": "2040",
          "note": "2026 Business Plan targets Phase I service in 2040 at about $126 billion, or $231 billion absent scope optimizations."
        }
      ],
      "milestones": [
        {
          "name": "Proposition 1A approved",
          "planned_date": null,
          "actual_date": "2008-11-04"
        },
        {
          "name": "Groundbreaking in Fresno",
          "planned_date": null,
          "actual_date": "2015-01-06"
        },
        {
          "name": "Federal funding withdrawn (about $4 billion)",
          "planned_date": null,
          "actual_date": "2025-07"
        },
        {
          "name": "First passenger service, Central Valley (forecast)",
          "planned_date": null,
          "actual_date": "2033"
        },
        {
          "name": "Phase 1 service (forecast)",
          "planned_date": "2020",
          "actual_date": "2040"
        }
      ],
      "headline": "California voters were told in 2008 that high-speed rail from San Francisco to Anaheim would cost $33.6 billion by 2020; the 2026 plan says about $126 billion and 2040.",
      "summary": "The California High-Speed Rail Authority is building an electrified high-speed line meant to link San Francisco and Los Angeles in 2 hours 40 minutes, as Proposition 1A required. Voters approved $9 billion in bonds in November 2008. Construction began in Fresno in January 2015 on the Central Valley segment. No track had been laid for passenger service by 2026; the 2026 Business Plan targets first service between Merced and Bakersfield in 2033 and Phase 1 in 2040.",
      "what_went_wrong_or_right": "The 2008 estimate was produced before engineering and alignment work, in constant 2008 dollars, while the $9 billion state bond was fixed, so inflation alone widened the gap; it also assumed $12-16 billion in federal funds and $6.7-7.5 billion in private investment that did not materialize at that scale (Eno Center). Converting to year-of-expenditure dollars raised the figure to $42.6 billion in 2009, and fuller design raised it to $65-75 billion in 2011. Funding came in pieces, and construction began in the Central Valley in 2015 without full funding for a usable segment; by 2018 the Authority was publishing cost ranges ($63.3-98.1 billion) rather than a single figure. In 2025 the federal government withdrew about $4 billion in grants, cutting available funding to $39 billion (LAO). The state Inspector General's July 2026 review found that recent cost reductions in the Merced-Bakersfield estimate came from planning to build less, not from efficiency, and that omitted financing and contingency would add billions.",
      "lessons": [
        "Never publish a fixed-dollar promise without stating the price base and inflation path.",
        "Start construction only when full funding for a usable segment is secured.",
        "Distinguish genuine savings from scope reductions when reporting cost changes."
      ],
      "fun_fact": "The Authority's 2026 plan says Phase I would cost about $231 billion without the scope optimizations it proposes.",
      "method_tags": [
        "phased_delivery",
        "design_build"
      ],
      "related_history_ids": [
        "rcf-2004",
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "High-Speed Rail: Draft 2026 Business Plan (handout, 27 April 2026)",
          "publisher": "Legislative Analyst's Office, California",
          "url": "https://lao.ca.gov/handouts/transportation/2026/High-Speed-Rail-Draft-2026-Business-Plan-042726.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Review of the 2026 Business Plan (31 July 2026)",
          "publisher": "Office of the Inspector General, High-Speed Rail",
          "url": "https://hsr.ca.gov/wp-content/uploads/2026/07/OIG-HSR-Review-of-2026-Business-Plan-A11Y.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Timeline of California High-Speed Rail Cost Estimates",
          "publisher": "Eno Center for Transportation",
          "url": "https://enotrans.org/article/timeline-california-high-speed-rail-cost-estimates",
          "accessed": "2026-10-25"
        },
        {
          "title": "California High-Speed Rail",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/California_High-Speed_Rail",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the November 2008 business plan for Phase 1 (San Francisco-Anaheim, about 520 miles), $33.6 billion in 2008 dollars (Eno Center), with service by 2020 (widely cited; the 2020 date was confirmed in search results from the California Assembly transportation committee background paper, but not in a page opened in full, so it is lower confidence). Prop 1A authorized $9 billion for HSR and $950 million for connecting rail (Wikipedia, LAO). Latest forecast: $126 billion for Phase I and service in 2040 in the draft 2026 Business Plan (LAO, 27 April 2026); search results indicate the final 2026 plan gives $126.2 billion with completion in 2039 and service in 2040. The Authority's own figure of $231 billion for Phase I absent optimizations is the upper bound of actual_cost_range; the lower figure reflects scope reductions, which the Inspector General criticized. Later estimates are in year-of-expenditure dollars while the baseline is in constant 2008 dollars, so overrun_basis is nominal. No planned start date was published in 2008. fx = 1.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 5,
      "slug": "big-dig",
      "name": "Central Artery/Tunnel Project (Big Dig)",
      "short_name": "Big Dig",
      "category": "infrastructure",
      "subcategory": "highway tunnel",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Boston",
      "lat": 42.3601,
      "lng": -71.056,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": null,
      "planned_end": "1998",
      "actual_start": "1991",
      "actual_end": "2007-12",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 197.5,
      "delay_months": 113.5,
      "delay_pct": null,
      "planned_cost": 2800000000,
      "actual_cost": 14600000000,
      "planned_cost_range": [
        2600000000,
        2800000000
      ],
      "actual_cost_range": [
        14600000000,
        14800000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1982,
      "cost_year": 2007,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 2800000000,
      "cost_usd_nominal": 14600000000,
      "planned_cost_usd_today": 9341379310,
      "cost_usd_today": 22669715936,
      "overrun_usd_today": 18322099182,
      "overrun_pct": 421.4,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Planning and environmental review",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1982",
          "actual_end": "1991",
          "note": "Planning began in 1982 with an estimate of $2.8 billion and completion in 1998."
        },
        {
          "name": "Ted Williams Tunnel (I-90 harbor crossing)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1991",
          "actual_end": "1995-12",
          "note": "Ground broken in 1991; the tunnel opened to limited commercial and HOV traffic in late 1995."
        },
        {
          "name": "Cost growth and federal scrutiny",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1996",
          "actual_end": "1997",
          "note": "GAO put total cost at $10.4 billion in 1996 against an official $7.8 billion, with substantial completion scheduled for December 2004."
        },
        {
          "name": "Central Artery tunnels (I-93) and Zakim Bridge",
          "planned_start": null,
          "planned_end": "1998",
          "actual_start": "1991",
          "actual_end": "2005-03",
          "note": "I-93 northbound tunnel opened 29 March 2003; southbound followed; Zakim Bridge fully in use by March 2005."
        },
        {
          "name": "Surface restoration and close-out",
          "planned_start": null,
          "planned_end": "1998",
          "actual_start": "2005",
          "actual_end": "2007-12",
          "note": "Fatal ceiling-panel collapse in the I-90 connector on 10 July 2006; project declared complete in December 2007."
        }
      ],
      "milestones": [
        {
          "name": "Groundbreaking",
          "planned_date": null,
          "actual_date": "1991"
        },
        {
          "name": "Ted Williams Tunnel opens",
          "planned_date": null,
          "actual_date": "1995-12"
        },
        {
          "name": "I-93 northbound tunnel opens",
          "planned_date": null,
          "actual_date": "2003-03-29"
        },
        {
          "name": "Ceiling collapse kills a motorist",
          "planned_date": null,
          "actual_date": "2006-07-10"
        },
        {
          "name": "Project complete",
          "planned_date": "1998",
          "actual_date": "2007-12"
        }
      ],
      "headline": "Boston's Big Dig was planned at $2.8 billion for 1998 and finished in December 2007 at $14.6 billion, before interest.",
      "summary": "The Central Artery/Tunnel Project replaced Boston's elevated Interstate 93 with tunnels under downtown, extended I-90 to Logan Airport through the Ted Williams Tunnel, and added the Leonard P. Zakim Bunker Hill Memorial Bridge. Managed by a Bechtel and Parsons Brinckerhoff joint venture under the Massachusetts Highway Department and later the Turnpike Authority, it was the most expensive US highway project. Construction ran from 1991 to December 2007, nine years later than first planned.",
      "what_went_wrong_or_right": "The first estimate was made before the scope was set. The 1982 figure of $2.8 billion covered a project that was then enlarged, with the harbor tunnel, interchanges and environmental mitigation for the city, and it was later reported in year-of-expenditure dollars as inflation accumulated over a 25-year program. GAO's July 1996 testimony found that the official $7.8 billion estimate left out more than $1 billion of costs counted in previous estimates and did not account for inflation; GAO's own figure was $10.4 billion. Its 1997 report traced a further rise to $10.8 billion mainly to construction bids above projections and design-phase estimates over budget, and found contract cost growth at 17.4 percent against a 10.7 percent containment goal. Underground tunneling under a working city, which FHWA called inherently risky, added further growth. After the 2006 ceiling collapse and leaks, the Bechtel/Parsons Brinckerhoff consortium agreed to pay $407 million in restitution. The project did deliver its traffic goals and reclaimed surface land for the Rose Kennedy Greenway.",
      "lessons": [
        "Publish estimates with their price base and exclusions; Big Dig figures mixed constant and inflated dollars.",
        "Track contract cost growth against a stated limit and report breaches early.",
        "Freeze scope before quoting a number to legislators and the public."
      ],
      "fun_fact": "Including borrowing costs, the project's cost was reported at about $21.93 billion, with bonds being repaid for decades after opening.",
      "method_tags": [
        "phased_delivery",
        "cost_plus"
      ],
      "related_history_ids": [
        "rcf-2004",
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Big Dig",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Big_Dig",
          "accessed": "2026-10-25"
        },
        {
          "title": "Central Artery/Tunnel Project: Cost and Financing (GAO/T-RCED-96-218)",
          "publisher": "US General Accounting Office",
          "url": "https://www.govinfo.gov/content/pkg/GAOREPORTS-T-RCED-96-218/html/GAOREPORTS-T-RCED-96-218.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Transportation Infrastructure: Progress On and Challenges to Central Artery/Tunnel Project's Costs and Financing (GAO/RCED-97-170)",
          "publisher": "US General Accounting Office",
          "url": "https://www.govinfo.gov/content/pkg/GAOREPORTS-RCED-97-170/html/GAOREPORTS-RCED-97-170.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the original estimate of $2.8 billion with completion in 1998 (Wikipedia); widely described as being in 1982 dollars. A Cato Institute post (not opened, 403) gives $2.6 billion as the figure officials cited when the project started in 1985, hence planned_cost_range. Actual: $14.6 billion at completion in December 2007 (Wikipedia; a cited reference gives $14.8 billion), nominal, excluding interest; with interest about $21.93 billion per Wikipedia. The overrun is nominal: the baseline is in 1982 dollars while the actual mixes year-of-expenditure dollars, so a real-terms overrun would be smaller. Planned start not published separately; actual construction start given as 1991 (year precision). GAO 1996-97 figures are interim estimates used only for narrative. fx = 1 (USD).",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 6,
      "slug": "channel-tunnel",
      "name": "Channel Tunnel",
      "short_name": "Channel Tunnel",
      "category": "infrastructure",
      "subcategory": "tunnel",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom",
        "France"
      ],
      "continent": "Europe",
      "city": "Folkestone (Cheriton) / Coquelles",
      "lat": 51.096,
      "lng": 1.136,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1987-12-01",
      "planned_end": "1993-05",
      "actual_start": "1987-12-01",
      "actual_end": "1994-05-06",
      "actual_is_forecast": false,
      "planned_duration_months": 65.5,
      "actual_duration_months": 77.2,
      "delay_months": 11.7,
      "delay_pct": 17.9,
      "planned_cost": 2600000000,
      "actual_cost": 4650000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "GBP",
      "planned_cost_year": 1985,
      "cost_year": 1985,
      "planned_fx_to_usd": 1.2974,
      "actual_fx_to_usd": 1.2974,
      "planned_cost_usd_nominal": 3372200000,
      "cost_usd_nominal": 6031050000,
      "planned_cost_usd_today": 10094689047,
      "cost_usd_today": 18053963103,
      "overrun_usd_today": 7959274056,
      "overrun_pct": 78.8,
      "overrun_basis": "real",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 80,
      "reported_overrun_source": "Wikipedia (Channel Tunnel, Cost section; Flyvbjerg et al. 2003 and Anguera 2006 cited)",
      "phases": [
        {
          "name": "Concession, treaty and legislation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1986-01",
          "actual_end": "1987-07",
          "note": "CTG/F-M scheme selected January 1986; Treaty of Canterbury February 1986; Channel Tunnel Act Royal Assent July 1987. 55-year BOOT concession."
        },
        {
          "name": "Mobilization and site works",
          "planned_start": "1987-12-01",
          "planned_end": null,
          "actual_start": "1987-12-01",
          "actual_end": "1988-06",
          "note": "TransManche Link (TML) began design-build works for Eurotunnel on 1 December 1987."
        },
        {
          "name": "Tunnel boring",
          "planned_start": "1988",
          "planned_end": null,
          "actual_start": "1988-06",
          "actual_end": "1991",
          "note": "French boring began June 1988, UK TBMs December 1988. Service tunnel breakthrough 1 December 1990; running tunnels followed in 1991."
        },
        {
          "name": "Fit-out, systems and rolling stock",
          "planned_start": null,
          "planned_end": "1993-05",
          "actual_start": "1991",
          "actual_end": "1994-05",
          "note": "Rail systems, cooling, signalling and shuttle rolling stock; enhanced safety requirements from the intergovernmental safety authority raised costs."
        },
        {
          "name": "Opening and phased start of services",
          "planned_start": "1993-05",
          "planned_end": "1993-05",
          "actual_start": "1994-05-06",
          "actual_end": "1994-11",
          "note": "Official opening 6 May 1994, one year later than planned; freight from June 1994, Eurostar passenger trains from November 1994."
        }
      ],
      "milestones": [
        {
          "name": "Treaty of Canterbury signed",
          "planned_date": null,
          "actual_date": "1986-02"
        },
        {
          "name": "Construction starts",
          "planned_date": "1987-12-01",
          "actual_date": "1987-12-01"
        },
        {
          "name": "Service tunnel breakthrough (Fagg and Cozette)",
          "planned_date": null,
          "actual_date": "1990-12-01"
        },
        {
          "name": "Official opening",
          "planned_date": "1993-05",
          "actual_date": "1994-05-06"
        }
      ],
      "headline": "The Channel Tunnel opened a year late with an 80 percent real-terms construction overrun, £4.65 billion against £2.6 billion at 1985 prices.",
      "summary": "The 50 km rail tunnel under the Strait of Dover was the third serious attempt after abandoned starts in the 1880s and 1974-75. Built without public money as a build-own-operate-transfer concession, it was financed by Eurotunnel and designed and built by the Anglo-French TransManche Link consortium. Boring started in 1988, the service tunnel broke through on 1 December 1990, and Queen Elizabeth II and President Mitterrand opened the tunnel on 6 May 1994. Ten workers died during construction.",
      "what_went_wrong_or_right": "The overrun came from three named sources. First, the scope grew after contract award: the intergovernmental commission and safety authority that controlled engineering and safety decisions imposed enhanced safety, security and environmental requirements, which Getlink's own history cites as part of the cause. Second, governance was split: Eurotunnel financed the work, TML designed and built it under a construction contract, and the two governments kept control of final engineering and safety decisions, so changes passed through three parties with different incentives. Third, financing: as costs and delay grew, interest accumulated and financing costs ended about 140 percent above forecast. The engineering itself was a success. The UK and French tunnelling teams met with an error of about 30 cm horizontally and 8 cm vertically. Traffic forecasts were the larger failure: the 1985 forecast of passenger numbers was not reached, and Eurotunnel went through repeated restructurings, entering bankruptcy protection in 2006.",
      "lessons": [
        "Fix safety and regulatory requirements before signing a fixed or target-price contract.",
        "On privately financed projects, delay compounds through interest; model financing cost risk explicitly.",
        "Treat demand forecasts with the same scepticism as cost estimates."
      ],
      "fun_fact": "When the service tunnels met on 1 December 1990, the two bores were misaligned by only about 30 cm horizontally and 8 cm vertically.",
      "method_tags": [
        "design_build",
        "ppp",
        "phased_delivery"
      ],
      "related_history_ids": [
        "rcf-2004",
        "big-things-2023",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Channel Tunnel",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Channel_Tunnel",
          "accessed": "2026-10-25"
        },
        {
          "title": "Getlink (Eurotunnel)",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Getlink",
          "accessed": "2026-10-25"
        },
        {
          "title": "Tunnel sous la Manche",
          "publisher": "Wikipedia (French)",
          "url": "https://fr.wikipedia.org/wiki/Tunnel_sous_la_Manche",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: total investment cost of GBP 2.6 billion at 1985 prices; actual GBP 4.65 billion at 1985 prices at completion in 1994, an 80 percent real overrun (Wikipedia Cost section, which cites Flyvbjerg, Bruzelius and Rothengatter 2003 and Anguera 2006). Both figures are in 1985 prices, so actual_cost_year is 1985 and both fx values use the 1985 Fed H.10 annual average (about $1.297 per pound). Other figures in circulation are on different bases: TML's original estimate of about GBP 4.7 billion and a final cost of about GBP 9.5 billion (Getlink article, nominal, including financing). Financing costs were about 140 percent above forecast. Planned opening: Wikipedia states the tunnel opened 'one year later than originally planned', so planned_end is set to May 1993 at month precision. The exact running-tunnel breakthrough dates in 1991 are given at year precision. French Wikipedia gives an initial construction estimate of 27.3 billion francs and a final 87.9 billion (unit and price base not stated), plus a works start of 15 December 1987 and commercial service from 1 June 1994; these are not used in the main fields. HFW and Construction News pages returned 403, so confidence is medium.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 7,
      "slug": "brasilia",
      "name": "Construction of Brasília",
      "short_name": "Brasília",
      "category": "infrastructure",
      "subcategory": "new capital city",
      "country": "Brazil",
      "country_code": "BR",
      "countries": [
        "Brazil"
      ],
      "continent": "South America",
      "city": "Brasília",
      "lat": -15.7939,
      "lng": -47.8828,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": "1956",
      "planned_end": "1960-04-21",
      "actual_start": "1956",
      "actual_end": "1960-04-21",
      "actual_is_forecast": false,
      "planned_duration_months": 45.7,
      "actual_duration_months": 45.7,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": null,
      "actual_cost": 1500000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": null,
      "cost_year": 1960,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": 1500000000,
      "planned_cost_usd_today": null,
      "cost_usd_today": 16324521935,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Launch under 'Fifty Years in Five'",
          "planned_start": "1956",
          "planned_end": null,
          "actual_start": "1956-01",
          "actual_end": "1956",
          "note": "President Juscelino Kubitschek initiated planning and construction in 1956; the state company NOVACAP led development."
        },
        {
          "name": "Pilot plan",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1957",
          "actual_end": "1957",
          "note": "Lúcio Costa's pilot plan won the competition in 1957 (5,550 people competed); Oscar Niemeyer designed the main buildings and Roberto Burle Marx the landscapes."
        },
        {
          "name": "Date fixed by law",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1957-10-01",
          "actual_end": "1957-10-01",
          "note": "Law 3,273 of 1 October 1957 fixed 21 April 1960 for the transfer of the capital."
        },
        {
          "name": "Main construction",
          "planned_start": "1956",
          "planned_end": "1960-04-21",
          "actual_start": "1956",
          "actual_end": "1960-04-21",
          "note": "Built in 41 months; a 1959 census counted about 64,000 people in the area, 54.5 percent of them construction workers."
        },
        {
          "name": "Inauguration and continued build-out",
          "planned_start": "1960-04-21",
          "planned_end": null,
          "actual_start": "1960-04-21",
          "actual_end": "1975",
          "note": "Inaugurated 21 April 1960 as planned; much of the city, including the move of embassies, was completed in the early 1970s."
        }
      ],
      "milestones": [
        {
          "name": "Pilot plan selected",
          "planned_date": null,
          "actual_date": "1957"
        },
        {
          "name": "Transfer date fixed by Law 3,273",
          "planned_date": null,
          "actual_date": "1957-10-01"
        },
        {
          "name": "Inauguration of the capital",
          "planned_date": "1960-04-21",
          "actual_date": "1960-04-21"
        }
      ],
      "headline": "Brazil built a new capital in 41 months and inaugurated it on 21 April 1960, the date set by law, at an estimated cost of about US$1.5 billion.",
      "summary": "Brasília was built on Brazil's central plateau to move the capital inland from Rio de Janeiro, a transfer required by the 1946 constitution. President Juscelino Kubitschek made it the centerpiece of his 'Fifty Years in Five' program. Lúcio Costa's airplane-shaped pilot plan was chosen in 1957 and Oscar Niemeyer designed the main buildings. A 1957 law fixed the inauguration for 21 April 1960, and the city was inaugurated that day after 41 months of construction.",
      "what_went_wrong_or_right": "The schedule was met because the date was fixed by law and treated as immovable. Law 3,273 of October 1957 set 21 April 1960 for the transfer, Kubitschek's term ran to 1961, and NOVACAP drove construction with tens of thousands of workers brought in from elsewhere. Cost control was the casualty. No published construction budget exists, records were poor and bureaucratic steps were cut for speed, according to JSTOR Daily. The most cited figure is economist Eugênio Gudin's estimate of about US$1.5 billion, roughly 10 to 12 percent of Brazil's GDP; Poder360 quotes Marcelo Paiva Abreu calling it the only known total, while Ipea's Rodrigo Orair says it is probably an underestimate because it omits roads such as the Belém-Brasília highway and later works. A 1996 recalculation by Ib Teixeira was far higher. The government financed the work partly by printing money and issuing debt, which JSTOR Daily links to a legacy of inflation. The city opened incomplete, and embassies moved only in the early 1970s.",
      "lessons": [
        "A fixed, legally binding date can force delivery but shifts the pain to cost and quality.",
        "Track spending from day one; without records, no one can judge the outcome.",
        "Define what 'complete' means; an inauguration is not a finished city."
      ],
      "fun_fact": "The village where the first construction workers lived, Vila Amaury, now lies under the artificial Lake Paranoá.",
      "method_tags": [
        "fast_track",
        "big_bang"
      ],
      "related_history_ids": [
        "cpm-1957",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Brasília",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Brasília",
          "accessed": "2026-10-25"
        },
        {
          "title": "History of Brasília",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/History_of_Brasília",
          "accessed": "2026-10-25"
        },
        {
          "title": "Building Brasília",
          "publisher": "JSTOR Daily",
          "url": "https://daily.jstor.org/building-brasilia",
          "accessed": "2026-10-25"
        },
        {
          "title": "Construção de Brasília custou US$ 1,5 bilhão em valor de 1960",
          "publisher": "Poder360",
          "url": "https://www.poder360.com.br/brasilia/construcao-de-brasilia-custou-uss-1-5-bilhao-em-valor-de-1960/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Lei nº 3.273, de 1º de outubro de 1957",
          "publisher": "Senado Federal (Brazil)",
          "url": "https://legis.senado.leg.br/norma/545050/publicacao/15714476",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "No construction budget was published, so planned_cost is null and no overrun can be computed. Planned end: 21 April 1960, fixed by Law 3,273 of 1 October 1957 (Senado Federal). Actual cost: Eugênio Gudin's estimate of about US$1.5bn; Poder360 dates it to 1960 values, while JSTOR Daily and Wikipedia describe it as 1954 dollars, and Wikipedia attributes a similar figure to President Café Filho. Ib Teixeira's 1996 recalculation ($155bn at the time, per JSTOR Daily) is not comparable and is not used. GDP share is given as 12.3 percent (JSTOR Daily) or about 10 percent (Poder360). Law 3,273 cites the transitional provisions of the 1946 constitution. Kubitschek's term (1956-1961) per Poder360. Phase dates within 1956 are approximate. Editor decision 2026-10-25: kept in the dataset (flag was: no published baseline budget; planned_cost is null).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 8,
      "slug": "crossrail",
      "name": "Crossrail (Elizabeth line)",
      "short_name": "Crossrail",
      "category": "infrastructure",
      "subcategory": "metro / regional rail",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "London",
      "lat": 51.5163,
      "lng": -0.131,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2009",
      "planned_end": "2018-05",
      "actual_start": "2009-05-15",
      "actual_end": "2023-05-21",
      "actual_is_forecast": false,
      "planned_duration_months": 106.5,
      "actual_duration_months": 168.2,
      "delay_months": 60.2,
      "delay_pct": 56.5,
      "planned_cost": 15900000000,
      "actual_cost": 18900000000,
      "planned_cost_range": [
        14800000000,
        15900000000
      ],
      "actual_cost_range": null,
      "cost_currency": "GBP",
      "planned_cost_year": 2007,
      "cost_year": 2022,
      "planned_fx_to_usd": 2.002,
      "actual_fx_to_usd": 1.2369,
      "planned_cost_usd_nominal": 31831800000,
      "cost_usd_nominal": 23379300000,
      "planned_cost_usd_today": 49425881078,
      "cost_usd_today": 25721483682,
      "overrun_usd_today": 4082775188,
      "overrun_pct": 18.9,
      "overrun_basis": "nominal",
      "rebaseline_cost": 14800000000,
      "rebaseline_cost_year": 2010,
      "rebaseline_end": "2019-12",
      "rebaseline_label": "2010 Crossrail funding settlement",
      "rebaseline_overrun_pct": 27.7,
      "rebaseline_delay_months": 41.2,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Funding and powers",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2007",
          "actual_end": "2008-07",
          "note": "Government announced a GBP 15.9 billion funding package in 2007; Crossrail Act 2008 received Royal Assent in July 2008."
        },
        {
          "name": "Enabling works and re-baseline",
          "planned_start": "2009",
          "planned_end": null,
          "actual_start": "2009-05-15",
          "actual_end": "2010-12",
          "note": "Piling began at Canary Wharf on 15 May 2009. After the 2010 Spending Review funding was cut to GBP 14.8 billion and full opening moved from May 2018 to December 2019."
        },
        {
          "name": "Tunnelling",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2012",
          "actual_end": "2015-06-04",
          "note": "Tunnel boring officially completed at Farringdon on 4 June 2015."
        },
        {
          "name": "Stations, track and systems fit-out",
          "planned_start": null,
          "planned_end": "2018-12",
          "actual_start": "2015",
          "actual_end": "2021",
          "note": "Track installation finished September 2017. In August 2018 the December 2018 central-section opening was abandoned; integrating train software with three signalling systems was the main problem."
        },
        {
          "name": "Trial running and trial operations",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2021-05",
          "actual_end": "2022-05",
          "note": "Trial running from May 2021, trial operations from November 2021; COVID-19 restrictions cut site productivity in 2020."
        },
        {
          "name": "Phased opening",
          "planned_start": "2018-12",
          "planned_end": "2019-12",
          "actual_start": "2022-05-24",
          "actual_end": "2023-05-21",
          "note": "Central section Paddington-Abbey Wood opened 24 May 2022; full-route timetable from 21 May 2023."
        }
      ],
      "milestones": [
        {
          "name": "Crossrail Act Royal Assent",
          "planned_date": null,
          "actual_date": "2008-07"
        },
        {
          "name": "Construction starts at Canary Wharf",
          "planned_date": "2009",
          "actual_date": "2009-05-15"
        },
        {
          "name": "Tunnelling complete",
          "planned_date": null,
          "actual_date": "2015-06-04"
        },
        {
          "name": "Central section opens",
          "planned_date": "2018-12",
          "actual_date": "2022-05-24"
        },
        {
          "name": "Full-route service",
          "planned_date": "2018-05",
          "actual_date": "2023-05-21"
        }
      ],
      "headline": "Crossrail's central section opened three and a half years late, in May 2022, with costs at £18.9 billion against £15.9 billion first announced in 2007.",
      "summary": "Crossrail built twin-bore tunnels under central London linking the Great Western line at Paddington with lines to Shenfield and Abbey Wood, with new central stations. Sponsored by the Department for Transport and Transport for London and delivered by Crossrail Ltd, construction started in May 2009. Branded the Elizabeth line, the central section opened on 24 May 2022, and the full timetable began on 21 May 2023.",
      "what_went_wrong_or_right": "Civil engineering went well: tunnelling finished on schedule in 2015. The failure came in systems integration and governance. The NAO's May 2019 report found that the programme was dominated by a fixed December 2018 opening date, set in 2010, which forced many activities to run in parallel. Design and contract changes raised contract costs by about GBP 2.5 billion between 2013 and 2018, the contractual model removed downward pressure on costs, and there was no detailed, achievable delivery plan until late 2018. The NAO also described an optimistic 'can do' culture that became unrealistic. Crossrail itself cited the difficulty of writing and testing software to integrate trains with three different signalling systems, plus late installation of tunnel equipment. Sponsors learned of the delay only weeks before the planned opening, announcing it in August 2018. Funding was raised to GBP 17.6 billion in December 2018 and later to GBP 18.8 billion. COVID-19 added several months in 2020.",
      "lessons": [
        "Do not let a fixed opening date override evidence from integration testing.",
        "Plan systems integration and software as the critical path, not civil works.",
        "Require a detailed, resource-loaded schedule and independent assurance before committing to dates."
      ],
      "fun_fact": "The 2007 cost estimates were set at a level the government judged had a 95 percent probability of not being exceeded.",
      "method_tags": [
        "phased_delivery",
        "critical_path"
      ],
      "related_history_ids": [
        "rcf-2004",
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Crossrail",
          "publisher": "National Audit Office (HC 965, 24 January 2014)",
          "url": "https://www.nao.org.uk/wp-content/uploads/2014/01/Crossrail.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Completing Crossrail (press release, 3 May 2019)",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/press-releases/crossrail/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Completing Crossrail (Summary)",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/wp-content/uploads/2019/05/Completing-Crossrail-Summary.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Crossrail",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Crossrail",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "high",
      "notes": "Baseline: the 2007 government funding package of GBP 15.9 billion for the infrastructure programme, with full opening planned for May 2018 (NAO 2014, paras 2.2 and 2.8). In 2010 the Spending Review cut available funding to GBP 14.8 billion and moved full opening to December 2019, with the central section in December 2018 (NAO 2014, 2019); the 2010 figure is the lower bound of planned_cost_range and is what the NAO uses as its comparator. Actual: GBP 18.9 billion as of May 2022 (Wikipedia; NAO 2021 update gave an GBP 18.8 billion funding package). Actual end is the full-route timetable of 21 May 2023, compared against the 2007 full-opening plan; the central section opened 24 May 2022 against a planned December 2018. The tunnelling start is given at year precision (2012). Figures nominal. FX: Fed H.10 annual averages, about $2.00 per pound (2007) and $1.24 (2022). Baseline audit 2026-10-25: Planned figures unchanged (2007 funding package of GBP 15.9 billion and May 2018 full opening are the first approved). Added the 2010 Spending Review settlement of GBP 14.8 billion with full opening in December 2019 (NAO 2014) as the rebaseline; it is the comparator the NAO uses.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 9,
      "slug": "dubai-metro",
      "name": "Dubai Metro Red Line",
      "short_name": "Dubai Metro",
      "category": "infrastructure",
      "subcategory": "metro",
      "country": "United Arab Emirates",
      "country_code": "AE",
      "countries": [
        "United Arab Emirates"
      ],
      "continent": "Asia",
      "city": "Dubai",
      "lat": 25.2665,
      "lng": 55.3143,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "2006",
      "planned_end": "2009-09-09",
      "actual_start": "2006-03-21",
      "actual_end": "2009-09-09",
      "actual_is_forecast": false,
      "planned_duration_months": 38.3,
      "actual_duration_months": 41.6,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 15500000000,
      "actual_cost": 28000000000,
      "planned_cost_range": [
        15500000000,
        16000000000
      ],
      "actual_cost_range": null,
      "cost_currency": "AED",
      "planned_cost_year": 2005,
      "cost_year": 2010,
      "planned_fx_to_usd": 0.2723,
      "actual_fx_to_usd": 0.2723,
      "planned_cost_usd_nominal": 4220650000,
      "cost_usd_nominal": 7624400000,
      "planned_cost_usd_today": 6957708085,
      "cost_usd_today": 11256839615,
      "overrun_usd_today": 5025374828,
      "overrun_pct": 80.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 75,
      "reported_overrun_source": "The National, 31 August 2009",
      "phases": [
        {
          "name": "Design-and-build contract award",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2005",
          "actual_end": "2005-05",
          "note": "The Roads and Transport Authority awarded an AED 12.45 billion design-and-build contract to the Dubai Rail Link (DURL) consortium of Japanese firms and Turkey's Yapi Merkezi in May 2005."
        },
        {
          "name": "Red Line construction",
          "planned_start": "2006",
          "planned_end": "2009-09",
          "actual_start": "2006-03-21",
          "actual_end": "2009-09",
          "note": "Work officially began on 21 March 2006; the RTA said in February 2009 the project would be completed on schedule despite the financial crisis."
        },
        {
          "name": "Red Line opening (first 10 stations)",
          "planned_start": "2009-09-09",
          "planned_end": "2009-09-09",
          "actual_start": "2009-09-09",
          "actual_end": "2009-09-09",
          "note": "Opened at 9:09:09 pm on 9 September 2009 with 10 of 29 planned stations."
        },
        {
          "name": "Remaining Red Line stations",
          "planned_start": "2009-09",
          "planned_end": "2010-02",
          "actual_start": "2010-04-30",
          "actual_end": "2011-03-11",
          "note": "Stations opened in batches on 30 April, 15 May and 15 October 2010 and 11 March 2011; the RTA had expected full operation by February 2010."
        },
        {
          "name": "Green Line (same budget envelope)",
          "planned_start": null,
          "planned_end": "2010",
          "actual_start": null,
          "actual_end": "2011-09-09",
          "note": "In August 2009 the Green Line was expected the following summer; it opened on 9 September 2011, with Al Jadaf and Creek stations on 1 March 2014."
        }
      ],
      "milestones": [
        {
          "name": "DURL contract awarded",
          "planned_date": null,
          "actual_date": "2005-05"
        },
        {
          "name": "Construction begins",
          "planned_date": null,
          "actual_date": "2006-03-21"
        },
        {
          "name": "Red Line opens",
          "planned_date": "2009-09-09",
          "actual_date": "2009-09-09"
        },
        {
          "name": "All original Red Line stations open",
          "planned_date": "2010-02",
          "actual_date": "2011-03-11"
        },
        {
          "name": "Green Line opens",
          "planned_date": "2010",
          "actual_date": "2011-09-09"
        }
      ],
      "headline": "Dubai's Red Line opened on its fixed date of 9 September 2009, but the two-line metro's budget rose from AED 15.5 billion to about AED 28 billion.",
      "summary": "The Dubai Metro Red Line is a driverless rail line running mostly on viaduct from Rashidiya through the city center and along Sheikh Zayed Road to Jebel Ali. The Roads and Transport Authority (RTA) awarded a design-and-build contract to the Dubai Rail Link consortium in May 2005, and work started on 21 March 2006. The line opened on schedule on 9 September 2009 with 10 stations; the rest opened through March 2011, and the Green Line followed in September 2011.",
      "what_went_wrong_or_right": "The opening date was met. The RTA fixed the launch for 9/9/09 and opened the line at 9:09:09 pm that day, after telling the press in February 2009 that the financial crisis would not delay it. The method was to open a working core and finish the rest later: only 10 of 29 stations opened at launch, and the remainder followed over the next 18 months rather than by the February 2010 date the RTA had forecast. Cost grew sharply. RTA chairman Mattar Al Tayer said in 2009 that the two lines would cost about AED 28 billion against an original budget of AED 15.5 billion; The National put the rise at 75 percent over original estimates. The RTA said this was not an overrun but the result of scope changes it chose to make: a 4.5 km extension to Emirates Road with extra stations and a new depot, an added Mall of the Emirates station, more than 3 km of extra Green Line track at Al Jadaf, and substantially redesigned stations and footbridges.",
      "lessons": [
        "A fixed, symbolic opening date can be held by opening a working core and staging the rest.",
        "Track scope changes separately so the baseline stays comparable with the outturn.",
        "Freeze station designs before contract award to avoid costly redesign during construction."
      ],
      "fun_fact": "The Red Line opened at 9 minutes and 9 seconds past 9 pm on 9 September 2009, or 9:09:09 on 09/09/09.",
      "method_tags": [
        "design_build",
        "phased_delivery",
        "fast_track"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Changes to metro put cost up by Dh12bn (31 August 2009)",
          "publisher": "The National",
          "url": "https://www.thenationalnews.com/uae/transport/changes-to-metro-put-cost-up-by-dh12bn-1.562126/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Dubai Metro budget up by Dh12.5 billion",
          "publisher": "Gulf News",
          "url": "https://gulfnews.com/uae/dubai-metro-budget-up-by-dh125-billion-1.546549",
          "accessed": "2026-10-25"
        },
        {
          "title": "Dubai Metro",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Dubai_Metro",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Scope: the published budget covers Phase 1, the Red and Green Lines together; no separate Red Line outturn was found, so cost figures are for both lines while the schedule fields track the Red Line. Baseline cost: AED 15.5 billion, the original budget cited by RTA chairman Mattar Al Tayer (Gulf News) and the value of the 35 km first phase (Wikipedia); The National gave Dh16 billion, hence planned_cost_range. The DURL design-and-build contract itself was AED 12.45 billion (Railway Gazette, via Wikipedia). Actual cost: about AED 28 billion, the final figure Al Tayer forecast in 2009 for completion by mid-2010; a 2014 report also described the system as built for Dh28 billion. This was announced as a forecast and no audited outturn was found. The RTA disputes that this is an overrun, citing deliberate scope additions. reported_overrun_pct of 75 is The National's figure (based on Dh16 billion). Schedule baseline: the 9 September 2009 opening date; actual_end is the Red Line opening, with later station openings shown as phases. FX: UAE dirham pegged at AED 3.6725 per US dollar (Central Bank of the UAE), giving $0.2723 per dirham for both years.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 10,
      "slug": "interstate-highway-system",
      "name": "Dwight D. Eisenhower National System of Interstate and Defense Highways",
      "short_name": "US Interstate System",
      "category": "infrastructure",
      "subcategory": "highway network",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Nationwide (completed at Glenwood Canyon, Colorado)",
      "lat": 39.58,
      "lng": -107.24,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1956",
      "planned_end": "1969",
      "actual_start": "1956-06-29",
      "actual_end": "1992-10-14",
      "actual_is_forecast": false,
      "planned_duration_months": 156,
      "actual_duration_months": 435.5,
      "delay_months": 279.4,
      "delay_pct": 179.1,
      "planned_cost": 37622000000,
      "actual_cost": 128900000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        114000000000,
        128900000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1958,
      "cost_year": 1991,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 37622000000,
      "cost_usd_nominal": 128900000000,
      "planned_cost_usd_today": 419830276817,
      "cost_usd_today": 304692768141,
      "overrun_usd_today": 215762191547,
      "overrun_pct": 242.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Federal-Aid Highway Act and early contracts",
          "planned_start": "1956",
          "planned_end": null,
          "actual_start": "1956-06-29",
          "actual_end": "1958",
          "note": "Act signed 29 June 1956; first contract in Missouri on US 66; Kansas began paving 26 September 1956. Title I set the system at 41,000 miles."
        },
        {
          "name": "Main network construction",
          "planned_start": "1958",
          "planned_end": "1969",
          "actual_start": "1958",
          "actual_end": "1974",
          "note": "First mandated cost estimate to Congress in 1958 ($37.6bn). Nebraska became the first state to finish its mainline Interstates in 1974."
        },
        {
          "name": "Environmental review era and redefinition",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1969",
          "actual_end": "1986",
          "note": "1969 National Environmental Policy Act lengthened reviews; the 1981 Highway Act redefined what counted as completion. I-80 became a continuous coast-to-coast freeway in 1986."
        },
        {
          "name": "Last links: I-70 Glenwood Canyon",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1980",
          "actual_end": "1992-10-14",
          "note": "Final approval 1979, construction from 1980, opened 14 October 1992 at $490 million for 12.5 miles."
        }
      ],
      "milestones": [
        {
          "name": "Federal-Aid Highway Act signed",
          "planned_date": null,
          "actual_date": "1956-06-29"
        },
        {
          "name": "First Interstate Cost Estimate",
          "planned_date": null,
          "actual_date": "1958"
        },
        {
          "name": "Final Interstate Cost Estimate",
          "planned_date": null,
          "actual_date": "1991-01"
        },
        {
          "name": "Original system proclaimed complete",
          "planned_date": "1969",
          "actual_date": "1992-10-14"
        }
      ],
      "headline": "The Interstate System's cost estimate rose from $37.6 billion in 1958 to $128.9 billion in 1991, and it took 36 years instead of about 12.",
      "summary": "The Interstate System is a network of about 41,000 miles of limited-access highways authorized by the Federal-Aid Highway Act of 1956, signed by President Eisenhower on 29 June 1956. The federal government paid most of the cost from a dedicated Highway Trust Fund. Congress required periodic cost estimates, the first in 1958 and the last in 1991. The original system was proclaimed complete when I-70 through Glenwood Canyon, Colorado, opened on 14 October 1992.",
      "what_went_wrong_or_right": "The network was delivered, but at more than three times the first mandated estimate and almost three times the planned duration. FHWA's table of the 15 legislatively required estimates shows the total rising from $37.622 billion in 1958 to $128.9 billion in January 1991, with the federal share going from $33.952 billion to $114.3 billion. FHWA attributes the changes to system adjustments, new eligibility rules and legislation, unit price changes, social, economic and environmental requirements, right-of-way and design changes, extra interchanges and construction overruns. Much of the growth is inflation, since the estimates are in current dollars. The schedule slipped as urban routes met resistance and the 1969 National Environmental Policy Act added review; Glenwood Canyon alone was planned from 1960 and finished in 1992 at $490 million for 12.5 miles. Wikipedia reports that the initial estimate was $25 billion over 12 years. The approach that worked was a dedicated trust fund and uniform national standards, which kept money flowing for decades.",
      "lessons": [
        "Re-estimate on a fixed schedule and report it to the funder, as Congress required here.",
        "Separate inflation from scope growth when reporting long-program costs.",
        "Budget time for environmental and community review in urban segments."
      ],
      "fun_fact": "In 1986, I-80 became the world's first continuous freeway to span from the Atlantic to the Pacific.",
      "method_tags": [
        "phased_delivery",
        "waterfall"
      ],
      "related_history_ids": [
        "cpm-1957",
        "pert-1958",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Interstate Cost Estimates, 1958-1991",
          "publisher": "Federal Highway Administration",
          "url": "https://www.fhwa.dot.gov/highwayhistory/data/page03.cfm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Interstate Highway System",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Interstate_Highway_System",
          "accessed": "2026-10-25"
        },
        {
          "title": "The last piece of the Interstate Highway System may have been the toughest",
          "publisher": "ASCE Civil Engineering",
          "url": "https://asce.org/publications-and-news/civil-engineering-source/civil-engineering-magazine/issues/magazine-issue/article/2021/03/the-last-piece-of-the-interstate-highway-system-may-have-been-the-toughest",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline (as instructed): the 1958 Interstate Cost Estimate to Congress, $37.622bn total ($33.952bn federal share), per FHWA. Wikipedia cites an initial 1956 estimate of $25bn over 12 years. Actual: the final estimate of January 1991, $128.9bn total ($114.3bn federal); Wikipedia gives $114bn, hence the range. All figures are current dollars of their year, so basis is nominal and much of the growth is inflation. Planned end 1969 is derived from the 12-year horizon of the original estimate starting 1956-57; it is approximate. 'Completed' in 1992 refers to the original system as proclaimed with I-70 Glenwood Canyon; FHWA describes the system as essentially complete by 1998. Coordinates are Glenwood Canyon, Colorado. Baseline audit 2026-10-25: Planned figures unchanged at the 1958 Interstate Cost Estimate, as previously instructed by the editor; the 1956 $25bn over 12 years (Wikipedia) is earlier but was a federal funding authorization rather than a cost estimate. Editor may wish to review under the first-announced rule.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 11,
      "slug": "erie-canal",
      "name": "Erie Canal",
      "short_name": "Erie Canal",
      "category": "infrastructure",
      "subcategory": "canal",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Rome, New York (Albany to Buffalo)",
      "lat": 43.2128,
      "lng": -75.4557,
      "era": "1800s",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1817-07-04",
      "planned_end": null,
      "actual_start": "1817-07-04",
      "actual_end": "1825-10-26",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 99.7,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": 5000000,
      "actual_cost": 7143789,
      "planned_cost_range": null,
      "actual_cost_range": [
        7143789,
        7150000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1817,
      "cost_year": 1825,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 5000000,
      "cost_usd_nominal": 7143789,
      "planned_cost_usd_today": 100781250,
      "cost_usd_today": 203282819,
      "overrun_usd_today": 61003408,
      "overrun_pct": 42.9,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Authorization",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1817-03",
          "actual_end": "1817-04-15",
          "note": "Canal commissioners' March 1817 report revised the estimate to $5,000,000; the legislature authorized construction on 15 April 1817."
        },
        {
          "name": "Middle section, Rome to Utica and Salina",
          "planned_start": "1817-07-04",
          "planned_end": null,
          "actual_start": "1817-07-04",
          "actual_end": "1820",
          "note": "Ground broken at Rome on 4 July 1817; Rome-Utica opened October 1819; Utica to Salina (Syracuse) completed 1820."
        },
        {
          "name": "Eastern section to Albany",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1820",
          "actual_end": "1823-09-10",
          "note": "Brockport to Albany opened 10 September 1823."
        },
        {
          "name": "Western section to Buffalo",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1823",
          "actual_end": "1825-10-26",
          "note": "In 1824 the commissioners fixed Buffalo as the western terminus; the full 363-mile canal was navigable on 26 October 1825."
        }
      ],
      "milestones": [
        {
          "name": "Construction authorized",
          "planned_date": null,
          "actual_date": "1817-04-15"
        },
        {
          "name": "Groundbreaking at Rome",
          "planned_date": "1817-07-04",
          "actual_date": "1817-07-04"
        },
        {
          "name": "First section opens (Rome-Utica)",
          "planned_date": null,
          "actual_date": "1819-10-23"
        },
        {
          "name": "Full canal opens",
          "planned_date": null,
          "actual_date": "1825-10-26"
        }
      ],
      "headline": "New York built the 363-mile Erie Canal in eight years for $7.14 million, about 43 percent above the 1817 estimate of $5 million.",
      "summary": "The Erie Canal linked the Hudson River at Albany with Lake Erie at Buffalo, opening a water route from New York City to the Great Lakes. Championed by De Witt Clinton and paid for by New York State, it was authorized in April 1817, begun at Rome on 4 July 1817 and opened in sections from 1819. The full canal opened on 26 October 1825 at a recorded cost of $7,143,789, and tolls soon repaid the state's construction debt.",
      "what_went_wrong_or_right": "The canal overran its 1817 estimate by roughly 43 percent in nominal terms, but delivered on its economic case. The commissioners' revised March 1817 estimate was $5 million, close to the $5 million figures of 1810-1811 surveys; the State Engineer's 1878 report records a final cost of $7,143,789. Opening in sections was the key decision. Building the middle section first, Rome to Utica in 1819 and on to Salina in 1820, produced early toll revenue and public support before the eastern section to Albany (1823) and the western section to Buffalo were finished. Opponents had called it 'Clinton's Folly', and in 1819 critics estimated that at that pace it would take 30 years; instead it was finished in eight. Toll revenue covered the construction debt quickly, and through 1883 tolls brought in $121 million against $78 million of total costs, according to a 1961 New York legislative report.",
      "lessons": [
        "Open usable sections early to earn revenue and build support during construction.",
        "Treat early sections as a test of cost and productivity before committing to harder stretches.",
        "A credible revenue case can carry a project through a moderate overrun."
      ],
      "fun_fact": "At the 1825 'Wedding of the Waters', Clinton poured Lake Erie water into New York Harbor.",
      "method_tags": [
        "phased_delivery",
        "iterative"
      ],
      "related_history_ids": [
        "adamiecki-1896"
      ],
      "sources": [
        {
          "title": "Erie Canal",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Erie_Canal",
          "accessed": "2026-10-25"
        },
        {
          "title": "Report of the Joint Legislative Committee on the Barge Canal (1961), Chapter 1",
          "publisher": "New York State Legislature (via eriecanal.org)",
          "url": "https://eriecanal.org/texts/NYS1961/chap1.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "History of Livingston County, New York, part 22",
          "publisher": "ldsgenealogy.com (transcription of 1881 county history)",
          "url": "https://ldsgenealogy.com/NY/books/History-of-Livingston-County-New-York-with-illustrations-and-biographical-sketches-of-some-of-its-prominent-men-and-pioneers-part-22.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "The Building of the Erie Canal (Epochs of American History, vol. 5)",
          "publisher": "USGenNet",
          "url": "https://usgennet.org/usa/topic/preservation/epochs/vol5/pg161.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: $5,000,000 revised estimate in the canal commissioners' report of March 1817 (Van Rensselaer, Clinton, Young, Ellicott, Holley), as cited in the Livingston County history. Actual: $7,143,789 per the State Engineer's Report of 1878 (p. 85), cited in the same history; the 1961 legislative report rounds it to $7,150,000 (range). Both nominal dollars; no FX needed. No formal completion date was set in 1817, so planned_end is null; Clinton said in 1820 the canal could be completed in five years. The 1819 '30 years at this pace' remark is from Wikipedia.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 12,
      "slug": "transcontinental-railroad",
      "name": "First Transcontinental Railroad",
      "short_name": "Transcontinental RR",
      "category": "infrastructure",
      "subcategory": "railway",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Promontory Summit, Utah",
      "lat": 41.6181,
      "lng": -112.5517,
      "era": "1800s",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": null,
      "planned_end": "1876-07-01",
      "actual_start": "1863-01-08",
      "actual_end": "1869-05-10",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 76.1,
      "delay_months": -85.7,
      "delay_pct": null,
      "planned_cost": null,
      "actual_cost": 99500000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": null,
      "cost_year": 1869,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": 99500000,
      "planned_cost_usd_today": null,
      "cost_usd_today": 2406656250,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Pacific Railroad Act and financing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1862-07-01",
          "actual_end": "1863-01-08",
          "note": "Lincoln signed the Act on 1 July 1862: federal bonds of $16,000 per mile, doubled and trebled in harder terrain, plus land grants."
        },
        {
          "name": "Central Pacific builds east from Sacramento",
          "planned_start": null,
          "planned_end": "1876-07-01",
          "actual_start": "1863-01-08",
          "actual_end": "1869-05-10",
          "note": "Ground broken 8 January 1863; the Sierra Nevada crossing relied heavily on Chinese laborers."
        },
        {
          "name": "Union Pacific builds west from Omaha",
          "planned_start": null,
          "planned_end": "1876-07-01",
          "actual_start": "1865-07",
          "actual_end": "1869-05-10",
          "note": "Union Pacific did not start construction until July 1865, per Wikipedia."
        },
        {
          "name": "Junction at Promontory Summit",
          "planned_start": null,
          "planned_end": "1876-07-01",
          "actual_start": "1869-05-10",
          "actual_end": "1869-05-10",
          "note": "Golden spike ceremony joining the two lines, seven years before the statutory deadline."
        }
      ],
      "milestones": [
        {
          "name": "Pacific Railroad Act signed",
          "planned_date": null,
          "actual_date": "1862-07-01"
        },
        {
          "name": "Central Pacific groundbreaking",
          "planned_date": null,
          "actual_date": "1863-01-08"
        },
        {
          "name": "Golden spike at Promontory Summit",
          "planned_date": "1876-07-01",
          "actual_date": "1869-05-10"
        }
      ],
      "headline": "The first US transcontinental railroad was joined at Promontory Summit on 10 May 1869, seven years ahead of the 1 July 1876 deadline set by Congress.",
      "summary": "The first transcontinental railroad linked the existing eastern network at Council Bluffs and Omaha with Sacramento, California. Authorized by the Pacific Railroad Act of 1862, it was built by the Central Pacific from the west starting in January 1863 and the Union Pacific from the east, with federal bonds and land grants paid per mile of track. The lines met at Promontory Summit, Utah, on 10 May 1869. The NPS puts construction costs at about $63.5 million for the Union Pacific and $36 million for the Central Pacific.",
      "what_went_wrong_or_right": "Measured against the schedule Congress set, the railroad was early. Section 17 of the 1862 Act required a continuous line by 1 July 1876; it was joined in May 1869. The financing design drove the pace: federal bonds were issued per mile completed, at $16,000 on level ground, double in foothills and treble in the mountains, which rewarded speed and length of track more than quality or route efficiency. The Central Pacific struggled to find labor until it hired Chinese workers, who became the core of its Sierra Nevada workforce. The Union Pacific started slowly and did not begin real construction until July 1865. The incentive also invited abuse. Union Pacific insiders ran construction through Crédit Mobilier, which billed far more than the work cost; Wikipedia cites roughly $94 million billed against about $50 million in actual building cost. No official construction budget was set at authorization, so a planned-versus-actual cost comparison is not possible.",
      "lessons": [
        "Pay-per-mile incentives speed delivery but need quality and cost controls attached.",
        "Related-party construction contracts need independent audit to prevent inflated billing.",
        "Labor supply is a critical-path risk; plan recruitment before construction starts."
      ],
      "fun_fact": "Mormon workers signed a lone tree beside the track 1,000 miles from Omaha, now known as the Thousand Mile Tree.",
      "method_tags": [
        "phased_delivery",
        "cost_plus"
      ],
      "related_history_ids": [
        "adamiecki-1896",
        "taylor-1911"
      ],
      "sources": [
        {
          "title": "First transcontinental railroad",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/First_transcontinental_railroad",
          "accessed": "2026-10-25"
        },
        {
          "title": "Pacific Railway Act (primary source text)",
          "publisher": "American Battlefield Trust",
          "url": "https://www.battlefields.org/learn/primary-sources/pacific-railway-act",
          "accessed": "2026-10-25"
        },
        {
          "title": "Golden Spike National Historic Site handbook (NPS Historical Handbook 40)",
          "publisher": "National Park Service (via npshistory.com)",
          "url": "https://www.npshistory.com/handbooks/historical/40/hh40i.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "No construction budget was approved in 1862, so planned_cost is null and no overrun can be computed. Planned end: 1 July 1876, the completion deadline in Section 17 of the Pacific Railroad Act of 1862. Actual cost: $99.5m is the sum of NPS handbook figures ($63.5m Union Pacific, about half from the government loan; $36m Central Pacific, whose books were partly destroyed). Other sources give about $50m for the Union Pacific's actual cost to contractors. Figures are nominal 1860s dollars, partly paid in bonds and stock valued below par. Union Pacific's groundbreaking ceremony date was not confirmed in sources opened; its construction start is given as July 1865. Completion here is the Promontory junction of 10 May 1869. Editor decision 2026-10-25: kept in the dataset (flag was: no published baseline budget; planned_cost is null).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 13,
      "slug": "golden-gate-bridge",
      "name": "Golden Gate Bridge",
      "short_name": "Golden Gate Bridge",
      "category": "infrastructure",
      "subcategory": "bridge",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "San Francisco",
      "lat": 37.8197,
      "lng": -122.4786,
      "era": "1900-1945",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": "1933-01-05",
      "planned_end": null,
      "actual_start": "1933-01-05",
      "actual_end": "1937-05-27",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 52.7,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": 35000000,
      "actual_cost": 33666000,
      "planned_cost_range": [
        27000000,
        35000000
      ],
      "actual_cost_range": [
        33666000,
        35000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1930,
      "cost_year": 1937,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 35000000,
      "cost_usd_nominal": 33666000,
      "planned_cost_usd_today": 674551793,
      "cost_usd_today": 753978125,
      "overrun_usd_today": -29876042,
      "overrun_pct": -3.8,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Bond approval and contract award",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1930-11",
          "actual_end": "1932-11",
          "note": "Voters approved the bond issue in November 1930; contracts totaling $23,843,905 were awarded in November 1932."
        },
        {
          "name": "Marin tower",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1933-11-07",
          "actual_end": "1934-06-28",
          "note": "Some sources give November 1934 for completion."
        },
        {
          "name": "San Francisco pier, fender and tower",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1933",
          "actual_end": "1935-06-28",
          "note": "Open-water pier inside a fender wall finished October 1934; tower built January to June 1935."
        },
        {
          "name": "Cable spinning",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1935-08-02",
          "actual_end": "1936-05",
          "note": "Footwalk wires August-September 1935; main cable spinning and compression October 1935 to May 1936."
        },
        {
          "name": "Suspended structure and roadway",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1936-07",
          "actual_end": "1937-04-19",
          "note": "Main span halves joined 18 November 1936; roadway completed 19 April 1937. Ten men died on 17 February 1937 when a scaffold broke through the safety net."
        },
        {
          "name": "Opening",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1937-05-27",
          "actual_end": "1937-05-27",
          "note": "Opened to pedestrians on 27 May 1937, ahead of schedule."
        }
      ],
      "milestones": [
        {
          "name": "Bond issue approved by voters",
          "planned_date": null,
          "actual_date": "1930-11"
        },
        {
          "name": "Construction starts",
          "planned_date": "1933-01-05",
          "actual_date": "1933-01-05"
        },
        {
          "name": "Main span halves joined",
          "planned_date": null,
          "actual_date": "1936-11-18"
        },
        {
          "name": "Bridge opens",
          "planned_date": null,
          "actual_date": "1937-05-27"
        }
      ],
      "headline": "The Golden Gate Bridge was built for about $35 million, the size of its bond issue, and finished ahead of schedule and $1.3 million under budget.",
      "summary": "Chief engineer Joseph Strauss's Golden Gate Bridge spans the Golden Gate strait between San Francisco and Marin County. Financed by a $35 million bond issue of the Golden Gate Bridge and Highway District, backed by Bank of America, it was built between January 1933 and April 1937 and opened on 27 May 1937. Its 1,280 m main span was the world's longest at the time. Eleven men died during construction; a safety net saved 19 others.",
      "what_went_wrong_or_right": "The project is a rare case of a megaproject landing on budget during the Depression. The district fixed the financing first: voters approved bonds in November 1930, and contracts for the main work, totaling $23.8 million, were awarded in November 1932 before construction began. Strauss replaced his early hybrid cantilever-suspension design, estimated at $17 million, with a pure suspension bridge; the FHWA notes the $35 million bond was well below early construction estimates of up to $100 million. The hardest technical task was the San Francisco pier, built in open water within a fender wall against strong tidal currents. Safety practice was unusually strict for the period: hard hats, glare-free goggles, special diets against dizziness and a net under the deck. The one catastrophic failure came on 17 February 1937, when a scaffold fell through the net and ten men died. The bonds were retired in 1971 with $35 million principal and nearly $39 million interest paid from tolls.",
      "lessons": [
        "Secure financing and award major contracts before breaking ground.",
        "Simplify the design concept early; Golden Gate's switch to pure suspension paid off.",
        "Invest in site safety systems; the net saved 19 lives but needed redundancy."
      ],
      "fun_fact": "The 19 workers whose falls were caught by the safety net called themselves the Half Way to Hell Club.",
      "method_tags": [
        "fixed_price",
        "phased_delivery"
      ],
      "related_history_ids": [
        "hoover-gantt-1931",
        "gantt-1910"
      ],
      "sources": [
        {
          "title": "Golden Gate Bridge",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Golden_Gate_Bridge",
          "accessed": "2026-10-25"
        },
        {
          "title": "Construction",
          "publisher": "Golden Gate Bridge, Highway and Transportation District",
          "url": "https://www.goldengate.org/bridge/history-research/bridge-construction/construction/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Golden Gate Bridge (Contributions and Crossroads fact sheet)",
          "publisher": "Federal Highway Administration",
          "url": "https://www.fhwa.dot.gov/candc/factsheets/goldengatebridge.pdf",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the $35 million bond issue authorized after the November 1930 vote (Golden Gate Bridge District; FHWA). Wikipedia gives the budget at bond approval as $27 million (and calls the measure a $30 million bond), hence planned_cost_range. Actual: total construction cost about $35 million including a $1,334,000 surplus (District), i.e. FHWA's 'under budget by $1.3 million'; the lower bound of actual_cost_range ($33,666,000) is $35 million less that surplus. A New World Encyclopedia entry (search result only, not opened) claims a $30.1 million budget and $36.7 million actual, a 22 percent overrun; this is the upper bound of the range and why confidence is disputed. Planned completion date was not found in any opened source; FHWA states the bridge was completed ahead of schedule. Cost figures nominal USD; fx = 1. UPDATE 2026-10-25: actual_cost changed from $35,000,000 to $33,666,000: the District states the $35 million authorized bond issue covered total construction with $1,334,000 surplus, and FHWA says the bridge was completed $1.3 million under budget, so spending was $35m less the surplus. planned_cost remains the $35 million bond authorization (like-for-like: authorized amount vs amount spent). The $36.7-36.8 million 'final cost' claims were not found in any opened source and were removed from the range. Planned completion date: not found on the District construction page, the FHWA fact sheet or Wikipedia; FHWA says only 'ahead of schedule', so planned_end stays null.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 14,
      "slug": "gotthard-base-tunnel",
      "name": "Gotthard Base Tunnel",
      "short_name": "Gotthard Base Tunnel",
      "category": "infrastructure",
      "subcategory": "tunnel",
      "country": "Switzerland",
      "country_code": "CH",
      "countries": [
        "Switzerland"
      ],
      "continent": "Europe",
      "city": "Erstfeld / Bodio",
      "lat": 46.8358,
      "lng": 8.6464,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1999",
      "planned_end": "2017",
      "actual_start": "1999-11-04",
      "actual_end": "2016-12-11",
      "actual_is_forecast": false,
      "planned_duration_months": 216,
      "actual_duration_months": 205.2,
      "delay_months": -6.7,
      "delay_pct": -3.1,
      "planned_cost": 6323000000,
      "actual_cost": 9560000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "CHF",
      "planned_cost_year": 1998,
      "cost_year": 1998,
      "planned_fx_to_usd": 0.6894,
      "actual_fx_to_usd": 0.6894,
      "planned_cost_usd_nominal": 4359076200,
      "cost_usd_nominal": 6590664000,
      "planned_cost_usd_today": 8610465952,
      "cost_usd_today": 13018512495,
      "overrun_usd_today": 4408046542,
      "overrun_pct": 51.2,
      "overrun_basis": "real",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Referendum and exploration",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1992-09-27",
          "actual_end": "1996",
          "note": "Voters approved the NRLA (NEAT) on 27 September 1992 with 63.6 percent; sounding drills began in 1993. In 1995 the Federal Council chose to build Gotthard and Lötschberg in parallel."
        },
        {
          "name": "Funding vote and preparatory works",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1996",
          "actual_end": "1999-11-04",
          "note": "Preparatory works from 1996; 1998 funding vote (63.5 percent yes) allotted CHF 13.6bn of a CHF 30bn public transport fund to the NRLA."
        },
        {
          "name": "Excavation",
          "planned_start": "1999",
          "planned_end": null,
          "actual_start": "1999-11-04",
          "actual_end": "2011-03-23",
          "note": "First blast at Amsteg 4 November 1999; TBM boring from 2003; east tube breakthrough 15 October 2010, west tube 23 March 2011."
        },
        {
          "name": "Rail systems installation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2011-09-02",
          "actual_end": "2016-05",
          "note": "Rail technology installation began in the north on 2 September 2011 (tunnel-online); commissioning May 2016."
        },
        {
          "name": "Handover, trial operation and service start",
          "planned_start": null,
          "planned_end": "2017",
          "actual_start": "2016-05-31",
          "actual_end": "2016-12-11",
          "note": "Handover to the federal government 31 May 2016; inauguration 1 June 2016; timetabled passenger service 11 December 2016, about a year earlier than the pre-2011 schedule."
        }
      ],
      "milestones": [
        {
          "name": "NRLA referendum",
          "planned_date": null,
          "actual_date": "1992-09-27"
        },
        {
          "name": "Final breakthrough (west tube)",
          "planned_date": null,
          "actual_date": "2011-03-23"
        },
        {
          "name": "Official inauguration",
          "planned_date": null,
          "actual_date": "2016-06-01"
        },
        {
          "name": "Timetabled service",
          "planned_date": "2017",
          "actual_date": "2016-12-11"
        }
      ],
      "headline": "The 57 km Gotthard Base Tunnel opened about a year early in 2016, but at CHF 9.56 billion it cost 51 percent more than the 1998 estimate in constant prices.",
      "summary": "The Gotthard Base Tunnel is the world's longest railway tunnel, two single-track bores of 57 km under the Swiss Alps between Erstfeld and Bodio. It is the centerpiece of the New Railway Link through the Alps (NRLA), approved by referendum in 1992. Excavation started in 1999 and ended in 2011, with up to 2,450 m of rock overhead. AlpTransit Gotthard handed the tunnel over on 31 May 2016 and timetabled service began on 11 December 2016.",
      "what_went_wrong_or_right": "Schedule went better than cost. Swiss federal figures put the 1998 projected cost of the tunnel at CHF 6.323 billion and the December 2015 projection at CHF 9.560 billion, both on a 1998 price base without inflation, a real increase of about 51 percent. Swissinfo reported in 2005 that extra costs came from geology and from rail equipment that proved more complex than foreseen. The parliamentary NEAT supervisory delegation tracked forecasts against a fixed 1998 price base, which kept real increases visible and separate from inflation. Excavation finished in March 2011 and fit-out progressed well enough that in August 2011 the Federal Office of Transport moved timetabled operation forward to the end of 2016, a year earlier than planned. Nine workers died during construction. The line was disrupted again in August 2023 when a freight derailment closed one bore until September 2024.",
      "lessons": [
        "Report forecasts on a fixed price base so real growth is separated from inflation.",
        "Approve explicit geological reserves for deep tunnels rather than hiding risk in base estimates.",
        "Parallel headings from intermediate shafts can recover schedule lost to bad ground."
      ],
      "fun_fact": "Excavation removed about 28.2 million tonnes of rock, described as equal to five Great Pyramids of Giza.",
      "method_tags": [
        "phased_delivery",
        "critical_path",
        "simulation"
      ],
      "related_history_ids": [
        "cpm-1957",
        "rcf-2004"
      ],
      "sources": [
        {
          "title": "Gotthard Base Tunnel",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Gotthard_Base_Tunnel",
          "accessed": "2026-10-25"
        },
        {
          "title": "NRLA",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/NRLA",
          "accessed": "2026-10-25"
        },
        {
          "title": "Major rail projects swallow more money",
          "publisher": "Swissinfo",
          "url": "https://www.swissinfo.ch/eng/major-rail-projects-swallow-more-money/4302350",
          "accessed": "2026-10-25"
        },
        {
          "title": "NEAT supervisory delegation press release, 27 August 2014",
          "publisher": "Swiss Parliament",
          "url": "https://www.parlament.ch/press-releases/Pages/2014/mm-nad-2014-08-27.aspx",
          "accessed": "2026-10-25"
        },
        {
          "title": "Gotthard-Tunnel schon 2016 fertig (23 August 2011)",
          "publisher": "eurotransport.de",
          "url": "https://www.eurotransport.de/logistik/spedition-und-logistik/alp-transit-gotthard-tunnel-schon-2016-fertig/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline cost: CHF 6.323bn, the 1998 projected total cost of the tunnel at the start of NRLA funding (the 1992 referendum figure for the tunnel alone was not found). Actual: CHF 9.560bn, December 2015 projected final cost. NEAT forecasts are on a 1998 price base without inflation (parliament.ch 2014), so the comparison is treated as real. The often-quoted CHF 12.2bn covers Gotthard plus Ceneri. Planned end: the 1990s baseline opening year was not found; 2017 is the official target in force before August 2011, when operation was moved forward a year (eurotransport.de). Treat planned_end as a later baseline. FX: approximate 1998 annual average, about 1.45 CHF per USD (Federal Reserve H.10), not re-checked in this session. Baseline audit 2026-10-25: Planned fields are a later baseline (1998 cost, pre-2011 2017 target); the first approved 1992 figures could still not be sourced, so they are left unchanged.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 15,
      "slug": "heathrow-terminal-5",
      "name": "Heathrow Terminal 5",
      "short_name": "Heathrow T5",
      "category": "infrastructure",
      "subcategory": "airport terminal",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "London",
      "lat": 51.4728,
      "lng": -0.4875,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "on_time_on_budget",
      "planned_start": "2002-09",
      "planned_end": "2008-03",
      "actual_start": "2002-09",
      "actual_end": "2008-03-27",
      "actual_is_forecast": false,
      "planned_duration_months": 66,
      "actual_duration_months": 66.4,
      "delay_months": 0.4,
      "delay_pct": 0.6,
      "planned_cost": 4300000000,
      "actual_cost": 4300000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        4200000000,
        4300000000
      ],
      "cost_currency": "GBP",
      "planned_cost_year": 2002,
      "cost_year": 2008,
      "planned_fx_to_usd": 1.5023,
      "actual_fx_to_usd": 1.8542,
      "planned_cost_usd_nominal": 6458600000,
      "cost_usd_nominal": 7976500000,
      "planned_cost_usd_today": 11560953747,
      "cost_usd_today": 11927764683,
      "overrun_usd_today": 0,
      "overrun_pct": 0,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 0,
      "reported_overrun_source": "GIHub case study; Designing Buildings Wiki (on time and within budget)",
      "phases": [
        {
          "name": "Public planning inquiry",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1995-05-16",
          "actual_end": "1999-03-17",
          "note": "Longest planning inquiry in UK history, nearly four years."
        },
        {
          "name": "Government decision",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1999-03-17",
          "actual_end": "2001-11-20",
          "note": "Transport Secretary Stephen Byers granted planning permission on 20 November 2001."
        },
        {
          "name": "Construction under the T5 Agreement",
          "planned_start": "2002-09",
          "planned_end": "2008-03",
          "actual_start": "2002-09",
          "actual_end": "2008-03-14",
          "note": "Earthworks from September 2002; BAA held the major risks and paid suppliers cost plus a fixed fee with incentives. In 2004 £100m of contingency was moved into a central pot."
        },
        {
          "name": "Opening and operational start",
          "planned_start": "2008-03",
          "planned_end": "2008-03",
          "actual_start": "2008-03-14",
          "actual_end": "2008-03-27",
          "note": "Official opening by Queen Elizabeth II 14 March 2008; passenger operations 27 March 2008. Over the next 10 days about 42,000 bags were delayed and more than 500 flights cancelled."
        }
      ],
      "milestones": [
        {
          "name": "Planning permission granted",
          "planned_date": null,
          "actual_date": "2001-11-20"
        },
        {
          "name": "Construction start",
          "planned_date": "2002-09",
          "actual_date": "2002-09"
        },
        {
          "name": "First passengers",
          "planned_date": "2008-03",
          "actual_date": "2008-03-27"
        }
      ],
      "headline": "BAA delivered the £4.3 billion Heathrow Terminal 5 on time and within budget, then lost more than 500 flights in its first ten days.",
      "summary": "Heathrow Terminal 5 is a terminal complex for British Airways at London's busiest airport, designed by the Richard Rogers Partnership with Arup and Mott MacDonald. After a public inquiry from 1995 to 1999 and approval in November 2001, construction began in September 2002 under BAA's T5 Agreement, a relational contract in which the client held the major risks. The terminal opened to passengers on 27 March 2008. Its main building is the largest free-standing building in the UK.",
      "what_went_wrong_or_right": "Construction was a recognized success; the handover was not. BAA's pre-project study of UK projects over £1 billion and international airports found none delivered on time, on budget and to standard, and predicted T5 would be about £1 billion over budget, a year late and cause at least two deaths if run conventionally. BAA responded with the T5 Agreement: a cost-plus contract with a fixed fee and incentive fund, in which BAA retained the major risks, removed contractors' risk contingencies and pooled contingency centrally. GIHub and Designing Buildings Wiki both report that the project was finished on time and within its £4.3 billion budget. Operational readiness was the weak point. On opening day, 27 March 2008, British Airways cancelled 34 flights and suspended check-in; over ten days about 42,000 bags were delayed and more than 500 flights cancelled, blamed on IT problems and car parking. The case shows that integration and trial operations belong inside the project plan, not after it.",
      "lessons": [
        "If the client holds the risk, it can remove contractors' inflated contingencies.",
        "Pool contingency centrally and spend it where risks actually arise.",
        "Treat operational trials and staff readiness as deliverables on the critical path."
      ],
      "fun_fact": "Archaeologists working on the T5 site recovered more than 80,000 artefacts.",
      "method_tags": [
        "cost_plus",
        "critical_path"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Heathrow Terminal 5",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Heathrow_Terminal_5",
          "accessed": "2026-10-25"
        },
        {
          "title": "Heathrow Terminal 5 case study",
          "publisher": "Global Infrastructure Hub",
          "url": "https://infrastructuredeliverymodels.gihub.org/case-studies/heathrow-terminal-5/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Procurement of Heathrow T5",
          "publisher": "Designing Buildings Wiki",
          "url": "https://www.designingbuildings.co.uk/w/Procurement_of_Heathrow_T5",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: £4.3bn budget described as the 'planned' budget by GIHub; the date the budget was set is not given in sources opened, so 2002 (construction start) is assumed as price year. Actual: delivered 'within' £4.3bn (GIHub, Designing Buildings Wiki); Wikipedia's infobox gives £4.2bn, hence the range. No independent audit-office outturn was found; on-budget claims originate with BAA and project participants. Planned end: sources say on time; the exact planned opening day was not found, so March 2008 is used. Planned start September 2002 assumes construction began as planned. FX: approximate annual averages, 2002 about 1.50 and 2008 about 1.85 USD per GBP (Federal Reserve H.10), not re-checked in this session.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 16,
      "slug": "hs2",
      "name": "High Speed 2 (Phase 1, London-West Midlands)",
      "short_name": "HS2",
      "category": "infrastructure",
      "subcategory": "high-speed rail",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "London to Birmingham",
      "lat": 52.4823,
      "lng": -1.8869,
      "era": "2015-now",
      "status": "ongoing",
      "outcome": "over_budget_and_late",
      "planned_start": "2017",
      "planned_end": "2026-12",
      "actual_start": "2020-09-04",
      "actual_end": "2039-10",
      "actual_is_forecast": true,
      "planned_duration_months": 113.5,
      "actual_duration_months": 229.4,
      "delay_months": 154,
      "delay_pct": 135.7,
      "planned_cost": 16600000000,
      "actual_cost": 95200000000,
      "planned_cost_range": [
        15800000000,
        17400000000
      ],
      "actual_cost_range": [
        87700000000,
        102700000000
      ],
      "cost_currency": "GBP",
      "planned_cost_year": 2010,
      "cost_year": 2025,
      "planned_fx_to_usd": 1.5465,
      "actual_fx_to_usd": 1.32,
      "planned_cost_usd_nominal": 25647000000,
      "cost_usd_nominal": 125568800000,
      "planned_cost_usd_today": 37865820998,
      "cost_usd_today": 125568800000,
      "overrun_usd_today": 103673400000,
      "overrun_pct": 473.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Proposal, route and funding envelopes",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2010",
          "actual_end": "2016-06",
          "note": "2010 DfT estimate for Phase 1 of GBP 15.8-17.4 billion; June 2013 network package of GBP 42.6 billion (2011 prices) plus GBP 7.5 billion rolling stock; 2015 Spending Review package GBP 55.7 billion (2015 prices). NAO in 2016 gave Phase 1 a 60 percent chance of opening by December 2026."
        },
        {
          "name": "Hybrid bill and Royal Assent",
          "planned_start": null,
          "planned_end": "2016-12",
          "actual_start": "2013-11",
          "actual_end": "2017-02",
          "note": "High Speed Rail (London - West Midlands) Act 2017 received Royal Assent in February 2017."
        },
        {
          "name": "Enabling works and Oakervee review",
          "planned_start": "2017",
          "planned_end": null,
          "actual_start": "2017",
          "actual_end": "2020-04-15",
          "note": "The 2019 Oakervee review raised the whole-programme cost estimate to as much as GBP 87.7 billion (2019 prices). Notice to proceed given on 15 April 2020."
        },
        {
          "name": "Main civil works (tunnels, viaducts)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2020-09-04",
          "actual_end": null,
          "note": "Main construction formally began 4 September 2020. Phase 2 north of Birmingham cancelled in October 2023. Northolt and Bromford tunnels completed in 2025."
        },
        {
          "name": "Reset: Stewart and Lovegrove reviews",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2025-03",
          "actual_end": "2026-05-19",
          "note": "HS2 Ltd chief executive Mark Wild said in March 2025 the company had failed to control costs; Heidi Alexander told the Commons in June 2025 that the 2033 window was impossible and on 19 May 2026 set a new cost range and opening windows."
        },
        {
          "name": "Rail systems, testing and opening (forecast)",
          "planned_start": null,
          "planned_end": "2026-12",
          "actual_start": null,
          "actual_end": "2039-10",
          "note": "Old Oak Common-Birmingham Curzon Street forecast May 2036 to October 2039; Euston to Handsacre May 2040 to December 2043."
        }
      ],
      "milestones": [
        {
          "name": "Phase 1 Royal Assent",
          "planned_date": "2016-12",
          "actual_date": "2017-02"
        },
        {
          "name": "Notice to proceed for main works",
          "planned_date": null,
          "actual_date": "2020-04-15"
        },
        {
          "name": "Phase 2 (north of Birmingham) cancelled",
          "planned_date": null,
          "actual_date": "2023-10"
        },
        {
          "name": "Cost and schedule reset announced",
          "planned_date": null,
          "actual_date": "2026-05-19"
        },
        {
          "name": "First passenger services (forecast, latest in window)",
          "planned_date": "2026-12",
          "actual_date": "2039-10"
        }
      ],
      "headline": "HS2's first phase was costed at about £16 billion and due in 2026; the May 2026 reset puts it at £87.7 to 102.7 billion and opening by 2036 to 2039.",
      "summary": "High Speed 2 is a new high-speed railway from London to the West Midlands, originally the first phase of a Y-shaped network to Manchester and Leeds. Promoted by the Department for Transport and built by HS2 Ltd, Phase 1 received Royal Assent in 2017 and main construction began in 2020. The northern legs were cancelled in 2023. After reviews by James Stewart and Stephen Lovegrove, the government in May 2026 set a cost range of £87.7 to 102.7 billion and opening windows from 2036.",
      "what_went_wrong_or_right": "Costs were set before design maturity and then repeatedly re-based. The 2010 Phase 1 estimate of GBP 15.8-17.4 billion was followed by a June 2013 network package of GBP 42.6 billion and the 2015 package of GBP 55.7 billion, and by 2016 the NAO found the Phase 1 forecast already exceeded available funding with less contingency than planned. The 2019 Oakervee review put the full programme at up to GBP 87.7 billion. Specification was a named cause: the May 2026 Lovegrove review cited 'gold plating', including the pursuit of the highest possible speeds, and the government cut the design speed from 360 km/h to 320 km/h. Political change disrupted scope, with Phase 2 north of Birmingham cancelled in October 2023 after sunk design work. Delivery control was weak: in March 2025 chief executive Mark Wild wrote that HS2 had 'failed in its mission to control costs and deliver to schedule' and estimated the programme was about one-third complete against a planned three-quarters. About GBP 44 billion had been spent by 2026.",
      "lessons": [
        "Tie design standards such as top speed to measured benefits, not prestige.",
        "Publish confidence levels with dates; HS2's 2026 date had only 60 percent confidence in 2016.",
        "Scope cuts after construction starts rarely recover the money already committed."
      ],
      "fun_fact": "An internal review found that cancelling HS2 outright would cost at least as much as completing it.",
      "method_tags": [
        "phased_delivery",
        "reference_class"
      ],
      "related_history_ids": [
        "rcf-2004",
        "big-things-2023",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Progress with preparations for High Speed 2 (Summary, HC 235, June 2016)",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/wp-content/uploads/2016/06/Progress-with-preparations-for-High-Speed-2-Summary-1.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "HS2 could cost more than GBP 100bn and may not open until 2039, says minister",
          "publisher": "The Irish News (PA Media)",
          "url": "https://www.irishnews.com/news/uk/hs2-could-cost-more-than-100bn-and-may-not-open-until-2039-says-minister-EN7K4CGVL5OHLGRVVHPBDBTBCU/",
          "accessed": "2026-10-25"
        },
        {
          "title": "High Speed 2",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/High_Speed_2",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline choice: the first published Phase 1 figure, the 2010 DfT estimate of GBP 15.8-17.4 billion for London-Birmingham (Wikipedia), stored as the midpoint GBP 16.6 billion with the range; its price base was not confirmed in an opened source (planned_cost_year set to 2010). Phase 1 opening was expected by December 2026 when proposed in 2010 (Wikipedia; NAO 2016). Alternatives that users may prefer: the 2013 Spending Review network envelope of GBP 42.6 billion (2011 prices, plus GBP 7.5 billion rolling stock) or the 2015 package of GBP 55.7 billion (2015 prices, NAO 2016); both cover the full Y network, not Phase 1 alone, so they are not used as the Phase 1 baseline. The original full-network estimate was GBP 32.7 billion (2011 prices) per PA Media. Latest forecast: GBP 87.7-102.7 billion in 2025 prices for completing the line (Euston to Handsacre), announced by Heidi Alexander on 19 May 2026 (PA Media), stored as the midpoint GBP 95.2 billion; scope includes rolling stock and Euston works per reports, while the 2010 figure likely excluded rolling stock, so the comparison overstates like-for-like growth. actual_end uses the latest date in the first-services window (October 2039); Euston services are forecast May 2040 to December 2043. The baseline and forecast are in different price bases, so overrun_basis is nominal. Planned start 2017 is the Phase 1 construction start expected by NAO (2016). FX: Fed H.10 annual average 2010 about $1.55 per pound; 2025 about $1.32 (approximate). Baseline audit 2026-10-25: Planned figures unchanged (2010 Phase 1 estimate is the first published). No Phase 1 rebaseline was stored: the 2013 and 2015 envelopes cover the full network, and the April 2020 Phase 1 budget was not found in an opened source.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 17,
      "slug": "hong-kong-airport",
      "name": "Hong Kong International Airport at Chek Lap Kok and the Airport Core Programme",
      "short_name": "Hong Kong Airport",
      "category": "infrastructure",
      "subcategory": "airport",
      "country": "Hong Kong",
      "country_code": "HK",
      "countries": [
        "Hong Kong"
      ],
      "continent": "Asia",
      "city": "Chek Lap Kok, Lantau Island",
      "lat": 22.3089,
      "lng": 113.9146,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "late",
      "planned_start": "1992",
      "planned_end": "1997-06",
      "actual_start": "1992",
      "actual_end": "1998-07-06",
      "actual_is_forecast": false,
      "planned_duration_months": 59.5,
      "actual_duration_months": 72.2,
      "delay_months": 12.7,
      "delay_pct": 21.4,
      "planned_cost": 163700000000,
      "actual_cost": 155300000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        155300000000,
        160200000000
      ],
      "cost_currency": "HKD",
      "planned_cost_year": 1992,
      "cost_year": 1998,
      "planned_fx_to_usd": 0.1282,
      "actual_fx_to_usd": 0.1282,
      "planned_cost_usd_nominal": 20986340000,
      "cost_usd_nominal": 19909460000,
      "planned_cost_usd_today": 48148645838,
      "cost_usd_today": 39327077481,
      "overrun_usd_today": -2127156799,
      "overrun_pct": -5.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": "1998-07-06",
      "rebaseline_label": "January 1998 official opening date",
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": 0,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Strategy and Sino-British agreement",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1989-10-11",
          "actual_end": "1991-09-03",
          "note": "Governor David Wilson announced the Port and Airport Development Strategy on 11 October 1989; the Memorandum of Understanding on the new airport was signed in Beijing on 3 September 1991."
        },
        {
          "name": "Airport site formation and construction",
          "planned_start": "1992",
          "planned_end": "1997-06",
          "actual_start": "1992",
          "actual_end": "1998-07-02",
          "note": "Chek Lap Kok and Lam Chau islands were levelled and 9.38 sq km of seabed reclaimed for a 1,248-hectare platform; terminal designed by a Mott Connell-led team with BAA and Foster and Partners."
        },
        {
          "name": "Airport Railway, Lantau Link and other core projects",
          "planned_start": "1992",
          "planned_end": "1997-06",
          "actual_start": "1992",
          "actual_end": "1998-06",
          "note": "During 1997 eight of the 10 ACP projects were substantially complete ahead of schedule and below budget; the Airport Railway was finished for the airport opening."
        },
        {
          "name": "Relocation from Kai Tak",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1998-05-06",
          "actual_end": "1998-08-05",
          "note": "Move carried out in five phases; 29 aircraft flew over on the night of 5-6 July 1998."
        },
        {
          "name": "Opening and operational recovery",
          "planned_start": "1998-04",
          "planned_end": null,
          "actual_start": "1998-07-06",
          "actual_end": "1998-12",
          "note": "Flight information displays and the cargo system failed on opening; by December 1998 over 76 percent of departures were on time or within 15 minutes."
        }
      ],
      "milestones": [
        {
          "name": "Airport decision announced",
          "planned_date": null,
          "actual_date": "1989-10-11"
        },
        {
          "name": "Sino-British airport MOU signed",
          "planned_date": null,
          "actual_date": "1991-09-03"
        },
        {
          "name": "Official opening ceremony",
          "planned_date": null,
          "actual_date": "1998-07-02"
        },
        {
          "name": "Commercial operations begin, Kai Tak closes",
          "planned_date": "1997-06",
          "actual_date": "1998-07-06"
        }
      ],
      "headline": "Hong Kong's Airport Core Programme finished at HK$155.3 billion, HK$8.4 billion below its 1992-93 budget, though the airport itself opened about a year after its mid-1997 target.",
      "summary": "The Airport Core Programme comprised 10 projects built to replace Kai Tak with a new airport on a reclaimed platform at Chek Lap Kok, off Lantau Island: the airport, the Airport Railway, the Lantau Link bridges, the Western Harbour Crossing, expressways, and reclamation and new-town works. Construction began in 1992 under the Airport Authority, MTR Corporation and government departments, coordinated by the New Airport Projects Co-ordination Office. Kai Tak closed and the new airport began commercial operations on 6 July 1998.",
      "what_went_wrong_or_right": "On cost, the programme is a rare success. The government's 1997 Yearbook records that the ACP budget was cut three times, by a total of HK$8.4 billion, from HK$163.7 billion projected in 1992-93 to HK$155.3 billion in money-of-the-day prices, and that eight of the 10 projects were substantially complete ahead of schedule and below budget during 1997. A 2006 government reply to the Legislative Council reported final spending below estimate for all three delivery bodies: the Airport Authority spent HK$49.3 billion against HK$49.8 billion, and MTR's Airport Railway HK$33.5 billion against HK$34.0 billion. Savings came partly from scope cuts, such as building the Airport Railway with two tracks rather than four. Schedule was weaker: the airport was targeted for mid-1997, ahead of the handover, then for April 1998, and opened on 6 July 1998. Opening day was marred by failures of the flight information display system and the cargo handling system, which disrupted freight for months and forced the reuse of Kai Tak's cargo terminal.",
      "lessons": [
        "A dedicated coordination office across many delivery bodies can hold a multi-project programme to budget.",
        "Trim scope early, as with the two-track railway, rather than absorbing overruns later.",
        "Test operational IT systems end to end before a big-bang opening."
      ],
      "fun_fact": "Guinness World Records lists the Chek Lap Kok airport as the most expensive airport project ever.",
      "method_tags": [
        "phased_delivery",
        "big_bang",
        "critical_path"
      ],
      "related_history_ids": [
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Hong Kong 1997 Yearbook, Chapter 16: Project Management and Cost Control",
          "publisher": "Hong Kong Government",
          "url": "https://www.yearbook.gov.hk/1997/ch16/e16h.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Airport Core Programme: Cost",
          "publisher": "New Airport Projects Co-ordination Office (archived government site)",
          "url": "https://www.info.gov.hk/archive/napco/cost.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "LegCo question on Airport Core Programme expenditure (written reply, 11 January 2006)",
          "publisher": "Hong Kong SAR Government Information Services",
          "url": "https://www.info.gov.hk/gia/general/200601/11/P200601110108.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Hong Kong 1998 Yearbook: Civil Aviation",
          "publisher": "Hong Kong SAR Government",
          "url": "https://www.yearbook.gov.hk/1998/ewww/14/1413/middle-middle.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Airport Core Programme",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Airport_Core_Programme",
          "accessed": "2026-10-25"
        },
        {
          "title": "Hong Kong International Airport",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Hong_Kong_International_Airport",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Scope: the whole 10-project Airport Core Programme, of which the airport is the centerpiece. Baseline: the ACP budget of HK$163.7 billion projected in 1992-93, in money-of-the-day prices (Hong Kong 1997 Yearbook); planned_cost_year set to 1992. Actual: the HK$155.3 billion money-of-the-day estimate as the programme closed (1997 Yearbook; NAPCO cost page). Wikipedia, citing a Transparency International working paper, gives HK$160.2 billion; that is the upper end of actual_cost_range. A single audited final total for all 10 projects was not found; the 2006 LegCo reply gives final spending only by delivery body (government HK$48.0bn, Airport Authority HK$49.3bn, MTR HK$33.5bn), excluding private franchisee and Western Harbour Crossing spending. The airport alone: Airport Authority estimate HK$49.8bn vs HK$49.3bn spent. Schedule baseline: Wikipedia (ACP article) gives construction from 1992 with planned completion in mid-1997; later official targets were April 1998 and then 6 July 1998 (announced January 1998). The common claim that the airport was on time holds against the 1998 target, not the original mid-1997 one. Construction start and the ancillary-project end are at year/month precision. FX: Hong Kong dollar linked exchange rate peg of HK$7.80 per US dollar (in force since October 1983), giving about $0.1282 per HK$ for both years; market annual averages were close to 7.74-7.75. Baseline audit 2026-10-25: Planned figures unchanged (1992-93 ACP budget, mid-1997 completion). Added the 6 July 1998 opening date announced in January 1998 as the schedule rebaseline; no revised budget is stored.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 18,
      "slug": "hong-kong-zhuhai-macau-bridge",
      "name": "Hong Kong–Zhuhai–Macau Bridge",
      "short_name": "HK–Zhuhai–Macau Bridge",
      "category": "infrastructure",
      "subcategory": "bridge-tunnel",
      "country": "China",
      "country_code": "CN",
      "countries": [
        "China",
        "Hong Kong",
        "Macau"
      ],
      "continent": "Asia",
      "city": "Hong Kong / Zhuhai / Macau",
      "lat": 22.283,
      "lng": 113.7806,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2009-12",
      "planned_end": "2016",
      "actual_start": "2009-12-15",
      "actual_end": "2018-10-24",
      "actual_is_forecast": false,
      "planned_duration_months": 78.5,
      "actual_duration_months": 106.3,
      "delay_months": 27.8,
      "delay_pct": 35.3,
      "planned_cost": 38000000000,
      "actual_cost": 48070000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "CNY",
      "planned_cost_year": 2009,
      "cost_year": 2017,
      "planned_fx_to_usd": 0.1464,
      "actual_fx_to_usd": 0.1479,
      "planned_cost_usd_nominal": 5563200000,
      "cost_usd_nominal": 7114360000,
      "planned_cost_usd_today": 8348683108,
      "cost_usd_today": 9344479093,
      "overrun_usd_today": 1957539099,
      "overrun_pct": 26.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": 48070000000,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": "revised budget approved by the Ministry of Transport",
      "rebaseline_overrun_pct": 0,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Main Bridge construction start and island reclamation",
          "planned_start": "2009-12",
          "planned_end": null,
          "actual_start": "2009-12-15",
          "actual_end": "2011-12",
          "note": "Mainland works started 15 December 2009; the Hong Kong section was held back by an environmental judicial review and started December 2011."
        },
        {
          "name": "Bridges, artificial islands and immersed tunnel",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2011-12",
          "actual_end": "2017-05-02",
          "note": "Last bridge tower erected 2 June 2016; final immersed-tunnel joint installed 2 May 2017."
        },
        {
          "name": "Main Bridge completion",
          "planned_start": null,
          "planned_end": "2016",
          "actual_start": "2017-05-02",
          "actual_end": "2017-07-06",
          "note": "Viaduct and 6.7 km undersea tunnel completed 6 July 2017."
        },
        {
          "name": "Link roads, ports and systems",
          "planned_start": null,
          "planned_end": "2016",
          "actual_start": "2017-07-06",
          "actual_end": "2018-02-06",
          "note": "Entire project declared complete 6 February 2018."
        },
        {
          "name": "Opening",
          "planned_start": "2016",
          "planned_end": "2016",
          "actual_start": "2018-10-23",
          "actual_end": "2018-10-24",
          "note": "Inaugurated 23 October 2018; opened to the public 24 October 2018."
        }
      ],
      "milestones": [
        {
          "name": "Construction start",
          "planned_date": "2009-12",
          "actual_date": "2009-12-15"
        },
        {
          "name": "Final tunnel joint",
          "planned_date": null,
          "actual_date": "2017-05-02"
        },
        {
          "name": "Opening to traffic",
          "planned_date": "2016",
          "actual_date": "2018-10-24"
        }
      ],
      "headline": "The 55 km Hong Kong–Zhuhai–Macau crossing opened in October 2018, about two years late, and its Main Bridge budget rose from CNY 38 billion to CNY 48.07 billion.",
      "summary": "The Hong Kong–Zhuhai–Macau Bridge is a 55 km system of bridges, four artificial islands and a 6.7 km immersed tunnel across the Pearl River estuary, the world's longest open-sea fixed link. Construction began on 15 December 2009 with opening planned for late 2016. The Main Bridge was completed in July 2017 and the crossing opened on 24 October 2018. Total spending including link roads and border facilities is reported at about CNY 127 billion.",
      "what_went_wrong_or_right": "The project ran about two years past its late-2016 target and over budget. Caixin reported in December 2017 that the Ministry of Transport approved a revised Main Bridge budget of CNY 48.07 billion against an original plan of CNY 38 billion, after contractors sought more money for complicated construction conditions, rising labor and material costs and changes to construction plans. The governments had to find an extra CNY 4.6 billion, of which Hong Kong paid CNY 2 billion and Macau CNY 590 million. In Hong Kong, a judicial review of the environmental assessment held up the start of the Hong Kong section until December 2011, and parts of the reclaimed border-crossing island moved by up to six or seven metres, according to the Highways Department. Building the deep immersed-tube tunnel in open sea was technically novel and difficult. Safety was a serious problem: Wikipedia, citing official and press figures, reports 19 worker deaths, nine on the mainland side and more than ten on the Hong Kong side.",
      "lessons": [
        "Settle environmental approvals before awarding cross-border works to avoid split start dates.",
        "Multi-government projects need one agreed mechanism for sharing overruns.",
        "Reclamation settlement is a known risk; monitor it publicly to protect credibility."
      ],
      "fun_fact": "Hong Kong and Macau drive on the left, but traffic on the bridge itself drives on the right.",
      "method_tags": [
        "design_build",
        "modular",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Hong Kong–Zhuhai–Macau Bridge",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Hong_Kong–Zhuhai–Macau_Bridge",
          "accessed": "2026-10-25"
        },
        {
          "title": "China's Mega Bridge Will Cost $1.5 Billion More Than Expected",
          "publisher": "Caixin Global",
          "url": "https://www.caixinglobal.com/2017-12-15/chinas-mega-bridge-will-cost-15-billion-more-than-expected-101185276.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Colossal bridge price overruns",
          "publisher": "Macau Business",
          "url": "https://www.macaubusiness.com/colossal-bridge-price-overruns/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Scope: Main Bridge only (22.9 km bridge plus 6.7 km tunnel and islands), the part jointly funded by the three governments. Baseline: CNY 38bn original plan and CNY 48.07bn revised budget approved by the Ministry of Transport, both per Caixin (15 December 2017); the year of the original plan is not stated and is assumed to be the 2009 start. The CNY 15.73bn figure in Macau Business is the governments' capital contribution, not the total budget. Total for all components (Main Bridge, link roads, ports) is reported at about CNY 127bn (Wikipedia), with no published total baseline. Planned opening 'late 2016' per Wikipedia. FX: approximate annual averages, 2009 about 6.83 and 2017 about 6.76 CNY per USD (Federal Reserve H.10), not re-checked in this session. Baseline audit 2026-10-25: Planned figures unchanged (original CNY 38bn plan). Added the CNY 48.07bn revised budget approved by the Ministry of Transport (Caixin) as the rebaseline; its approval year is not stated.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 19,
      "slug": "millau-viaduct",
      "name": "Millau Viaduct",
      "short_name": "Millau Viaduct",
      "category": "infrastructure",
      "subcategory": "bridge",
      "country": "France",
      "country_code": "FR",
      "countries": [
        "France"
      ],
      "continent": "Europe",
      "city": "Millau",
      "lat": 44.0794,
      "lng": 3.0222,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "2001-10",
      "planned_end": "2005-01-10",
      "actual_start": "2001-10-16",
      "actual_end": "2004-12-16",
      "actual_is_forecast": false,
      "planned_duration_months": 38.8,
      "actual_duration_months": 38,
      "delay_months": -0.8,
      "delay_pct": -2.1,
      "planned_cost": 320000000,
      "actual_cost": 394000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        394000000,
        400000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2001,
      "cost_year": 2004,
      "planned_fx_to_usd": 0.8952,
      "actual_fx_to_usd": 1.2438,
      "planned_cost_usd_nominal": 286464000,
      "cost_usd_nominal": 490136000,
      "planned_cost_usd_today": 520868107,
      "cost_usd_today": 835459091,
      "overrun_usd_today": 156913636,
      "overrun_pct": 23.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Concession award and approval",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1998-05-20",
          "actual_end": "2001-10-08",
          "note": "Concession decree signed 20 May 1998; concession agreement with Eiffage signed 27 September 2001 and approved by decree 2001-923 of 8 October 2001."
        },
        {
          "name": "Foundations",
          "planned_start": "2001-10",
          "planned_end": null,
          "actual_start": "2001-10-16",
          "actual_end": "2002-03",
          "note": "Work began 16 October 2001; first stone laid 14 December 2001. Four 15 m deep piles per pier."
        },
        {
          "name": "Piers",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2002-03",
          "actual_end": "2003-11",
          "note": "Piers emerged in March 2002, rising about 4 m every three days with sliding formwork; last piers finished November 2003."
        },
        {
          "name": "Deck launching",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2003-02-25",
          "actual_end": "2004-05-28",
          "note": "Steel deck pushed out from both ends in 600 mm cycles; halves met on 28 May 2004."
        },
        {
          "name": "Masts, stays, load tests",
          "planned_start": null,
          "planned_end": "2005-01-10",
          "actual_start": "2004-06",
          "actual_end": "2004-12-14",
          "note": "Masts tilted up, stays tensioned, weight tests, temporary supports removed; inauguration 14 December 2004."
        },
        {
          "name": "Opening to traffic",
          "planned_start": "2005-01-10",
          "planned_end": "2005-01-10",
          "actual_start": "2004-12-16",
          "actual_end": "2004-12-16",
          "note": "Opened 16 December 2004, ahead of the planned 10 January 2005 date."
        }
      ],
      "milestones": [
        {
          "name": "First stone",
          "planned_date": null,
          "actual_date": "2001-12-14"
        },
        {
          "name": "Deck halves join",
          "planned_date": null,
          "actual_date": "2004-05-28"
        },
        {
          "name": "Opening to traffic",
          "planned_date": "2005-01-10",
          "actual_date": "2004-12-16"
        }
      ],
      "headline": "Eiffage built the 343 m tall Millau Viaduct in about three years and opened it on 16 December 2004, 25 days ahead of plan.",
      "summary": "The Millau Viaduct carries the A75 autoroute 270 m above the Tarn valley in southern France. Designed by engineer Michel Virlogeux with architect Norman Foster, it was financed and built by Eiffage under a 75-year toll concession, with no public subsidy. Work began in October 2001 and the bridge opened on 16 December 2004, ahead of its planned January 2005 date. At 343 m it was the world's tallest bridge structure for about two decades.",
      "what_went_wrong_or_right": "The viaduct is a schedule success built on a strong contractual incentive. Under the concession, Eiffage carried construction and traffic risk, financed the work privately and, according to Batiweb's 2002 report, had 39 months to finish under penalties of up to EUR 25,000 per day of delay. That structure rewarded speed. Eiffage launched the steel deck incrementally, pushing it out in 600 mm cycles, so the deck could be assembled on land while the piers rose with sliding formwork at about 4 m every three days. The halves met in May 2004 and traffic began on 16 December 2004, about three weeks before the 10 January 2005 target. Cost reporting is less tidy: the EUR 320 million figure reported in 2002 covers the viaduct alone, while French Wikipedia says the whole works were valued at close to EUR 400 million and English Wikipedia gives EUR 394 million plus EUR 20 million for the toll plaza. The apparent gap is mostly a difference in scope, not a documented overrun.",
      "lessons": [
        "Daily delay penalties plus private financing give a contractor strong reasons to finish early.",
        "Launching a deck from both ends lets the deck and the piers be built at the same time.",
        "Publish costs with a clear scope so budget and outturn can be compared."
      ],
      "fun_fact": "Pier P2 is about 13 m taller than the Eiffel Tower.",
      "method_tags": [
        "design_build",
        "ppp",
        "fixed_price",
        "fast_track"
      ],
      "related_history_ids": [
        "cpm-1957",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Millau Viaduct",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Millau_Viaduct",
          "accessed": "2026-10-25"
        },
        {
          "title": "Viaduc de Millau",
          "publisher": "Wikipédia (French)",
          "url": "https://fr.wikipedia.org/wiki/Viaduc_de_Millau",
          "accessed": "2026-10-25"
        },
        {
          "title": "Le coup d'envoi de deux super-chantiers (23 January 2002)",
          "publisher": "Batiweb",
          "url": "https://www.batiweb.com/actualites/architecture/le-coup-d-8217-envoi-de-deux-super-chantiers-47",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: EUR 320m cost and 39-month deadline reported by Batiweb in January 2002, after the concession was approved (decree of 8 October 2001); French Wikipedia says the 320m is the viaduct alone within roughly EUR 400m of total works. Actual: EUR 394m (English Wikipedia; toll plaza a further EUR 20m). The two figures likely differ in scope, so the apparent 23% gap should not be read as an overrun. Planned opening 10 January 2005 per English Wikipedia. FX: approximate annual averages, 2001 about 0.895 USD per EUR and 2004 about 1.244 USD per EUR (Federal Reserve H.10), not re-checked in this session.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 20,
      "slug": "oresund-bridge",
      "name": "Øresund Bridge (Øresund Fixed Link, coast-to-coast)",
      "short_name": "Øresund Bridge",
      "category": "infrastructure",
      "subcategory": "bridge-tunnel",
      "country": "Denmark",
      "country_code": "DK",
      "countries": [
        "Denmark",
        "Sweden"
      ],
      "continent": "Europe",
      "city": "Copenhagen / Malmö",
      "lat": 55.5706,
      "lng": 12.8494,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1995",
      "planned_end": "2000-07-01",
      "actual_start": "1995",
      "actual_end": "2000-07-01",
      "actual_is_forecast": false,
      "planned_duration_months": 60,
      "actual_duration_months": 60,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 13925000000,
      "actual_cost": 14800000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "DKK",
      "planned_cost_year": 1990,
      "cost_year": 1990,
      "planned_fx_to_usd": 0.1616,
      "actual_fx_to_usd": 0.1616,
      "planned_cost_usd_nominal": 2250280000,
      "cost_usd_nominal": 2391680000,
      "planned_cost_usd_today": 5545455680,
      "cost_usd_today": 5893913398,
      "overrun_usd_today": 348457718,
      "overrun_pct": 6.3,
      "overrun_basis": "real",
      "rebaseline_cost": 14750000000,
      "rebaseline_cost_year": 1990,
      "rebaseline_end": null,
      "rebaseline_label": "May 1997 revised budget, 1990 prices",
      "rebaseline_overrun_pct": 0.3,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Treaty and parliamentary approval",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1991-03-23",
          "actual_end": "1991-08-14",
          "note": "Danish-Swedish agreement signed 23 March 1991; Riksdag approval 12 June 1991; Folketing approval 14 August 1991 (117 to 42)."
        },
        {
          "name": "Consortium set-up, design and contracts",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1992-01",
          "actual_end": "1995-11",
          "note": "Øresundskonsortiet formed January 1992 by state-owned SVEDAB and A/S Øresundsforbindelsen; Sundlink signed the DKK 6.8bn bridge contract in November 1995."
        },
        {
          "name": "Construction of tunnel, Peberholm and bridge",
          "planned_start": "1995",
          "planned_end": null,
          "actual_start": "1995",
          "actual_end": "1999-08-14",
          "note": "20 immersed tunnel elements, artificial island of Peberholm, 49 access spans and 203.5 m pylons; last bridge span placed 14 August 1999."
        },
        {
          "name": "Systems installation and testing",
          "planned_start": null,
          "planned_end": "2000-07-01",
          "actual_start": "1999-08-14",
          "actual_end": "2000-06-30",
          "note": "Construction finished about three months ahead of schedule, per Wikipedia."
        },
        {
          "name": "Opening",
          "planned_start": "2000-07-01",
          "planned_end": "2000-07-01",
          "actual_start": "2000-07-01",
          "actual_end": "2000-07-01",
          "note": "Opened on the planned date."
        }
      ],
      "milestones": [
        {
          "name": "Governments sign fixed-link agreement",
          "planned_date": null,
          "actual_date": "1991-03-23"
        },
        {
          "name": "Last bridge span in place",
          "planned_date": null,
          "actual_date": "1999-08-14"
        },
        {
          "name": "Opening to traffic",
          "planned_date": "2000-07-01",
          "actual_date": "2000-07-01"
        }
      ],
      "headline": "The 16 km Øresund road-rail link opened on its planned date, 1 July 2000, for DKK 14.8 billion in 1990 prices.",
      "summary": "The Øresund Fixed Link joins Copenhagen and Malmö with a 4 km immersed tunnel, the artificial island of Peberholm and a 7.8 km cable-stayed bridge carrying a motorway above a double-track railway. It was agreed by Denmark and Sweden in 1991, built from 1995 by the Sundlink consortium and opened on 1 July 2000. The coast-to-coast link is financed by state-guaranteed loans repaid from tolls and rail fees, with full repayment now expected around 2050.",
      "what_went_wrong_or_right": "On delivery the project performed well: the Swedish government reported in 1999/2000 that construction would close within the consortium budget of DKK 14,750 million in July 1990 prices, and the operator now states final construction cost at DKK 14.8 billion in 1990 prices. The opening date of 1 July 2000 was held despite setbacks, including a skewed tunnel element and 16 unexploded Second World War bombs found on the seabed. The weaker part is the front end. Aalborg University researcher Mette Skamris and Rigsrevisionen (the Danish auditor-general) criticised how the 1991 financial case was built: the discount rate was cut from the 7 percent government guideline to 5 percent and traffic forecasts were raised until a projected DKK 400 million deficit became a small surplus before the construction act passed. Flyvbjerg, Bruzelius and Rothengatter argue that overruns should be measured from the 1991 decision, while link management argued that politically approved environmental design changes should be excluded. Repayment has also stretched, from 30 years in 2000 to about 50 years today.",
      "lessons": [
        "Fix the cost baseline at the decision to build and keep it; later rebaselining hides overruns.",
        "Stress-test discount rates and traffic forecasts before approval, not after.",
        "A single owner company with a clear budget and reserve helps hold a fixed opening date."
      ],
      "fun_fact": "Construction crews found 16 unexploded Second World War bombs on the Øresund seabed.",
      "method_tags": [
        "design_build",
        "fixed_price",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Øresund Bridge",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Øresund_Bridge",
          "accessed": "2026-10-25"
        },
        {
          "title": "Prop. 1999/2000:66 Villkoren för järnvägstrafiken på den fasta förbindelsen över Öresund m.m.",
          "publisher": "Swedish Government (via lagen.nu)",
          "url": "https://lagen.nu/prop/1999/2000:66",
          "accessed": "2026-10-25"
        },
        {
          "title": "Construction costs for the Øresund Bridge and Øresund Landworks",
          "publisher": "Sund & Bælt",
          "url": "https://sundogbaelt.dk/en/about-us/finance-economics/construction-costs/construction-costs-for-the-oresund-bridge-and-oresund-landwors/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Store transportprojekter: Før-og-efter studier af trafik og økonomi (Skamris, 1995)",
          "publisher": "Aalborg University, Trafikdage",
          "url": "https://journals.aau.dk/index.php/td/article/download/3891/3354/13869",
          "accessed": "2026-10-25"
        },
        {
          "title": "Megaprojects and Risk: An Anatomy of Ambition, Chapter 1",
          "publisher": "Flyvbjerg, Bruzelius, Rothengatter (arXiv)",
          "url": "https://arxiv.org/pdf/1303.7404",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Scope: coast-to-coast link only (tunnel, Peberholm, bridge); Danish and Swedish land works (DKK 5.4bn in 1991 prices) excluded. Baseline: the original 1991 construction-act budget (Lovforslag L 178, May 1991) could not be retrieved; the earliest budget found in sources opened is DKK 13,925 million (July 1990 prices) cited in Swedish government report skr. 1995/96:130, revised to DKK 14,750 million in May 1997 (prop. 1996/97:161). Actual: DKK 14.8bn in 1990 prices per Sund & Bælt. Both in 1990 prices, so basis is real. Flyvbjerg et al. use the 1991 decision as baseline and report a larger overrun; the operator disputes that baseline, so confidence is disputed. Wikipedia's DKK 19.6bn figure appears to be nominal. Start month in 1995 not confirmed. FX: approximate 1990 annual average of about 6.19 DKK per USD (Federal Reserve H.10/G.5A historical series), not re-checked in this session. Baseline audit 2026-10-25: Planned figures unchanged: the 1991 construction-act budget (Lovforslag L 178) that Flyvbjerg uses could still not be sourced, so the earliest found figure (DKK 13,925m, 1990 prices) remains. Added the May 1997 revision to DKK 14,750m (prop. 1996/97:161, 1990 prices) as the rebaseline.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 21,
      "slug": "panama-canal",
      "name": "Panama Canal",
      "short_name": "Panama Canal",
      "category": "infrastructure",
      "subcategory": "canal",
      "country": "Panama",
      "country_code": "PA",
      "countries": [
        "Panama",
        "United States",
        "France"
      ],
      "continent": "North America",
      "city": "Culebra Cut (Gaillard Cut), near Panama City",
      "lat": 9.0833,
      "lng": -79.6833,
      "era": "1900-1945",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1904-05-04",
      "planned_end": "1918",
      "actual_start": "1904-05-04",
      "actual_end": "1914-08-15",
      "actual_is_forecast": false,
      "planned_duration_months": 169.9,
      "actual_duration_months": 123.4,
      "delay_months": -46.5,
      "delay_pct": -27.4,
      "planned_cost": 139705200,
      "actual_cost": 375000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1906,
      "cost_year": 1914,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 139705200,
      "cost_usd_nominal": 375000000,
      "planned_cost_usd_today": 5006103000,
      "cost_usd_today": 12053571429,
      "overrun_usd_today": 7563047143,
      "overrun_pct": 168.4,
      "overrun_basis": "nominal",
      "rebaseline_cost": 297766000,
      "rebaseline_cost_year": 1909,
      "rebaseline_end": "1915-01-01",
      "rebaseline_label": "1908-09 revised estimate and fixed completion date (Taft, 1909)",
      "rebaseline_overrun_pct": 25.9,
      "rebaseline_delay_months": -4.5,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "French attempt (Compagnie universelle, de Lesseps)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1881-01-01",
          "actual_end": "1889-05-15",
          "note": "Sea-level canal attempt; work suspended 15 May 1889 after bankruptcy. About US$287 million spent and an estimated 22,000 deaths."
        },
        {
          "name": "US takeover, sanitation and preparation (Wallace, Stevens)",
          "planned_start": "1904-05-04",
          "planned_end": null,
          "actual_start": "1904-05-04",
          "actual_end": "1907-04-01",
          "note": "US took control of the property on 4 May 1904. Stevens rebuilt the railroad and housing and argued in 1906 for a lock-and-lake design."
        },
        {
          "name": "Lock canal design adopted",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1906-01-01",
          "actual_end": "1906-06-29",
          "note": "Board of Consulting Engineers split in January 1906; Congress authorized a lock canal on 29 June 1906 at an estimated $139.7 million (construction only)."
        },
        {
          "name": "Main construction under Goethals (Culebra Cut, Gatun Dam, locks)",
          "planned_start": "1907-04-01",
          "planned_end": "1918",
          "actual_start": "1907-04-01",
          "actual_end": "1913-10-10",
          "note": "Goethals replaced Stevens in 1907. On 10 October 1913 the Gamboa Dike was blown up, flooding the Culebra Cut."
        },
        {
          "name": "Opening to traffic",
          "planned_start": null,
          "planned_end": "1918",
          "actual_start": "1914-08-15",
          "actual_end": "1914-08-15",
          "note": "SS Ancon made the first official transit on 15 August 1914; the planned grand ceremony did not take place."
        }
      ],
      "milestones": [
        {
          "name": "US takes control of canal property",
          "planned_date": null,
          "actual_date": "1904-05-04"
        },
        {
          "name": "Congress authorizes lock canal",
          "planned_date": null,
          "actual_date": "1906-06-29"
        },
        {
          "name": "Gamboa Dike blown, Culebra Cut flooded",
          "planned_date": null,
          "actual_date": "1913-10-10"
        },
        {
          "name": "First official transit (SS Ancon)",
          "planned_date": "1918",
          "actual_date": "1914-08-15"
        }
      ],
      "headline": "The US opened the Panama Canal in August 1914, ahead of its revised 1915 target, at about $375 million against a 1906 construction estimate of $139.7 million.",
      "summary": "After the French company of Ferdinand de Lesseps abandoned a sea-level canal in 1889, the United States took over the works in May 1904. Congress chose a lock-and-lake design in June 1906. Under George Goethals the Army-led Isthmian Canal Commission dug the Culebra Cut, dammed the Chagres River to form Gatun Lake and built three flights of locks. The canal opened on 15 August 1914. About 5,600 workers died during the American era, according to hospital records.",
      "what_went_wrong_or_right": "The schedule was met; the budget was not, though the comparison is not like-for-like. In 1909 President Taft wrote that the original 1906 estimate of $139,705,200 excluded interest, sanitation, Zone government and the $50 million paid to Panama and the French company. On the same basis the estimate had already risen to $297,766,000, or $375 million including everything. Taft listed the causes: excavation yardage underestimated by 50 percent because of inadequate surveys, a wider canal and larger locks requested by the Navy, dams moved to Miraflores and Pedro Miguel, harder rock that raised average excavation cost about 20 percent, and higher wages and housing costs. Landslides in the Culebra Cut kept adding spoil. What went right was the decision to drop the sea-level plan for locks and a lake, the sanitation campaign led by William Gorgas, and Goethals's centralized control. The Panama Canal Authority says the final cost came in about $23 million below the 1907 estimate.",
      "lessons": [
        "Survey the ground properly before fixing the estimate; Panama's excavation volumes were underestimated by half.",
        "State what an estimate excludes. Panama's first figure left out sanitation, government and land purchase.",
        "Changing the concept early (sea level to locks) can rescue a project that failed under the old plan."
      ],
      "fun_fact": "By 1 July 1914 the Americans had excavated 238,845,587 cubic yards of material, according to the Panama Canal Authority.",
      "method_tags": [
        "phased_delivery",
        "cost_plus"
      ],
      "related_history_ids": [
        "taylor-1911",
        "gantt-1910"
      ],
      "sources": [
        {
          "title": "Panama Canal",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Panama_Canal",
          "accessed": "2026-10-25"
        },
        {
          "title": "End of the Construction",
          "publisher": "Panama Canal Authority",
          "url": "https://pancanal.com/en/end-of-the-construction/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Article by the President in McClure's Magazine: An Answer to the Panama Canal Critics (1 May 1909)",
          "publisher": "The American Presidency Project, UC Santa Barbara",
          "url": "https://www.presidency.ucsb.edu/documents/article-the-president-mcclures-magazine-answer-the-panama-canal-critics",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the 1906 Board of Consulting Engineers lock-canal estimate of $139,705,200 adopted when Congress authorized a lock canal on 29 June 1906, as quoted by Taft (1909). That figure covers construction only and excludes interest, sanitation, Zone government and the $50 million paid to Panama ($10m) and the French company ($40m). The actual figure of about $375 million (Panama Canal Authority) includes those payments; fortifications (about $12 million) are excluded. The two figures are therefore not on the same basis and the implied overrun overstates construction growth; no authoritative overrun percentage was found. Taft's 1909 like-for-like estimate was $297,766,000. Planned end: Taft (1909) gives completion 'on or before the 1st of January, 1915'; Wikipedia states Goethals finished two years ahead of a 10 June 1916 target, so the target date itself is disputed. The French phase (1881-1889, about US$287 million) is shown for context only and is not included in costs. Planned start set equal to the 1904 takeover. All figures are nominal US dollars; fx = 1. Baseline audit 2026-10-25: Planned cost unchanged ($139,705,200, 1906). planned_end changed from 1 January 1915 to 1918: Taft (1909) says the 1 January 1915 date \"has been fixed\" later, while the estimate made at the 1906 lock-canal decision was \"twelve or fifteen years\", so 1918 (the earlier end of that range, year precision) is used as the first announced schedule. Taft gives the then-current estimate of $297,766,000 (Goethals) and the fixed 1 January 1915 date, now stored as the rebaseline. Main-construction and opening phase and the first-transit milestone planned dates moved to 1918.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 22,
      "slug": "second-avenue-subway",
      "name": "Second Avenue Subway Phase 1",
      "short_name": "Second Ave Subway",
      "category": "infrastructure",
      "subcategory": "metro",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "New York City",
      "lat": 40.7777,
      "lng": -73.951,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2007-04",
      "planned_end": "2013-12",
      "actual_start": "2007-04-12",
      "actual_end": "2017-01-01",
      "actual_is_forecast": false,
      "planned_duration_months": 80,
      "actual_duration_months": 116.6,
      "delay_months": 36.5,
      "delay_pct": 45.7,
      "planned_cost": 4049614000,
      "actual_cost": 4450000000,
      "planned_cost_range": [
        4049614000,
        4866614000
      ],
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2007,
      "cost_year": 2017,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 4049614000,
      "cost_usd_nominal": 4450000000,
      "planned_cost_usd_today": 6287917742,
      "cost_usd_today": 5844929405,
      "overrun_usd_today": 525893911,
      "overrun_pct": 9.9,
      "overrun_basis": "nominal",
      "rebaseline_cost": 4450000000,
      "rebaseline_cost_year": 2008,
      "rebaseline_end": null,
      "rebaseline_label": "MTA Phase 1 budget raised after the FFGA",
      "rebaseline_overrun_pct": 0,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Funding and groundbreaking",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2005-11",
          "actual_end": "2007-11",
          "note": "State transportation bond approved November 2005; tunneling contract to S3 on 20 March 2007; ceremonial groundbreaking 12 April 2007; Full Funding Grant Agreement with $1.3 billion federal share in November 2007."
        },
        {
          "name": "Utility relocation and launch box",
          "planned_start": "2007-04",
          "planned_end": "2007-12",
          "actual_start": "2007-04-23",
          "actual_end": "2010-05",
          "note": "Utility relocation took 14 months against eight planned; launch box excavation delayed the tunnel boring machine until May 2010."
        },
        {
          "name": "Tunnel boring",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2010-05-14",
          "actual_end": "2011-09-22",
          "note": "TBM started 14 May 2010, reached 65th Street on 5 February 2011 and broke through to the 63rd Street bellmouth on 22 September 2011."
        },
        {
          "name": "Station caverns (72nd and 86th Streets)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2010-10",
          "actual_end": "2013-11",
          "note": "72nd Street mining contract October 2010; blasting complaints led to building evacuations in 2009; cavern blasting finished November 2013."
        },
        {
          "name": "Fit-out, systems and testing",
          "planned_start": null,
          "planned_end": "2013-12",
          "actual_start": "2013-06",
          "actual_end": "2016-12-31",
          "note": "Final major contract June 2013; 84 percent complete by August 2015. An extra $66 million in February 2016 accelerated work toward a December 2016 deadline."
        },
        {
          "name": "Opening",
          "planned_start": "2013-12",
          "planned_end": "2013-12",
          "actual_start": "2017-01-01",
          "actual_end": "2017-01-01",
          "note": "Ceremonial train on 31 December 2016; regular service from noon on 1 January 2017."
        }
      ],
      "milestones": [
        {
          "name": "Groundbreaking",
          "planned_date": "2007-04",
          "actual_date": "2007-04-12"
        },
        {
          "name": "Full Funding Grant Agreement signed",
          "planned_date": null,
          "actual_date": "2007-11-19"
        },
        {
          "name": "TBM breaks through at 63rd Street",
          "planned_date": null,
          "actual_date": "2011-09-22"
        },
        {
          "name": "Revenue service begins",
          "planned_date": "2013-12",
          "actual_date": "2017-01-01"
        }
      ],
      "headline": "The first 2.9 km of the Second Avenue Subway opened three years late on 1 January 2017, at $4.45 billion for three new stations.",
      "summary": "Phase 1 of the Second Avenue Subway extended the Q train from 63rd Street up Second Avenue to 96th Street on Manhattan's Upper East Side, with new stations at 72nd, 86th and 96th Streets. Work on the line had stopped in the 1970s. The Metropolitan Transportation Authority broke ground in April 2007, bored the tunnels in 2010-2011, mined two station caverns, and opened the line on 1 January 2017, three years after the end-2013 date promised in 2007.",
      "what_went_wrong_or_right": "Phase 1 stayed within its $4.45 billion budget as reported by the MTA, but the budget was protected partly by cutting scope: after cost increases from materials and diesel prices in 2008, features were scaled back. The 72nd Street station was cut from three tracks and two island platforms to two tracks and one platform, its width reduced from 100 to 70 feet, and platform screen doors were dropped in 2012. Schedule slipped repeatedly, from 2012 (2005 statement) to end-2013 (2007 promise) and then 2014, 2015 and 2016. Named causes: utility relocation took 14 months instead of eight; launch-box excavation delayed the start of tunnel boring to May 2010; controlled blasting was delayed when two buildings were evacuated in June 2009; and in 2016 testing of systems ran at about 14 tests a week against roughly 40 needed, with elevators, escalators and fire alarms unfinished. Federal monitors projected in June 2015 that the line would not open until February 2018. The December 2016 opening came after Governor Andrew Cuomo intervened and the MTA added $66 million to accelerate work. A construction manager summed up the result as four and a half billion dollars for three stations.",
      "lessons": [
        "Survey and price utility relocation in dense streets before fixing the master schedule.",
        "Staff systems testing early; commissioning, not tunneling, set Second Avenue's final date.",
        "Report scope cuts alongside 'on budget' claims."
      ],
      "fun_fact": "The April 2007 groundbreaking was held in a tunnel segment at 99th Street that had been built in the 1970s for an earlier, abandoned attempt at the line.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Construction of the Second Avenue Subway",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Construction_of_the_Second_Avenue_Subway",
          "accessed": "2026-10-25"
        },
        {
          "title": "Second Avenue Subway",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Second_Avenue_Subway",
          "accessed": "2026-10-25"
        },
        {
          "title": "72nd Street station (Second Avenue Subway)",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/72nd_Street_station_(Second_Avenue_Subway)",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the Phase 1 budget of $4.45 billion that the MTA says the project was built within (Wikipedia), with revenue service promised 'by the end of 2013' in 2007. Federal Transit Administration project management oversight reports from late 2007 (transit.dot.gov, returned 403 when opened; figure seen in search results only) list the Full Funding Grant Agreement total project cost as $4,866.614 million, signed 19 November 2007 with $1.3 billion in federal funds; that figure likely includes financing costs and is the upper bound of planned_cost_range. Earlier schedule statements: completion in 2012 (MTA, 2005). Because the actual equals the reported budget, the record shows no cost overrun; the overrun appears only as scope reductions and a three-year delay. Phase 1 length (about 2.9 km / 1.8 miles) per Wikipedia. Figures nominal; fx = 1. Only Wikipedia pages could be opened in this session for this project (web search budget exhausted); an MTA Inspector General or FTA source would raise confidence. UPDATE 2026-10-25: planned_cost changed from $4.45bn to $4,049.614 million: the FFGA signed 19 November 2007 set a total of $4,866.614 million (federal $1.3-1.35 billion), which FTA oversight reports state includes $817 million of financing costs (local share $3.52 billion incl. financing). Removing financing gives $4,049.6 million, comparable with the MTA's $4.45 billion construction budget, which was raised after the FFGA to reflect market conditions (March 2008 PMOC report) and which the MTA says the line was built within. This shows about 10% nominal cost growth on top of the scope cuts. Caveats: the FTA PMOC PDFs (transit.dot.gov: Oct 2010, Jan 2011, Mar 2008, Dec 2007) returned HTTP 403; the $4,866.614m and $817m financing figures, and the January 2007 PMOC forecast of December 2013 revenue operations (moved to June 2014 by December 2007), come from search-result excerpts of those reports. That the MTA's $4.45bn excludes financing is inferred, not stated in an opened source. Editor may prefer to revert to $4.45bn if these cannot be verified. Baseline audit 2026-10-25: Planned figures unchanged (November 2007 FFGA, excluding financing, with revenue service by end-2013). The 2005 MTA statement of completion in 2012 predates funding approval and is not used as the schedule baseline. Added the MTA $4.45 billion Phase 1 budget, raised after the FFGA (March 2008 PMOC report, search excerpt), as the rebaseline; its revised opening date was not sourced.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 23,
      "slug": "seikan-tunnel",
      "name": "Seikan Tunnel",
      "short_name": "Seikan Tunnel",
      "category": "infrastructure",
      "subcategory": "tunnel",
      "country": "Japan",
      "country_code": "JP",
      "countries": [
        "Japan"
      ],
      "continent": "Asia",
      "city": "Tsugaru Strait (Aomori / Hokkaido)",
      "lat": 41.3158,
      "lng": 140.335,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": null,
      "planned_end": null,
      "actual_start": "1971-09-28",
      "actual_end": "1988-03-13",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 197.5,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": 201400000000,
      "actual_cost": 690000000000,
      "planned_cost_range": [
        201400000000,
        538400000000
      ],
      "actual_cost_range": [
        690000000000,
        745500000000
      ],
      "cost_currency": "JPY",
      "planned_cost_year": 1971,
      "cost_year": 1988,
      "planned_fx_to_usd": 0.002875,
      "actual_fx_to_usd": 0.0078,
      "planned_cost_usd_nominal": 579025000,
      "cost_usd_nominal": 5383380000,
      "planned_cost_usd_today": 4603177383,
      "cost_usd_today": 14655093275,
      "overrun_usd_today": 10377505180,
      "overrun_pct": 242.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": 538400000000,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": "later 'planning stage' estimate (year not stated)",
      "rebaseline_overrun_pct": 28.2,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Geological surveys",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1946",
          "actual_end": "1964",
          "note": "Surveying began in 1946, induced by postwar conditions; five ferries including the Tōya Maru sank in 1954."
        },
        {
          "name": "Investigative and pilot excavation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1964",
          "actual_end": "1971-09-28",
          "note": "Japan Railway Construction Public Corporation set up in 1964 and excavation of survey works began; Japanese Wikipedia lists a 1961 start for the earliest works."
        },
        {
          "name": "Main construction and pilot tunnel",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1971-09-28",
          "actual_end": "1983-01-27",
          "note": "Main works began 28 September 1971. Severe flooding, worst at the Yoshioka shaft on 6 May 1976 at 85 tonnes per minute. Pilot tunnel broke through 27 January 1983."
        },
        {
          "name": "Main bore completion",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1983-01-27",
          "actual_end": "1985-03-10",
          "note": "Main tunnel holed through 10 March 1985."
        },
        {
          "name": "Track, systems and opening",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1985-03-10",
          "actual_end": "1988-03-13",
          "note": "52 km of continuous welded rail laid; opened 13 March 1988."
        }
      ],
      "milestones": [
        {
          "name": "Main works begin",
          "planned_date": null,
          "actual_date": "1971-09-28"
        },
        {
          "name": "Pilot tunnel breakthrough",
          "planned_date": null,
          "actual_date": "1983-01-27"
        },
        {
          "name": "Main tunnel breakthrough",
          "planned_date": null,
          "actual_date": "1985-03-10"
        },
        {
          "name": "Opening",
          "planned_date": null,
          "actual_date": "1988-03-13"
        }
      ],
      "headline": "The Seikan Tunnel was planned as an eight-year, ¥201.4 billion job; it took 24 years from the start of works and cost about ¥690 billion.",
      "summary": "The Seikan Tunnel carries rail traffic under the Tsugaru Strait between Honshu and Hokkaido, reaching about 240 m below sea level. Surveys began in 1946 and main works in September 1971. Crews fought repeated floods in volcanic, faulted rock before the pilot tunnel broke through in 1983 and the main bore in 1985. It opened on 13 March 1988 and has carried Hokkaido Shinkansen trains since 2016. It was the world's longest undersea tunnel by total length.",
      "what_went_wrong_or_right": "Geology was the main cause of cost growth and delay. Japanese Wikipedia records that planners originally expected to finish close to schedule using tunnel boring machines, but the TBM was abandoned after less than 2 km in the fractured, water-bearing rock beneath the strait. Crews switched to dynamite and mechanical picking, driving a pilot tunnel, then a service tunnel, then the main bore under the sea. Major inflows hit in 1969, 1974 and, worst of all, at the Yoshioka shaft on 6 May 1976, at a peak of 85 tonnes of water per minute. Thirty-four workers died over the project. The tunnel body cost ¥745.5 billion against ¥538.4 billion at the planning stage, about 38 percent more in nominal yen, and the whole Kaikyo line cost about ¥900 billion against ¥689 billion. Toyo Keizai reports that the original plan was to finish in eight years for ¥201.4 billion; the works took 24 years to opening and cost ¥690 billion.1 trillion was almost twelve times the original budget, which implies a much smaller earliest baseline that is not documented in sources opened. Meanwhile air travel overtook the ferries the tunnel was meant to replace; about 90 percent of passenger travel between the islands is still by plane.",
      "lessons": [
        "Probe ahead with pilot headings when geology under water is uncertain.",
        "Do not lock the plan to one excavation method before ground conditions are proven.",
        "Re-check the demand case during long builds; competing modes can change the business case."
      ],
      "fun_fact": "Its two undersea stations were the first railway stations in the world built under the sea.",
      "method_tags": [
        "phased_delivery",
        "iterative"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Seikan Tunnel",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Seikan_Tunnel",
          "accessed": "2026-10-25"
        },
        {
          "title": "青函トンネル (Seikan Tunnel)",
          "publisher": "Wikipedia (Japanese)",
          "url": "https://ja.wikipedia.org/wiki/青函トンネル",
          "accessed": "2026-10-25"
        },
        {
          "title": "青函トンネル開業記念日 (Seikan Tunnel opening anniversary)",
          "publisher": "Zatsuneta",
          "url": "https://zatsuneta.com/archives/103132.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Seikan Tunnel at 30: the contradiction facing the Shinkansen (青函トンネル30年、新幹線が直面する大矛盾)",
          "publisher": "Toyo Keizai Online, 19 March 2018",
          "url": "https://toyokeizai.net/articles/-/212935",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: ¥538.4bn 'planning stage' figure for the tunnel body (Japanese and English Wikipedia); the year of that estimate is not stated, so planned_cost_year and planned_fx_to_usd are null. Actual: ¥745.5bn for the tunnel body. English Wikipedia also says the ¥1.1 trillion total was almost 12 times the original budget, implying an earlier, much lower baseline not found in sources opened; hence 'disputed'. No originally planned completion year was found, so planned dates are null. FX: approximate 1988 annual average, about 128 JPY per USD (Federal Reserve H.10), not re-checked in this session. UPDATE 2026-10-25: Baseline changed from ¥538.4bn to ¥201.4bn: Toyo Keizai (19 March 2018) states the original plan was completion in 8 years at a total cost (総工費) of ¥201.4 billion, and that it took 24 years from start of works to opening, with total cost swelling to ¥690 billion. actual_cost changed from ¥745.5bn to ¥690bn so planned and actual come from the same source and the same 'total cost' definition; ¥745.5bn (tunnel body, Wikipedia) is the top of actual_cost_range. The ¥538.4bn 'planning stage' figure is therefore a later revision, not the original; it is kept as the top of planned_cost_range. The year of the ¥201.4bn plan is not stated; 1971 (approval of the construction plan and start of main works, September 1971) is assumed, though '24 years to opening' implies counting from the 1964 investigative works. Either way the yen was pegged at 360 per USD, so planned_fx_to_usd = 1/360 = 0.002778. The 'almost twelve times the original budget' claim (English Wikipedia, citing Langmead & Garnaut 2001, ¥1.1 trillion total) does not match ¥201.4bn (about 5.5 times) and must refer to a lower or different baseline that was not found. Originally planned completion year not found; planned_end stays null. Baseline audit 2026-10-25: Planned cost unchanged (original JPY 201.4bn). The JPY 538.4bn planning-stage figure is now stored as the rebaseline (its year is not stated). planned_fx_to_usd changed from the 360 peg (0.002778) to the 1971 annual average in tools/fx.json (0.002875), since the yen was revalued in December 1971.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 24,
      "slug": "stuttgart-21",
      "name": "Stuttgart 21 rail project",
      "short_name": "Stuttgart 21",
      "category": "infrastructure",
      "subcategory": "railway station and rail node",
      "country": "Germany",
      "country_code": "DE",
      "countries": [
        "Germany"
      ],
      "continent": "Europe",
      "city": "Stuttgart",
      "lat": 48.784,
      "lng": 9.1813,
      "era": "2000-2014",
      "status": "ongoing",
      "outcome": "over_budget_and_late",
      "planned_start": "2010-02-02",
      "planned_end": "2019",
      "actual_start": "2010-02-02",
      "actual_end": "2031-12",
      "actual_is_forecast": true,
      "planned_duration_months": 113,
      "actual_duration_months": 262.4,
      "delay_months": 149.5,
      "delay_pct": 132.3,
      "planned_cost": 3076000000,
      "actual_cost": 14500000000,
      "planned_cost_range": [
        3076000000,
        4526000000
      ],
      "actual_cost_range": null,
      "cost_currency": "EUR",
      "planned_cost_year": 2009,
      "cost_year": 2026,
      "planned_fx_to_usd": 1.3935,
      "actual_fx_to_usd": 1.13,
      "planned_cost_usd_nominal": 4284868000,
      "cost_usd_nominal": 16805500000,
      "planned_cost_usd_today": 6430292834,
      "cost_usd_today": 16805500000,
      "overrun_usd_today": 13240416000,
      "overrun_pct": 371.4,
      "overrun_basis": "nominal",
      "rebaseline_cost": 6500000000,
      "rebaseline_cost_year": 2013,
      "rebaseline_end": null,
      "rebaseline_label": "March 2013 official cost estimate",
      "rebaseline_overrun_pct": 123.1,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Concept and planning",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1994-04",
          "actual_end": "2009-04-02",
          "note": "Announced April 1994; 1995 feasibility study estimated about EUR 2.5 billion. Financing agreement signed 2 April 2009."
        },
        {
          "name": "Start of works and protests",
          "planned_start": "2010-02-02",
          "planned_end": null,
          "actual_start": "2010-02-02",
          "actual_end": "2011-11",
          "note": "Construction began 2 February 2010; police operation against protesters on 30 September 2010; state referendum on exit in November 2011 did not stop the project."
        },
        {
          "name": "Tunnels and underground through station",
          "planned_start": "2010",
          "planned_end": "2019",
          "actual_start": "2010",
          "actual_end": null,
          "note": "Cost frame raised to EUR 6.5 billion (2013, target 2021), EUR 8.2 billion (2018, target 2025), EUR 9.15 billion (2022), about EUR 11 billion (2023)."
        },
        {
          "name": "Digital rail node (ETCS) and systems",
          "planned_start": null,
          "planned_end": null,
          "actual_start": null,
          "actual_end": "2031-12",
          "note": "Digitalisation proved far more demanding than expected; faulty cable installation, a 2013 technical building no longer fit for purpose and a redesigned emergency power concept drove the 2026 re-plan."
        },
        {
          "name": "Opening of new main station (forecast)",
          "planned_start": "2019",
          "planned_end": "2019",
          "actual_start": "2031-12",
          "actual_end": "2031-12",
          "note": "December 2026 opening cancelled in 2025; ninth postponement announced June 2026 sets December 2031. Airport station December 2030, S-Bahn trunk July 2032, Pfaffensteig tunnel December 2033."
        }
      ],
      "milestones": [
        {
          "name": "Financing agreement signed",
          "planned_date": null,
          "actual_date": "2009-04-02"
        },
        {
          "name": "Construction starts",
          "planned_date": "2010-02-02",
          "actual_date": "2010-02-02"
        },
        {
          "name": "Court rules partners need not share overruns",
          "planned_date": null,
          "actual_date": "2025-08"
        },
        {
          "name": "Main station opening (forecast)",
          "planned_date": "2019",
          "actual_date": "2031-12"
        }
      ],
      "headline": "Stuttgart 21 was agreed in 2009 at about €3.1 billion for 2019; Deutsche Bahn now forecasts €14.5 billion and December 2031.",
      "summary": "Stuttgart 21 replaces Stuttgart's terminus station with an underground through station and new approach tunnels, integrated with the Wendlingen-Ulm high-speed line and a new airport station. Deutsche Bahn, the federal government, Baden-Württemberg and the city signed the financing agreement in April 2009, and construction began in February 2010 amid large protests. After nine postponements the main station is forecast to open in December 2031, with related works phased to 2033.",
      "what_went_wrong_or_right": "The 2009 financing agreement fixed costs at EUR 2.81 billion at 2004 prices, EUR 3.076 billion with general price increases, plus a EUR 1.45 billion risk budget, a cap of EUR 4.526 billion. Internal DB calculations reported in late 2009 already pointed higher, and the cost frame rose through EUR 6.5 billion (2013), 8.2 billion (2018) and about 11 billion (2023). In June 2026 DB added about EUR 3 billion more, to EUR 14.5 billion. Named causes in that re-plan: digitalisation of the rail node was much harder than planned, planning processes were not mature enough, cables were laid incorrectly (DB cites about 100 km to be redone), a technical building built in 2013 no longer fits current needs, and the emergency power concept had to be redesigned because new requirements were addressed too late. Funding disputes followed: Baden-Württemberg refused to contribute beyond its share, and in 2025 the courts upheld the ruling that DB must bear overruns above the cap alone. Political conflict, including the 2010 protests and a 2011 referendum, shaped the early years.",
      "lessons": [
        "A contractual cost cap does not cap cost; it only decides who pays the overrun.",
        "Commit to signalling and digital systems specifications before civil works lock in buildings.",
        "Re-baseline openly; repeated small postponements erode credibility more than one honest reset."
      ],
      "fun_fact": "Some S-Bahn trains upgraded for the digital node are due to be retired shortly after the new station opens, which a state politician called a misinvestment.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Stuttgart 21",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Stuttgart_21",
          "accessed": "2026-10-25"
        },
        {
          "title": "Bahn muss Mehrkosten von Stuttgart 21 alleine tragen (press release, 5 August 2025)",
          "publisher": "Ministerium für Verkehr Baden-Württemberg",
          "url": "https://www.baden-wuerttemberg.de/de/service/presse/pressemitteilung/pid/bahn-muss-mehrkosten-von-stuttgart-21-alleine-tragen",
          "accessed": "2026-10-25"
        },
        {
          "title": "Eröffnung von Stuttgart 21 auf 2031 verschoben: Die Chronologie",
          "publisher": "Wochenblatt Reporter (dpa)",
          "url": "https://www.wochenblatt-reporter.de/c-wirtschaft-handel/eroeffnung-von-stuttgart-21-auf-2031-verschoben-die-chronologie_a810128",
          "accessed": "2026-10-25"
        },
        {
          "title": "Stuttgart 21: Eröffnung nun für 2031 geplant",
          "publisher": "Heidelberg24",
          "url": "https://www.heidelberg24.de/politik-und-wirtschaft/stuttgart-21-eroeffnung-nun-fuer-2031-geplant-und-liegt-bei-14-milliarden-euro-zr-94371775.html",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the financing agreement of 2 April 2009, EUR 3.076 billion (EUR 2.81 billion at 1 January 2004 prices, nominalised), with a risk budget of EUR 1.45 billion giving a cap of EUR 4.526 billion (Baden-Württemberg Ministry of Transport press release, 5 August 2025); planned_cost_range covers both. Earlier figures (EUR 2.5 billion, 1995 feasibility study; EUR 2.8 billion, 2007 deal per Wikipedia) predate approval. Planned completion 2019 (dpa chronology). Latest forecast: EUR 14.5 billion and December 2031 for the main station, announced by DB chief Evelyn Palla in late June 2026 (Heidelberg24, 27 June 2026); the dpa chronology of 26 June 2026 still cited about EUR 11.3 billion, the pre-announcement figure. Scope of EUR 14.5 billion is the Stuttgart 21 project; the Wendlingen-Ulm line is a separate project. Figures nominal. FX: Fed H.10 annual average 2009, about $1.39 per euro; for 2026 the 2025 average of about $1.13 is used as a proxy because the 2026 annual average is not yet published. No Bundesrechnungshof figure was opened. Baseline audit 2026-10-25: Planned figures unchanged: the 2009 financing agreement (EUR 3.076bn, cap EUR 4.526bn including the risk budget, completion 2019) is the first approved; the 2007 EUR 2.8bn estimate is the same budget in 2004 prices and the 1995 EUR 2.5bn feasibility figure was not found in an opened source. The cap stays in planned_cost_range. Added the rebaseline: \"In March 2013, total costs were officially estimated at EUR 6.5 billion\" (Wikipedia); the revised completion date of that decision was not sourced.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 25,
      "slug": "suez-canal",
      "name": "Suez Canal",
      "short_name": "Suez Canal",
      "category": "infrastructure",
      "subcategory": "canal",
      "country": "Egypt",
      "country_code": "EG",
      "countries": [
        "Egypt",
        "France"
      ],
      "continent": "Africa",
      "city": "Ismailia",
      "lat": 30.5852,
      "lng": 32.3266,
      "era": "1800s",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1859-04-25",
      "planned_end": "1865",
      "actual_start": "1859-04-25",
      "actual_end": "1869-11-17",
      "actual_is_forecast": false,
      "planned_duration_months": 74.2,
      "actual_duration_months": 126.7,
      "delay_months": 52.5,
      "delay_pct": 70.8,
      "planned_cost": 200000000,
      "actual_cost": 432807882,
      "planned_cost_range": null,
      "actual_cost_range": [
        400000000,
        432807882
      ],
      "cost_currency": "FRF",
      "planned_cost_year": 1858,
      "cost_year": 1869,
      "planned_fx_to_usd": 0.193,
      "actual_fx_to_usd": 0.193,
      "planned_cost_usd_nominal": 38600000,
      "cost_usd_nominal": 83531921,
      "planned_cost_usd_today": 1436365385,
      "cost_usd_today": 2020428345,
      "overrun_usd_today": 1086790845,
      "overrun_pct": 116.4,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Concession and company formation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1854",
          "actual_end": "1858-12-15",
          "note": "De Lesseps obtained concessions from Sa'id Pasha in 1854 and 1856; the Suez Canal Company was formed on 15 December 1858 with 200 million francs of capital."
        },
        {
          "name": "Excavation with corvee labor",
          "planned_start": "1859-04-25",
          "planned_end": null,
          "actual_start": "1859-04-25",
          "actual_end": "1864-07-06",
          "note": "First pickaxe blow near Pelusium/Port Said on 25 April 1859. Mediterranean water reached Lake Timsah on 12 November 1862."
        },
        {
          "name": "Arbitration and switch to mechanical dredging",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1864-07-06",
          "actual_end": "1864-12-31",
          "note": "Napoleon III's arbitration of July 1864 ended forced labor and awarded the company 84 million francs; machines replaced manual digging."
        },
        {
          "name": "Mechanized excavation to the Red Sea",
          "planned_start": null,
          "planned_end": "1865",
          "actual_start": "1865",
          "actual_end": "1869-08-15",
          "note": "Funded partly by a 100-million-franc bond issue launched in 1867. Mediterranean and Red Sea waters met in the Bitter Lakes on 15 August 1869."
        },
        {
          "name": "Inauguration",
          "planned_start": null,
          "planned_end": "1865",
          "actual_start": "1869-11-17",
          "actual_end": "1869-11-17",
          "note": "Ceremonies began at Port Said on 15 November; the canal was inaugurated on 17 November 1869. Remaining works continued to 1871."
        }
      ],
      "milestones": [
        {
          "name": "Suez Canal Company founded",
          "planned_date": null,
          "actual_date": "1858-12-15"
        },
        {
          "name": "Construction begins at Port Said",
          "planned_date": "1859-04-25",
          "actual_date": "1859-04-25"
        },
        {
          "name": "Mediterranean water reaches Lake Timsah",
          "planned_date": null,
          "actual_date": "1862-11-12"
        },
        {
          "name": "End of corvee labor (arbitration award)",
          "planned_date": null,
          "actual_date": "1864-07-06"
        },
        {
          "name": "Canal inaugurated",
          "planned_date": "1865",
          "actual_date": "1869-11-17"
        }
      ],
      "headline": "The Suez Canal took ten years instead of the six announced and cost 433 million francs against a 200-million-franc estimate.",
      "summary": "Ferdinand de Lesseps won a concession from Egypt's ruler Sa'id Pasha and floated the Suez Canal Company in 1858 with 200 million francs of capital, the cost estimated by an international commission. Digging began at Port Said in April 1859, first by tens of thousands of conscripted Egyptian laborers. After forced labor was ended in 1864, steam dredgers took over. The sea-level canal opened on 17 November 1869, linking the Mediterranean and the Red Sea.",
      "what_went_wrong_or_right": "The estimate rested on a construction method that was later withdrawn. Early excavation relied on the corvee, a system of unpaid forced labor supplied by the Egyptian government. Pressure from Britain and the Ottoman court led to Napoleon III's arbitration in July 1864, which ended forced labor, returned land grants to Egypt and required Egypt to pay the company 84 million francs. The company then had to mechanize, buying and designing large steam dredgers and excavators, which added cost and time. Financing was also fragile: shares sold well in France but poorly abroad, and Sa'id Pasha had to take up 177,000 of the 400,000 shares to complete the capital. A further 100 million francs of bonds had to be sold in 1867, partly through lotteries approved by the French government. The final bill of 432,807,882 francs (Fondation Napoleon) was more than double the estimate, and Egypt bore about half of the total. The works themselves succeeded: the flat desert route and sea-level design avoided locks.",
      "lessons": [
        "An estimate that depends on one labor or supply arrangement is only as safe as that arrangement.",
        "Plan for financing shortfalls; Suez needed a sovereign backstop and a later bond issue.",
        "Mechanization chosen mid-project can rescue a schedule but rarely the original budget."
      ],
      "fun_fact": "The Mediterranean and Red Sea waters first met in the Bitter Lakes on 15 August 1869, three months before the official inauguration.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Suez Canal",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Suez_Canal",
          "accessed": "2026-10-25"
        },
        {
          "title": "Suez Company (1858-1997)",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Suez_Company_(1858%E2%80%931997)",
          "accessed": "2026-10-25"
        },
        {
          "title": "Le percement de l'isthme de Suez",
          "publisher": "Fondation Napoleon",
          "url": "https://www.napoleon.org/histoire-des-2-empires/articles/le-percement-de-listhme-de-suez/",
          "accessed": "2026-10-25"
        },
        {
          "title": "L'aventure de la construction du canal de Suez",
          "publisher": "Futura Sciences",
          "url": "https://www.futura-sciences.com/sciences/questions-reponses/histoire-histoire-aventure-construction-canal-suez-13690/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the 200-million-franc cost estimate of the International Scientific Commission, which also set the company's 1858 capital (400,000 shares at 500 francs). Note that the 200 million is also the share capital, so planned cost and capitalization coincide. Actual: total payments of 432,807,882 francs per Fondation Napoleon; Futura Sciences rounds to 400 million; de Lesseps's own account gives GBP 11,627,000 (Wikipedia, Suez Company). Planned duration: six years announced (Futura Sciences, a secondary popular source; no primary document found), so planned_end is set to 1865 at year precision. FX: French franc under the bimetallic/gold standard at about 5.18 francs per US gold dollar (25.22 francs per pound sterling, pound at $4.8665), i.e. about $0.193 per franc (MeasuringWorth parity); the US was on inconvertible greenbacks in 1869, so the gold-dollar parity is used for both years. Death toll estimates vary from under 3,000 to Nasser's 1956 claim of 120,000 and are not used here.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 26,
      "slug": "sydney-harbour-bridge",
      "name": "Sydney Harbour Bridge",
      "short_name": "Sydney Harbour Bridge",
      "category": "infrastructure",
      "subcategory": "bridge",
      "country": "Australia",
      "country_code": "AU",
      "countries": [
        "Australia",
        "United Kingdom"
      ],
      "continent": "Oceania",
      "city": "Sydney",
      "lat": -33.8523,
      "lng": 151.2108,
      "era": "1900-1945",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1923",
      "planned_end": null,
      "actual_start": "1923-07-28",
      "actual_end": "1932-03-19",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 103.7,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": 5750000,
      "actual_cost": 6250000,
      "planned_cost_range": [
        4217721,
        5750000
      ],
      "actual_cost_range": [
        6250000,
        10057170
      ],
      "cost_currency": "AUP",
      "planned_cost_year": 1922,
      "cost_year": 1932,
      "planned_fx_to_usd": 4.43,
      "actual_fx_to_usd": 2.81,
      "planned_cost_usd_nominal": 25466750,
      "cost_usd_nominal": 17506250,
      "planned_cost_usd_today": 489842557,
      "cost_usd_today": 413104802,
      "overrun_usd_today": 33048384,
      "overrun_pct": 8.7,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Legislation and tendering",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1922",
          "actual_end": "1924-03-24",
          "note": "Sydney Harbour Bridge Act 1922; tenders called 1922; contract signed with Dorman Long & Co of Middlesbrough on 24 March 1924 at AU£4,217,721."
        },
        {
          "name": "Site clearance and approaches",
          "planned_start": "1923",
          "planned_end": null,
          "actual_start": "1923-07-28",
          "actual_end": "1928-09",
          "note": "First sod turned at Milsons Point on 28 July 1923; about 800 homes demolished. Approach-span piers in place by September 1926; abutments and approach spans complete by September 1928. A 1926 strike delayed work."
        },
        {
          "name": "Steel arch erection",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1928-10-26",
          "actual_end": "1930-08-19",
          "note": "Two half-arches cantilevered out from each shore, held back by anchorage cables; halves met on 19 August 1930."
        },
        {
          "name": "Deck, pylons and finishing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1930-08",
          "actual_end": "1932-01-21",
          "note": "Deck completed June 1931; last pylon stone 15 January 1932; final rivet 21 January 1932; test train 19 January 1932."
        },
        {
          "name": "Load testing and opening",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1932-01-19",
          "actual_end": "1932-03-19",
          "note": "Opened on Saturday 19 March 1932."
        }
      ],
      "milestones": [
        {
          "name": "First sod turned",
          "planned_date": null,
          "actual_date": "1923-07-28"
        },
        {
          "name": "Dorman Long contract signed",
          "planned_date": null,
          "actual_date": "1924-03-24"
        },
        {
          "name": "Arch halves meet",
          "planned_date": null,
          "actual_date": "1930-08-19"
        },
        {
          "name": "Bridge opens",
          "planned_date": null,
          "actual_date": "1932-03-19"
        }
      ],
      "headline": "The Sydney Harbour Bridge cost about AU£6.25 million against a 1922 statutory estimate of £5.75 million, and was paid off only in 1988.",
      "summary": "The steel arch bridge across Sydney Harbour, championed by chief engineer John Bradfield of the New South Wales Department of Public Works, was built by Dorman Long & Co of Middlesbrough under a 1924 contract. Work began with clearance at Milsons Point in July 1923. The two half-arches met on 19 August 1930 and the bridge opened on 19 March 1932. It carries rail, road and footways. Sixteen workers died during construction.",
      "what_went_wrong_or_right": "The core structure was delivered close to the design concept, and the cantilevered arch erection, with each half held back by cables anchored in rock tunnels until the two met, worked as planned. Costs grew mainly outside the steel contract. The Sydney Harbour Bridge Act 1922 set the estimated cost, including land resumptions, at £5,750,000, not to be exceeded by more than 10 percent. The final figure of about £6.25 million (Wikipedia) breaches that limit, and other accounts that include wider works and charges put the total at £10,057,170, about double the original quote. Delays came from industrial action and coordination: a 1932 Dorman Long statement attributed higher costs to the 1926 strike and other troubles, and the 1930 Public Works Department annual report noted that work was held up until anchorage cables were attached and because final approved plans were not complete. Clearing the north shore approach required demolishing about 800 homes, a social cost not captured in the budget.",
      "lessons": [
        "A statutory cap with a tolerance band makes overruns visible; define clearly what it covers.",
        "Finalize approved plans before the critical erection phase; Sydney lost time waiting on drawings.",
        "Count land acquisition and displacement in the baseline, not as an afterthought."
      ],
      "fun_fact": "The loan for the bridge was not fully paid off until 1988.",
      "method_tags": [
        "fixed_price",
        "phased_delivery"
      ],
      "related_history_ids": [
        "gantt-1910",
        "taylor-1911"
      ],
      "sources": [
        {
          "title": "Sydney Harbour Bridge",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Sydney_Harbour_Bridge",
          "accessed": "2026-10-25"
        },
        {
          "title": "A dinky-di 75th (Sydney Harbour Bridge history)",
          "publisher": "Building Today (NZ)",
          "url": "https://buildingtoday.co.nz/?p=1200",
          "accessed": "2026-10-25"
        },
        {
          "title": "John Job Crew Bradfield",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/John_Job_Crew_Bradfield",
          "accessed": "2026-10-25"
        },
        {
          "title": "Sydney Harbour Bridge",
          "publisher": "Railway Wonders of the World",
          "url": "https://railwaywondersoftheworld.com/sydney-harbour.html",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Currency: Australian pound (AU£), which has no ISO 4217 code; stored as the non-ISO code 'AUP'. Do not treat as modern AUD (AUD replaced the pound in 1966 at A$2 = AU£1). Baseline: section 4 of the Sydney Harbour Bridge Act 1922, estimated cost GBP 5,750,000 including land resumptions, not to be exceeded by more than 10 percent (text of the Act at legislation.nsw.gov.au/view/pdf/asmade/act-1922-28, seen in search results; the PDF returned 403 and could not be opened, so this figure is lower-confidence). The Dorman Long contract price of AU£4,217,721 11s 10d (Wikipedia) is the lower bound of planned_cost_range. Actual: AU£6.25 million (Wikipedia); Building Today gives £10,057,170 7s 9d, likely including interest, rail and road works, hence actual_cost_range. No contractual completion date was found in any opened source, so planned_end is null. FX: the Australian pound was at par with sterling in 1922 (about $4.43 per pound, MeasuringWorth sterling-dollar annual average); by 1932 it traded at about AU£1.25 per pound sterling, with sterling about $3.51, giving roughly $2.81 per AU£. These rates are approximate. Bradfield biography (Wikipedia) confirms the 1922 Bridge Bill and the January 1924 tender opening. The web search budget ran out before a primary NSW source could be opened. UPDATE 2026-10-25: Checked again: Wikipedia confirms the Dorman Long contract of 24 March 1924 at AU£4,217,721 11s 10d and a total financial cost of AU£6.25 million (no breakdown). No opened source gives the final cost of the Dorman Long contract alone, so a contract-vs-contract pair is not possible; the main fields stay as statutory estimate (AU£5.75m, incl. land resumptions) vs total cost (AU£6.25m), both whole-project figures. A 1924 Sydney Mail report (search excerpt only; Engineers Australia heritage page behind a bot check) gives a Parliament-authorised total of £6,325,000 including approaches and resumptions and says the tender was £111,809 under Bradfield's estimate; not used. Railway Wonders of the World confirms the £4,217,721 contract and its March 1924 letting but gives no contract completion period. Planned completion date not found; planned_end stays null.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 27,
      "slug": "burj-khalifa",
      "name": "Burj Khalifa",
      "short_name": "Burj Khalifa",
      "category": "buildings",
      "subcategory": "skyscraper",
      "country": "United Arab Emirates",
      "country_code": "AE",
      "countries": [
        "United Arab Emirates",
        "South Korea",
        "Belgium"
      ],
      "continent": "Asia",
      "city": "Dubai",
      "lat": 25.1972,
      "lng": 55.2742,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2004-01",
      "planned_end": "2008-12",
      "actual_start": "2004-01-06",
      "actual_end": "2010-01-04",
      "actual_is_forecast": false,
      "planned_duration_months": 59,
      "actual_duration_months": 71.9,
      "delay_months": 12.6,
      "delay_pct": 21.4,
      "planned_cost": 900000000,
      "actual_cost": 1500000000,
      "planned_cost_range": [
        900000000,
        1000000000
      ],
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2007,
      "cost_year": 2010,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 900000000,
      "cost_usd_nominal": 1500000000,
      "planned_cost_usd_today": 1397448243,
      "cost_usd_today": 2214634519,
      "overrun_usd_today": 885853807,
      "overrun_pct": 66.7,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Excavation and foundations",
          "planned_start": "2004-01",
          "planned_end": null,
          "actual_start": "2004-01-06",
          "actual_end": "2004-09-20",
          "note": "Wikipedia gives both 6 and 12 January 2004 as the start of works."
        },
        {
          "name": "Superstructure (Samsung C&T, BESIX, Arabtec JV)",
          "planned_start": "2004-09-21",
          "planned_end": null,
          "actual_start": "2004-09-21",
          "actual_end": "2009-01-17",
          "note": "Main contractor started 21 September 2004; height kept secret until topping out at 829.8 m."
        },
        {
          "name": "Facade cladding",
          "planned_start": null,
          "planned_end": null,
          "actual_start": null,
          "actual_end": "2009-10-01",
          "note": "Original curtain-wall contractor Schmidlin went bankrupt; Far East Aluminium completed the cladding."
        },
        {
          "name": "Interior fit-out and commissioning",
          "planned_start": null,
          "planned_end": "2008-12",
          "actual_start": null,
          "actual_end": "2010-01-04",
          "note": "In March 2008 Emaar said it was four months behind; several interior designs were rejected."
        },
        {
          "name": "Remaining facilities",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2010-01-04",
          "actual_end": "2011-01-23",
          "note": "Last major planned facility became operational on 23 January 2011."
        }
      ],
      "milestones": [
        {
          "name": "Main contractor starts construction",
          "planned_date": null,
          "actual_date": "2004-09-21"
        },
        {
          "name": "Topping out at 829.8 m",
          "planned_date": null,
          "actual_date": "2009-01-17"
        },
        {
          "name": "Exterior complete",
          "planned_date": null,
          "actual_date": "2009-10-01"
        },
        {
          "name": "Opening",
          "planned_date": "2008-12",
          "actual_date": "2010-01-04"
        }
      ],
      "headline": "The world's tallest building opened 13 months after its end-2008 target, at about US$1.5 billion against early reports of US$900 million.",
      "summary": "Emaar Properties began work on Burj Dubai in January 2004 as the centerpiece of its Downtown development. A joint venture of Samsung C&T, BESIX and Arabtec built the concrete core, with Turner as project manager, and the tower topped out at 829.8 m on 17 January 2009. Cladding problems and interior redesigns pushed completion from the end of 2008 to January 2010. The tower was renamed Burj Khalifa at its opening on 4 January 2010, after Abu Dhabi's ruler.",
      "what_went_wrong_or_right": "The structure itself went largely to plan: the buttressed core allowed fast, repetitive floor cycles, and the main contractor reached the top in just over four years. Delays came from the envelope and the interiors. In early 2007 Gulf News reported the tower two months behind after Swiss curtain-wall contractor Schmidlin went bankrupt, forcing Emaar to bring in a replacement (Far East Aluminium). In March 2008 Emaar admitted a four-month slip, and chairman Mohamed Alabbar said several interior designs had been rejected because quality came first. A labor strike at subcontractor Arabtec was also reported. The 2008 financial crisis hit Dubai while fit-out was under way, and Abu Dhabi's support during the crisis led to the renaming. Emaar never published a formal baseline budget; press reports moved from US$900 million (2007) and US$1 billion (2008) to Alabbar's estimate of about US$1.5 billion at completion.",
      "lessons": [
        "Check the financial strength of key specialty subcontractors; one facade insolvency can set the critical path.",
        "Freeze interior design before fit-out starts on a fixed opening target.",
        "Publish a baseline budget; without one, nobody can measure performance."
      ],
      "fun_fact": "Emaar kept the final height secret during construction, saying it would not be announced until completion, and topped out at 829.8 m in January 2009.",
      "method_tags": [
        "design_build",
        "fast_track"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Burj Khalifa",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Burj_Khalifa",
          "accessed": "2026-10-25"
        },
        {
          "title": "Burj Dubai hits snags",
          "publisher": "Gulf News",
          "url": "https://gulfnews.com/amp/story/business%2Fproperty%2Fburj-dubai-hits-snags-1.83358",
          "accessed": "2026-10-25"
        },
        {
          "title": "World's Tallest Building Completion Delayed by Four Months, Developer Says",
          "publisher": "Construction Equipment Guide (AP)",
          "url": "https://www.constructionequipmentguide.com/worlds-tallest-building-completion-delayed-by-four-months-developer-says/10154",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "No official baseline budget was published by Emaar. planned_cost uses the earliest press figure found, US$900 million (Gulf News, February 2007), with US$1 billion (AP, March 2008) in the range; these may cover the tower structure only, while the US$1.5 billion (AED 5.5 billion) from Mohamed Alabbar may include fit-out, so the overrun is uncertain in scope. Planned completion: end of 2008 (Q4 2008 delivery target, Gulf News 2007; AP 2008). Actual end uses the 4 January 2010 opening. Wikipedia is internally inconsistent on the start date (6 or 12 January 2004). Costs in USD as reported; AED is pegged at about 0.2723 USD, so no conversion needed.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 28,
      "slug": "eiffel-tower",
      "name": "Eiffel Tower",
      "short_name": "Eiffel Tower",
      "category": "buildings",
      "subcategory": "tower",
      "country": "France",
      "country_code": "FR",
      "countries": [
        "France"
      ],
      "continent": "Europe",
      "city": "Paris",
      "lat": 48.8582,
      "lng": 2.2945,
      "era": "1800s",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1887-01",
      "planned_end": "1889-05-06",
      "actual_start": "1887-01-28",
      "actual_end": "1889-03-31",
      "actual_is_forecast": false,
      "planned_duration_months": 27.7,
      "actual_duration_months": 26.1,
      "delay_months": -1.2,
      "delay_pct": -4.3,
      "planned_cost": 6500000,
      "actual_cost": 7799401.31,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "FRF",
      "planned_cost_year": 1887,
      "cost_year": 1889,
      "planned_fx_to_usd": 0.193,
      "actual_fx_to_usd": 0.193,
      "planned_cost_usd_nominal": 1254500,
      "cost_usd_nominal": 1505284,
      "planned_cost_usd_today": 44952917,
      "cost_usd_today": 53939360,
      "overrun_usd_today": 8986443,
      "overrun_pct": 20,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Design and contract",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1884-05",
          "actual_end": "1887-01-08",
          "note": "Koechlin and Nouguier sketched the pylon in 1884; contract with the state and city signed 8 January 1887."
        },
        {
          "name": "Foundations",
          "planned_start": "1887-01",
          "planned_end": null,
          "actual_start": "1887-01-28",
          "actual_end": "1887-06-30",
          "note": "Four masonry pedestals ready by the end of June 1887."
        },
        {
          "name": "Ironwork to first level",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1887-07-01",
          "actual_end": "1888-03",
          "note": "Joining the four legs at the first level was the critical stage, completed by the end of March 1888."
        },
        {
          "name": "Second level",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1888-04",
          "actual_end": "1888-08-21",
          "note": "Second level completed 21 August 1888."
        },
        {
          "name": "Upper tower to summit",
          "planned_start": null,
          "planned_end": "1889-05-06",
          "actual_start": "1888-08-21",
          "actual_end": "1889-03-31",
          "note": "Eiffel led officials to the top on foot on 31 March 1889."
        },
        {
          "name": "Opening to the public",
          "planned_start": "1889-05-06",
          "planned_end": "1889-05-06",
          "actual_start": "1889-05-15",
          "actual_end": "1889-05-15",
          "note": "Opened nine days after the Exposition Universelle opened on 6 May 1889; lifts were not yet running."
        }
      ],
      "milestones": [
        {
          "name": "Contract signed",
          "planned_date": null,
          "actual_date": "1887-01-08"
        },
        {
          "name": "Legs joined at first level",
          "planned_date": null,
          "actual_date": "1888-03"
        },
        {
          "name": "Structure completed",
          "planned_date": "1889-05-06",
          "actual_date": "1889-03-31"
        },
        {
          "name": "Opened to the public",
          "planned_date": "1889-05-06",
          "actual_date": "1889-05-15"
        }
      ],
      "headline": "Built in about 26 months for the 1889 World's Fair, the Eiffel Tower cost 7.8 million francs against an estimate of 6.5 million.",
      "summary": "Gustave Eiffel's company won the contest for a centerpiece of the 1889 Exposition Universelle, marking the centenary of the French Revolution. The contract of 8 January 1887 gave Eiffel 1.5 million francs toward an estimated 6.5 million and the right to run the tower for 20 years. Foundations started on 28 January 1887, ironwork on 1 July 1887, and the 300-meter structure was finished on 31 March 1889, before the fair opened. Final cost was 7,799,401.31 francs.",
      "what_went_wrong_or_right": "The schedule held because the work was industrialized off site. Eiffel's drawing office produced more than 5,000 drawings, and 18,038 wrought-iron parts were prefabricated at his Levallois-Perret works to tight tolerances, then joined on site with 2.5 million rivets by about 300 on-site workers. Erection used creeper cranes climbing the legs, and the most difficult step, joining the four legs at the first level, was finished by the end of March 1888. Only one worker died. The financial structure shifted risk to the builder: the state and city contributed 1.5 million francs, less than a quarter of the 6.5 million estimate, and Eiffel raised the rest through a company in which he put up half the capital, in exchange for 20 years of operating income. Cost still rose to about 7.8 million francs, roughly 20% above the 1887 estimate. A public protest by artists, published in Le Temps on 14 February 1887, did not stop the work.",
      "lessons": [
        "Prefabricate and pre-drill components off site to make assembly fast and predictable.",
        "Identify the single hardest step early (joining the legs) and plan the critical path around it.",
        "Concession financing can align the builder with the deadline, since revenue starts only at opening."
      ],
      "fun_fact": "The lifts were not finished when the tower opened, so nearly 30,000 visitors climbed the stairs before the lifts entered service on 26 May 1889.",
      "method_tags": [
        "modular",
        "ppp",
        "critical_path"
      ],
      "related_history_ids": [
        "adamiecki-1896"
      ],
      "sources": [
        {
          "title": "Eiffel Tower",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Eiffel_Tower",
          "accessed": "2026-10-25"
        },
        {
          "title": "LEGO Architecture 21019 Eiffel Tower booklet (history and facts)",
          "publisher": "LEGO Group",
          "url": "https://www.lego.com/cdn/cs/set/assets/bltab6941ae7803cfea/21019_EiffelTower_A4_ENUS_v2_2_2.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "The construction of the Eiffel tower",
          "publisher": "Histoires de Parfums blog",
          "url": "https://www.histoiresdeparfums.com/blogs/hdp-blog/the-construction-of-the-eiffel-tower",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the 6.5 million franc estimate referred to in the 8 January 1887 contract (Wikipedia). An earlier spring 1885 estimate of 3,155,000 francs appears only in low-quality German-language FAQ sites and is not used. Actual: 7,799,401.31 gold francs (LEGO Architecture booklet; widely repeated). Planned end: the tower was built as the entrance to the Exposition Universelle, which opened 6 May 1889; no separate contract completion date was found, so the Exposition opening is used as the deadline. One blog source claims the build took twice the time originally planned; this is unsupported and not used. The May 1884 Koechlin sketch, Levallois-Perret factory, creeper cranes and the lifts entering service on 26 May 1889 are from Wikipedia; the first-level and second-level dates come from Wikipedia captions. FX: France was on the gold standard (Latin Monetary Union), roughly 5.18 francs per US dollar, so 0.193 USD per franc for both years; MeasuringWorth's table did not load, so this is an approximation. Construction start date in Wikipedia's infobox is 28 January 1887 (foundations).",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 29,
      "slug": "elbphilharmonie",
      "name": "Elbphilharmonie Hamburg",
      "short_name": "Elbphilharmonie",
      "category": "buildings",
      "subcategory": "concert hall",
      "country": "Germany",
      "country_code": "DE",
      "countries": [
        "Germany",
        "Switzerland"
      ],
      "continent": "Europe",
      "city": "Hamburg",
      "lat": 53.5414,
      "lng": 9.9842,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2007",
      "planned_end": "2010",
      "actual_start": "2007-04-02",
      "actual_end": "2016-10-31",
      "actual_is_forecast": false,
      "planned_duration_months": 36,
      "actual_duration_months": 115,
      "delay_months": 76,
      "delay_pct": 211.1,
      "planned_cost": 77000000,
      "actual_cost": 789000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        777000000,
        789000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2005,
      "cost_year": 2016,
      "planned_fx_to_usd": 1.2449,
      "actual_fx_to_usd": 1.1072,
      "planned_cost_usd_nominal": 95865000,
      "cost_usd_nominal": 873423000,
      "planned_cost_usd_today": 158032693,
      "cost_usd_today": 1171709307,
      "overrun_usd_today": 1057359983,
      "overrun_pct": 924.7,
      "overrun_basis": "nominal",
      "rebaseline_cost": 114300000,
      "rebaseline_cost_year": 2006,
      "rebaseline_end": null,
      "rebaseline_label": "2006 revised budget (city share)",
      "rebaseline_overrun_pct": 590.3,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Concept and feasibility",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2003",
          "actual_end": "2005",
          "note": "Herzog & de Meuron presented the glass wave on Kaispeicher A in 2003; 2005 feasibility study put total cost at EUR 186m."
        },
        {
          "name": "Contract and early construction",
          "planned_start": "2007",
          "planned_end": null,
          "actual_start": "2007-04-02",
          "actual_end": "2008-11",
          "note": "Foundation stone laid 2 April 2007; contract with Hochtief amended in November 2008, total estimate EUR 450m."
        },
        {
          "name": "Main construction",
          "planned_start": "2007",
          "planned_end": "2010",
          "actual_start": "2007-04-02",
          "actual_end": "2011-11",
          "note": "Disputes between the city, architects and Hochtief over design and costs."
        },
        {
          "name": "Construction halt over roof safety",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2011-11",
          "actual_end": "2013",
          "note": "Work stopped over safety of the 2,000-tonne roof; roof lowered at end of 2012."
        },
        {
          "name": "Restart under new agreement and completion",
          "planned_start": null,
          "planned_end": "2016-10",
          "actual_start": "2013",
          "actual_end": "2016-10-31",
          "note": "City agreed to pay about EUR 200m more, Hochtief took on all risks, completion fixed for October 2016."
        },
        {
          "name": "Opening",
          "planned_start": "2010",
          "planned_end": "2010",
          "actual_start": "2017-01-11",
          "actual_end": "2017-01-11",
          "note": "Inaugural concert by the NDR Elbphilharmonie Orchestra."
        }
      ],
      "milestones": [
        {
          "name": "Foundation stone laid",
          "planned_date": null,
          "actual_date": "2007-04-02"
        },
        {
          "name": "Construction halted",
          "planned_date": null,
          "actual_date": "2011-11"
        },
        {
          "name": "Hochtief handover",
          "planned_date": "2010",
          "actual_date": "2016-10-31"
        },
        {
          "name": "Inaugural concert",
          "planned_date": "2010",
          "actual_date": "2017-01-11"
        }
      ],
      "headline": "Hamburg taxpayers were told the Elbphilharmonie would cost them EUR 77 million; the bill reached EUR 789 million and the hall opened seven years late.",
      "summary": "Hamburg commissioned Herzog & de Meuron to place a glass concert hall on top of the Kaispeicher A warehouse in HafenCity. A 2005 feasibility study estimated EUR 186 million in total, of which EUR 77 million from the city, with opening in 2010. Hochtief started in April 2007. Contract amendments, design disputes and a halt from 2011 over the roof drove costs up until a 2013 settlement shifted risk to the contractor. The building was handed over on 31 October 2016 and opened on 11 January 2017.",
      "what_went_wrong_or_right": "The Hamburg parliament's inquiry committee, which reported in 2014, blamed an unfinished plan, weak political oversight and supervision, and disorder on the construction site, and named the city's project company ReGe and its head Hartmut Wegener among those responsible (SRF; Karlsruhe city council summary). The city tendered and signed the construction contract with Hochtief before the design was complete, so every later design detail became a claim. Costs rose to EUR 241.3 million in total in 2006 and to an estimated EUR 450 million after the contract was amended in November 2008. Unclear division of responsibility between the city, the architects and the contractor led to prolonged disputes, and in November 2011 work stopped over the safety of the 2,000-tonne roof. The turnaround came in a settlement at the end of 2012 and in 2013: the city paid about EUR 200 million extra and Hochtief took on all construction risk, after which the project finished on the new date of October 2016.",
      "lessons": [
        "Do not sign a construction contract before the design is complete.",
        "Give one party clear responsibility for design-construction interfaces.",
        "When a project is stuck, reset the contract so one party carries the risk."
      ],
      "fun_fact": "The Grand Hall is lined with about 10,000 individually microshaped drywall plates that disperse sound waves, according to Wikipedia.",
      "method_tags": [
        "fixed_price",
        "design_build"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Elbphilharmonie",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Elbphilharmonie",
          "accessed": "2026-10-25"
        },
        {
          "title": "Elbphilharmonie: Der stuermische Weg zur perfekten Welle",
          "publisher": "SRF",
          "url": "https://www.srf.ch/kultur/musik/elbphilharmonie-der-stuermische-weg-zur-perfekten-welle",
          "accessed": "2026-10-25"
        },
        {
          "title": "EUR 700m over budget, Hamburg concert hall finally finished",
          "publisher": "The Local Germany",
          "url": "https://www.thelocal.de/20161101/700m-over-budget-hamburg-concert-hall-finally-finished-elbphilharmonie",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the 2005 feasibility study, total EUR 186 million with the city's share EUR 77 million and opening planned for 2010 (SRF; The Local). The main fields use the public share on both sides: EUR 77 million planned versus EUR 789 million city cost (SRF, The Local; a Karlsruhe council document cites EUR 777-789 million). On a whole-project basis, Wikipedia gives EUR 241 million in 2007 rising to EUR 866 million at completion (another passage says EUR 870 million); the total-cost overrun on the 2005 figure is about 366%. Wikipedia's figure of EUR 241 million is the 2006/2007 revised estimate, not the first. The SRF timeline dates the Hochtief settlement to the end of 2012; the restart phase is dated 2013 as an approximation. FX: Federal Reserve G.5A annual averages, 2005 USD 1.2449/EUR and 2016 USD 1.1072/EUR. The glass building sits on Kaispeicher A, a 1963 warehouse by Werner Kallmorgen (Wikipedia). Era is set by actual start (2007). Nominal figures. Baseline audit 2026-10-25: Planned figures unchanged (2005 feasibility study, city share EUR 77m, opening 2010, is the first). Added the 2006 revision (total EUR 241.3m, city share EUR 114.3m) as the rebaseline (SRF timeline). SRF also gives the 2010 rise of the city share to EUR 323m with opening moved to 2012, and the 2012 Hochtief settlement fixing completion for October 2016.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 30,
      "slug": "elizabeth-tower-renovation",
      "name": "Elizabeth Tower (Big Ben) conservation project",
      "short_name": "Big Ben restoration",
      "category": "buildings",
      "subcategory": "clock tower",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "London",
      "lat": 51.5007,
      "lng": -0.1246,
      "era": "2015-now",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2017",
      "planned_end": "2021",
      "actual_start": "2017-08-21",
      "actual_end": "2022-11-13",
      "actual_is_forecast": false,
      "planned_duration_months": 48,
      "actual_duration_months": 62.7,
      "delay_months": 16.4,
      "delay_pct": 34.2,
      "planned_cost": 29000000,
      "actual_cost": 79700000,
      "planned_cost_range": null,
      "actual_cost_range": [
        79700000,
        80000000
      ],
      "cost_currency": "GBP",
      "planned_cost_year": 2016,
      "cost_year": 2020,
      "planned_fx_to_usd": 1.3554,
      "actual_fx_to_usd": 1.2837,
      "planned_cost_usd_nominal": 39309500,
      "cost_usd_nominal": 102247130,
      "planned_cost_usd_today": 52734250,
      "cost_usd_today": 127200846,
      "overrun_usd_today": 80916975,
      "overrun_pct": 174.8,
      "overrun_basis": "nominal",
      "rebaseline_cost": 79700000,
      "rebaseline_cost_year": 2020,
      "rebaseline_end": null,
      "rebaseline_label": "February 2020 budget approved by the Commons and Lords Commissions",
      "rebaseline_overrun_pct": 0,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Survey, design and procurement",
          "planned_start": "2016",
          "planned_end": "2017",
          "actual_start": "2016",
          "actual_end": "2017-08",
          "note": "Priced at GBP 29m in spring 2016; Sir Robert McAlpine won the pre-construction and scaffolding contracts in November 2016 by two-stage tender. Architect: Purcell."
        },
        {
          "name": "Scaffolding and conservation works",
          "planned_start": "2017-08",
          "planned_end": "2021",
          "actual_start": "2017-08-21",
          "actual_end": "2021-12",
          "note": "Chimes silenced 21 August 2017 for a planned four-year programme. In 2017 the estimate rose to GBP 61.1m after 16 months of survey and design; in February 2020 to GBP 79.7m after bomb damage, asbestos, lead paint and pollution damage were found."
        },
        {
          "name": "COVID-19 site stoppage and recovery",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2020-03-25",
          "actual_end": "2021",
          "note": "Work on the parliamentary estate stopped on 25 March 2020; the Commons attributed later delay and cost to the pandemic."
        },
        {
          "name": "Scaffold and gantry removal",
          "planned_start": null,
          "planned_end": "2021",
          "actual_start": "2021-12",
          "actual_end": "2022-04",
          "note": "The tower emerged from scaffolding in December 2021; the supporting gantry was removed in April 2022."
        },
        {
          "name": "Clock reinstatement and return to service",
          "planned_start": null,
          "planned_end": "2021",
          "actual_start": "2022-04",
          "actual_end": "2022-11-13",
          "note": "The bells returned to regular service for Remembrance Sunday, 13 November 2022."
        }
      ],
      "milestones": [
        {
          "name": "First cost estimate (GBP 29m)",
          "planned_date": null,
          "actual_date": "2016"
        },
        {
          "name": "Chimes silenced, works begin",
          "planned_date": "2017-08",
          "actual_date": "2017-08-21"
        },
        {
          "name": "Budget raised to GBP 79.7m",
          "planned_date": null,
          "actual_date": "2020-02"
        },
        {
          "name": "Big Ben returns to regular service",
          "planned_date": "2021",
          "actual_date": "2022-11-13"
        }
      ],
      "headline": "The repair of Big Ben's tower, priced at £29 million in 2016, ended up costing about £80 million and finished more than a year after its 2021 target.",
      "summary": "The Elizabeth Tower conservation project was the largest repair of the Palace of Westminster clock tower in its history. Commissioned by the House of Commons and House of Lords Commissions, designed by Purcell and built by Sir Robert McAlpine, it stripped and repaired the cast-iron roof, stonework, clock dials and the Great Clock mechanism. The bells fell silent on 21 August 2017 for a planned four-year programme and returned to regular service on 13 November 2022.",
      "what_went_wrong_or_right": "The cost grew in two big steps because the condition of the tower was not known when the first price was set. The spring 2016 estimate of GBP 29m rose to GBP 61.1m in 2017 after 16 months of detailed design and survey work. Construction Management reported that further stone surveys, slower than expected re-glazing and repainting, unrecorded utilities under Speaker's Green and New Palace Yard, and a risk allowance raised from GBP 5.8m to GBP 17.2m drove that rise, and parliamentary officials admitted estimating failures, saying early estimates had been set low to avoid market-driven escalation. In February 2020 the budget rose again to GBP 79.7m: Second World War bomb damage was worse than thought, asbestos turned up in unexpected places, lead paint was widespread, and about 700 stone repairs were needed, nearly double the estimate. A failed in-house attempt to restore the clock mechanism added almost GBP 2m. COVID-19 then stopped work in March 2020 and pushed completion into 2022.",
      "lessons": [
        "Survey a historic structure intrusively before fixing a public budget.",
        "Do not set early estimates low for tactical reasons; it destroys trust when they rise.",
        "Size contingency for unknown conditions in old buildings, not new-build norms."
      ],
      "fun_fact": "All 1,296 pieces of glass in the clock dials were replaced, and the dial frames were repainted in their original Prussian blue.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004"
      ],
      "sources": [
        {
          "title": "McAlpine's Big Ben contract cost climbs to GBP 61m (2 October 2017)",
          "publisher": "Construction Management (CIOB)",
          "url": "https://constructionmanagement.co.uk/mcalpines-big-ben-contract-cost-climbs-61m/",
          "accessed": "2026-10-25"
        },
        {
          "title": "List of blunders unveiled as Elizabeth Tower repair bill soars to GBP 80m (14 February 2020)",
          "publisher": "Scottish Construction Now",
          "url": "https://www.scottishconstructionnow.com/article/and-finally-list-of-blunders-unveiled-as-elizabeth-tower-repair-bill-soars-to-80m",
          "accessed": "2026-10-25"
        },
        {
          "title": "How Big Ben's Elizabeth Tower was refurbished (May 2023)",
          "publisher": "ASCE Civil Engineering",
          "url": "https://www.asce.org/publications-and-news/civil-engineering-source/civil-engineering-magazine/article/2023/05/how-big-bens-elizabeth-tower-was-refurbished",
          "accessed": "2026-10-25"
        },
        {
          "title": "Elizabeth Tower",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Elizabeth_Tower",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the spring 2016 estimate of GBP 29m (Construction Management 2017; Wikipedia citing BBC, 26 April 2016), with a planned four-year programme from August 2017 to 2021 (Wikipedia citing BBC and The Guardian, 14 August 2017). Actual: GBP 79.7m, the budget the House of Commons and Lords Commissions approved in February 2020 (Scottish Construction Now reporting the parliamentary announcement); ASCE (2023) gives the completed project as about GBP 80m. Trade press (Building / Building Design, 2021) reported a COVID-related rise of about 11 percent to close to GBP 89m; those pages did not load for verification, so that figure is not used, and the final outturn may be higher than the actual_cost shown. The parliament.uk pages returned HTTP 403 and could not be opened; parliamentary statements are cited via the press reports above. Actual end is the return of the bells to regular service on 13 November 2022; ASCE says minor works continued to April 2023. FX: Federal Reserve H.10 annual averages, $1.3554 per pound (2016) and $1.2837 (2020). Baseline audit 2026-10-25: Planned figures unchanged (spring 2016 GBP 29m). Added the February 2020 approved budget of GBP 79.7m as the rebaseline; the same figure is used as actual_cost because no final outturn was verified.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 31,
      "slug": "empire-state-building",
      "name": "Empire State Building",
      "short_name": "Empire State Building",
      "category": "buildings",
      "subcategory": "skyscraper",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "New York City",
      "lat": 40.7484,
      "lng": -73.9857,
      "era": "1900-1945",
      "status": "completed",
      "outcome": "on_time_on_budget",
      "planned_start": "1929-10-01",
      "planned_end": "1931-05-01",
      "actual_start": "1929-10-01",
      "actual_end": "1931-04-11",
      "actual_is_forecast": false,
      "planned_duration_months": 19,
      "actual_duration_months": 18.3,
      "delay_months": -0.7,
      "delay_pct": -3.5,
      "planned_cost": 50000000,
      "actual_cost": 40948900,
      "planned_cost_range": [
        43000000,
        60000000
      ],
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1929,
      "cost_year": 1931,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 50000000,
      "cost_usd_nominal": 40948900,
      "planned_cost_usd_today": 937500000,
      "cost_usd_today": 866915990,
      "overrun_usd_today": -191617927,
      "overrun_pct": -18.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Demolition of the Waldorf-Astoria",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1929-10-01",
          "actual_end": "1930-03",
          "note": "Hotel demolition began 1 October 1929 and overlapped with excavation."
        },
        {
          "name": "Excavation and foundations",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1930-01-22",
          "actual_end": "1930-03",
          "note": "Two 12-hour shifts of 300 men dug the 55-foot foundation; nearly complete by early March 1930."
        },
        {
          "name": "Steel frame erection",
          "planned_start": null,
          "planned_end": "1930-10-01",
          "actual_start": "1930-04-01",
          "actual_end": "1930-09-19",
          "note": "Topped out at 1,048 feet twelve days ahead of schedule; up to four and a half stories per week."
        },
        {
          "name": "Enclosure and fit-out",
          "planned_start": null,
          "planned_end": "1931-04-23",
          "actual_start": "1930-06",
          "actual_end": "1931-04-11",
          "note": "Structure completed 410 days after construction began, twelve days ahead of schedule."
        },
        {
          "name": "Opening",
          "planned_start": "1931-05-01",
          "planned_end": "1931-05-01",
          "actual_start": "1931-05-01",
          "actual_end": "1931-05-01",
          "note": "Opened on the date set in Shreve, Lamb and Harmon's programme."
        }
      ],
      "milestones": [
        {
          "name": "Construction begins on site",
          "planned_date": null,
          "actual_date": "1930-03-17"
        },
        {
          "name": "Steel topped out",
          "planned_date": "1930-10-01",
          "actual_date": "1930-09-19"
        },
        {
          "name": "Structure complete",
          "planned_date": "1931-04-23",
          "actual_date": "1931-04-11"
        },
        {
          "name": "Official opening",
          "planned_date": "1931-05-01",
          "actual_date": "1931-05-01"
        }
      ],
      "headline": "The Empire State Building rose in 410 days and cost $40.9 million including land and demolition, against a $50 million budget.",
      "summary": "Developers John J. Raskob and Pierre du Pont, with Al Smith as the public face, set a fixed programme: occupancy by 1 May 1931 and a budget of $50 million including land. Demolition of the Waldorf-Astoria began in October 1929, steel rose from April 1930, and the frame topped out in September 1930. Contractor Starrett Brothers and Eken finished the structure on 11 April 1931, twelve days early, and the tower opened on schedule. The Depression cut labor and material prices, and the total came to about $40.9 million, below the estimate.",
      "what_went_wrong_or_right": "Most things went right, for identifiable reasons. Architects Shreve, Lamb and Harmon worked from a fixed brief and a fixed opening date, and the design was frozen early after fifteen iterations. Starrett Brothers and Eken ran the site like a production line: trades followed each other floor by floor on a tight schedule, and up to 3,500 workers built four and a half stories a week. Demolition, excavation and erection overlapped, an early form of fast-track construction, according to Jacobsson and Wilson (Business Horizons, 2018). The steel topped out twelve days ahead of schedule and the structure was finished in 410 days. Context mattered as much as method: the Depression lowered wages and material costs after the October 1929 crash, which Jacobsson and Wilson cite as a main reason the building cost $24.7 million instead of the estimated $43 million. The downside was commercial: the building opened into a collapsed office market and was largely empty for years.",
      "lessons": [
        "Freeze the design before construction starts; fifteen early iterations were cheaper than changes on site.",
        "Overlap demolition, excavation and erection only when logistics and supply are scheduled in detail.",
        "Separate luck from skill: falling Depression prices explain part of the underrun."
      ],
      "fun_fact": "On 14 August 1930, 3,439 workers were on site in a single day, according to Wikipedia's construction history.",
      "method_tags": [
        "fast_track",
        "critical_path",
        "lean",
        "fixed_price"
      ],
      "related_history_ids": [
        "gantt-1910",
        "taylor-1911",
        "hoover-gantt-1931"
      ],
      "sources": [
        {
          "title": "Revisiting the construction of the Empire State Building: Have we forgotten something?",
          "publisher": "Jacobsson and Wilson, Business Horizons 61(1), 2018 (IDEAS/RePEc listing)",
          "url": "https://ideas.repec.org/a/eee/bushor/v61y2018i1p47-57.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Empire State Building",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Empire_State_Building",
          "accessed": "2026-10-25"
        },
        {
          "title": "Building the Empire State",
          "publisher": "The Skyscraper Museum",
          "url": "https://old.skyscraper.org/EXHIBITIONS/BUILDING_THE_EMPIRE_STATE/CONTENT/bes_07.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Empire State Building: the world's most famous office building",
          "publisher": "CityPASS",
          "url": "https://www.citypass.com/articles/new-york/empire-state-building-worlds-famous-office-building",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Cost figures vary by scope. Main fields use construction-only figures from Jacobsson and Wilson (2018): estimate $43 million, actual $24.7 million. Wikipedia gives a $50 million budget at design stage and a total of $40,948,900 including demolition of the Waldorf-Astoria (and, per wider sources, land); EBSCO cites a $60 million budget, not used. The Skyscraper Museum gives about $25 million. Schedule: Lamb's programme set completion for 1 May 1931; Wikipedia says steel topped out 19 September 1930 twelve days ahead of schedule and the structure was finished 11 April 1931 twelve days ahead, so planned dates of about 1 October 1930 and 23 April 1931 are inferred from those statements. Wikipedia also says the opening was 45 days ahead of a projected date, which conflicts with the 1 May programme date; treated as unresolved. Jacobsson and Wilson say the project took 1 year and 45 days against 1 year and 6 months anticipated. planned_start/actual_start use the start of demolition (1 October 1929); site construction began 17 March 1930. USD, so fx = 1. UPDATE 2026-10-25: Main fields changed to a like-for-like whole-project pair: planned $50 million (the budget within which the plans were devised, Stern, Gilmartin & Mellins 1987 via Wikipedia) vs actual $40,948,900 total (Wikipedia: includes demolition of the Waldorf-Astoria; CityPASS labels it 'building and property'). Previously planned $43m vs actual $24.7m. The $24,718,000 figure is building only (CityPASS), so it is not comparable with a whole-project budget and was removed from actual_cost_range. planned_cost_range now spans the $43 million estimate (Jacobsson and Wilson 2018) to the $60 million 'budgeted for construction' (Sinclair 1998 via Wikipedia). Whether the $50 million budget included land is not stated explicitly.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 32,
      "slug": "gateway-arch",
      "name": "Gateway Arch (Jefferson National Expansion Memorial)",
      "short_name": "Gateway Arch",
      "category": "buildings",
      "subcategory": "monument",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "St. Louis",
      "lat": 38.6247,
      "lng": -90.1848,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1959-06",
      "planned_end": "1964",
      "actual_start": "1959-06-23",
      "actual_end": "1967-07-24",
      "actual_is_forecast": false,
      "planned_duration_months": 60.5,
      "actual_duration_months": 97,
      "delay_months": 36.8,
      "delay_pct": 60.7,
      "planned_cost": 11442418,
      "actual_cost": 13000000,
      "planned_cost_range": [
        8067000,
        11442418
      ],
      "actual_cost_range": [
        13000000,
        13500000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1962,
      "cost_year": 1967,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 11442418,
      "cost_usd_nominal": 13000000,
      "planned_cost_usd_today": 121788112,
      "cost_usd_today": 125523952,
      "overrun_usd_today": 15039527,
      "overrun_pct": 13.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Site clearance and railroad relocation",
          "planned_start": "1959-06",
          "planned_end": null,
          "actual_start": "1959-06-23",
          "actual_end": "1961-11-17",
          "note": "Groundbreaking June 23, 1959 for the railroad work; MacDonald Construction's low bid was $2,426,115. Trains began running on the relocated tracks November 17, 1961."
        },
        {
          "name": "Arch foundations and visitor center shell",
          "planned_start": "1962-03",
          "planned_end": null,
          "actual_start": "1962-03-14",
          "actual_end": "1963-02-12",
          "note": "Contract with MacDonald Construction signed March 14, 1962 for $11,442,418. First foundation concrete poured June 27, 1962, followed by a stop order for plan changes."
        },
        {
          "name": "Stainless steel arch erection",
          "planned_start": "1963-02",
          "planned_end": "1964",
          "actual_start": "1963-02-12",
          "actual_end": "1965-10-28",
          "note": "Steel subcontracted to Pittsburgh-Des Moines Steel. Delayed by a May 1963 operating engineers' strike, post-tensioning bar problems in the south leg and a June 1964 stop order over design concerns. Completion targets moved from 1964 to February 1965 and then May 15, 1965. Topped out October 28, 1965."
        },
        {
          "name": "Tram system and visitor center completion",
          "planned_start": null,
          "planned_end": "1964-12-02",
          "actual_start": "1965-10-28",
          "actual_end": "1967-07-24",
          "note": "Bi-State's tram had first been promised for December 2, 1964. The visitor center opened June 10, 1967 and the north-leg tram July 24, 1967; the south tram followed March 19, 1968."
        }
      ],
      "milestones": [
        {
          "name": "Saarinen design chosen in competition",
          "planned_date": null,
          "actual_date": "1948-02-18"
        },
        {
          "name": "Arch contract signed",
          "planned_date": null,
          "actual_date": "1962-03-14"
        },
        {
          "name": "First steel section set",
          "planned_date": null,
          "actual_date": "1963-02-12"
        },
        {
          "name": "Topping out",
          "planned_date": "1964",
          "actual_date": "1965-10-28"
        },
        {
          "name": "Dedication",
          "planned_date": "1965-10",
          "actual_date": "1968-05-25"
        }
      ],
      "headline": "Expected to finish for St. Louis's 1964 bicentennial, the Gateway Arch topped out in October 1965 and cost about $13 million against an $11.4 million contract.",
      "summary": "The Gateway Arch, designed by Eero Saarinen after a 1947-48 competition, is the centerpiece of the Jefferson National Expansion Memorial on the St. Louis riverfront, managed by the National Park Service. After site clearance and railroad relocation from 1959, MacDonald Construction signed the arch and visitor center contract in March 1962. The first steel section was set in February 1963, and the two legs were joined on October 28, 1965. The tram to the top opened in July 1967, and the memorial was dedicated in May 1968.",
      "what_went_wrong_or_right": "The National Park Service administrative history records a project driven by funding as much as engineering. Congress repeatedly approved less than the Park Service requested, so work proceeded in separately funded phases. When arch bids were opened in January 1962 they ranged from $11.9 million to $12.8 million against an engineers' estimate of $8,067,000, and the contract was signed at $11,442,418 after scope reductions. Construction then met several named delays: a stop order for plan changes after the first foundation pour in 1962, a strike by hoisting and operating engineers in May 1963, problems with post-tensioning bars in the south leg in 1963-64, and a June 1964 stop order over design concerns raised by consultants to the steel subcontractor. Welding heat distorted some stainless steel sections, and workers in the narrow legs competed for space. The administrative history states that arch construction costs ran $4 million above estimate. Completion slipped from the 1964 bicentennial to October 1965. Congress did not appropriate the remaining funds in 1966 and 1967, which delayed the tram and dedication.",
      "lessons": [
        "Reconcile the engineers' estimate with market prices before bidding; a 40 percent gap signals trouble.",
        "Phase-by-phase appropriations stretch schedules; secure multi-year funding where possible.",
        "Plan crew access and work zones in confined structures."
      ],
      "fun_fact": "On the day the arch was closed, workers sprayed the south leg with water to cool the steel so the final section would fit the gap.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [],
      "sources": [
        {
          "title": "Jefferson National Expansion Memorial: An Administrative History, Chapter VII (1959-1968)",
          "publisher": "National Park Service (via NPS History)",
          "url": "https://www.npshistory.com/publications/jeff/adhi/chap7-1.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Gateway Arch",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Gateway_Arch",
          "accessed": "2026-10-25"
        },
        {
          "title": "Gateway Arch National Park Purpose and Significance",
          "publisher": "National Park Service",
          "url": "https://home.nps.gov/jeff/learn/news/gateway-arch-national-park-purpose-and-significance.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline cost: the March 14, 1962 contract with MacDonald Construction for the arch and visitor center shell, $11,442,418 (NPS administrative history). The engineers' estimate of $8,067,000 is the low end of the planned range. Baseline schedule: completion expected by fall 1964 for the city's bicentennial (Wikipedia). Actual cost: $13 million (Wikipedia); the NPS administrative history says contracts for the project totaled $13,500,000, hence the range. Scope excludes earlier land acquisition and railroad relocation (about $9 million spent 1935-1959 per NPS) and the Bi-State tram, funded separately at $1,977,750. Actual end is the opening of the tram to the public; the arch structure was topped out October 28, 1965. Figures are nominal USD; no FX needed.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 33,
      "slug": "guggenheim-bilbao",
      "name": "Guggenheim Museum Bilbao",
      "short_name": "Guggenheim Bilbao",
      "category": "buildings",
      "subcategory": "art museum",
      "country": "Spain",
      "country_code": "ES",
      "countries": [
        "Spain",
        "United States"
      ],
      "continent": "Europe",
      "city": "Bilbao",
      "lat": 43.2686,
      "lng": -2.934,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "late",
      "planned_start": "1991",
      "planned_end": "1997",
      "actual_start": "1991",
      "actual_end": "1997-10-18",
      "actual_is_forecast": false,
      "planned_duration_months": 72,
      "actual_duration_months": 75.6,
      "delay_months": 3.6,
      "delay_pct": 4.9,
      "planned_cost": 100000000,
      "actual_cost": 100000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        89000000,
        100000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1991,
      "cost_year": 1997,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 100000000,
      "cost_usd_nominal": 100000000,
      "planned_cost_usd_today": 236379184,
      "cost_usd_today": 200559701,
      "overrun_usd_today": 0,
      "overrun_pct": 0,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Agreement and architect selection",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1991",
          "actual_end": "1991",
          "note": "The Basque Government proposed the museum to the Solomon R. Guggenheim Foundation and agreed to pay the US$100 million construction cost; the Foundation selected Frank Gehry."
        },
        {
          "name": "Design and digital modeling",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1991",
          "actual_end": "1993-10",
          "note": "Gehry's office used Dassault Systemes' CATIA software, including for schematic design from fall 1993, to define the curved forms and price them."
        },
        {
          "name": "Construction",
          "planned_start": null,
          "planned_end": "1997",
          "actual_start": "1993-10-22",
          "actual_end": "1997",
          "note": "Ground was broken October 22, 1993; Ferrovial was the builder. The exterior uses about 33,000 thin titanium plates."
        },
        {
          "name": "Opening",
          "planned_start": null,
          "planned_end": "1997",
          "actual_start": "1997-10",
          "actual_end": "1997-10-18",
          "note": "King Juan Carlos I opened the museum on October 18, 1997."
        }
      ],
      "milestones": [
        {
          "name": "Basque Government funding agreement",
          "planned_date": null,
          "actual_date": "1991"
        },
        {
          "name": "Groundbreaking",
          "planned_date": null,
          "actual_date": "1993-10-22"
        },
        {
          "name": "Official opening",
          "planned_date": "1997",
          "actual_date": "1997-10-18"
        }
      ],
      "headline": "Frank Gehry's titanium museum opened in October 1997 on time and on its roughly $100 million budget, a rare result for a landmark building.",
      "summary": "The Guggenheim Museum Bilbao was a partnership between the Basque Government, which paid for the building, and the Solomon R. Guggenheim Foundation, which ran the program. Frank Gehry designed it on a former port site on the Nervion river, using CATIA software from aerospace to model and cost its curved titanium forms. Ground was broken on October 22, 1993, Ferrovial built it, and King Juan Carlos I opened it on October 18, 1997. It is widely cited as delivered on time and on budget.",
      "what_went_wrong_or_right": "Most sources agree the building was delivered on time and on budget. The Association for Project Management, drawing on Bent Flyvbjerg's analysis, names specific reasons. The objectives were clear from the start. Three tiers of government backed a single consortium and kept their support steady for the five years of the project. Once the outline was agreed, politicians did not interfere with the design, a model Flyvbjerg calls the organization of the artist. Gehry identified which items on his wish list were essential and protected those. Wikipedia, citing Paul Goldberger and Dassault Systemes, credits Gehry's method of a detailed cost estimate, CATIA visualizations and close work with the building trades, which let complex geometry be priced and fabricated with confidence. The APM also notes that titanium was unusually cheap in the mid-1990s, which helped the cladding fit the budget. Partners included the engineering firm IDOM and the Guggenheim Foundation.",
      "lessons": [
        "Agree the outline, then keep sponsors out of design detail.",
        "Use digital models to price complex geometry before committing to it.",
        "Rank the wish list early and protect only the essential items."
      ],
      "fun_fact": "The museum's skin uses about 33,000 titanium plates, rolled in Pittsburgh to a thickness of about 0.4 mm.",
      "method_tags": [
        "simulation",
        "prototyping"
      ],
      "related_history_ids": [
        "big-things-2023",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Guggenheim Museum Bilbao",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Guggenheim_Museum_Bilbao",
          "accessed": "2026-10-25"
        },
        {
          "title": "Guggenheim Museum Bilbao: why was it such a stellar project success?",
          "publisher": "Association for Project Management",
          "url": "https://www.apm.org.uk/blog/guggenheim-museum-bilbao-why-was-it-such-a-stellar-project-success/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Guggenheim Museum Bilbao (image record with project metadata)",
          "publisher": "MIT Libraries, DOME",
          "url": "https://dome.mit.edu/handle/1721.3/174553?show=full",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the Basque Government's 1991 commitment to cover a US$100 million construction cost (Wikipedia, citing the New York Times, June 24, 1997). Actual: MIT DOME project metadata gives $100 million; Wikipedia, citing the Los Angeles Times (June 2, 1997), says Ferrovial built it for $89 million, which may be the construction contract only, so the actual range is $89-100 million. The APM blog mentions about EUR 200 million of public money, which likely includes wider costs such as art and site works; it is not used. No peseta figure from a primary source was found. No exact baseline opening date was published; sources state the project finished on schedule, so planned_end is 1997. Figures are nominal USD; no FX needed.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 34,
      "slug": "marina-bay-sands",
      "name": "Marina Bay Sands",
      "short_name": "Marina Bay Sands",
      "category": "buildings",
      "subcategory": "integrated resort",
      "country": "Singapore",
      "country_code": "SG",
      "countries": [
        "Singapore",
        "United States",
        "South Korea"
      ],
      "continent": "Asia",
      "city": "Singapore",
      "lat": 1.2825,
      "lng": 103.86,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2006-12",
      "planned_end": "2009-12",
      "actual_start": "2007-02",
      "actual_end": "2011-02-17",
      "actual_is_forecast": false,
      "planned_duration_months": 36,
      "actual_duration_months": 48.1,
      "delay_months": 14.1,
      "delay_pct": 39.1,
      "planned_cost": 5050000000,
      "actual_cost": 8000000000,
      "planned_cost_range": [
        3850000000,
        5050000000
      ],
      "actual_cost_range": null,
      "cost_currency": "SGD",
      "planned_cost_year": 2006,
      "cost_year": 2010,
      "planned_fx_to_usd": 0.6296,
      "actual_fx_to_usd": 0.7337,
      "planned_cost_usd_nominal": 3179480000,
      "cost_usd_nominal": 5869600000,
      "planned_cost_usd_today": 5077825850,
      "cost_usd_today": 8666012513,
      "overrun_usd_today": 3195592114,
      "overrun_pct": 58.4,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Tender award and design",
          "planned_start": "2006-05",
          "planned_end": "2006-12",
          "actual_start": "2006-05-27",
          "actual_end": "2007-02",
          "note": "Las Vegas Sands declared winner of the Marina Bay integrated resort tender on 27 May 2006; Moshe Safdie design."
        },
        {
          "name": "Site preparation and foundations",
          "planned_start": "2006-12",
          "planned_end": null,
          "actual_start": "2007-02",
          "actual_end": null,
          "note": "Groundbreaking delayed about three months to clear embedded rock at the site."
        },
        {
          "name": "Hotel towers, podium and SkyPark (Ssangyong E&C)",
          "planned_start": null,
          "planned_end": "2009-12",
          "actual_start": "2007-02",
          "actual_end": "2010-06-23",
          "note": "Material cost escalation and labor shortages, worsened by the 2008 financial crisis; project split into phases."
        },
        {
          "name": "Phased opening",
          "planned_start": "2009-12",
          "planned_end": "2009-12",
          "actual_start": "2010-04-27",
          "actual_end": "2011-02-17",
          "note": "Casino and part of the hotel opened 27 April 2010; SkyPark 23-24 June 2010; grand opening 17 February 2011."
        }
      ],
      "milestones": [
        {
          "name": "Tender awarded to Las Vegas Sands",
          "planned_date": null,
          "actual_date": "2006-05-27"
        },
        {
          "name": "Groundbreaking",
          "planned_date": "2006-12",
          "actual_date": "2007-02"
        },
        {
          "name": "Soft opening (casino)",
          "planned_date": "2009-12",
          "actual_date": "2010-04-27"
        },
        {
          "name": "SkyPark opens",
          "planned_date": null,
          "actual_date": "2010-06-23"
        },
        {
          "name": "Grand opening",
          "planned_date": "2009-12",
          "actual_date": "2011-02-17"
        }
      ],
      "headline": "Marina Bay Sands was pitched at S$3.85 billion plus land and opened in stages from 2010 at about S$8 billion.",
      "summary": "Singapore awarded the Marina Bay integrated resort to Las Vegas Sands on 27 May 2006, at a fixed land price of S$1.2 billion. The company committed S$3.85 billion of investment, excluding land, and planned to open in a single phase in 2009. Ssangyong Engineering and Construction built Moshe Safdie's three 55-story towers joined by a rooftop SkyPark. Rising material costs and labor shortages, then the 2008 financial crisis, forced a phased opening from April 2010 to February 2011, with total cost put at S$8 billion.",
      "what_went_wrong_or_right": "The cost growth came mainly from market conditions during a regional construction boom. Wikipedia attributes the delays to escalating material costs and labor shortages from the outset, worsened by the 2008 financial crisis. By January 2008, an SEC filing reported by the Las Vegas Review-Journal said the project could cost as much as US$4.6 billion against an original US$3.6 billion, citing a weaker US dollar and higher building and material costs in Singapore. Engineering novelty added risk: a 340-meter skyway joins the tops of the three towers and overhangs the north tower by 66.5 meters. Las Vegas Sands responded by splitting the single 2009 opening into phases, opening the casino and part of the hotel on 27 April 2010 so revenue could start, followed by the SkyPark in June 2010 and the grand opening on 17 February 2011. Sheldon Adelson put the total at S$8.0 billion, including land, as of July 2009. The government's fixed land price and tender terms limited public exposure to the overrun.",
      "lessons": [
        "In a construction boom, budget for material and labor escalation explicitly.",
        "Phased opening can bring revenue forward when a single big-bang opening slips.",
        "Price currency risk when costs and financing are in different currencies."
      ],
      "fun_fact": "The SkyPark platform overhangs the north hotel tower by 66.5 meters, according to Wikipedia.",
      "method_tags": [
        "phased_delivery",
        "design_build"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Marina Bay Sands",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Marina_Bay_Sands",
          "accessed": "2026-10-25"
        },
        {
          "title": "LV Sands secures loan to build Singapore resort",
          "publisher": "Las Vegas Review-Journal, 5 January 2008",
          "url": "https://preview.reviewjournal.com/?p=866521",
          "accessed": "2026-10-25"
        },
        {
          "title": "Las Vegas Sands Corp. Form 10-K for fiscal year 2010",
          "publisher": "US Securities and Exchange Commission",
          "url": "https://www.sec.gov/Archives/edgar/data/0001300514/000095012311020089/c08516e10vk.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: Las Vegas Sands' initial commitment of S$3.85 billion excluding land (Wikipedia) plus the fixed S$1.2 billion land price, giving S$5.05 billion on the same scope as the S$8.0 billion total including land that Sheldon Adelson gave in July 2009 (Wikipedia). The S$5.05 billion sum is computed here from two sourced figures; the range shows the excluding-land figure. In US dollars, the Review-Journal reports an original estimate of US$3.6 billion and a possible US$4.6 billion (2008); Reuters coverage in 2009 cited US$5.5 billion. Planned: single-phase completion in 2009 (Wikipedia), late 2009 (Review-Journal); construction expected to start by end of 2006 per a 2006 company statement quoted in press. Groundbreaking February 2007 (Inside Asian Gaming via search snippet; page could not be opened). SkyPark phase end uses 23 June 2010 (official celebration; Wikipedia says SkyPark opened on the second day, 24 June). The SEC 10-K was used for the 27 April 2010 opening date. FX: Federal Reserve G.5A annual averages, 2006 SGD 1.5882/USD (0.6296) and 2010 SGD 1.3629/USD (0.7337).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 35,
      "slug": "millennium-dome",
      "name": "Millennium Dome and Millennium Experience",
      "short_name": "Millennium Dome",
      "category": "buildings",
      "subcategory": "exhibition",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "London (Greenwich Peninsula)",
      "lat": 51.503,
      "lng": 0.0032,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "on_time_on_budget",
      "planned_start": "1997-06",
      "planned_end": "2000-12-31",
      "actual_start": "1997-06",
      "actual_end": "2000-12-31",
      "actual_is_forecast": false,
      "planned_duration_months": 42.5,
      "actual_duration_months": 42.5,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 758000000,
      "actual_cost": 789000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "GBP",
      "planned_cost_year": 1997,
      "cost_year": 2001,
      "planned_fx_to_usd": 1.6376,
      "actual_fx_to_usd": 1.4396,
      "planned_cost_usd_nominal": 1241604000,
      "cost_usd_nominal": 1136160000,
      "planned_cost_usd_today": 2490157276,
      "cost_usd_today": 2065842511,
      "overrun_usd_today": 81167450,
      "overrun_pct": 4.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Dome construction",
          "planned_start": "1997-06",
          "planned_end": null,
          "actual_start": "1997-06",
          "actual_end": "1999-06-22",
          "note": "Construction began after the June 19, 1997 government decision to proceed; the structure was completed June 22, 1999."
        },
        {
          "name": "Exhibition installation and opening",
          "planned_start": null,
          "planned_end": "1999-12-31",
          "actual_start": "1999-06-22",
          "actual_end": "1999-12-31",
          "note": "The NAO called opening on time a major achievement. Private opening with the New Year's Eve celebration on December 31, 1999."
        },
        {
          "name": "Millennium Experience operation",
          "planned_start": "2000-01-01",
          "planned_end": "2000-12-31",
          "actual_start": "2000-01-01",
          "actual_end": "2000-12-31",
          "note": "Open to the public for one year. The business plan assumed 12 million paying visitors; about 6.5 million visited. Four extra grants totaling GBP 179 million were needed during 2000."
        },
        {
          "name": "Wind-up of the operating company",
          "planned_start": "2001-01",
          "planned_end": null,
          "actual_start": "2001-01",
          "actual_end": "2001-12-18",
          "note": "The New Millennium Experience Company entered solvent voluntary liquidation on December 18, 2001; the NAO reported on the wind-up in April 2002."
        }
      ],
      "milestones": [
        {
          "name": "Government decides to proceed",
          "planned_date": null,
          "actual_date": "1997-06-19"
        },
        {
          "name": "Dome structure completed",
          "planned_date": null,
          "actual_date": "1999-06-22"
        },
        {
          "name": "Opening night",
          "planned_date": "1999-12-31",
          "actual_date": "1999-12-31"
        },
        {
          "name": "NAO report on the Dome",
          "planned_date": null,
          "actual_date": "2000-11-09"
        },
        {
          "name": "Closure to the public",
          "planned_date": "2000-12-31",
          "actual_date": "2000-12-31"
        }
      ],
      "headline": "The Dome opened on time and spent GBP 789 million against a GBP 758 million budget, but visitor income came in at about half the plan and Lottery grants rose from GBP 399 million to GBP 628 million.",
      "summary": "The Millennium Experience was a one-year national exhibition in a purpose-built tent structure on the Greenwich Peninsula, run by the New Millennium Experience Company and funded largely by the Millennium Commission from National Lottery money. The government confirmed it in June 1997, the Dome was finished in June 1999, and it opened on December 31, 1999. It closed as planned on December 31, 2000. The National Audit Office found spending close to budget but income far below it, because the 12 million visitor target was missed.",
      "what_went_wrong_or_right": "Delivery to the fixed date went well: the National Audit Office (NAO) called opening on time a major achievement, and spending of GBP 789 million was close to the May 1997 budget of GBP 758 million. The failure was on the revenue side. The business plan assumed 12 million paying visitors; by September 2000 the company was planning on 4.5 million paying visitors, and about 6.5 million people visited in the year. Income forecast at GBP 359 million in May 1997 was expected to be about GBP 189 million by December 2001. The NAO's 2000 report found the visitor and income targets highly ambitious and inherently risky, said the complex organizational arrangements set up at the start made the project harder to manage, and said financial management was not sufficiently robust. The Millennium Commission's grant rose from GBP 399 million to GBP 628 million, an increase of 57 percent, including four extra grants totaling GBP 179 million during 2000. The NAO also found the company's contract records inadequate.",
      "lessons": [
        "Test demand forecasts against reference classes; 12 million visitors had no precedent.",
        "A fixed opening date can be met while the business case still fails.",
        "Keep governance simple and records complete; the NAO cited both."
      ],
      "fun_fact": "Despite poor press coverage, 87 percent of visitors surveyed by August 2000 said they were satisfied with their visit.",
      "method_tags": [
        "fast_track",
        "big_bang"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004"
      ],
      "sources": [
        {
          "title": "The Millennium Dome (HC 936, 1999-2000)",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/reports/the-millennium-dome/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Winding-up the New Millennium Experience Company Limited",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/reports/winding-up-the-new-millennium-experience-company-limited/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Millennium Dome",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Millennium_Dome",
          "accessed": "2026-10-25"
        },
        {
          "title": "Foreign Exchange Rates G.5A, annual (releases of January 3, 2000 and January 2, 2002)",
          "publisher": "Federal Reserve Board",
          "url": "https://www.federalreserve.gov/releases/g5a/20020102/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "high",
      "notes": "Baseline: expenditure budgeted in May 1997 of GBP 758 million (NAO, April 2002). Actual: expenditure forecast in December 2001 of GBP 789 million (NAO, April 2002), down from GBP 793 million at the NAO's 2000 report; the company was in liquidation, so this is the last official figure. Cost covers the whole Millennium Experience (structure, exhibition and operation), not the building alone. Lottery grant: GBP 399 million initially, GBP 628 million in total, of which about GBP 25 million was expected not to be needed. The NAO's 57 percent figure is a grant increase, not a cost overrun, so reported_overrun_pct is null. Visitor numbers are from Wikipedia. The full NAO report PDFs are archived at the National Archives, which demanded a CAPTCHA, so figures come from the NAO report pages. FX: Federal Reserve G.5A annual averages, USD 1.6376 per pound for 1997 and USD 1.4396 for 2001.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 36,
      "slug": "mount-rushmore",
      "name": "Mount Rushmore National Memorial",
      "short_name": "Mount Rushmore",
      "category": "buildings",
      "subcategory": "monument (mountain sculpture)",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Keystone, South Dakota",
      "lat": 43.8789,
      "lng": -103.4592,
      "era": "1900-1945",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1927",
      "planned_end": "1932",
      "actual_start": "1927-10-04",
      "actual_end": "1941-10-31",
      "actual_is_forecast": false,
      "planned_duration_months": 60,
      "actual_duration_months": 168.9,
      "delay_months": 112,
      "delay_pct": 186.6,
      "planned_cost": 500000,
      "actual_cost": 989992.32,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1927,
      "cost_year": 1941,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 500000,
      "cost_usd_nominal": 989992,
      "planned_cost_usd_today": 9267241,
      "cost_usd_today": 21670081,
      "overrun_usd_today": 10725511,
      "overrun_pct": 98,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Washington figure",
          "planned_start": "1927",
          "planned_end": null,
          "actual_start": "1927-10-04",
          "actual_end": "1934-07-04",
          "note": "Carving began October 4, 1927; Washington was dedicated on July 4, 1934, about seven years later. Work stopped for a time in the Depression for lack of money."
        },
        {
          "name": "Jefferson, Lincoln and Roosevelt figures",
          "planned_start": null,
          "planned_end": "1932",
          "actual_start": "1934",
          "actual_end": "1939-07-02",
          "note": "Jefferson was first carved to Washington's right, blasted away because of poor rock, and restarted on the left; dedicated 1936. Lincoln was dedicated September 17, 1937 and Roosevelt July 2, 1939. Start year approximate."
        },
        {
          "name": "Hall of Records",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1938",
          "actual_end": "1939",
          "note": "A tunnel was cut about 70 ft into the granite behind the heads; Borglum stopped work in 1939 and the hall was never finished."
        },
        {
          "name": "Final work under Lincoln Borglum",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1941-03",
          "actual_end": "1941-10-31",
          "note": "After Gutzon Borglum died in March 1941, his son Lincoln continued until funding ran out; the memorial was declared complete October 31, 1941."
        }
      ],
      "milestones": [
        {
          "name": "South Dakota enabling law signed",
          "planned_date": null,
          "actual_date": "1925-03-05"
        },
        {
          "name": "Dedication ceremony with President Coolidge",
          "planned_date": null,
          "actual_date": "1927-08-10"
        },
        {
          "name": "Federal matching funds authorized (up to $250,000)",
          "planned_date": null,
          "actual_date": "1929-02-25"
        },
        {
          "name": "Washington figure dedicated",
          "planned_date": null,
          "actual_date": "1934-07-04"
        },
        {
          "name": "Memorial declared complete",
          "planned_date": "1932",
          "actual_date": "1941-10-31"
        }
      ],
      "headline": "Expected to take five years and $500,000, the carving of Mount Rushmore took 14 years and cost $989,992.32, and the figures were never finished below the chest.",
      "summary": "Mount Rushmore National Memorial in the Black Hills of South Dakota was promoted by state historian Doane Robinson and Senator Peter Norbeck to draw tourists, and carved by sculptor Gutzon Borglum with about 400 workers. Carving ran from October 4, 1927 to October 31, 1941, removing about 450,000 tons of rock, about 90 percent of it by dynamite. Federal matching funds paid most of the cost. The planned waist-length figures, a Hall of Records and an inscription panel were dropped when money ran out.",
      "what_went_wrong_or_right": "The early projection of about five years and $500,000 assumed steady funding and sound rock, and neither held. Funding was the main constraint. South Dakota's 1925 enabling law allocated no money; the 1929 federal act authorized matching funds of up to $250,000, but the first federal payment was only $54,670.56, matching what the private association had spent. Money became scarce during the Great Depression and work halted for a time. Geology forced rework: the first Jefferson figure, carved to Washington's right, had to be blasted away because the rock was poor, losing about 18 months of work. Management also changed hands: an executive order placed the project under the National Park Service in 1933, and Borglum regained control through a commission in 1938. After Borglum died in March 1941 and with U.S. entry into World War II approaching, the memorial was declared complete on October 31, 1941 with reduced scope. The National Park Service records that no worker died during the 14 years of carving.",
      "lessons": [
        "Test the material before committing; poor rock cost about 18 months on one figure.",
        "Matching-fund schemes stall when the private match dries up.",
        "Decide in advance which scope can be cut if money runs out."
      ],
      "fun_fact": "Nearly 400 men and women worked on the mountain for 14 years, and not one fatality occurred.",
      "method_tags": [
        "phased_delivery",
        "prototyping"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Mount Rushmore",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Mount_Rushmore",
          "accessed": "2026-10-25"
        },
        {
          "title": "Carving History",
          "publisher": "National Park Service",
          "url": "https://www.nps.gov/moru/learn/historyculture/carving-history.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Memorial History",
          "publisher": "National Park Service",
          "url": "https://www.nps.gov/moru/learn/historyculture/memorial-history.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Construction of Mount Rushmore",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Construction_of_Mount_Rushmore",
          "accessed": "2026-10-25"
        },
        {
          "title": "Mount Rushmore lot description (initial estimates of five years and $500,000)",
          "publisher": "RR Auction",
          "url": "https://www.rrauction.com/PastAuctionItem/3423939",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: Borglum's early estimate of about $500,000 and five years. The opened source for this is an RR Auction lot description; a 1970 Congressional Record item attributing the same figures to Borglum appeared in search results, but its PDF text could not be extracted. Planned end 1932 = five years from the 1927 start. Actual cost $989,992.32 from Wikipedia (also given by WorldAtlas and Garden of Praise); no NPS page I opened states the total. Most of it was federal money, but the exact federal share was not confirmed. The start year of the Jefferson-Lincoln-Roosevelt phase (1934) is approximate, because Jefferson's first attempt began earlier and was blasted away. The scale model preceding carving is the basis for the prototyping tag. Figures are nominal USD; no FX needed.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 37,
      "slug": "one-world-trade-center",
      "name": "One World Trade Center",
      "short_name": "One World Trade Center",
      "category": "buildings",
      "subcategory": "skyscraper",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "New York City",
      "lat": 40.713,
      "lng": -74.0132,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2006-04",
      "planned_end": "2011",
      "actual_start": "2006-04-27",
      "actual_end": "2014-11-03",
      "actual_is_forecast": false,
      "planned_duration_months": 62.5,
      "actual_duration_months": 102.2,
      "delay_months": 40.1,
      "delay_pct": 64.1,
      "planned_cost": 3000000000,
      "actual_cost": 3900000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2007,
      "cost_year": 2014,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 3000000000,
      "cost_usd_nominal": 3900000000,
      "planned_cost_usd_today": 4658160809,
      "cost_usd_today": 5303978071,
      "overrun_usd_today": 1223994940,
      "overrun_pct": 30,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Foundations and below-grade works",
          "planned_start": "2006-04",
          "planned_end": null,
          "actual_start": "2006-04-27",
          "actual_end": "2008-05-17",
          "note": "Utility work, footings and foundations began April 27, 2006; the first steel beam was welded to the base on December 19, 2006, and the concrete core reached street level on May 17, 2008."
        },
        {
          "name": "Concrete base and lower floors",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2008-05-17",
          "actual_end": "2010",
          "note": "The 187-foot concrete base added in the 2005 redesign took about two years; from 2010 floors rose at roughly one per week."
        },
        {
          "name": "Steel superstructure",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2010",
          "actual_end": "2012-08",
          "note": "52 floors by December 2010, 80 floors by September 2011, 93 stories of steel by March 2012; steel topped out in August 2012."
        },
        {
          "name": "Spire installation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2012-12-12",
          "actual_end": "2013-05-10",
          "note": "First spire section hoisted December 12, 2012; final piece lifted May 10, 2013, bringing the height to 1,776 ft."
        },
        {
          "name": "Fit-out and opening",
          "planned_start": null,
          "planned_end": "2011",
          "actual_start": "2013-05",
          "actual_end": "2014-11-03",
          "note": "The tower had been due for completion in 2011 (2008 press reports); it opened to tenants on November 3, 2014."
        }
      ],
      "milestones": [
        {
          "name": "Cornerstone laid",
          "planned_date": null,
          "actual_date": "2004-07-04"
        },
        {
          "name": "Final redesign unveiled",
          "planned_date": null,
          "actual_date": "2005-06-28"
        },
        {
          "name": "Spire completes 1,776 ft height",
          "planned_date": null,
          "actual_date": "2013-05-10"
        },
        {
          "name": "Building opens",
          "planned_date": "2011",
          "actual_date": "2014-11-03"
        },
        {
          "name": "One World Observatory opens",
          "planned_date": null,
          "actual_date": "2015-05-28"
        }
      ],
      "headline": "The tallest building in the Western Hemisphere opened three years late, with its estimated cost up from $3 billion to $3.9 billion.",
      "summary": "One World Trade Center is a 1,776-ft (541 m) office tower in Lower Manhattan, designed by David Childs of Skidmore, Owings & Merrill and developed by the Port Authority of New York and New Jersey, with the Durst Organization joining in 2010. The cornerstone was laid in 2004, but disputes over money, security and design held main construction back until April 2006. The tower had been due in 2011 and opened on November 3, 2014.",
      "what_went_wrong_or_right": "The schedule slipped before construction began. Wikipedia, citing contemporary reporting, records that disputes over money, security and design delayed work from the 2004 cornerstone until 2006. In April 2005 the design was reworked to add a 187-ft concrete base for security, and the final design was not unveiled until June 28, 2005, so the design was not frozen until a year before groundbreaking. In July 2008 the Port Authority's reassessment found that the 2011 completion target was not realistic. Construction Briefing reported at the time that rising commodity prices were pushing costs up and that disagreements among the 19 federal, state and city agencies involved had left issues unresolved. Once the base was finished, the steel frame went up steadily at about one floor per week in 2010. The February 2007 estimate of about $3 billion rose to $3.9 billion by 2012. The observatory opened in May 2015, one day ahead of its own revised schedule.",
      "lessons": [
        "Freeze security requirements before the design; a late concrete base reshaped the whole tower.",
        "Count the approving agencies early; 19 public bodies at one site need one schedule owner.",
        "Index long-horizon budgets for commodity prices such as steel and concrete."
      ],
      "fun_fact": "The final section of the spire, lifted on May 10, 2013, brought the tower to exactly 1,776 ft, a figure chosen to reference the year 1776.",
      "method_tags": [
        "phased_delivery",
        "critical_path"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "One World Trade Center",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/One_World_Trade_Center",
          "accessed": "2026-10-25"
        },
        {
          "title": "Construction set backs at New York's World Trade Centre",
          "publisher": "Construction Briefing",
          "url": "https://www.constructionbriefing.com/news/construction-set-backs-at-new-yorks-world-trade-centre/1025961.article",
          "accessed": "2026-10-25"
        },
        {
          "title": "New York will announce a new budget and construction timelines at Ground Zero",
          "publisher": "Archiweb (CTK)",
          "url": "https://www.archiweb.cz/en/n/foreign/new-york-oznami-novy-rozpocet-a-terminy-vystavby-na-ground-zero",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline cost: the February 2007 estimate of about $3 billion (about $1,150 per sq ft) reported by Wikipedia; press reports from 2006 cited lower figures of $2.1-2.3 billion, but I did not open a primary source for them, so they are not used. Baseline schedule: completion due in 2011, as reported by Construction Briefing (July 2008) and CTK (October 2008). Actual cost: $3.9 billion, reported as an estimate as of April 2012; no audited final figure was found. Cost covers the tower only, not the wider World Trade Center site. The Wikipedia infobox gives a May 10, 2013 topping-out date (spire) while the body gives August 2012 for steel; both are recorded in phases. All figures are nominal USD, so no FX conversion applies.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 38,
      "slug": "palace-of-westminster",
      "name": "Rebuilding the Palace of Westminster (Houses of Parliament)",
      "short_name": "Palace of Westminster",
      "category": "buildings",
      "subcategory": "parliament building",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "London",
      "lat": 51.4995,
      "lng": -0.1248,
      "era": "1800s",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1840",
      "planned_end": "1846",
      "actual_start": "1840-04-27",
      "actual_end": "1870",
      "actual_is_forecast": false,
      "planned_duration_months": 72,
      "actual_duration_months": 362.1,
      "delay_months": 288,
      "delay_pct": 400,
      "planned_cost": 724986,
      "actual_cost": 2400000,
      "planned_cost_range": [
        707104,
        750000
      ],
      "actual_cost_range": [
        2166846,
        2400000
      ],
      "cost_currency": "GBP",
      "planned_cost_year": 1836,
      "cost_year": 1870,
      "planned_fx_to_usd": 4.82,
      "actual_fx_to_usd": 5.59,
      "planned_cost_usd_nominal": 3494433,
      "cost_usd_nominal": 13408800,
      "planned_cost_usd_today": 102450408,
      "cost_usd_today": 341395105,
      "overrun_usd_today": 238267325,
      "overrun_pct": 231,
      "overrun_basis": "nominal",
      "rebaseline_cost": 2166846,
      "rebaseline_cost_year": 1854,
      "rebaseline_end": null,
      "rebaseline_label": "July 1854 estimate",
      "rebaseline_overrun_pct": 10.8,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Foundations and House of Lords",
          "planned_start": "1840",
          "planned_end": "1846",
          "actual_start": "1840-04-27",
          "actual_end": "1847",
          "note": "Sarah Barry laid the foundation stone on April 27, 1840. Foundations on gravel, quicksand and riverbed were slow. The Lords chamber opened in 1847."
        },
        {
          "name": "Clock Tower and Great Clock",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1843-09-28",
          "actual_end": "1859-05-31",
          "note": "Built by Grissell and Peto; clock designed by Edmund Beckett Denison and George Airy and made by Dent. Clock installed April 1859."
        },
        {
          "name": "House of Commons",
          "planned_start": null,
          "planned_end": "1846",
          "actual_start": "1847",
          "actual_end": "1852",
          "note": "The Commons chamber was completed and first used in 1852, about 12 years after work began."
        },
        {
          "name": "Victoria Tower and main works",
          "planned_start": null,
          "planned_end": "1846",
          "actual_start": "1852",
          "actual_end": "1860-05-12",
          "note": "Most of the work was done by 1860; Victoria Tower is dated 1858 (Wikipedia, Palace) or 1860 (Wikipedia, Charles Barry). Charles Barry died May 12, 1860."
        },
        {
          "name": "Completion under E. M. Barry",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1860-05",
          "actual_end": "1870",
          "note": "Barry's son Edward Middleton Barry finished the building; construction ended about a decade after 1860."
        }
      ],
      "milestones": [
        {
          "name": "Barry's design wins competition",
          "planned_date": null,
          "actual_date": "1836-01"
        },
        {
          "name": "Foundation stone laid",
          "planned_date": "1840",
          "actual_date": "1840-04-27"
        },
        {
          "name": "House of Lords opens",
          "planned_date": "1846",
          "actual_date": "1847"
        },
        {
          "name": "Great Bell first chimes",
          "planned_date": null,
          "actual_date": "1859-07-11"
        },
        {
          "name": "Construction finished",
          "planned_date": "1846",
          "actual_date": "1870"
        }
      ],
      "headline": "Charles Barry estimated six years and about GBP 725,000 to rebuild Parliament; it took 30 years and about GBP 2.4 million.",
      "summary": "After fire destroyed most of the old Palace of Westminster on October 16, 1834, a competition with 97 entries was won in January 1836 by Charles Barry's Perpendicular Gothic design, with interiors by Augustus Pugin. Barry estimated six years and GBP 724,986. The foundation stone was laid in 1840, the Lords chamber opened in 1847, the Commons in 1852, and the Clock Tower housing Big Ben was finished in 1859. Barry died in 1860 and his son completed the building around 1870.",
      "what_went_wrong_or_right": "Barry's 1836 estimate of GBP 724,986 excluded the site, the river embankment and furnishings, so the baseline was incomplete from the start. By July 1854 the estimate had reached GBP 2,166,846, and the final cost is usually given as about GBP 2.4 million. The Oxford University Press blog, summarizing a history of the project, lists named causes: an unclear client, with Barry taking conflicting instructions from government, Parliament and contractors; weak governance, as the Office of Woods could not cope and was replaced by the Office of Works in 1851, while a Royal Commission set up to control the budget gave up after three years; difficult ground of gravel, quicksand and riverbed; contractor problems, with the first firm dismissed for slow progress and a strike under the second; select committee inquiries that suspended work; disputes with specialists such as the ventilation engineer David Boswell Reid and the clock designer Edmund Beckett Denison; and quantity surveying still in its infancy. The Great Bell cracked in testing and again in 1859, adding further delay.",
      "lessons": [
        "Put site, enabling works and furnishings in the first estimate, or the baseline is fiction.",
        "Name one client with authority to approve changes; conflicting instructions breed scope creep.",
        "Specialist subcontracts need clear interfaces and dispute rules from day one."
      ],
      "fun_fact": "The first Great Bell, cast in 1856, cracked beyond repair during testing; its 13.5-ton replacement, recast at Whitechapel in 1858, cracked again in September 1859.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Palace of Westminster",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Palace_of_Westminster",
          "accessed": "2026-10-25"
        },
        {
          "title": "Charles Barry",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Charles_Barry",
          "accessed": "2026-10-25"
        },
        {
          "title": "Houses of Parliament: Victorian lessons learned",
          "publisher": "Oxford University Press blog",
          "url": "https://blog.oup.com/2016/09/houses-parliament-victorian-lessons-learned/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Big Ben",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Big_Ben",
          "accessed": "2026-10-25"
        },
        {
          "title": "Dollar-Pound Exchange Rate from 1791",
          "publisher": "MeasuringWorth",
          "url": "https://www.measuringworth.com/datasets/exchangepound/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: Barry's estimate of GBP 724,986 for six years of work, excluding site, embankment and furnishings (Wikipedia, Charles Barry). Other sources give GBP 707,104 (Building magazine, as reported in search results; page could not be opened), about GBP 710,000 (OUP blog) or less than GBP 750,000 (Exploring London), hence the planned range. Planned end 1846 = six years from the 1840 start. Actual cost: about GBP 2.4 million (OUP blog); the July 1854 estimate was GBP 2,166,846 and some sources say more than GBP 2 million, hence the range and the disputed rating. The end year is approximate: most work was done by 1860, with completion about a decade later. FX from MeasuringWorth: USD 4.82 per pound in 1836 and USD 5.59 in 1870; the 1870 rate is in U.S. greenback dollars while the U.S. was off the gold standard, so the USD conversion overstates the change. The Victoria Tower completion is given as 1858 or 1860 depending on the source. The UK Parliament website was not reachable (HTTP 403). Baseline audit 2026-10-25: Planned figures unchanged (Barry's GBP 724,986 estimate). Added the July 1854 estimate of GBP 2,166,846 as the rebaseline.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 39,
      "slug": "notre-dame-restoration",
      "name": "Restoration of Notre-Dame de Paris after the 2019 fire",
      "short_name": "Notre-Dame restoration",
      "category": "buildings",
      "subcategory": "cathedral restoration",
      "country": "France",
      "country_code": "FR",
      "countries": [
        "France"
      ],
      "continent": "Europe",
      "city": "Paris",
      "lat": 48.853,
      "lng": 2.3499,
      "era": "2015-now",
      "status": "completed",
      "outcome": "late",
      "planned_start": "2019-04-16",
      "planned_end": "2024-04",
      "actual_start": "2019-04-16",
      "actual_end": "2024-12-07",
      "actual_is_forecast": false,
      "planned_duration_months": 60,
      "actual_duration_months": 67.7,
      "delay_months": 7.7,
      "delay_pct": 12.9,
      "planned_cost": 717000000,
      "actual_cost": 703000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "EUR",
      "planned_cost_year": 2019,
      "cost_year": 2024,
      "planned_fx_to_usd": 1.1194,
      "actual_fx_to_usd": 1.082,
      "planned_cost_usd_nominal": 802323000,
      "cost_usd_nominal": 760646000,
      "planned_cost_usd_today": 1010344270,
      "cost_usd_today": 780656630,
      "overrun_usd_today": -15546505,
      "overrun_pct": -2,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 0,
      "reported_overrun_source": "Cour des comptes, third report (September 2025): budget and schedule rigorously respected, no overrun",
      "phases": [
        {
          "name": "Emergency securing and consolidation",
          "planned_start": "2019-04-16",
          "planned_end": null,
          "actual_start": "2019-04-16",
          "actual_end": "2021-09",
          "note": "Budget EUR 165 million, of which EUR 151 million was used. Included removing the fire-damaged scaffolding around the old spire (June 2020) and building temporary supports and a protective 'umbrella'. The site was shut for a time after failing lead inspections, and the COVID-19 pandemic slowed work in 2020."
        },
        {
          "name": "Restoration: timber roof and spire",
          "planned_start": "2021-09",
          "planned_end": "2024-04",
          "actual_start": "2021-09",
          "actual_end": "2024-03-06",
          "note": "Oaks for the spire selected from March 2021; oak trusses hoisted from July 2023; the golden rooster returned to the spire in December 2023; spire scaffolding removed January 24 to March 6, 2024. Roof and spire were rebuilt largely in their original form, in oak and lead."
        },
        {
          "name": "Restoration: interior, windows and organ",
          "planned_start": null,
          "planned_end": "2024-04",
          "actual_start": "2022-03",
          "actual_end": "2024-11-29",
          "note": "Organ restoration began August 2020 (pipes coated in lead dust); stained glass cleaning from spring 2022. The restored interior was unveiled November 29, 2024. Restoration phase budget EUR 552 million."
        },
        {
          "name": "Reopening",
          "planned_start": null,
          "planned_end": "2024-04",
          "actual_start": "2024-12-07",
          "actual_end": "2024-12-08",
          "note": "Ceremonial reopening on December 7, 2024 and first public services on December 8, 2024. Remaining work (chevet, sacristy, pre-fire defects) continues in a later phase, scheduled for 2025-2028, funded from the surplus of donations."
        }
      ],
      "milestones": [
        {
          "name": "Fire",
          "planned_date": null,
          "actual_date": "2019-04-15"
        },
        {
          "name": "Restoration law adopted by Parliament",
          "planned_date": null,
          "actual_date": "2019-07-16"
        },
        {
          "name": "Structure declared secure",
          "planned_date": null,
          "actual_date": "2021-09"
        },
        {
          "name": "Rooster returned to new spire",
          "planned_date": null,
          "actual_date": "2023-12"
        },
        {
          "name": "Cathedral reopens",
          "planned_date": "2024-04",
          "actual_date": "2024-12-07"
        }
      ],
      "headline": "Rebuilt in five years and eight months for about EUR 703 million, Notre-Dame reopened in December 2024 within budget, according to France's Court of Audit.",
      "summary": "On April 15, 2019, a fire destroyed the roof and spire of Notre-Dame de Paris. President Emmanuel Macron set a five-year target the next day, and a July 2019 law created a dedicated public body, led first by General Jean-Louis Georgelin and, after his death in August 2023, by Philippe Jost. More than EUR 843 million in donations paid for the work. After a securing phase to September 2021, the roof and spire were rebuilt largely in their original form, and the cathedral reopened on December 7, 2024.",
      "what_went_wrong_or_right": "France's Court of Audit (Cour des comptes), in its third and final report in September 2025, described the restoration as a success with budget and timetable rigorously respected and no extra cost. The securing phase used EUR 151 million of a EUR 165 million budget, and the restoration phase had a EUR 552 million budget, leaving about EUR 140 million of donations for pre-fire defects and the sacristy. The court's president, Pierre Moscovici, praised the creation of a single public body to run the project. Several factors helped: a fixed public deadline, a special law passed 95 days after the fire, and donations that removed the usual funding uncertainty. The decision to rebuild the spire and roof largely as before ended the design debate opened by an international competition. Setbacks included a site shutdown after failed lead inspections and pandemic slowdowns in 2020. Measured against the five-year target of April 2024, the reopening came about eight months later. Earlier court reports asked for more transparency on how donations covered the public body's running costs.",
      "lessons": [
        "A single empowered delivery body with its own law can move fast on a heritage site.",
        "Settle the design question early; rebuilding as before removed a source of delay.",
        "Secure the structure fully before letting the main restoration contracts."
      ],
      "fun_fact": "The golden rooster returned to the top of the new spire in December 2023 was redesigned as a phoenix, and a time capsule of relics was placed inside it.",
      "method_tags": [
        "phased_delivery",
        "fast_track"
      ],
      "related_history_ids": [
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Chantier de Notre-Dame de Paris : une gestion exemplaire",
          "publisher": "Batiweb",
          "url": "https://www.batiweb.com/actualites/patrimoine/chantier-de-notre-dame-de-paris-une-gestion-exemplaire-47153",
          "accessed": "2026-10-25"
        },
        {
          "title": "Notre-Dame de Paris : publication du troisieme rapport de la Cour des comptes sur le chantier de conservation et de restauration de la cathedrale",
          "publisher": "French Ministry of Culture",
          "url": "https://www.culture.gouv.fr/presse/communiques-de-presse/notre-dame-de-paris-publication-du-troisieme-rapport-de-la-cour-des-comptes-sur-le-chantier-de-conservation-et-de-restauration-de-la-cathedrale",
          "accessed": "2026-10-25"
        },
        {
          "title": "Notre-Dame de Paris fire",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Notre-Dame_de_Paris_fire",
          "accessed": "2026-10-25"
        },
        {
          "title": "Notre Dame Cathedral: A timeline of events in the restoration project (AP)",
          "publisher": "Fox News / Associated Press",
          "url": "https://www.foxnews.com/world/notre-dame-cathedral-timeline-events-restoration-project.amp",
          "accessed": "2026-10-25"
        },
        {
          "title": "Foreign Exchange Rates G.5A, annual (releases of January 2, 2020 and January 5, 2026)",
          "publisher": "Federal Reserve Board",
          "url": "https://www.federalreserve.gov/releases/g5a/current/default.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline schedule: Macron's five-year target announced April 16, 2019, i.e. April 2024. A November 2022 ABC News report (cited by Wikipedia) described the work as on track for the fifth anniversary; the reopening came in December 2024. The Cour des comptes judged the calendar respected, apparently against the later December 2024 target rather than April 2024. Baseline cost: the sum of the securing-phase budget (EUR 165 million) and the restoration-phase budget (EUR 552 million) reported by Batiweb from the Cour des comptes' September 2025 report; no single total was published at the 2019 go-ahead, and the restoration budget was set after 2019, so the 2019 price year is approximate. Actual: EUR 151 million spent on securing plus the EUR 552 million restoration budget, about EUR 703 million (my sum; the court reports no overrun). Excludes the later 2025-2028 phase. Donations: more than EUR 843 million (Ministry of Culture). FX: Federal Reserve G.5A annual averages, USD 1.1194 per euro for 2019 and USD 1.0820 for 2024. Wikipedia's 'Restoration of Notre-Dame de Paris' page returned 404, so the fire article was used.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 40,
      "slug": "rijksmuseum-renovation",
      "name": "Rijksmuseum renovation, Amsterdam",
      "short_name": "Rijksmuseum renovation",
      "category": "buildings",
      "subcategory": "museum",
      "country": "Netherlands",
      "country_code": "NL",
      "countries": [
        "Netherlands"
      ],
      "continent": "Europe",
      "city": "Amsterdam",
      "lat": 52.36,
      "lng": 4.8852,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2003",
      "planned_end": "2005",
      "actual_start": "2003-12-07",
      "actual_end": "2013-04-13",
      "actual_is_forecast": false,
      "planned_duration_months": 24,
      "actual_duration_months": 112.2,
      "delay_months": 93.4,
      "delay_pct": 389.1,
      "planned_cost": 91664000,
      "actual_cost": 370000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        370000000,
        375000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2000,
      "cost_year": 2013,
      "planned_fx_to_usd": 0.9232,
      "actual_fx_to_usd": 1.3281,
      "planned_cost_usd_nominal": 84624205,
      "cost_usd_nominal": 491397000,
      "planned_cost_usd_today": 158210470,
      "cost_usd_today": 679180854,
      "overrun_usd_today": 510920222,
      "overrun_pct": 303.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": 272000000,
      "rebaseline_cost_year": 2003,
      "rebaseline_end": "2008",
      "rebaseline_label": "2003 budget at closure (State Secretary Van der Laan)",
      "rebaseline_overrun_pct": 36,
      "rebaseline_delay_months": 57.4,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Decision, budget and design",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1999",
          "actual_end": "2003",
          "note": "Renovation decided in 1999; the 2000 budget was 202 million guilders with completion in 2005. In 2003 State Secretary Medy van der Laan set a EUR 272m budget. Architects: Cruz y Ortiz."
        },
        {
          "name": "Closure and first works",
          "planned_start": "2003-12",
          "planned_end": null,
          "actual_start": "2003-12-07",
          "actual_end": "2007-06",
          "note": "Main building closed 7 December 2003. More than 80 permits were needed and a long dispute ran over keeping the public cycle passage through the building. BAM completed studios and the cellar; work stopped in summer 2007."
        },
        {
          "name": "Failed tender and re-tender in seven lots",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2007-06",
          "actual_end": "2009-05",
          "note": "BAM, the only bidder, offered EUR 222m for the main building against a EUR 134m cap; the minister rejected it in February 2008 and moved reopening to 2013. Re-tendered as seven lots; results reported to parliament on 19 May 2009."
        },
        {
          "name": "Main reconstruction",
          "planned_start": null,
          "planned_end": "2005",
          "actual_start": "2009",
          "actual_end": "2012-07-16",
          "note": "Main-building works budgeted at EUR 144m came in at EUR 158m after re-tender; the total project envelope rose to EUR 366m (2013 prices)."
        },
        {
          "name": "Fit-out, rehang and reopening",
          "planned_start": null,
          "planned_end": "2005",
          "actual_start": "2012-07-16",
          "actual_end": "2013-04-13",
          "note": "Main artworks moved back from the Philips Wing in March 2013; Queen Beatrix reopened the museum on 13 April 2013."
        }
      ],
      "milestones": [
        {
          "name": "Main building closes",
          "planned_date": "2003-12",
          "actual_date": "2003-12-07"
        },
        {
          "name": "Sole tender rejected, reopening moved to 2013",
          "planned_date": null,
          "actual_date": "2008-02"
        },
        {
          "name": "Reconstruction complete",
          "planned_date": null,
          "actual_date": "2012-07-16"
        },
        {
          "name": "Museum reopens",
          "planned_date": "2005",
          "actual_date": "2013-04-13"
        }
      ],
      "headline": "Planned in 2000 as a 202-million-guilder (about EUR 92 million) job finishing in 2005, the Rijksmuseum renovation reopened in April 2013 at about EUR 370 million.",
      "summary": "The Dutch state renovated and partly rebuilt Pierre Cuypers's 1885 Rijksmuseum in Amsterdam to a design by Spanish architects Cruz y Ortiz, restoring decorated interiors, opening up the courtyards as an atrium entrance and keeping the cycle passage through the building. The client was the Rijksgebouwendienst with the museum and the culture ministry. The main building closed on 7 December 2003, with a small selection, including The Night Watch, shown in the Philips Wing. It reopened on 13 April 2013.",
      "what_went_wrong_or_right": "Fragmented governance and a failed tender caused most of the delay. Binnenlands Bestuur listed more than 80 required permits, a long dispute with the cycling lobby over keeping the public passage through the building, and a failed tender. In 2007-08 BAM was the only bidder for the main building and offered EUR 222m against a ministry cap of EUR 134m set by an independent advisory bureau; work stopped in summer 2007, and in February 2008 culture minister Ronald Plasterk rejected the bid and moved reopening to 2013. MPs complained in 2009 that responsibility was always passed between the museum management, the city, the contractor, the project office, the cycling union and the architects, and that the Spanish architects were left to manage Dutch permit and consultation procedures. Re-tendering the work as seven lots during the construction slump brought the main-building price down to EUR 158m. The overall envelope rose from EUR 272m (2003) to EUR 333m and then EUR 366m (2013 prices), funded partly by rent that was not paid while the museum stayed shut.",
      "lessons": [
        "Name one accountable client lead to manage permits, stakeholders and contractors.",
        "Settle public access disputes, such as a through route, before tendering.",
        "Splitting a failed single-bidder tender into lots can restore competition."
      ],
      "fun_fact": "A public cycle path runs through the middle of the Rijksmuseum, and the dispute over keeping it was one cause of the delay.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Verslag van een algemeen overleg, Cultuurnota 2005-2008 (Kamerstuk 28 989, nr. 100, 15 July 2009)",
          "publisher": "Tweede Kamer der Staten-Generaal",
          "url": "https://zoek.officielebekendmakingen.nl/kst-28989-100.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Rijksmuseum reopening delayed until 2013 (27 February 2008)",
          "publisher": "DutchNews.nl",
          "url": "https://www.dutchnews.nl/2008/02/rijksmuseum_reopening_delayed/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Feestelijke heropening in 2008, 2010, 2013 (13 June 2008)",
          "publisher": "Binnenlands Bestuur",
          "url": "https://www.binnenlandsbestuur.nl/sociaal/burgerparticipatie/feestelijke-heropening-in-2008-2010-2013",
          "accessed": "2026-10-25"
        },
        {
          "title": "Verbouwing Rijksmuseum 5,5 miljoen goedkoper dan gevreesd (12 May 2014)",
          "publisher": "Cultureel Persbureau",
          "url": "https://cultureelpersbureau.nl/en/2014/05/rebuilding-realm-55-million-good-better-than-feared",
          "accessed": "2026-10-25"
        },
        {
          "title": "Rijksmuseum",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Rijksmuseum",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the EUR 272m budget set in 2003 by State Secretary Medy van der Laan (Minister Plasterk, Kamerstuk 28 989 nr. 100), with reopening about five years after the December 2003 closure, i.e. 2008 (Binnenlands Bestuur 2008: reopening now five years later than expected at closure; Wikipedia: initially five years). An earlier plan existed: the September 2000 budget of 202 million guilders (about EUR 91.7m at the fixed rate of 2.20371) with completion in 2005; against that, MPs said the budget had more than tripled and reopening slipped eight years. The 2003 figure is used because it is the budget at closure and start of works and appears to cover the scope finally built; the choice changes the overrun from about 36 percent to about 300 percent. Actual: EUR 370m from the minister's financial final report as reported by Cultureel Persbureau (May 2014), EUR 5.5m below the 2010 estimate of about EUR 375.5m; The Economist (via Wikipedia) gives about EUR 375m. The EUR 366m envelope of 2009 was in 2013 prices; figures are otherwise nominal. Actual_cost_year set to 2013. The phase dates for 2007 stoppage and 2009 restart are at month/year precision. FX: Federal Reserve G.5A annual averages, $1.1321 per euro (2003) and $1.3281 (2013). Baseline audit 2026-10-25: Planned changed from the 2003 budget of EUR 272m with 2008 reopening to the first approved plan, the September 2000 budget of 202 million guilders (EUR 91.664m at the fixed rate of 2.20371) with completion in 2005; the 2003 EUR 272m budget and 2008 reopening are now the rebaseline. Phase and milestone planned end dates moved from 2008 to 2005. planned_fx_to_usd is the 2000 Fed G.5A average (0.9232, tools/fx.json). The earlier sentence explaining why the 2003 figure was used is superseded.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 41,
      "slug": "scottish-parliament-building",
      "name": "Scottish Parliament Building (Holyrood)",
      "short_name": "Scottish Parliament",
      "category": "buildings",
      "subcategory": "parliament building",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom",
        "Spain"
      ],
      "continent": "Europe",
      "city": "Edinburgh",
      "lat": 55.9522,
      "lng": -3.1747,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1999-06",
      "planned_end": "2001-07",
      "actual_start": "1999-06",
      "actual_end": "2004-09-07",
      "actual_is_forecast": false,
      "planned_duration_months": 25,
      "actual_duration_months": 62.7,
      "delay_months": 37.7,
      "delay_pct": 150.9,
      "planned_cost": 40000000,
      "actual_cost": 414400000,
      "planned_cost_range": [
        10000000,
        90000000
      ],
      "actual_cost_range": [
        414400000,
        431000000
      ],
      "cost_currency": "GBP",
      "planned_cost_year": 1997,
      "cost_year": 2004,
      "planned_fx_to_usd": 1.6376,
      "actual_fx_to_usd": 1.833,
      "planned_cost_usd_nominal": 65520000,
      "cost_usd_nominal": 759595200,
      "planned_cost_usd_today": 131406716,
      "cost_usd_today": 1294764545,
      "overrun_usd_today": 1169787273,
      "overrun_pct": 936,
      "overrun_basis": "nominal",
      "rebaseline_cost": 195000000,
      "rebaseline_cost_year": 2000,
      "rebaseline_end": null,
      "rebaseline_label": "April 2000 Parliament-approved budget",
      "rebaseline_overrun_pct": 112.5,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 1600,
      "reported_overrun_source": "Flyvbjerg 2014, What You Should Know About Megaprojects, Table 2",
      "phases": [
        {
          "name": "Site choice and architect selection",
          "planned_start": "1997-07",
          "planned_end": "1998-07",
          "actual_start": "1997-07",
          "actual_end": "1998-07-06",
          "note": "Enric Miralles (EMBT/RMJM) design announced 6 July 1998."
        },
        {
          "name": "Design development",
          "planned_start": "1998-07",
          "planned_end": "1999-06",
          "actual_start": "1998-07",
          "actual_end": "2003",
          "note": "Design was not fixed at handover to the Parliament in June 1999; floor area grew 47% by 2000."
        },
        {
          "name": "Demolition and enabling works",
          "planned_start": "1999-06",
          "planned_end": null,
          "actual_start": "1999-06",
          "actual_end": "2000",
          "note": "Former Scottish and Newcastle brewery cleared."
        },
        {
          "name": "Main construction (construction management, Bovis Lend Lease)",
          "planned_start": "1999-06",
          "planned_end": "2001-07",
          "actual_start": "1999-06",
          "actual_end": "2004-08",
          "note": "Forecast completion slipped from July 2001 to December 2002, November 2003 and August 2004 (Audit Scotland)."
        },
        {
          "name": "Occupation and opening",
          "planned_start": "2001-07",
          "planned_end": "2001-07",
          "actual_start": "2004-09-07",
          "actual_end": "2004-10-09",
          "note": "First debate 7 September 2004; Queen opened the building 9 October 2004."
        }
      ],
      "milestones": [
        {
          "name": "Miralles design announced",
          "planned_date": null,
          "actual_date": "1998-07-06"
        },
        {
          "name": "Parliament sets GBP 195m budget",
          "planned_date": null,
          "actual_date": "2000-04"
        },
        {
          "name": "Fraser Inquiry announced",
          "planned_date": null,
          "actual_date": "2003-06-12"
        },
        {
          "name": "First debate in new building",
          "planned_date": "2001-07",
          "actual_date": "2004-09-07"
        },
        {
          "name": "Fraser Inquiry report published",
          "planned_date": null,
          "actual_date": "2004-09"
        }
      ],
      "headline": "Holyrood was first priced at GBP 10-40 million and finished three years late at GBP 414 million.",
      "summary": "After the 1997 devolution referendum, the Scottish Office estimated a new parliament building at GBP 10-40 million. Enric Miralles won the design in July 1998 and work began at Holyrood in June 1999, with completion due in July 2001. Under construction management procurement, with the design still developing and the brief growing, the forecast cost rose to GBP 431 million. MSPs held their first debate there in September 2004. Both Audit Scotland and the Fraser Inquiry examined why.",
      "what_went_wrong_or_right": "Lord Fraser's inquiry (reported September 2004) named the choice of construction management as the single factor behind most of the project's misfortunes. The method leaves cost risk with the client, and civil servants adopted it to save time without properly assessing the risk or asking ministers to approve it. Audit Scotland (June 2004) found that forecast costs more than doubled from GBP 195 million in September 2000 to GBP 431 million in February 2004, and cited weak leadership, poor cost control and more than 2,000 design changes. Earlier, its 2000 report showed that almost half of the construction cost increase came from a 47% rise in floor area, plus a complex design, higher quality, security needs and Queensberry House. Estimates were kept low: the January 1998 budget of GBP 50 million for construction excluded about GBP 40 million of fees, VAT and other costs. The deaths of architect Enric Miralles (July 2000) and First Minister Donald Dewar (October 2000) removed the project's two main champions. Fraser concluded the building could never have cost under GBP 50 million and estimated GBP 150 million was lost to delays.",
      "lessons": [
        "Choose procurement routes for their risk allocation, not only speed, and get explicit sign-off.",
        "Publish whole-project budgets including fees, VAT and contingency, not construction cost alone.",
        "Freeze the brief: a 47% increase in floor area doubled construction estimates."
      ],
      "fun_fact": "Flyvbjerg's table of large-project overruns ranks Holyrood second at 1,600%, behind only the Suez Canal.",
      "method_tags": [
        "fast_track",
        "cost_plus"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Management of the Holyrood building project",
          "publisher": "Audit Scotland (Auditor General for Scotland), June 2004",
          "url": "https://audit.scot/uploads/docs/report/2004/nr_040629_holyrood_project.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Scottish Parliament Building",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Scottish_Parliament_Building",
          "accessed": "2026-10-25"
        },
        {
          "title": "What You Should Know About Megaprojects, and Why: An Overview",
          "publisher": "Bent Flyvbjerg (arXiv preprint)",
          "url": "https://arxiv.org/abs/1409.0003",
          "accessed": "2026-10-25"
        },
        {
          "title": "Parallels with Overseas Experience: The Holyrood Building Project, Scotland",
          "publisher": "ANU Press",
          "url": "https://press-files.anu.edu.au/downloads/press/p118751/mobile/ch05s07.html",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the 1997 Scotland's Parliament White Paper estimate of GBP 10-40 million (building only, per Wikipedia's summary of the Fraser Inquiry); the upper figure, GBP 40 million, is used as the most-cited value. Audit Scotland's Exhibit 2 instead uses a January 1998 whole-project baseline of GBP 90 million (GBP 50 million construction plus GBP 40 million fees, VAT and other costs) with completion in July 2001; against that the overrun is about 360%. Flyvbjerg reports 1,600%. Actual: GBP 414.4 million final figure announced February 2007; Audit Scotland's May 2004 forecast was GBP 431 million. Actual end is the first debate on 7 September 2004 (formal opening 9 October 2004). The Fraser Inquiry report itself could not be opened online (archived site unavailable); its findings are taken from Wikipedia's cited summary and press coverage, and its publication date is given as September 2004. FX: Federal Reserve G.5A annual averages, 1997 USD 1.6376/GBP and 2004 USD 1.8330/GBP. Design development end date (2003) is approximate. Figures nominal. Baseline audit 2026-10-25: Planned figures unchanged (1997 White Paper estimate, upper figure GBP 40m, is the first announced). Added the GBP 195m budget set by the Parliament in April 2000 as the rebaseline; the January 1998 GBP 90m whole-project figure stays in planned_cost_range.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 42,
      "slug": "statue-of-liberty",
      "name": "Statue of Liberty (Liberty Enlightening the World)",
      "short_name": "Statue of Liberty",
      "category": "buildings",
      "subcategory": "monument",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States",
        "France"
      ],
      "continent": "North America",
      "city": "New York City (Liberty Island)",
      "lat": 40.6892,
      "lng": -74.0445,
      "era": "1800s",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1875",
      "planned_end": "1876",
      "actual_start": "1875-11",
      "actual_end": "1886-10-28",
      "actual_is_forecast": false,
      "planned_duration_months": 12,
      "actual_duration_months": 131.4,
      "delay_months": 123.9,
      "delay_pct": 1032.4,
      "planned_cost": 125000,
      "actual_cost": 282000,
      "planned_cost_range": null,
      "actual_cost_range": [
        250000,
        300000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1877,
      "cost_year": 1886,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 125000,
      "cost_usd_nominal": 282000,
      "planned_cost_usd_today": 3779297,
      "cost_usd_today": 10105000,
      "overrun_usd_today": 5625833,
      "overrun_pct": 125.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 100,
      "reported_overrun_source": "NPS Historical Handbook No. 11 (committee had to double its original estimate)",
      "phases": [
        {
          "name": "Fundraising in France",
          "planned_start": "1875",
          "planned_end": "1876",
          "actual_start": "1875-11",
          "actual_end": "1882-07",
          "note": "The Franco-American Union formed in November 1875; a lottery was added in 1878, and the full statue cost (about $250,000) was not subscribed until July 1882."
        },
        {
          "name": "Arm and torch fabrication",
          "planned_start": null,
          "planned_end": "1876",
          "actual_start": "1876",
          "actual_end": "1876",
          "note": "Built at the Gaget, Gauthier & Co. workshop in Paris and shown at the 1876 Philadelphia Centennial Exposition; the whole statue had been meant for the centennial."
        },
        {
          "name": "Head fabrication",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1877",
          "actual_end": "1878",
          "note": "Bartholdi concentrated on the head after 1877; it was exhibited at the 1878 Paris World's Fair."
        },
        {
          "name": "Iron framework and assembly in Paris",
          "planned_start": null,
          "planned_end": "1883",
          "actual_start": "1881",
          "actual_end": "1884-07-04",
          "note": "Eiffel and Koechlin's iron truss replaced the masonry pier planned by Viollet-le-Duc (d. 1879). Start year approximate; the statue was complete to the waist in 1882 and presented to the U.S. on July 4, 1884."
        },
        {
          "name": "Pedestal construction",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1883",
          "actual_end": "1886-04-22",
          "note": "Richard Morris Hunt's design was cut from 114 ft to 89 ft to save money. Work stopped in early 1885 when funds ran out and resumed May 11, 1885, with 38 of 46 masonry courses still to build."
        },
        {
          "name": "Shipping and reassembly",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1885-01",
          "actual_end": "1886-10-28",
          "note": "Disassembled and crated from January 1885; the Isere reached New York in June 1885; reassembly began April 1886 after the pedestal was finished."
        }
      ],
      "milestones": [
        {
          "name": "Arm and torch shown in Philadelphia",
          "planned_date": "1876",
          "actual_date": "1876"
        },
        {
          "name": "French statue fund fully subscribed",
          "planned_date": null,
          "actual_date": "1882-07"
        },
        {
          "name": "Statue presented in Paris",
          "planned_date": null,
          "actual_date": "1884-07-04"
        },
        {
          "name": "Pulitzer's pedestal fund completed",
          "planned_date": null,
          "actual_date": "1885-08-11"
        },
        {
          "name": "Dedication",
          "planned_date": "1876",
          "actual_date": "1886-10-28"
        }
      ],
      "headline": "Meant for the 1876 centennial, the statue was dedicated ten years late, and its pedestal cost about twice the $125,000 first estimated.",
      "summary": "Frederic-Auguste Bartholdi's copper statue was financed by the French public and built in Paris, with an iron framework engineered by Gustave Eiffel. Americans paid for Richard Morris Hunt's granite-faced pedestal on Bedloe's Island. Conceived to mark the 1876 centennial of U.S. independence, only the arm and torch were ready that year. The statue was finished in Paris in 1884, shipped in 1885, and dedicated on October 28, 1886, after a newspaper campaign rescued the pedestal fund.",
      "what_went_wrong_or_right": "The project was split by funding source, and both halves ran short. In France, the National Park Service history records that the statue cost much more than anticipated (about $250,000 in the end), and the money was not fully subscribed until July 1882 despite a lottery added in 1878. In the United States, the American Committee calculated in 1877 that the pedestal and erection would cost $125,000, then found it had to double that estimate. Hunt's pedestal was cut from 114 ft to 89 ft for cost reasons. By January 1885 the committee had no money left; its treasurer reported $182,000 raised and spent and said $100,000 more was needed or work would be abandoned. Joseph Pulitzer's New York World then raised $102,000 from about 120,000 donors by August 11, 1885. Technical design also changed mid-stream: after Viollet-le-Duc died in 1879, Eiffel replaced the planned masonry core with a flexible iron truss, which is still in use.",
      "lessons": [
        "Tie the deadline to secured funding; a centennial date with no money behind it slipped ten years.",
        "When two parties fund two halves, track both budgets on one schedule.",
        "Small donations at scale can close a funding gap fast when the appeal is public."
      ],
      "fun_fact": "About 80 percent of the $102,000 raised by Pulitzer's New York World for the pedestal came in gifts of less than one dollar.",
      "method_tags": [
        "phased_delivery",
        "modular"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Statue of Liberty",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Statue_of_Liberty",
          "accessed": "2026-10-25"
        },
        {
          "title": "Statue of Liberty National Monument, Historical Handbook No. 11: Plan Approved and Funds Raised",
          "publisher": "National Park Service (via NPS History)",
          "url": "https://npshistory.com/handbooks/historical/11/hh11c.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Statue of Liberty National Monument, Historical Handbook No. 11 (continued)",
          "publisher": "National Park Service (via NPS History)",
          "url": "https://npshistory.com/handbooks/historical/11/hh11d.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Cost scope is the U.S.-funded pedestal and erection only, the part with a published baseline: the American Committee's 1877 estimate of $125,000 (NPS handbook). The NPS says the committee had to double it. The actual figure of $282,000 is derived from the NPS handbook: $182,000 raised and nearly all spent by March 1885 plus the $100,000 still needed. Wikipedia says the U.S. had to raise up to $300,000, so the range is $250,000-$300,000. The French-funded statue itself cost about $250,000 (NPS); a 1955 NPS brochure gives about $210,000. No franc baseline for the statue was found, so it is excluded from the cost fields. The planned end is the 1876 centennial target. The start of the Paris assembly phase (1881) is approximate. Figures are nominal USD; no FX needed.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 43,
      "slug": "sydney-opera-house",
      "name": "Sydney Opera House",
      "short_name": "Sydney Opera House",
      "category": "buildings",
      "subcategory": "opera house",
      "country": "Australia",
      "country_code": "AU",
      "countries": [
        "Australia"
      ],
      "continent": "Oceania",
      "city": "Sydney",
      "lat": -33.8568,
      "lng": 151.2153,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1959-03-02",
      "planned_end": "1963-01-26",
      "actual_start": "1959-03-02",
      "actual_end": "1973-10-20",
      "actual_is_forecast": false,
      "planned_duration_months": 46.8,
      "actual_duration_months": 175.6,
      "delay_months": 128.8,
      "delay_pct": 275.3,
      "planned_cost": 7000000,
      "actual_cost": 102000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "AUD",
      "planned_cost_year": 1957,
      "cost_year": 1973,
      "planned_fx_to_usd": 1.12,
      "actual_fx_to_usd": 1.4875,
      "planned_cost_usd_nominal": 7798000,
      "cost_usd_nominal": 144738000,
      "planned_cost_usd_today": 89390581,
      "cost_usd_today": 1049730247,
      "overrun_usd_today": 977689936,
      "overrun_pct": 1357.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 1400,
      "reported_overrun_source": "Flyvbjerg 2014, What You Should Know About Megaprojects, Table 2",
      "phases": [
        {
          "name": "Design competition and planning",
          "planned_start": "1957-01-29",
          "planned_end": "1959-03-01",
          "actual_start": "1957-01-29",
          "actual_end": "1959-03-01",
          "note": "Utzon announced as winner on 29 January 1957; construction started before the design was resolved."
        },
        {
          "name": "Stage I: podium (Civil & Civic)",
          "planned_start": "1959-03-02",
          "planned_end": null,
          "actual_start": "1959-03-02",
          "actual_end": "1963-02",
          "note": "47 weeks behind by January 1961; podium columns later had to be rebuilt to carry the roof."
        },
        {
          "name": "Stage II: roof shells (MR Hornibrook)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1963",
          "actual_end": "1967",
          "note": "Shell geometry was solved only after years of work with Ove Arup & Partners."
        },
        {
          "name": "Utzon resignation and design handover",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1966-02-28",
          "actual_end": "1966-04",
          "note": "Utzon left on 28 February 1966; Peter Hall appointed design lead in April 1966."
        },
        {
          "name": "Stage III: interiors and fit-out",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1967",
          "actual_end": "1973-09",
          "note": "Interiors redesigned by Hall, Todd and Littlemore; first public concert 5 September 1973."
        },
        {
          "name": "Opening",
          "planned_start": "1963-01-26",
          "planned_end": "1963-01-26",
          "actual_start": "1973-10-20",
          "actual_end": "1973-10-20",
          "note": "Formally opened by Queen Elizabeth II."
        }
      ],
      "milestones": [
        {
          "name": "Utzon wins design competition",
          "planned_date": null,
          "actual_date": "1957-01-29"
        },
        {
          "name": "Sod turned at Bennelong Point",
          "planned_date": "1959-03-02",
          "actual_date": "1959-03-02"
        },
        {
          "name": "Utzon resigns",
          "planned_date": null,
          "actual_date": "1966-02-28"
        },
        {
          "name": "Official opening",
          "planned_date": "1963-01-26",
          "actual_date": "1973-10-20"
        }
      ],
      "headline": "Estimated at A$7 million and due on Australia Day 1963, the Opera House opened ten years late at A$102 million.",
      "summary": "The New South Wales government picked Jorn Utzon's sail-roofed design in January 1957 and started building on Bennelong Point in March 1959, aiming to open on 26 January 1963. Construction began before the shells could be engineered, the podium had to be partly rebuilt, and Utzon resigned in 1966 after a dispute with the works minister. A local team finished the interiors, and Queen Elizabeth II opened the building on 20 October 1973. Lotteries paid for almost all of it.",
      "what_went_wrong_or_right": "The main cause was a design that was not frozen. Premier Joe Cahill pushed for an early start in 1959, before anyone knew how to build Utzon's shells, so Stage I (the podium, contractor Civil & Civic) went ahead without final loads. By January 1961 it was 47 weeks late, and the columns later had to be rebuilt to carry the roof. Finding a buildable geometry for the shells took Utzon and Ove Arup & Partners years. After a change of government, works minister Davis Hughes withheld payments and Utzon left on 28 February 1966, which forced a redesign of the interiors by Peter Hall's team. The NSW Treasury puts the result at A$102 million, 1,357% over the original A$7 million estimate and about ten years late, and Flyvbjerg lists a 1,400% overrun. The outcome was a building that became a national symbol, financed almost entirely by 496 Opera House lotteries rather than tax revenue.",
      "lessons": [
        "Do not start construction before the structural concept is proven; rework on the podium cost years.",
        "A politically fixed opening date does not make an unresolved design buildable on time.",
        "Losing the lead designer mid-project forces costly redesign; manage client-architect conflict early."
      ],
      "fun_fact": "The NSW Treasury records that 496 Opera House lotteries, selling 86.7 million tickets between 1957 and 1986, raised the A$102 million the building cost.",
      "method_tags": [
        "fast_track",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "The House the Lotteries Built",
          "publisher": "NSW Treasury",
          "url": "https://www.nsw.gov.au/departments-and-agencies/nsw-treasury/about-us/nsw-treasury-bicentenary/walking-a-tightrope/moments/house-lotteries-built",
          "accessed": "2026-10-25"
        },
        {
          "title": "What You Should Know About Megaprojects, and Why: An Overview",
          "publisher": "Bent Flyvbjerg, Project Management Journal (arXiv preprint)",
          "url": "https://arxiv.org/abs/1409.0003",
          "accessed": "2026-10-25"
        },
        {
          "title": "Sydney Opera House",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Sydney_Opera_House",
          "accessed": "2026-10-25"
        },
        {
          "title": "Australian dollar",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Australian_dollar",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "high",
      "notes": "Baseline: the 1957 estimate of GBP-A 3.5 million (A$7 million in decimal currency) with completion set for Australia Day, 26 January 1963 (Wikipedia; NSW Treasury). Actual: A$102 million at completion in 1973. NSW Treasury and Wikipedia state 1,357% over budget; Flyvbjerg's Table 2 rounds to 1,400%. FX: 1957 A$-equivalent valued at US$1.12 (A$1 = 8s sterling, GBP1 = US$2.80, per Wikipedia 'Australian dollar'); 1973 uses the peg of US$1.4875 set on 9 September 1973 (same source). Planned phase dates for Stages II and III were never published as a baseline; Wikipedia's stage numbering is inconsistent (it also calls planning Stage I). Figures are nominal; inflation 1957-1973 explains part of the gap.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 44,
      "slug": "walt-disney-concert-hall",
      "name": "Walt Disney Concert Hall",
      "short_name": "Disney Concert Hall",
      "category": "buildings",
      "subcategory": "concert hall",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Los Angeles",
      "lat": 34.0553,
      "lng": -118.2498,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1992",
      "planned_end": "1997",
      "actual_start": "1992-12",
      "actual_end": "2003-10-23",
      "actual_is_forecast": false,
      "planned_duration_months": 60,
      "actual_duration_months": 130.3,
      "delay_months": 75.7,
      "delay_pct": 126.2,
      "planned_cost": 210000000,
      "actual_cost": 274000000,
      "planned_cost_range": [
        100000000,
        210000000
      ],
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1991,
      "cost_year": 2003,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 210000000,
      "cost_usd_nominal": 274000000,
      "planned_cost_usd_today": 496396286,
      "cost_usd_today": 479549566,
      "overrun_usd_today": 112011577,
      "overrun_pct": 30.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Underground parking garage",
          "planned_start": "1992",
          "planned_end": null,
          "actual_start": "1992-12",
          "actual_end": "1996",
          "note": "The December 1992 groundbreaking covered only the garage, which Los Angeles County funded with bonds at a cost of $110 million."
        },
        {
          "name": "Construction halt and fundraising",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1994",
          "actual_end": "1999-12",
          "note": "Work on the hall stalled for lack of money as estimates rose to $265 million by 1995; Eli Broad and Mayor Richard Riordan led renewed fundraising from 1996."
        },
        {
          "name": "Concert hall construction",
          "planned_start": "1993",
          "planned_end": "1997",
          "actual_start": "1999-12",
          "actual_end": "2003-10",
          "note": "Second and final groundbreaking in December 1999; the stone exterior was replaced with less costly stainless steel."
        },
        {
          "name": "Dedication and opening",
          "planned_start": null,
          "planned_end": "1997",
          "actual_start": "2003-10-20",
          "actual_end": "2003-10-23",
          "note": "Dedicated October 20, 2003 (MousePlanet) and opened October 23, 2003 (Wikipedia)."
        }
      ],
      "milestones": [
        {
          "name": "Lillian Disney's $50 million gift",
          "planned_date": null,
          "actual_date": "1987"
        },
        {
          "name": "Gehry designs delivered",
          "planned_date": null,
          "actual_date": "1991"
        },
        {
          "name": "Garage groundbreaking",
          "planned_date": "1992",
          "actual_date": "1992-12"
        },
        {
          "name": "Final groundbreaking for the hall",
          "planned_date": null,
          "actual_date": "1999-12"
        },
        {
          "name": "Opening",
          "planned_date": "1997",
          "actual_date": "2003-10-23"
        }
      ],
      "headline": "Planned to open in 1997 for about $210 million, Frank Gehry's hall opened six years late in 2003 at $274 million.",
      "summary": "Walt Disney Concert Hall, home of the Los Angeles Philharmonic, began with Lillian Disney's $50 million gift in 1987. Frank Gehry delivered designs in 1991, and a garage was started under the site in December 1992, with the hall due to open in 1997. Rising costs and a fundraising shortfall stalled the hall itself for about five years. After renewed fundraising, construction restarted in December 1999, and the stainless-steel-clad hall opened on October 23, 2003, at a total project cost of $274 million including the $110 million garage.",
      "what_went_wrong_or_right": "Newsweek, writing in the mid-1990s, traced a cost rise of roughly $50 million mainly to a 1992 decision to fast-track the project by bidding contracts before the design drawings were finished. It also cited five years of negotiation with county and city officials after the 1987 gift, design changes such as a hotel added and then dropped and an atrium removed, leases still unsigned at the 1992 ceremony, and a fundraising shortfall during a California recession: the Music Center had pledged $22.5 million and was $20.5 million short. MousePlanet adds that estimates reached $265 million by 1995, when Los Angeles County threatened to withdraw unless $52.3 million more was raised within two years, and that work on the hall halted. Fundraising led by Eli Broad and Mayor Richard Riordan resumed in 1996, and a $25 million Walt Disney Company gift followed in 1997. To save money, the planned stone skin was replaced with stainless steel. The garage was built on its own schedule from 1992 to 1996.",
      "lessons": [
        "Do not bid construction before the design is finished on a one-off building.",
        "Secure funding before breaking ground; a garage with no hall above it is a sunk cost.",
        "Settle leases and agreements before the ceremony, not after."
      ],
      "fun_fact": "The hall's signature stainless steel skin was a cost-cutting change; the original design called for a stone exterior.",
      "method_tags": [
        "fast_track",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Walt Disney Concert Hall",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Walt_Disney_Concert_Hall",
          "accessed": "2026-10-25"
        },
        {
          "title": "Temple of Doom",
          "publisher": "Newsweek",
          "url": "https://www.newsweek.com/temple-doom-180748",
          "accessed": "2026-10-25"
        },
        {
          "title": "Walt Disney Concert Hall",
          "publisher": "MousePlanet",
          "url": "https://mouseplanet.com/walt-disney-concert-hall/495/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: Newsweek's 'original cost estimate' of $210 million with a 1997 opening; a search-result timeline dates the $210 million estimate (including the garage) to 1991, so 1991 is used as the price year. MousePlanet says $100 million was the original estimate, probably an earlier hall-only figure, hence the planned range. Newsweek gives an $81.5 million garage figure, while Wikipedia gives $110 million for the completed garage. Actual: $274 million total project cost including the $110 million garage (Wikipedia). The Newsweek article is undated online; its content suggests about 1996-97. Figures are nominal USD; no FX needed.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 45,
      "slug": "wembley-stadium",
      "name": "Wembley Stadium (2007 rebuild)",
      "short_name": "Wembley Stadium",
      "category": "buildings",
      "subcategory": "stadium",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom",
        "Australia"
      ],
      "continent": "Europe",
      "city": "London",
      "lat": 51.5556,
      "lng": -0.2794,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2002-09-30",
      "planned_end": "2006-05-13",
      "actual_start": "2002-09-30",
      "actual_end": "2007-03-09",
      "actual_is_forecast": false,
      "planned_duration_months": 43.4,
      "actual_duration_months": 53.3,
      "delay_months": 9.9,
      "delay_pct": 22.7,
      "planned_cost": 757000000,
      "actual_cost": 798000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        789000000,
        798000000
      ],
      "cost_currency": "GBP",
      "planned_cost_year": 2003,
      "cost_year": 2007,
      "planned_fx_to_usd": 1.6347,
      "actual_fx_to_usd": 2.002,
      "planned_cost_usd_nominal": 1237695000,
      "cost_usd_nominal": 1597596000,
      "planned_cost_usd_today": 2166190146,
      "cost_usd_today": 2480619692,
      "overrun_usd_today": 127450385,
      "overrun_pct": 5.4,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Financing and approvals",
          "planned_start": null,
          "planned_end": "2000-12",
          "actual_start": "2000",
          "actual_end": "2002-09",
          "note": "Demolition was first planned before Christmas 2000; financial and legal problems delayed the start by almost two years."
        },
        {
          "name": "Demolition of the old stadium",
          "planned_start": "2002-09-30",
          "planned_end": null,
          "actual_start": "2002-09-30",
          "actual_end": "2003",
          "note": "Twin Towers dismantled in December 2002."
        },
        {
          "name": "Main construction (Multiplex, fixed price)",
          "planned_start": "2003",
          "planned_end": "2006-03",
          "actual_start": "2003",
          "actual_end": "2007-03-09",
          "note": "Disputes with steel subcontractor Cleveland Bridge over the arch and roof steel; NAO expected completion in early 2006."
        },
        {
          "name": "Test events",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2007-03-17",
          "actual_end": "2007-03-24",
          "note": "Charity match on 17 March; England U21 v Italy U21 on 24 March 2007."
        },
        {
          "name": "Official opening",
          "planned_start": "2006-05-13",
          "planned_end": "2006-05-13",
          "actual_start": "2007-05-19",
          "actual_end": "2007-05-19",
          "note": "2006 FA Cup Final moved to Cardiff; stadium opened with the 2007 FA Cup Final."
        }
      ],
      "milestones": [
        {
          "name": "Demolition begins",
          "planned_date": "2000-12",
          "actual_date": "2002-09-30"
        },
        {
          "name": "2006 FA Cup Final moved to Cardiff",
          "planned_date": null,
          "actual_date": "2006-02"
        },
        {
          "name": "Handover to the FA",
          "planned_date": "2006-03",
          "actual_date": "2007-03-09"
        },
        {
          "name": "Opening FA Cup Final",
          "planned_date": "2006-05-13",
          "actual_date": "2007-05-19"
        }
      ],
      "headline": "The new Wembley opened a year late, and contractor Multiplex lost about A$251 million on its GBP 445 million fixed-price deal.",
      "summary": "Wembley National Stadium Limited, a Football Association subsidiary, rebuilt England's national stadium with a 90,000-seat bowl under a 133-meter arch. Demolition began on 30 September 2002, and in June 2003 the National Audit Office reported an expected cost of GBP 757 million with completion in early 2006. Australian contractor Multiplex agreed a fixed construction price of GBP 445 million. Steelwork disputes and delays pushed the 2006 FA Cup Final to Cardiff. The stadium was handed over on 9 March 2007 at a reported cost of GBP 798 million.",
      "what_went_wrong_or_right": "The client's budget was largely protected by a fixed-price contract, so most of the overrun fell on the contractor. Multiplex had agreed to build for GBP 445 million and in April 2008 reported an expected loss of about A$251 million on the job (KHL). The roof and arch were the main technical risk. Multiplex's dispute with steel subcontractor Cleveland Bridge, which held a GBP 60 million subcontract including the arch, went to court; in 2008 the court ruled that Cleveland Bridge owed Multiplex GBP 6.15 million. In December 2005 the builders admitted a material risk of missing the 2006 FA Cup Final, which the FA moved to Cardiff in February 2006, and in March 2006 the opening slipped to 2007. On the client side, the NAO had earlier criticized the procurement for meeting Multiplex before the formal process. Total client cost rose from the NAO's GBP 757 million to GBP 798 million, about 5% in nominal terms.",
      "lessons": [
        "A fixed price shifts cost risk to the contractor but does not protect the client's schedule.",
        "Manage critical specialty subcontracts, such as complex steelwork, as top project risks.",
        "Declare schedule risk early so fixtures and events can be relocated in time."
      ],
      "fun_fact": "The arch spans 315 meters and supports all the weight of the north roof and 60% of the retractable south roof.",
      "method_tags": [
        "fixed_price",
        "design_build"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "The English National Stadium Project at Wembley (HC 699)",
          "publisher": "National Audit Office, 6 June 2003",
          "url": "https://www.nao.org.uk/reports/the-english-national-stadium-project-at-wembley/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Wembley Stadium",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Wembley_Stadium",
          "accessed": "2026-10-25"
        },
        {
          "title": "Wembley loss",
          "publisher": "KHL International Construction, 25 April 2008",
          "url": "https://www.khl.com/news/wembley-loss/1019159.article",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: NAO report of 6 June 2003, which said the project was expected to cost GBP 757 million and was scheduled for completion in early 2006; this is the first audited whole-project figure found (earlier press figures of GBP 715-771 million exist). Planned opening is taken as the 2006 FA Cup Final (13 May 2006), the event the stadium was meant to host; NAO's 'early 2006' is used for planned handover (2006-03, approximate). Actual: Wikipedia text gives GBP 798 million, infobox GBP 789 million. Wikipedia also cites about GBP 1 billion including transport infrastructure and financing; not used. Contractor-side figures: fixed price GBP 445 million, expected Multiplex loss A$251 million (US$186 million) (KHL, 2008). Phase dates for financing (2000) and main construction start (2003) are year-level from Wikipedia. FX: Federal Reserve G.5A annual averages, 2003 USD 1.6347/GBP, 2007 USD 2.0020/GBP. Nominal figures.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 46,
      "slug": "apollo-program",
      "name": "Apollo program",
      "short_name": "Apollo",
      "category": "space_science",
      "subcategory": "crewed lunar program",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Cape Canaveral (Kennedy Space Center)",
      "lat": 28.6083,
      "lng": -80.6041,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1961-05-25",
      "planned_end": "1969-12-31",
      "actual_start": "1961-05-25",
      "actual_end": "1969-07-24",
      "actual_is_forecast": false,
      "planned_duration_months": 103.2,
      "actual_duration_months": 98,
      "delay_months": -5.2,
      "delay_pct": -5.1,
      "planned_cost": 20000000000,
      "actual_cost": 25400000000,
      "planned_cost_range": [
        7000000000,
        20000000000
      ],
      "actual_cost_range": [
        25400000000,
        25800000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1961,
      "cost_year": 1973,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 20000000000,
      "cost_usd_nominal": 25400000000,
      "planned_cost_usd_today": 215478841871,
      "cost_usd_today": 184216641679,
      "overrun_usd_today": 39164167916,
      "overrun_pct": 27,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Concept and goal-setting",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1960",
          "actual_end": "1961-05-25",
          "note": "Abe Silverstein named the program in early 1960; President Kennedy set the end-of-decade lunar landing goal on May 25, 1961."
        },
        {
          "name": "Launch vehicle and spacecraft development",
          "planned_start": "1961-05",
          "planned_end": null,
          "actual_start": "1961-10-27",
          "actual_end": "1967-01-27",
          "note": "First Saturn I flight on October 27, 1961. In 1962 the Bureau of the Budget projected Apollo costs of $16.4 billion through 1967."
        },
        {
          "name": "Apollo 1 fire and spacecraft redesign",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1967-01-27",
          "actual_end": "1968-10-11",
          "note": "A cabin fire during a pad test killed three astronauts on January 27, 1967. The first uncrewed Saturn V flew on November 9, 1967."
        },
        {
          "name": "Crewed flights to the first landing",
          "planned_start": null,
          "planned_end": "1969-12-31",
          "actual_start": "1968-10-11",
          "actual_end": "1969-07-24",
          "note": "Apollo 7 (first crewed flight) on October 11, 1968; Apollo 8 circled the Moon December 21-27, 1968; Apollo 11 landed July 20, 1969 and splashed down July 24."
        }
      ],
      "milestones": [
        {
          "name": "Kennedy sets the lunar landing goal",
          "planned_date": null,
          "actual_date": "1961-05-25"
        },
        {
          "name": "First Saturn V flight (Apollo 4)",
          "planned_date": null,
          "actual_date": "1967-11-09"
        },
        {
          "name": "Apollo 8 launches to lunar orbit",
          "planned_date": null,
          "actual_date": "1968-12-21"
        },
        {
          "name": "Apollo 11 lands on the Moon",
          "planned_date": "1969-12-31",
          "actual_date": "1969-07-20"
        },
        {
          "name": "Apollo 17, the last mission, launches",
          "planned_date": null,
          "actual_date": "1972-12-07"
        }
      ],
      "headline": "NASA met Kennedy's end-of-decade deadline with five months to spare, for $25.4 billion against an early estimate of $20 billion.",
      "summary": "Apollo was NASA's civil program to land astronauts on the Moon and return them safely, a goal President Kennedy set on May 25, 1961. After the Saturn I and Saturn V rockets were developed and the 1967 Apollo 1 fire forced a spacecraft redesign, Apollo 11 landed on July 20, 1969. Six landings followed through Apollo 17 in December 1972. NASA reported a total cost of $25.4 billion in 1973, about 27 percent above the $20 billion figure James Webb gave in 1961.",
      "what_went_wrong_or_right": "The program had a single fixed goal and a hard deadline, which kept scope stable for most of the decade. Cost estimating began low: preliminary NASA analysis put a lunar landing at $7 billion to $12 billion, and Administrator James Webb raised the figure to $20 billion before reporting it to Vice President Johnson in April 1961. Funding pressure appeared early. In 1962 Apollo chief Brainerd Holmes sought more than $400 million in supplemental funds to prevent schedule slippage, which Webb initially refused, and the Bureau of the Budget projected $16.4 billion in costs through 1967 alone. The worst setback was technical and human: the January 27, 1967 cabin fire killed three astronauts and halted crewed flights for 20 months while the command module was redesigned. At its peak the effort employed about 400,000 people across more than 20,000 firms and universities. NASA's 1973 report to Congress put the total at $25.4 billion; a 2019 reconstruction by Casey Dreier of the Planetary Society found $25.8 billion, within 1.6 percent.",
      "lessons": [
        "A single, measurable goal with a fixed date makes trade-offs easier to decide and scope creep easier to refuse.",
        "Pad an early estimate deliberately; Webb's $20 billion figure was roughly double his staff's low-end number.",
        "Treat a fatal test accident as a schedule event too: Apollo lost 20 months of crewed flying to the redesign."
      ],
      "fun_fact": "The Apollo missions brought back 382 kilograms (842 pounds) of lunar rock and soil.",
      "method_tags": [
        "pert",
        "phased_delivery",
        "critical_path"
      ],
      "related_history_ids": [
        "apollo-1961",
        "pert-1958",
        "wbs-1962"
      ],
      "sources": [
        {
          "title": "Apollo program",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Apollo_program",
          "accessed": "2026-10-25"
        },
        {
          "title": "How much did the Apollo program cost?",
          "publisher": "The Planetary Society",
          "url": "https://www.planetary.org/space-policy/cost-of-apollo",
          "accessed": "2026-10-25"
        },
        {
          "title": "Reconstructing the Cost of the One Giant Leap",
          "publisher": "The Planetary Society",
          "url": "https://www.planetary.org/articles/reconstructing-the-price-of-apollo",
          "accessed": "2026-10-25"
        },
        {
          "title": "The Kennedy-Webb Conversation: Background",
          "publisher": "NASA History Office",
          "url": "https://www.nasa.gov/history/JFK-Webbconv/pages/backgnd.html",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the $20 billion estimate NASA Administrator James Webb reported to Vice President Johnson in April 1961 (Wikipedia, citing Butts); preliminary NASA analysis had put the cost at $7-12 billion, stored as planned_cost_range. Actual: NASA's 1973 written testimony to Congress, $25.4 billion for 1960-1973 in then-year dollars; Planetary Society reconstruction gives $25.8 billion (range). Including Gemini and robotic lunar programs the total is about $28 billion. Inflation-adjusted figures of $257-309 billion exist but use different price bases. Overrun is nominal and understates real growth because spending spread over 1960-1973. Schedule: planned_end is Kennedy's 'before this decade is out' deadline; actual_end is Apollo 11 splashdown. The cost figure also covers Apollo 12-17 through December 1972 and close-out to 1973. Lat/lng is Launch Complex 39A. USD, so fx = 1.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 47,
      "slug": "cassini-huygens",
      "name": "Cassini–Huygens mission to Saturn",
      "short_name": "Cassini–Huygens",
      "category": "space_science",
      "subcategory": "planetary orbiter and probe",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States",
        "Italy",
        "France",
        "Germany",
        "United Kingdom"
      ],
      "continent": "North America",
      "city": "Pasadena (Jet Propulsion Laboratory)",
      "lat": 34.2013,
      "lng": -118.1714,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": "1990",
      "planned_end": null,
      "actual_start": "1990",
      "actual_end": "2017-09-15",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 326.5,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": null,
      "actual_cost": 3260000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        3260000000,
        3670000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": null,
      "cost_year": 2000,
      "planned_fx_to_usd": null,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": 3260000000,
      "planned_cost_usd_today": null,
      "cost_usd_today": 6094782609,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Joint CRAF/Cassini program",
          "planned_start": "1990",
          "planned_end": null,
          "actual_start": "1990",
          "actual_end": "1992",
          "note": "Congress approved both spacecraft on a shared design, on condition that one be dropped if costs passed $1.6 billion. Congressional cuts in FY1992 and FY1993 caused a two-year schedule extension and higher estimates; CRAF was cancelled."
        },
        {
          "name": "Restructured Cassini development",
          "planned_start": null,
          "planned_end": "1997-10",
          "actual_start": "1992",
          "actual_end": "1997-10-15",
          "note": "JPL restructured the project to cut costs; GAO reported it was then meeting its new cost and schedule goals. Launched on a Titan IVB/Centaur on October 15, 1997, a couple of days late because of high winds."
        },
        {
          "name": "Cruise to Saturn",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1997-10-15",
          "actual_end": "2004-07-01",
          "note": "After launch, engineers found the Huygens receiver could not handle the expected Doppler shift and changed Cassini's trajectory to fix it."
        },
        {
          "name": "Prime mission and Huygens landing",
          "planned_start": "2004-06",
          "planned_end": "2008-05",
          "actual_start": "2004-07-01",
          "actual_end": "2008-04-16",
          "note": "Saturn orbit insertion on July 1, 2004; Huygens separated on December 25, 2004 and landed on Titan on January 14, 2005."
        },
        {
          "name": "Equinox and Solstice extended missions",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2008-04-16",
          "actual_end": "2017-09-15",
          "note": "A two-year Equinox extension was announced April 16, 2008 and the Solstice extension on February 3, 2010; the spacecraft was deliberately plunged into Saturn on September 15, 2017."
        }
      ],
      "milestones": [
        {
          "name": "Launch",
          "planned_date": "1997-10",
          "actual_date": "1997-10-15"
        },
        {
          "name": "Saturn orbit insertion",
          "planned_date": null,
          "actual_date": "2004-07-01"
        },
        {
          "name": "Huygens lands on Titan",
          "planned_date": null,
          "actual_date": "2005-01-14"
        },
        {
          "name": "Grand Finale plunge into Saturn",
          "planned_date": null,
          "actual_date": "2017-09-15"
        }
      ],
      "headline": "Cassini–Huygens cost about $3.26 billion and survived the cancellation of its twin mission CRAF, then flew to Saturn and operated for 13 years.",
      "summary": "Cassini–Huygens was a joint mission of NASA, the European Space Agency and the Italian Space Agency to study Saturn, its rings and its moon Titan. Congress approved it in 1990 alongside the CRAF comet mission; budget cuts led NASA to cancel CRAF and restructure Cassini. The spacecraft launched on October 15, 1997, entered Saturn orbit on July 1, 2004 and delivered ESA's Huygens probe to Titan's surface on January 14, 2005. After two extensions it ended in Saturn's atmosphere on September 15, 2017.",
      "what_went_wrong_or_right": "Cassini began as half of a two-spacecraft program. Congress approved CRAF and Cassini together on the promise that a shared spacecraft design would save money, with the condition that one would be dropped if costs passed $1.6 billion. The comet penetrator instrument on CRAF grew from an estimated $22 million to as much as $120 million, Congress cut the program's budgets in FY1992 and FY1993, and the schedule stretched by two years. NASA cancelled CRAF; GAO later found little documented analysis behind that decision. Cassini itself was restructured to reduce costs, partly by moving about $94 million of development work into the operations account, which GAO flagged as a concern. After restructuring, the project met its new cost and schedule goals and launched in its October 1997 window. One design error surfaced in flight: the Huygens radio receiver's bandwidth was too narrow for the expected Doppler shift, and engineers solved it by redesigning Cassini's orbits. The mission returned data until 2017. Including launch, the total cost was about $3.26 billion, of which NASA paid about $2.6 billion, ESA $500 million and the Italian agency $160 million.",
      "lessons": [
        "Shared-design savings disappear when one project's cost growth can sink both.",
        "Moving work between budget accounts hides cost growth rather than removing it.",
        "Test end-to-end communication links under realistic flight conditions before launch."
      ],
      "fun_fact": "Cassini carried a DVD with more than 616,400 signatures from people in 81 countries.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Cassini–Huygens",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Cassini%E2%80%93Huygens",
          "accessed": "2026-10-25"
        },
        {
          "title": "Farewell, Cassini, and 'Thanks for the Ringside Seat'",
          "publisher": "SpacePolicyOnline",
          "url": "https://spacepolicyonline.com/news/farewell-cassni-and-thanks-for-the-ringside-seat/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Lessons learned: GAO report on CRAF/Cassini missions",
          "publisher": "American Institute of Physics, FYI",
          "url": "https://www.aip.org/fyi/1994/lessons-learned-gao-report-crafcassini-missions",
          "accessed": "2026-10-25"
        },
        {
          "title": "NASA: CRAF/Cassini program (NSIAD-94-24)",
          "publisher": "U.S. Government Accountability Office (via GovInfo)",
          "url": "https://www.govinfo.gov/content/pkg/GAOREPORTS-NSIAD-94-24/html/GAOREPORTS-NSIAD-94-24.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Anniversary of the launch of Cassini-Huygens",
          "publisher": "European Space Agency",
          "url": "https://www.esa.int/About_Us/ESA_history/Anniversary_of_the_launch_of_Cassini-Huygens",
          "accessed": "2026-10-25"
        },
        {
          "title": "Cassini",
          "publisher": "NASA",
          "url": "https://science.nasa.gov/mission/cassini/",
          "accessed": "2026-10-25"
        },
        {
          "title": "CRS analysis of federal big science projects: NASA",
          "publisher": "American Institute of Physics, FYI",
          "url": "https://www.aip.org/fyi/1994/crs-analysis-federal-big-science-projects-nasa",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: not established. The only approval-era figure found in opened sources is the $1.6 billion cost condition for the joint CRAF/Cassini program (SpacePolicyOnline), which covers two spacecraft and so is not comparable with Cassini's own cost; planned_cost is therefore null. GAO NSIAD-94-24 contains Cassini development estimates but the PDF is image-only and could not be read. Planned end is null: GAO says FY1992-93 cuts extended the schedule by two years, so the original 1990 launch date was earlier than October 1997, but the exact date was not confirmed. The October 1997 launch window (ESA) is used as the planned date of the launch milestone. Actual: about $3.26 billion from an October 2000 press kit (via Wikipedia): $1.4 billion pre-launch development, $704 million operations, $54 million tracking, $422 million launch vehicle; US $2.6 billion, ESA $500 million, ASI $160 million. It excludes inflation and the extended missions. SpacePolicyOnline gives $3.67 billion including launch (range). Countries beyond the US reflect ESA and ASI participation. USD, so fx = 1. UPDATE 2026-10-25: Baseline still not found. Searched: GAO NSIAD-94-24 and NSIAD-93-97 (NASA Program Costs, Dec 1992, which tabulates initial vs current estimates for 29 programs incl. CRAF/Cassini) on gao.gov and Justia; both PDFs are scanned images and could not be read. NTRS 19930010071 (CRAF paper) gives only the ~$500m joint-program saving. The 1994 CRS analysis (via AIP FYI) gives the initial estimate only as the $1.6 billion congressional cap for CRAF and Cassini combined, and a then-current (1994, post-restructuring) development estimate of $1.5 billion for Cassini alone; the like-for-like actual for that would be the $1.4 billion pre-launch development figure from the 2000 press kit, but $1.5 billion is a restructured estimate, not the go-ahead baseline, so planned_cost stays null. A search-result excerpt (not opened) says Cassini was originally scheduled to launch in April 1996; not used. planned_end stays null because actual_end (2017) includes two extended missions; the prime-mission phase now carries the planned four-year tour, June 2004 to May 2008 (Wikipedia overview). Editor decision 2026-10-25: kept in the dataset (flag was: Planned (baseline) cost and planned end date for Cassini alone are not available in the opened public sources, so no overrun can be computed.).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 48,
      "slug": "hubble-space-telescope",
      "name": "Hubble Space Telescope",
      "short_name": "Hubble",
      "category": "space_science",
      "subcategory": "space telescope",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Greenbelt, Maryland (Goddard Space Flight Center)",
      "lat": 38.9917,
      "lng": -76.852,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1977",
      "planned_end": "1983",
      "actual_start": "1977",
      "actual_end": "1993-12-13",
      "actual_is_forecast": false,
      "planned_duration_months": 72,
      "actual_duration_months": 197.4,
      "delay_months": 125.4,
      "delay_pct": 174.2,
      "planned_cost": 600000000,
      "actual_cost": 1500000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1977,
      "cost_year": 1990,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 600000000,
      "cost_usd_nominal": 1500000000,
      "planned_cost_usd_today": 3187808896,
      "cost_usd_today": 3696510443,
      "overrun_usd_today": 2217906266,
      "overrun_pct": 150,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Approval and design",
          "planned_start": "1977",
          "planned_end": "1979",
          "actual_start": "1977",
          "actual_end": "1979",
          "note": "Congress appropriated design and development funds in 1977; Lockheed was prime contractor and Perkin-Elmer built the optics, under Marshall Space Flight Center."
        },
        {
          "name": "Primary mirror grinding and polishing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1979",
          "actual_end": "1981-05",
          "note": "The mirror was completed by the end of 1981. The flawed null corrector that caused the later aberration traces back to this period."
        },
        {
          "name": "Assembly, testing and launch slips",
          "planned_start": "1981",
          "planned_end": "1983",
          "actual_start": "1981",
          "actual_end": "1986-01-28",
          "note": "By 1980 a launch before 1986 was ruled out; the date moved to April 1985, March 1986, then October 1986. Cost had roughly doubled to $1.2 billion by 1985."
        },
        {
          "name": "Storage after the Challenger accident",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1986-01-28",
          "actual_end": "1990-04-24",
          "note": "The Shuttle fleet was grounded; the telescope was kept in a clean room at roughly $6 million a month."
        },
        {
          "name": "Mirror flaw discovery and investigation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1990-04-24",
          "actual_end": "1990-11",
          "note": "Launched on STS-31; failed a focusing test on June 24, 1990. The Allen board, formed July 2, 1990, reported in November 1990."
        },
        {
          "name": "Corrective optics and first servicing mission",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1991-10",
          "actual_end": "1993-12-13",
          "note": "Ball Aerospace contracted to build COSTAR in October 1991; STS-61 launched December 2, 1993 and installed COSTAR and WFPC2 over five spacewalks."
        }
      ],
      "milestones": [
        {
          "name": "Launch on STS-31",
          "planned_date": "1983",
          "actual_date": "1990-04-24"
        },
        {
          "name": "Telescope fails focusing test",
          "planned_date": null,
          "actual_date": "1990-06-24"
        },
        {
          "name": "Allen failure report published",
          "planned_date": null,
          "actual_date": "1990-11"
        },
        {
          "name": "First servicing mission (STS-61) launches",
          "planned_date": null,
          "actual_date": "1993-12-02"
        }
      ],
      "headline": "Hubble reached orbit seven years late at about $1.5 billion, more than double its original $600 million estimate, then needed a 1993 repair mission to see clearly.",
      "summary": "The Hubble Space Telescope was approved in 1977 for a 1983 Shuttle launch, with the European Space Agency contributing hardware in return for at least 15 percent of observing time. Funding cuts, technical problems and the 1986 Challenger accident pushed the launch to April 24, 1990, by which time the telescope had cost about $1.5 billion. Weeks later its primary mirror was found to be ground to the wrong shape. Astronauts on STS-61 installed corrective optics in December 1993, and Hubble then reached its intended performance.",
      "what_went_wrong_or_right": "Hubble's early years show how budget pressure, a concurrent schedule and weak oversight compound. From 1977 to the planned 1983 launch the project faced repeated funding and schedule crises; by 1980 a launch before 1986 was ruled out, and by 1985 construction cost had roughly doubled from the original $600 million to about $1.2 billion. GAO warned in 1977 and 1980 that NASA's estimates left out major cost items. The Challenger accident in January 1986 then grounded the Shuttle, leaving the finished telescope in a clean room for four years at about $6 million a month. The biggest failure was in the optics: Perkin-Elmer, the low bidder at $64.2 million against Kodak-Itek's $99.8 million, polished the primary mirror too flat at the edge by about 2.2 micrometers because a lens in its reflective null corrector was 1.3 mm out of position. The November 1990 Allen report also blamed poor communication and oversight by NASA and the contractor. What went right was the design for servicing: the telescope could be repaired in orbit, and the 1993 STS-61 crew restored its vision in five spacewalks.",
      "lessons": [
        "Verify critical measurements with an independent method; a single test instrument hid Hubble's mirror error for nine years.",
        "Choosing the lowest bidder needs stronger oversight, not weaker.",
        "Design for maintenance: in-orbit servicing turned a flawed telescope into a successful one."
      ],
      "fun_fact": "Kodak's backup primary mirror for Hubble is on permanent display at the Smithsonian's National Air and Space Museum.",
      "method_tags": [
        "phased_delivery",
        "iterative"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "pmbok-1987"
      ],
      "sources": [
        {
          "title": "Experience with the Hubble Space Telescope: 20 years of an archetype (Lallo, 2012)",
          "publisher": "arXiv / Optical Engineering",
          "url": "https://arxiv.org/pdf/1203.0002",
          "accessed": "2026-10-25"
        },
        {
          "title": "Techno-turkey: Remembering Hubble's vision troubles, 30 years on",
          "publisher": "Astronomy Magazine",
          "url": "https://www.astronomy.com/space-exploration/techno-turkey-remembering-hubbles-vision-troubles-30-years-on/",
          "accessed": "2026-10-25"
        },
        {
          "title": "NASA Should Provide the Congress Complete Cost Information on the Space Telescope Program (PSAD-80-15)",
          "publisher": "U.S. Government Accountability Office",
          "url": "https://www.gao.gov/products/psad-80-15",
          "accessed": "2026-10-25"
        },
        {
          "title": "Status and Issues Pertaining to the Proposed Development of the Space Telescope Project (PSAD-77-98)",
          "publisher": "U.S. Government Accountability Office (via Justia)",
          "url": "http://gao.justia.com/national-aeronautics-and-space-administration/1977/5/status-and-issues-pertaining-to-the-proposed-development-of-the-space-telescope-project-psad-77-98/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Servicing Mission 1",
          "publisher": "NASA",
          "url": "https://science.nasa.gov/mission/hubble/observatory/missions-to-hubble/servicing-mission-1/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Hubble Space Telescope",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Hubble_Space_Telescope",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the original construction estimate of $600 million cited by Lallo (2012); GAO's 1977 review (PSAD-77-98) said NASA's estimates excluded about $227 million of development and $709 million of operations costs. Planned launch 1983 per GAO PSAD-80-15. Actual: about $1.5 billion at launch in 1990 (Astronomy Magazine); this excludes the 1993 servicing mission. Wikipedia gives about $4.7 billion (2010 dollars) at launch and about $11.3 billion (2015 dollars) cumulative including servicing; these are different scopes and price bases. ESA's hardware contribution (in return for at least 15 percent of observing time) is not included in US figures. actual_end is the end of STS-61 (about 10 days 19 hours after the December 2, 1993 launch), when design performance was restored; launch was 1990-04-24. Lat/lng is Goddard Space Flight Center (operations); development was led by Marshall Space Flight Center in Huntsville. USD, so fx = 1. Baseline audit 2026-10-25: Planned figures unchanged ($600m, 1983 launch). No earlier approved figure or formal rebaseline was found in an opened source (the Lallo PDF could not be text-extracted in this audit). Editor 2026-10-25: ESA share described as observing time, not cost, per the spoke research.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 49,
      "slug": "human-genome-project",
      "name": "Human Genome Project",
      "short_name": "Human Genome Project",
      "category": "space_science",
      "subcategory": "genomics research program",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States",
        "United Kingdom",
        "France",
        "Germany",
        "Japan",
        "China"
      ],
      "continent": "North America",
      "city": "Bethesda, Maryland (National Institutes of Health)",
      "lat": 39.0003,
      "lng": -77.1022,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "on_time_on_budget",
      "planned_start": "1990",
      "planned_end": "2005",
      "actual_start": "1990",
      "actual_end": "2003-04-14",
      "actual_is_forecast": false,
      "planned_duration_months": 180,
      "actual_duration_months": 153.4,
      "delay_months": -26.6,
      "delay_pct": -14.8,
      "planned_cost": 3000000000,
      "actual_cost": 2700000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1991,
      "cost_year": 1991,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 3000000000,
      "cost_usd_nominal": 2700000000,
      "planned_cost_usd_today": 7091375519,
      "cost_usd_today": 6382237967,
      "overrun_usd_today": -709137552,
      "overrun_pct": -10,
      "overrun_basis": "real",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Planning and first funding",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1988",
          "actual_end": "1990",
          "note": "A National Academy of Sciences committee outlined the goals in 1988; NIH created its Office for Human Genome Research and the first HGP line item appeared in the 1988 budget submission."
        },
        {
          "name": "Mapping and technology development",
          "planned_start": "1990",
          "planned_end": null,
          "actual_start": "1990",
          "actual_end": "1998",
          "note": "DOE and NIH signed a memorandum of understanding and launched the project in 1990, with a 2005 target. The 1996 Bermuda meetings set rules for rapid public release of sequence data."
        },
        {
          "name": "Large-scale sequencing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1998",
          "actual_end": "2000-06-26",
          "note": "Production sequencing scaled up as Celera Genomics launched a privately funded rival effort in 1998. A draft covering about 90 percent of the genome was announced on June 26, 2000."
        },
        {
          "name": "Draft analysis and publication",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2000-06-26",
          "actual_end": "2001-02",
          "note": "The public consortium and Celera each published draft papers in February 2001."
        },
        {
          "name": "Finishing the reference sequence",
          "planned_start": null,
          "planned_end": "2005",
          "actual_start": "2001-02",
          "actual_end": "2003-04-14",
          "note": "The consortium announced an essentially complete sequence on April 14, 2003, more than two years ahead of the 2005 target."
        }
      ],
      "milestones": [
        {
          "name": "Project launched by DOE and NIH",
          "planned_date": "1990",
          "actual_date": "1990"
        },
        {
          "name": "Bermuda data-sharing principles agreed",
          "planned_date": null,
          "actual_date": "1996"
        },
        {
          "name": "Working draft announced",
          "planned_date": null,
          "actual_date": "2000-06-26"
        },
        {
          "name": "Draft sequence published",
          "planned_date": null,
          "actual_date": "2001-02"
        },
        {
          "name": "Essentially complete sequence announced",
          "planned_date": "2005",
          "actual_date": "2003-04-14"
        }
      ],
      "headline": "The Human Genome Project finished in April 2003, more than two years early, at about $2.7 billion against a $3 billion estimate.",
      "summary": "The Human Genome Project, led in the United States by the National Institutes of Health and the Department of Energy, set out to sequence the 3 billion base pairs of human DNA. Congress funded it in 1990 with a 2005 target and a projected cost of about $3 billion. With partners in the UK, France, Germany, Japan and China, the consortium announced a draft in June 2000 and an essentially complete sequence on April 14, 2003. NHGRI says the project cost NIH about $2.7 billion in FY1991 dollars.",
      "what_went_wrong_or_right": "The project is a rare large program that finished early and below its estimate. It was planned in successive five-year phases, with mapping and technology development first, so the costly sequencing work was scaled up only after methods and automated sequencers had matured. Sequencing technology improved quickly during the 1990s, which lowered the unit cost of the main deliverable. Competition also mattered: Celera Genomics launched a privately funded effort in 1998, and the public consortium accelerated production, announcing a working draft with Celera in June 2000. Governance choices helped keep the effort coherent. The 1996 Bermuda Principles required rapid public release of sequence data, and from 1990 a fixed share of the budget funded research on ethical, legal and social issues. Some caveats apply: NHGRI notes that precise cost accounting is difficult, the $3 billion figure covered a broad range of genomics work beyond sequencing, and the 2003 sequence still had gaps that were not fully closed until the Telomere-to-Telomere consortium's work in 2022.",
      "lessons": [
        "Sequence a program so expensive production starts after the enabling technology has matured.",
        "Define what 'done' means up front; 'essentially complete' let the team declare success while gaps remained.",
        "Open data rules can speed a multi-partner program by removing duplicate work."
      ],
      "fun_fact": "Most of the DNA sequenced came from volunteers in Buffalo, New York, recruited through newspaper advertisements.",
      "method_tags": [
        "phased_delivery",
        "iterative"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004"
      ],
      "sources": [
        {
          "title": "Human Genome Project FAQ",
          "publisher": "National Human Genome Research Institute",
          "url": "https://www.genome.gov/Pages/Education/Smithsonian_Exhibition/Human_Genome_Project_FAQ.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Human Genome Project Fact Sheet",
          "publisher": "National Human Genome Research Institute",
          "url": "https://www.genome.gov/about-genomics/educational-resources/fact-sheets/human-genome-project",
          "accessed": "2026-10-25"
        },
        {
          "title": "Human Genome Project Budget",
          "publisher": "U.S. Department of Energy / Oak Ridge National Laboratory",
          "url": "https://doe-humangenomeproject.ornl.gov/human-genome-project-budget/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Human Genome Project",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Human_Genome_Project",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the roughly $3 billion total that Congress's 1990 plan was expected to cost over 15 years, with a 2005 target date (NHGRI FAQ). Its price base is not stated; NHGRI compares it directly with the actual figure, so FY1991 is assumed and overrun_basis set to 'real'. Actual: 'about $2.7 billion in FY 1991 dollars' cost to NIH (NHGRI FAQ). This excludes DOE spending: the DOE/ORNL budget table shows combined DOE and NIH appropriations of about $3.7 billion in then-year dollars for FY1990-2003, and notes the $3 billion figure covered broad genomics activities, not only sequencing. Partner-country spending (for example the UK's Wellcome Trust) is not included. Start month is commonly given as October 1990 but the opened sources give only the year. USD, so fx = 1.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 50,
      "slug": "international-space-station",
      "name": "International Space Station",
      "short_name": "Space Station (ISS)",
      "category": "space_science",
      "subcategory": "space station",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States",
        "Canada",
        "Japan",
        "Germany",
        "France",
        "Italy"
      ],
      "continent": "North America",
      "city": "Houston (Johnson Space Center)",
      "lat": 29.5593,
      "lng": -95.09,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1984",
      "planned_end": "1994",
      "actual_start": "1984",
      "actual_end": "2011-05",
      "actual_is_forecast": false,
      "planned_duration_months": 120,
      "actual_duration_months": 322.5,
      "delay_months": 202.5,
      "delay_pct": 168.7,
      "planned_cost": 8000000000,
      "actual_cost": 31000000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1984,
      "cost_year": 2008,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 8000000000,
      "cost_usd_nominal": 31000000000,
      "planned_cost_usd_today": 24791800128,
      "cost_usd_today": 46356259660,
      "overrun_usd_today": 34393353941,
      "overrun_pct": 287.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": 17400000000,
      "rebaseline_cost_year": 1993,
      "rebaseline_end": "2002-06",
      "rebaseline_label": "1993 redesign estimate",
      "rebaseline_overrun_pct": 78.2,
      "rebaseline_delay_months": 107,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Space Station Freedom design",
          "planned_start": "1984",
          "planned_end": "1994",
          "actual_start": "1984",
          "actual_end": "1993",
          "note": "Approved in 1984 at $8 billion (FY1984 dollars) for R&D through assembly, excluding launches, with completion targeted for 1994. By 1993 NASA's Freedom estimate was $30 billion to build."
        },
        {
          "name": "Redesign as the International Space Station",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1993",
          "actual_end": "1998-12-04",
          "note": "The 1993 redesign was estimated at $17.4 billion for construction, capped at $2.1 billion a year; the estimate rose to $21.3 billion by March 1998."
        },
        {
          "name": "Initial assembly",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1998-12-04",
          "actual_end": "2001-02-07",
          "note": "STS-88 delivered the US-built Unity node on December 4, 1998, two weeks after the first element; the US Destiny laboratory followed on February 7, 2001."
        },
        {
          "name": "Core assembly",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2001-02-07",
          "actual_end": "2003-02-01",
          "note": "In 2001 NASA identified about $4.8 billion in unfunded cost growth, putting the total more than 72 percent above the 1993 estimate."
        },
        {
          "name": "Stand-down after the Columbia accident",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2003-02-01",
          "actual_end": "2005-07-26",
          "note": "Shuttle-based assembly stopped for about two and a half years; flights resumed with STS-114."
        },
        {
          "name": "Completion of the US segment",
          "planned_start": null,
          "planned_end": "2002-06",
          "actual_start": "2005-07-26",
          "actual_end": "2011-05",
          "note": "The 1993 plan had targeted assembly complete in June 2002. The US Orbital Segment was completed in 2011 after STS-134 installed the Alpha Magnetic Spectrometer."
        }
      ],
      "milestones": [
        {
          "name": "Program approved (Space Station Freedom)",
          "planned_date": null,
          "actual_date": "1984"
        },
        {
          "name": "Unity node delivered by STS-88",
          "planned_date": null,
          "actual_date": "1998-12-04"
        },
        {
          "name": "Destiny laboratory launched",
          "planned_date": null,
          "actual_date": "2001-02-07"
        },
        {
          "name": "Assembly complete",
          "planned_date": "1994",
          "actual_date": "2011-05"
        }
      ],
      "headline": "Approved in 1984 as an $8 billion station to be finished by 1994, the US-led space station was completed in 2011 at a construction cost NASA put at $31 billion.",
      "summary": "NASA began the space station program in 1984 as Space Station Freedom, estimating $8 billion in FY1984 dollars for research and development through assembly and a 1994 completion. After years of cost growth the design was reworked in 1993 into the International Space Station with partner agencies. Assembly in orbit began in 1998, paused after the 2003 Columbia accident, and the US segment was completed in 2011. GAO reported in 2008 that NASA expected construction to cost $31 billion, excluding Shuttle launches.",
      "what_went_wrong_or_right": "The station's cost history is a series of baselines that did not hold. The 1984 estimate of $8 billion excluded launch costs and assumed completion within a decade. By 1993 NASA's estimate for Freedom was $30 billion to build and $90 billion including 30 years of operations, and the program was redesigned. The 1993 redesign promised construction for $17.4 billion and no more than $2.1 billion a year; NASA exceeded the annual cap in FY1998, an independent task force put the cost at $24.7 billion in April 1998, and in 2001 NASA found about $4.8 billion of further growth, more than 72 percent above the 1993 figure. GAO counted about $35 billion appropriated by 2006, and estimates of the total US cost to develop, assemble and operate the station reached about $100 billion. The schedule depended on the Shuttle: the planned June 2002 completion moved to 2006 and then beyond, and the Columbia accident in February 2003 stopped assembly for two and a half years. The modular design allowed the station to operate and host crews while still being built.",
      "lessons": [
        "State clearly what a baseline excludes; leaving out launch costs made the 1984 figure look far smaller than the program.",
        "Annual funding caps without scope control shift costs into later years instead of removing them.",
        "Modular delivery lets a project return value before it is finished."
      ],
      "fun_fact": "Building the complete station took more than 40 assembly flights, 36 of them by the Space Shuttle, for a mass of about 410,000 kilograms.",
      "method_tags": [
        "modular",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "wbs-1962"
      ],
      "sources": [
        {
          "title": "Space Stations (Issue Brief IB93017, December 2003)",
          "publisher": "Congressional Research Service (via EveryCRSReport)",
          "url": "https://www.everycrsreport.com/files/20031208_IB93017_55cdf4843a5796cadf361bc8dacbfd1f41f0d918.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "NASA: Challenges in Completing and Sustaining the International Space Station (GAO-08-581T)",
          "publisher": "U.S. Government Accountability Office",
          "url": "https://www.gao.gov/assets/a119821.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "NASA program history (President's Committee review)",
          "publisher": "The White House (Clinton administration archive)",
          "url": "https://clintonwhitehouse5.archives.gov/pcscb/rmo_nasa.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Assembly of the International Space Station",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Assembly_of_the_International_Space_Station",
          "accessed": "2026-10-25"
        },
        {
          "title": "What's the cost of the space station?",
          "publisher": "NBC News / Associated Press",
          "url": "https://www.nbcnews.com/id/wbna14505278",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: NASA's 1984 estimate of $8 billion (FY1984 dollars) for R&D through assembly complete, excluding launches (CRS IB93017), with completion by 1994 (Clinton White House archive). Actual: NASA's estimate of $31 billion for the entire cost to complete the station, reported by GAO in 2008 (GAO-08-581T); it is in then-year dollars, excludes Shuttle flights, and it is unclear whether it includes all pre-1993 Freedom spending. Scope matters: GAO estimated about $100 billion (2006) and $95.6 billion (1998) to develop, assemble and operate the station; NASA's FY1985-2012 life-cycle estimate was $72.3 billion; Wikipedia cites about $150 billion for all partners. Because the 1984 and 2008 figures differ in price base and possibly scope, confidence is 'disputed'. actual_end: US Orbital Segment completed in 2011 after STS-134 (May 2011). Partner countries listed are those of the main non-US partner agencies (CSA, JAXA, ESA members); see exclude_flag. USD, so fx = 1. Baseline audit 2026-10-25: Planned figures unchanged (1984 $8 billion and 1994 completion are the first). Added the 1993 redesign as the rebaseline: NASA said the new station would cost $17.4 billion to build, excluding money already spent, covering FY1994 to assembly complete then scheduled for June 2002 (CRS IB93017). CRS also reports the 2001 cost growth of $4.02 billion and the later $25 billion development cap. Editor decision 2026-10-25: kept in the dataset (flag was: A Russian state space agency is a major ISS partner and built the first launched element; this record keeps partner mentions minimal and names no Russian hardware. Editor to decide whether the project fits the no-Russian-content rule.).",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 51,
      "slug": "james-webb-space-telescope",
      "name": "James Webb Space Telescope",
      "short_name": "James Webb Telescope",
      "category": "space_science",
      "subcategory": "space telescope",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States",
        "Canada",
        "France"
      ],
      "continent": "North America",
      "city": "Greenbelt, Maryland (Goddard Space Flight Center)",
      "lat": 38.9917,
      "lng": -76.852,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1996",
      "planned_end": "2007",
      "actual_start": "1996",
      "actual_end": "2021-12-25",
      "actual_is_forecast": false,
      "planned_duration_months": 132,
      "actual_duration_months": 305.8,
      "delay_months": 173.8,
      "delay_pct": 131.7,
      "planned_cost": 1000000000,
      "actual_cost": 9700000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        9663000000,
        9700000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1999,
      "cost_year": 2021,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 1000000000,
      "cost_usd_nominal": 9700000000,
      "planned_cost_usd_today": 1932680783,
      "cost_usd_today": 11524929387,
      "overrun_usd_today": 10336792337,
      "overrun_pct": 870,
      "overrun_basis": "nominal",
      "rebaseline_cost": 4964000000,
      "rebaseline_cost_year": 2009,
      "rebaseline_end": "2014-06",
      "rebaseline_label": "FY2009 baseline commitment",
      "rebaseline_overrun_pct": 95.4,
      "rebaseline_delay_months": 90.3,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Next Generation Space Telescope concept studies",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1996",
          "actual_end": "2003-03",
          "note": "Proposed in 1996 at about $500 million; 1999 studies assumed a $1 billion budget and a 2007 launch."
        },
        {
          "name": "Formulation and prime contract",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2003-03",
          "actual_end": "2008",
          "note": "Northrop Grumman (then TRW) won the prime contract in March 2003. A 2005 replan raised life-cycle cost to $4.5 billion and moved launch to 2013."
        },
        {
          "name": "Development under the 2009 baseline",
          "planned_start": "2008",
          "planned_end": "2014-06",
          "actual_start": "2008",
          "actual_end": "2011-11",
          "note": "NASA committed to $4.964 billion and a June 2014 launch in FY2009. The October 2010 Casani review found this unachievable; Congress capped development at $8 billion in November 2011."
        },
        {
          "name": "Telescope and instrument build",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2011-11",
          "actual_end": "2016-11",
          "note": "The 18 primary mirror segments were mounted between November 2015 and February 3, 2016; telescope construction finished in November 2016."
        },
        {
          "name": "Observatory integration and test",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2016-11",
          "actual_end": "2019-08",
          "note": "Sunshield tore during a March 2018 deployment test; the June 2018 replan moved launch to March 2021 and raised life-cycle cost to $9.663 billion. Mechanical integration finished in August 2019."
        },
        {
          "name": "Final testing and launch campaign",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2019-08",
          "actual_end": "2021-12-25",
          "note": "Further slips from sunshield work and launch vehicle issues; launched on an Ariane 5 from Kourou on December 25, 2021."
        }
      ],
      "milestones": [
        {
          "name": "Baseline commitment (FY2009)",
          "planned_date": null,
          "actual_date": "2009"
        },
        {
          "name": "Congress caps development at $8 billion",
          "planned_date": null,
          "actual_date": "2011-11"
        },
        {
          "name": "NASA notifies Congress of cap breach",
          "planned_date": null,
          "actual_date": "2018-03-26"
        },
        {
          "name": "Launch",
          "planned_date": "2007",
          "actual_date": "2021-12-25"
        },
        {
          "name": "First full-color images released",
          "planned_date": null,
          "actual_date": "2022-07-12"
        }
      ],
      "headline": "Webb was pitched in the late 1990s as a roughly $1 billion telescope launching in 2007; it launched on Christmas Day 2021 at a life-cycle cost of $9.7 billion.",
      "summary": "The James Webb Space Telescope, NASA's infrared successor to Hubble built with the European and Canadian space agencies, was proposed in 1996 for about $500 million. NASA committed to a formal baseline in FY2009: $4.964 billion life-cycle cost and a June 2014 launch. Repeated technical problems led to replans in 2011 and 2018 and a near-cancellation by a House subcommittee. Webb launched on December 25, 2021 at a life-cycle cost of about $9.7 billion and released its first full-color images in July 2022.",
      "what_went_wrong_or_right": "Webb's estimates were unrealistic from the start. The National Academy of Sciences endorsed it in 2001 at about $1 billion, and the 2009 baseline of $4.964 billion was judged unachievable within a year by the Independent Comprehensive Review Panel chaired by John Casani, which in 2010 put the life-cycle cost at $6.5 billion and the earliest launch in late 2015. In July 2011 the House Appropriations Committee recommended cancelling the project; Congress instead funded a revised $8.835 billion plan with an $8 billion cap on development. Integration and testing then exposed further problems. The May 2018 Independent Review Board named five causes: human errors such as applying the wrong voltage in a wiring test, embedded problems such as sunshield fasteners that loosened under vibration, inexperience with novel technologies like the sunshield, excessive optimism, and system complexity. The board found 344 potential single-point failures. NASA reported a breach of the cap in March 2018, and GAO later said the launch had slipped more than seven years since 2009. Once launched, deployment worked as designed.",
      "lessons": [
        "An estimate set before the technology is mature is a guess; Webb's cost grew almost tenfold from its 2001 endorsement.",
        "Statutory cost caps do not control cost unless the baseline behind them is realistic.",
        "Budget schedule reserve for integration and test; most of Webb's late slips appeared there."
      ],
      "fun_fact": "Mechanical integration of the telescope with its spacecraft and sunshield, first scheduled for 2007, was completed in August 2019.",
      "method_tags": [
        "phased_delivery",
        "simulation"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "James Webb Space Telescope (JWST) (IF10940)",
          "publisher": "Congressional Research Service (via EveryCRSReport)",
          "url": "https://www.everycrsreport.com/files/2018-08-03_IF10940_365fe498c4f60065d078d2825e4225eb6e932e06.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "James Webb Space Telescope: Project Nearing Completion, but Work to Resolve Challenges Continues (GAO-21-406)",
          "publisher": "U.S. Government Accountability Office",
          "url": "https://www.gao.gov/products/gao-21-406",
          "accessed": "2026-10-25"
        },
        {
          "title": "James Webb Space Telescope",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/James_Webb_Space_Telescope",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "high",
      "notes": "Baseline: the FY2009 commitment of $4.964 billion life-cycle cost ($4.381 billion formulation and development plus $582 million operations) and a June 2014 launch (CRS IF10940). Earlier figures (about $500 million in 1996, about $1 billion in 2001, $4.5 billion in 2005) predate the formal baseline and are in notes only. Actual: about $9.7 billion life-cycle (GAO-21-406, NASA lifetime estimate); the 2018 replan figure was $9.663 billion (range). Life-cycle cost includes five years of operations after launch. Mixed-year nominal dollars. actual_end is launch date for comparability with the baseline launch date. ESA (Ariane 5 launch, instruments) and CSA contributions are not in NASA's figure; France listed because launch was from Kourou, French Guiana. GAO-20-224 cited a 95 percent cost increase, but that report was not opened, so reported_overrun_pct is null. USD, so fx = 1. Baseline audit 2026-10-25: Planned changed from the FY2009 baseline ($4.964 billion, June 2014 launch) to the first announced figures: the 1999 concept studies for a US$1 billion budget and a 2007 launch (Wikipedia: \"Two concept studies were commissioned in 1999, for a potential launch in 2007 and a US$1 billion budget\"); an earlier rough $500 million estimate for the 8 m concept is undated and not used. The FY2009 commitment is now the rebaseline. The launch milestone planned date moved to 2007; the phase labelled as the 2009 baseline keeps its 2008-2014 planned dates. The 1999 figure was a development budget target, not a life-cycle commitment, so the overrun versus the $9.7 billion life-cycle actual mixes scopes.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 52,
      "slug": "large-hadron-collider",
      "name": "Large Hadron Collider",
      "short_name": "Large Hadron Collider",
      "category": "space_science",
      "subcategory": "particle accelerator",
      "country": "Switzerland",
      "country_code": "CH",
      "countries": [
        "Switzerland",
        "France"
      ],
      "continent": "Europe",
      "city": "Geneva (CERN, Meyrin)",
      "lat": 46.2341,
      "lng": 6.0529,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1994-12",
      "planned_end": "2005",
      "actual_start": "1994-12",
      "actual_end": "2010-03-30",
      "actual_is_forecast": false,
      "planned_duration_months": 126.5,
      "actual_duration_months": 183.5,
      "delay_months": 57,
      "delay_pct": 45,
      "planned_cost": 2600000000,
      "actual_cost": 4332000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        3756000000,
        4332000000
      ],
      "cost_currency": "CHF",
      "planned_cost_year": 1996,
      "cost_year": 2008,
      "planned_fx_to_usd": 0.809,
      "actual_fx_to_usd": 0.9246,
      "planned_cost_usd_nominal": 2103400000,
      "cost_usd_nominal": 4005367200,
      "planned_cost_usd_today": 4317928071,
      "cost_usd_today": 5989478773,
      "overrun_usd_today": 2394685419,
      "overrun_pct": 66.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 18,
      "reported_overrun_source": "Physics Today, December 2001 (overrun on items in the original LHC budget, 480 MCHF)",
      "phases": [
        {
          "name": "Approval and funding plan",
          "planned_start": "1994-12",
          "planned_end": "1996-12",
          "actual_start": "1994-12",
          "actual_end": "1996-12-20",
          "note": "CERN Council approved a two-stage LHC ending in 2008; on December 20, 1996 it switched to a single-stage build with commissioning planned for 2005, after non-member states committed funds."
        },
        {
          "name": "Construction and installation",
          "planned_start": "1996-12",
          "planned_end": "2005",
          "actual_start": "1996-12",
          "actual_end": "2008-09-10",
          "note": "In September 2001 CERN disclosed costs 850 MCHF above the 2.6 billion CHF allotted, driven by magnets, computing and civil engineering for the CMS cavern."
        },
        {
          "name": "First beam and magnet incident",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2008-09-10",
          "actual_end": "2008-09-19",
          "note": "Beam circulated on September 10, 2008. Nine days later a faulty electrical connection between two magnets damaged a sector."
        },
        {
          "name": "Repair and consolidation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2008-09-19",
          "actual_end": "2009-11-23",
          "note": "Several months of repairs; first collisions came on November 23, 2009."
        },
        {
          "name": "Ramp-up to physics operation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2009-11-23",
          "actual_end": "2010-03-30",
          "note": "First collisions at a total energy of 7 TeV on March 30, 2010 began the research program."
        }
      ],
      "milestones": [
        {
          "name": "CERN Council approval",
          "planned_date": null,
          "actual_date": "1994-12"
        },
        {
          "name": "Cost overrun disclosed to Council",
          "planned_date": null,
          "actual_date": "2001-09"
        },
        {
          "name": "First beam",
          "planned_date": "2005",
          "actual_date": "2008-09-10"
        },
        {
          "name": "First 7 TeV collisions",
          "planned_date": null,
          "actual_date": "2010-03-30"
        },
        {
          "name": "Higgs boson discovery announced",
          "planned_date": null,
          "actual_date": "2012-07"
        }
      ],
      "headline": "CERN's collider started physics five years after its 2005 target, and its construction cost to CERN rose from an allotted 2.6 billion Swiss francs to 4.3 billion.",
      "summary": "The Large Hadron Collider is a 27-kilometer superconducting proton collider straddling the Swiss-French border near Geneva. CERN Council approved it in December 1994 and in 1996 chose a single-stage build aimed at commissioning in 2005. A 2001 budget crisis, magnet and civil engineering problems, and a September 2008 magnet-connection failure nine days after first beam delayed operations. Physics at 7 TeV began on March 30, 2010. CERN puts its construction cost at 4,332 million Swiss francs, plus about 1.5 billion for the detectors.",
      "what_went_wrong_or_right": "The cost crisis became public in September 2001, when CERN management told Council that costs had risen 850 million Swiss francs above the 2.6 billion allotted. About 480 million of this, roughly 18 percent, fell on items in the original LHC budget. Physics Today listed the causes: 150 million francs for unplanned magnet prototypes, magnet assembly about 180 million over expectations, 120 million for a computing grid, 70 million for problems excavating the CMS cavern, 150 million for outside contractors, and a shortfall in non-member contributions. Council members said management had not taken the tight budget seriously. The funding model added risk: the 1996 decision to build in one stage depended on non-member states, while member contributions were cut by up to 9.3 percent against the 1994 level. The schedule slipped from 2005 to first beam on September 10, 2008, and a faulty electrical connection between two magnets then damaged a sector on September 19, costing more than a year before physics. Once running, the machine delivered its main goal, the Higgs boson discovery announced in July 2012.",
      "lessons": [
        "Count prototype and tooling costs in the baseline; unplanned magnet prototypes alone added 150 million francs.",
        "A plan that depends on outside contributions needs a fallback if they fall short.",
        "Thousands of identical joints need identical inspection; one bad splice idled the machine for over a year."
      ],
      "fun_fact": "CERN's 4,332 million franc figure excludes most detector costs: the four main detectors cost about 1.5 billion francs more, mostly paid by the experimental collaborations.",
      "method_tags": [
        "prototyping",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "The Large Hadron Collider",
          "publisher": "CERN",
          "url": "https://home.cern/science/accelerators/large-hadron-collider",
          "accessed": "2026-10-25"
        },
        {
          "title": "LHC completion foreseen for 2005 with reduced CERN budget (Council press release, 20 December 1996)",
          "publisher": "CERN",
          "url": "https://home.cern/?p=6235",
          "accessed": "2026-10-25"
        },
        {
          "title": "CERN cost overrun (news, December 2001)",
          "publisher": "Physics Today",
          "url": "https://physicstoday.aip.org/article/54/12/21/411586",
          "accessed": "2026-10-25"
        },
        {
          "title": "Switzerland / U.S. Foreign Exchange Rate, annual (AEXSZUS)",
          "publisher": "Federal Reserve Bank of St. Louis (FRED), from Federal Reserve H.10/G.5A",
          "url": "https://fred.stlouisfed.org/data/AEXSZUS.txt",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the 2.6 billion CHF allotted to the LHC as cited by Physics Today (2001), which corresponds to the funding approved in December 1994 and kept in the December 1996 single-stage decision; the price base is not stated (1996 assumed). Planned end: commissioning in 2005 under the 1996 plan; the original December 1994 approval was for a two-stage machine completed in 2008. Actual: CERN's construction cost table, 3,756 MCHF for machine and areas plus 493 MCHF CERN share of detectors and 83 MCHF computing, total 4,332 MCHF; the main value uses the total because the 2001 overrun breakdown shows the 2.6 billion budget covered CERN's detector share and computing. It is not clear whether the two figures treat CERN personnel costs the same way, so confidence is 'disputed'. actual_end is the start of 7 TeV physics; first beam was 2008-09-10. FX: FRED annual averages, 1.2361 CHF/USD in 1996 (0.809 USD/CHF) and 1.0816 CHF/USD in 2008 (0.9246 USD/CHF). Site is CERN Meyrin on the Swiss-French border. Baseline audit 2026-10-25: Planned cost unchanged. The December 1994 approval was the first, for a two-stage machine completed in 2008 at the same CHF 2.6 billion; the 1996 single-stage plan (2005) is kept as planned_end because it is the scope finally built. No formal later rebaseline was sourced.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 53,
      "slug": "mars-pathfinder",
      "name": "Mars Pathfinder",
      "short_name": "Mars Pathfinder",
      "category": "space_science",
      "subcategory": "planetary lander and rover",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Pasadena (Jet Propulsion Laboratory)",
      "lat": 34.2013,
      "lng": -118.1714,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "late",
      "planned_start": "1993",
      "planned_end": "1997-07",
      "actual_start": "1993",
      "actual_end": "1997-09-27",
      "actual_is_forecast": false,
      "planned_duration_months": 48.5,
      "actual_duration_months": 50.9,
      "delay_months": 2.4,
      "delay_pct": 4.9,
      "planned_cost": 175000000,
      "actual_cost": 175000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1993,
      "cost_year": 1997,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 175000000,
      "cost_usd_nominal": 175000000,
      "planned_cost_usd_today": 390031099,
      "cost_usd_today": 350979478,
      "overrun_usd_today": 0,
      "overrun_pct": 0,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Design and development",
          "planned_start": "1993",
          "planned_end": "1996-12",
          "actual_start": "1993",
          "actual_end": "1996-12-04",
          "note": "A Discovery-class mission led by JPL project manager Tony Spear, with goals of three years of development, under $150 million for the lander and $25 million for the rover."
        },
        {
          "name": "Cruise to Mars",
          "planned_start": "1996-12",
          "planned_end": "1997-07",
          "actual_start": "1996-12-04",
          "actual_end": "1997-07-04",
          "note": "Launched on a Delta II 7925 from Cape Canaveral on December 4, 1996, a month after Mars Global Surveyor."
        },
        {
          "name": "Surface operations",
          "planned_start": "1997-07",
          "planned_end": "1997-07",
          "actual_start": "1997-07-04",
          "actual_end": "1997-09-27",
          "note": "Landed in Ares Vallis on airbags, bouncing at least 15 times. Sojourner rolled off on July 6 and worked 83 days against a planned seven; contact was lost on September 27, 1997."
        }
      ],
      "milestones": [
        {
          "name": "Launch",
          "planned_date": "1996-12",
          "actual_date": "1996-12-04"
        },
        {
          "name": "Landing in Ares Vallis",
          "planned_date": "1997-07",
          "actual_date": "1997-07-04"
        },
        {
          "name": "Sojourner rover drives onto the surface",
          "planned_date": null,
          "actual_date": "1997-07-06"
        },
        {
          "name": "Flight software patched for priority inversion",
          "planned_date": null,
          "actual_date": "1997-07-21"
        },
        {
          "name": "Last transmission",
          "planned_date": null,
          "actual_date": "1997-09-27"
        }
      ],
      "headline": "Mars Pathfinder was built in about three years for $150 million plus $25 million for its rover, and Sojourner worked 83 days on a planned seven-day mission.",
      "summary": "Mars Pathfinder was an early NASA Discovery mission, built at the Jet Propulsion Laboratory to show that a lander and rover could reach Mars quickly and cheaply. The goals were about three years of development, under $150 million for the lander and $25 million for the Sojourner rover. It launched on December 4, 1996, landed on July 4, 1997 using airbags, and returned data until September 27, 1997. Including launch and operations, NASA put the total at about $265 million.",
      "what_went_wrong_or_right": "Pathfinder was the model for NASA's 'faster, better, cheaper' approach of the 1990s: a hard cost cap, a short schedule and a fixed planetary launch window. The team met its targets, with NASA reporting $150 million for the lander's development and construction and about $25 million for the rover. Its entry, descent and landing system combined a parachute, retrorockets and airbags that inflated about 355 meters above the surface; the lander hit at 14 meters per second and bounced at least 15 times before stopping. The mission exceeded its goals, with Sojourner operating 83 days against a planned seven and the lander returning data until late September 1997. Not everything was clean. A priority inversion bug in the flight software, seen in preflight testing but given low priority, caused four computer resets in July 1997 before engineers patched it on July 21. The mission was also deliberately narrow: a technology demonstration with a small instrument set, which made the tight cap achievable.",
      "lessons": [
        "A fixed launch window and a hard cost cap force early scope decisions.",
        "A known bug marked low priority in testing can still stop operations; review deferred defects before launch.",
        "Narrow scope made 'faster, better, cheaper' work here; copying the cap without the scope does not."
      ],
      "fun_fact": "Pathfinder cost about one-fifteenth as much as a Viking mission to Mars.",
      "method_tags": [
        "lean",
        "prototyping"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "agile-manifesto-2001"
      ],
      "sources": [
        {
          "title": "Mars Pathfinder (NSSDCA/COSPAR ID 1996-068A)",
          "publisher": "NASA Space Science Data Coordinated Archive",
          "url": "https://nssdc.gsfc.nasa.gov/nmc/spacecraft/display.action?id=1996-068A",
          "accessed": "2026-10-25"
        },
        {
          "title": "Mars Pathfinder",
          "publisher": "NASA",
          "url": "https://science.nasa.gov/mission/mars-pathfinder/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Mars Pathfinder",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Mars_Pathfinder",
          "accessed": "2026-10-25"
        },
        {
          "title": "Mars Pathfinder Sojourner Rover",
          "publisher": "NASA Jet Propulsion Laboratory",
          "url": "https://www.jpl.nasa.gov/missions/mars-pathfinder-sojourner-rover/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the mission's stated targets of three years of development and under $150 million for the lander plus $25 million for the rover (Wikipedia, citing mission goals); planned_cost is the sum, $175 million, and planned_cost_year 1993 is an assumption (start of development). Actual: NASA NSSDCA reports lander development and construction at $150 million and the rover at about $25 million, so actual_cost is $175 million on the same scope. Totals including launch and operations are about $265 million (NSSDCA) or $280 million (Wikipedia). Planned start '1993' is derived from the three-year development goal ending with the December 1996 launch; no opened source gives the exact start date. Planned end '1997-07' reflects the July 1997 arrival and the planned seven-day rover mission (JPL); the lander's planned surface lifetime was not found in an opened source. The 'faster, better, cheaper' label is from Wikipedia's description of the mission goals. USD, so fx = 1.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 54,
      "slug": "curiosity-rover",
      "name": "Mars Science Laboratory (Curiosity rover)",
      "short_name": "Curiosity rover",
      "category": "space_science",
      "subcategory": "planetary rover",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Pasadena (Jet Propulsion Laboratory)",
      "lat": 34.2013,
      "lng": -118.1714,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2004",
      "planned_end": "2009-10",
      "actual_start": "2004",
      "actual_end": "2011-11-26",
      "actual_is_forecast": false,
      "planned_duration_months": 63.5,
      "actual_duration_months": 88.8,
      "delay_months": 25.4,
      "delay_pct": 40,
      "planned_cost": 1600000000,
      "actual_cost": 2500000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2006,
      "cost_year": 2011,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 1600000000,
      "cost_usd_nominal": 2500000000,
      "planned_cost_usd_today": 2555298778,
      "cost_usd_today": 3578032544,
      "overrun_usd_today": 1288091716,
      "overrun_pct": 56.3,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 56,
      "reported_overrun_source": "NASA Office of Inspector General, IG-11-019 (June 2011), as reported by NBC News",
      "phases": [
        {
          "name": "Formulation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2004",
          "actual_end": "2006",
          "note": "Project confirmed for development in 2006 with a life-cycle estimate of about $1.6 billion."
        },
        {
          "name": "Development toward the 2009 launch window",
          "planned_start": "2006",
          "planned_end": "2009-10",
          "actual_start": "2006",
          "actual_end": "2008-12-04",
          "note": "Dry-lubricant actuators proved very hard to make work and were replaced with conventional designs; the heat shield had to be redesigned for the larger spacecraft."
        },
        {
          "name": "Two-year slip and completion",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2008-12-04",
          "actual_end": "2011-06",
          "note": "NASA announced on December 4, 2008 that it could not finish in time for 2009; the next Mars window was 26 months later. Development cost rose 86 percent, from $969 million to $1.8 billion."
        },
        {
          "name": "Final testing and launch campaign",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2011-06",
          "actual_end": "2011-11-26",
          "note": "In June 2011 the Inspector General reported about 1,200 unresolved problem and failure reports as of February 2011. Launch came on November 26, 2011, one day after the window opened."
        }
      ],
      "milestones": [
        {
          "name": "Delay to 2011 announced",
          "planned_date": null,
          "actual_date": "2008-12-04"
        },
        {
          "name": "NASA OIG report on readiness",
          "planned_date": null,
          "actual_date": "2011-06-08"
        },
        {
          "name": "Launch",
          "planned_date": "2009-10",
          "actual_date": "2011-11-26"
        },
        {
          "name": "Landing in Gale Crater",
          "planned_date": null,
          "actual_date": "2012-08-06"
        }
      ],
      "headline": "Curiosity missed its 2009 launch window by two years, and its life-cycle cost rose 56 percent to about $2.5 billion.",
      "summary": "The Mars Science Laboratory is NASA's car-sized Curiosity rover, built at the Jet Propulsion Laboratory. Confirmed in 2006 at a life-cycle cost of about $1.6 billion, it was due to launch in fall 2009. Problems with actuators, the heat shield and late deliveries of components forced NASA in December 2008 to slip the launch to the next Mars window, 26 months later. Curiosity launched on November 26, 2011 and landed in Gale Crater on August 6, 2012. The Inspector General put the life-cycle cost at about $2.5 billion.",
      "what_went_wrong_or_right": "MSL grew in scope and novelty faster than its budget. Its large rover required a new heat shield and a new landing system, and the team's choice of dry-lubricant actuators for the rover's joints proved very hard to make work, forcing a late switch to conventional actuators. Contractors also delivered critical components and instruments late. On December 4, 2008 NASA concluded the work could not be finished for the fall 2009 launch window; because Mars windows open only every 26 months, the slip was two years and added hundreds of millions of dollars. The NASA Inspector General reported in June 2011 that development cost had risen 86 percent, from $969 million to $1.8 billion, and life-cycle cost 56 percent, from $1.6 billion to $2.5 billion. It found managers may have been overly optimistic about the time and money needed, with more than three times the planned number of critical tasks still open and about 1,200 unresolved problem reports. A missed 2011 window would have cost about $570 million more. The rover launched on time in 2011 and landed successfully.",
      "lessons": [
        "When a launch window is fixed, schedule margin is worth more than cost margin.",
        "Avoid stacking several new technologies on one critical path.",
        "Track open problem reports as a leading indicator of schedule risk."
      ],
      "fun_fact": "Missing the November 2011 launch window would have delayed the mission another 26 months and, the Inspector General estimated, cost about $570 million.",
      "method_tags": [
        "prototyping",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "critical-chain-1997"
      ],
      "sources": [
        {
          "title": "NASA's next Mars rover still faces big challenges, audit reveals",
          "publisher": "NBC News / Space.com",
          "url": "https://www.nbcnews.com/id/wbna43327621",
          "accessed": "2026-10-25"
        },
        {
          "title": "MSL launch delayed two years",
          "publisher": "The Planetary Society",
          "url": "https://planetary.org/articles/20081204-msl-launch-delayed-two-years",
          "accessed": "2026-10-25"
        },
        {
          "title": "Mars Science Laboratory: Curiosity Rover",
          "publisher": "NASA",
          "url": "https://science.nasa.gov/mission/msl-curiosity/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: life-cycle cost of about $1.6 billion when the project was confirmed in 2006, with launch in the fall 2009 window (NASA OIG IG-11-019 via NBC News; Planetary Society). A House Science Committee document cites a development baseline of $969 million, consistent with the OIG figures. Earlier 2000-era proposals of about $600 million predate the baseline. GAO's 2012 assessment measured growth of $881 million against a 2008 baseline. Actual: about $2.5 billion life-cycle (OIG, June 2011), a pre-launch estimate; final cost was not found in an opened source. planned_end '2009-10' approximates the fall 2009 window (sources say fall/October 2009). actual_end is launch for comparability; landing was 2012-08-06. Formulation start year 2004 is approximate (instrument selection era). The primary OIG PDF could not be downloaded; figures are from press coverage of it. USD, so fx = 1.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 55,
      "slug": "new-horizons",
      "name": "New Horizons mission to Pluto",
      "short_name": "New Horizons",
      "category": "space_science",
      "subcategory": "planetary flyby probe",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Laurel, Maryland (Johns Hopkins Applied Physics Laboratory)",
      "lat": 39.1655,
      "lng": -76.8977,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "on_time_on_budget",
      "planned_start": "2001-11-29",
      "planned_end": "2015-07-14",
      "actual_start": "2001-11-29",
      "actual_end": "2015-07-14",
      "actual_is_forecast": false,
      "planned_duration_months": 163.5,
      "actual_duration_months": 163.5,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 700000000,
      "actual_cost": 700000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2001,
      "cost_year": 2016,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 700000000,
      "cost_usd_nominal": 700000000,
      "planned_cost_usd_today": 1272787070,
      "cost_usd_today": 939059900,
      "overrun_usd_today": 0,
      "overrun_pct": 0,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Proposal competition and selection",
          "planned_start": "2001-01-20",
          "planned_end": "2001-11",
          "actual_start": "2001-01-20",
          "actual_end": "2001-11-29",
          "note": "NASA requested Pluto-Kuiper Belt flyby proposals on January 20, 2001, shortlisted two in June 2001 and selected New Horizons, led by Alan Stern of Southwest Research Institute, on November 29, 2001."
        },
        {
          "name": "Funding fight and design",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2001-11-29",
          "actual_end": "2002",
          "note": "The mission was left out of NASA's 2003 budget request; funding was secured after the 2002 Planetary Science Decadal Survey ranked it first among medium-size missions."
        },
        {
          "name": "Spacecraft build and test",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2002",
          "actual_end": "2005-09-24",
          "note": "Built at the Johns Hopkins Applied Physics Laboratory; reduced plutonium production at the Department of Energy left the power source with 9.75 kg of fuel instead of the 10.9 kg designed."
        },
        {
          "name": "Launch campaign",
          "planned_start": "2005-09",
          "planned_end": "2006-02-14",
          "actual_start": "2005-09-24",
          "actual_end": "2006-01-19",
          "note": "The spacecraft arrived at Kennedy Space Center on September 24, 2005. The launch period ran January 11 to February 14, 2006; launch came on January 19 on an Atlas V 551."
        },
        {
          "name": "Cruise to Jupiter and Pluto",
          "planned_start": "2006-01",
          "planned_end": "2015-07-14",
          "actual_start": "2006-01-19",
          "actual_end": "2015-07-14",
          "note": "A Jupiter gravity assist on February 28, 2007 cut about three years off the trip; closest approach to Pluto came on July 14, 2015."
        }
      ],
      "milestones": [
        {
          "name": "NASA selects New Horizons",
          "planned_date": null,
          "actual_date": "2001-11-29"
        },
        {
          "name": "Launch",
          "planned_date": "2006-01-11",
          "actual_date": "2006-01-19"
        },
        {
          "name": "Jupiter gravity assist",
          "planned_date": "2007-02",
          "actual_date": "2007-02-28"
        },
        {
          "name": "Pluto closest approach",
          "planned_date": "2015-07-14",
          "actual_date": "2015-07-14"
        },
        {
          "name": "Last Pluto flyby data received",
          "planned_date": null,
          "actual_date": "2016-10-25"
        }
      ],
      "headline": "New Horizons made its 2006 launch window and reached Pluto in July 2015, the earliest date planned, within a total budget of about $700 million.",
      "summary": "New Horizons was the first mission to Pluto, selected by NASA on November 29, 2001 and run by Southwest Research Institute and the Johns Hopkins Applied Physics Laboratory. It survived an early funding cut, launched on January 19, 2006 within a 35-day window, used Jupiter's gravity in February 2007, and flew past Pluto on July 14, 2015, the earliest arrival the plan allowed. NASA put the mission's cost at about $700 million for 2001-2016, the ceiling for its program class.",
      "what_went_wrong_or_right": "New Horizons was a principal-investigator mission under NASA's New Frontiers rules, which made the PI responsible for cost, schedule and performance and set a total cost limit of $700 million. Its predecessor concept, Pluto-Kuiper Express, had been cancelled in 2000 when estimates exceeded available funds, so the team had a clear cost ceiling from the start. The schedule was driven by physics: only launches between January 11 and February 2, 2006 could use a Jupiter gravity assist that cut three to five years off the trip. NASA's launch planning showed that later departures meant later arrivals, with Pluto-direct launches in February reaching Pluto as late as 2020. Political risk was the biggest early threat: NASA left the mission out of its 2003 budget, and it was restored after the 2002 Decadal Survey ranked it first among medium-size missions. One shortfall was outside the team's control: delays at the Department of Energy reduced plutonium production, so the power source carried 9.75 kg of fuel instead of 10.9 kg, and instruments could not all run at once.",
      "lessons": [
        "A hard launch window makes schedule protection worth paying for.",
        "Give one accountable leader authority over cost, schedule and scope.",
        "Track supplier risks you do not control, such as government-furnished fuel, from day one."
      ],
      "fun_fact": "The New Horizons power source was originally a spare built for the Cassini mission.",
      "method_tags": [
        "fixed_price",
        "lean",
        "critical_path"
      ],
      "related_history_ids": [
        "cpm-1957",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "New Horizons Launch Press Kit (December 2005)",
          "publisher": "NASA",
          "url": "https://www.nasa.gov/pdf/139889main_PressKit12_05.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "New Horizons",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/New_Horizons",
          "accessed": "2026-10-25"
        },
        {
          "title": "Breakthrough Performance to Pluto and Beyond",
          "publisher": "Insigniam",
          "url": "https://insigniam.com/breakthrough-performance-to-pluto-and-beyond/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the New Frontiers program rule that 'total mission cost must be under $700 million' (NASA press kit, 2005), used as the planned cost; a separate approved project baseline was not found. APL's initial white paper proposed about $500 million (Insigniam), which predates selection. Planned schedule: launch period January 11 to February 14, 2006; the press kit arrival table gives Pluto close approach on July 14, 2015 for any launch from January 11 to 27, so the January 19 launch arrived exactly on the planned date. Actual: approximately $700 million including development, launch vehicle, operations, data analysis and outreach over 2001-2016 (press kit; Wikipedia); a precise final figure was not found, so cost growth cannot be measured more finely than 'about on budget'. Lat/lng is the Johns Hopkins Applied Physics Laboratory, which built and operates the spacecraft. USD, so fx = 1.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 56,
      "slug": "rosetta-mission",
      "name": "Rosetta comet mission",
      "short_name": "Rosetta",
      "category": "space_science",
      "subcategory": "comet orbiter and lander",
      "country": "Germany",
      "country_code": "DE",
      "countries": [
        "Germany",
        "France",
        "Italy",
        "United Kingdom",
        "Netherlands"
      ],
      "continent": "Europe",
      "city": "Darmstadt (ESA European Space Operations Centre)",
      "lat": 49.8711,
      "lng": 8.6227,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1993-11",
      "planned_end": "2011-11",
      "actual_start": "1993-11",
      "actual_end": "2014-08-06",
      "actual_is_forecast": false,
      "planned_duration_months": 216,
      "actual_duration_months": 248.7,
      "delay_months": 32.7,
      "delay_pct": 15.1,
      "planned_cost": 1000000000,
      "actual_cost": 1400000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        1300000000,
        1400000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2003,
      "cost_year": 2014,
      "planned_fx_to_usd": 1.1321,
      "actual_fx_to_usd": 1.3297,
      "planned_cost_usd_nominal": 1132000000,
      "cost_usd_nominal": 1862000000,
      "planned_cost_usd_today": 1981204776,
      "cost_usd_today": 2532309531,
      "overrun_usd_today": 723517009,
      "overrun_pct": 40,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Approval and mission definition",
          "planned_start": "1993-11",
          "planned_end": null,
          "actual_start": "1993-11",
          "actual_end": "1996",
          "note": "ESA approved Rosetta in November 1993 as a Cornerstone mission of its Horizon 2000 program, after an earlier comet sample-return concept proved infeasible."
        },
        {
          "name": "Spacecraft and lander development",
          "planned_start": "1996",
          "planned_end": "2003-01-12",
          "actual_start": "1996",
          "actual_end": "2002-12-11",
          "note": "Built for a January 12, 2003 launch to comet 46P/Wirtanen. On December 11, 2002 the first Ariane 5 ECA failed, grounding the launcher."
        },
        {
          "name": "Postponement and retargeting",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2002-12-11",
          "actual_end": "2004-03-02",
          "note": "ESA retargeted the mission to comet 67P/Churyumov-Gerasimenko, reachable with the same Ariane 5 version; Rosetta launched from Kourou on March 2, 2004."
        },
        {
          "name": "Cruise and hibernation",
          "planned_start": "2003-01",
          "planned_end": "2011-11",
          "actual_start": "2004-03-02",
          "actual_end": "2014-01-20",
          "note": "The spacecraft entered hibernation on June 8, 2011 for a planned 31 months and woke on January 20, 2014."
        },
        {
          "name": "Approach and arrival at the comet",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2014-01-20",
          "actual_end": "2014-08-06",
          "note": "Rosetta reached 67P in May 2014 and entered orbit on August 6, 2014, the first spacecraft to orbit a comet."
        }
      ],
      "milestones": [
        {
          "name": "ESA approval",
          "planned_date": null,
          "actual_date": "1993-11"
        },
        {
          "name": "Launch",
          "planned_date": "2003-01-12",
          "actual_date": "2004-03-02"
        },
        {
          "name": "Arrival at the target comet",
          "planned_date": "2011-11",
          "actual_date": "2014-08-06"
        },
        {
          "name": "Philae lands on comet 67P",
          "planned_date": null,
          "actual_date": "2014-11-12"
        },
        {
          "name": "Rosetta ends mission on the comet surface",
          "planned_date": null,
          "actual_date": "2016-09-30"
        }
      ],
      "headline": "A launcher failure cost Rosetta its January 2003 window and its original comet, but ESA's about 1.4 billion euro mission still became the first to orbit a comet.",
      "summary": "Rosetta was a European Space Agency mission, approved in November 1993, to orbit a comet and place a lander on its nucleus. It was due to launch in January 2003 to comet 46P/Wirtanen, but the December 2002 failure of a new Ariane 5 variant grounded the launcher. ESA retargeted the spacecraft to comet 67P/Churyumov-Gerasimenko, launched it on March 2, 2004 and reached the comet on August 6, 2014. The Philae lander touched down on November 12, 2014. ESA puts the total cost close to 1.4 billion euros.",
      "what_went_wrong_or_right": "Rosetta's main setback came from outside the project. The spacecraft was ready for a January 12, 2003 launch to comet Wirtanen when the first Ariane 5 ECA failed on December 11, 2002, carrying a commercial satellite. With the launcher grounded, Rosetta missed its window. ESA chose a new target, comet 67P/Churyumov-Gerasimenko, because it could be reached using the same Ariane 5 version, while a 2004 Wirtanen mission would have needed a more powerful rocket. The switch kept the spacecraft design but stretched the cruise to ten years; arrival moved from 2011 to 2014. ESA reports the Philae lander alone cost 220 million euros in 2014 economic conditions, including the expenses of the one-year delay. During the cruise, Rosetta was put into hibernation from June 2011 to January 2014, with almost all electronics switched off, and woke on schedule. At the comet, Philae bounced on landing on November 12, 2014 and came to rest about two hours later, while the orbiter worked until it was set down on the comet on September 30, 2016.",
      "lessons": [
        "A launcher is a single point of failure for the schedule; plan backup windows or targets in advance.",
        "A flexible mission design can absorb an external shock by changing the goal instead of the hardware.",
        "Record the cost of delays separately so their effect on the budget stays visible."
      ],
      "fun_fact": "Rosetta was the first spacecraft to orbit a comet, entering orbit around 67P on August 6, 2014.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Rosetta: Frequently asked questions",
          "publisher": "European Space Agency",
          "url": "https://www.esa.int/Science_Exploration/Space_Science/Rosetta/Frequently_asked_questions",
          "accessed": "2026-10-25"
        },
        {
          "title": "Rosetta (spacecraft)",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Rosetta_(spacecraft)",
          "accessed": "2026-10-25"
        },
        {
          "title": "U.S. / Euro Foreign Exchange Rate, annual (AEXUSEU)",
          "publisher": "Federal Reserve Bank of St. Louis (FRED), from Federal Reserve H.10/G.5A",
          "url": "https://fred.stlouisfed.org/data/AEXUSEU.txt",
          "accessed": "2026-10-25"
        },
        {
          "title": "Comet chaser is grounded",
          "publisher": "Physics World, 15 January 2003",
          "url": "https://physicsworld.com/a/comet-chaser-is-grounded/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Future of Rosetta comet explorer hinges on money",
          "publisher": "Spaceflight Now, 18 May 2003",
          "url": "https://spaceflightnow.com/news/n0305/18rosetta",
          "accessed": "2026-10-25"
        },
        {
          "title": "ESA confirms ROSETTA and FIRST in its long-term science programme (8 November 1993)",
          "publisher": "European Space Agency",
          "url": "https://www.esa.int/Newsroom/Press_Releases/ESA_confirms_ROSETTA_and_FIRST_in_its_long-term_science_programme",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: ESA's approved cost at the November 1993 approval was not found in an opened source (planned_cost null); a 2003 Nature news item, 'Spiralling costs dog comet mission', is paywalled and was not read. Planned schedule: launch January 12, 2003 and rendezvous with 46P/Wirtanen in 2011 (Wikipedia; ESA FAQ). Actual: 'close to 1.4 billion Euros' covering spacecraft, instruments including the lander, launch and operations from 1996 to the planned 2015 end (ESA FAQ); the price year is not stated, so 2014 is assumed. Wikipedia gives about 1.3 billion euros (range). Instrument contributions funded nationally may not be fully included. actual_end is orbit arrival at the comet, to compare with the planned 2011 rendezvous; the mission ended on 2016-09-30. Country and coordinates are ESA's operations center in Darmstadt; the spacecraft was built by an international industrial team and countries listed are major ESA member contributors. FX: FRED annual average 1.3297 USD per EUR in 2014. UPDATE 2026-10-25: Planned arrival: Physics World (15 Jan 2003) says Rosetta was scheduled to reach 46P/Wirtanen in November 2011 after the 12 January 2003 launch; planned_end set to 2011-11. ESA's FAQ says the 2014 rendezvous was 'two years later than planned', which conflicts; the dated 2003 report is preferred. Planned cost: EUR 1 billion for the full Rosetta mission (Physics World, Jan 2003; Spaceflight Now, May 2003, says $1 billion), with the delay expected to add EUR 50-100 million (Physics World) or about $80 million (Spaceflight Now). Scope is the whole mission, comparable with ESA's 'close to 1.4 billion euros' actual (spacecraft, instruments incl. lander, launch, operations). The 1993 ESA press release confirming Rosetta gives no cost; searches for a 1993 MECU/MAU figure found nothing. FX 2003: FRED AEXUSEU 1.1321. Editor decision 2026-10-25: kept in the dataset (flag was: planned_cost is the pre-delay mission cost reported in January 2003 (about EUR 1 billion), not ESA's November 1993 approval baseline, which was not found; the computed growth reflects mainly the launch delay and retargeting. Editor to decide.).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 57,
      "slug": "space-shuttle-program",
      "name": "Space Shuttle program (development to first flight)",
      "short_name": "Space Shuttle",
      "category": "space_science",
      "subcategory": "reusable launch system",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Cape Canaveral (Kennedy Space Center)",
      "lat": 28.6083,
      "lng": -80.6041,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1972-01-05",
      "planned_end": "1979-03",
      "actual_start": "1972-01-05",
      "actual_end": "1981-04-14",
      "actual_is_forecast": false,
      "planned_duration_months": 86.3,
      "actual_duration_months": 111.3,
      "delay_months": 25,
      "delay_pct": 28.9,
      "planned_cost": 5150000000,
      "actual_cost": 6744000000,
      "planned_cost_range": [
        5150000000,
        5500000000
      ],
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1971,
      "cost_year": 1971,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 5150000000,
      "cost_usd_nominal": 6744000000,
      "planned_cost_usd_today": 40941865242,
      "cost_usd_today": 53613968776,
      "overrun_usd_today": 12672103533,
      "overrun_pct": 31,
      "overrun_basis": "real",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Approval and configuration choices",
          "planned_start": "1972-01-05",
          "planned_end": null,
          "actual_start": "1972-01-05",
          "actual_end": "1972-08",
          "note": "Nixon approved the Shuttle on January 5, 1972. In March 1972 NASA chose solid rocket boosters, partly to stay within the $5.5 billion development ceiling; the orbiter contract went to North American Rockwell in August."
        },
        {
          "name": "Design, engine and orbiter development",
          "planned_start": "1972-08",
          "planned_end": null,
          "actual_start": "1972-08",
          "actual_end": "1976-09-17",
          "note": "Main engine testing suffered nozzle failures and broken turbine blades. The first orbiter, Enterprise, was completed on September 17, 1976."
        },
        {
          "name": "Approach and landing tests",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1977-02",
          "actual_end": "1977",
          "note": "Enterprise flew captive tests on the carrier aircraft from February 1977 and made its first free glide on August 12, 1977."
        },
        {
          "name": "Columbia completion and tile installation",
          "planned_start": null,
          "planned_end": "1979-03",
          "actual_start": "1979-03-25",
          "actual_end": "1980-12-29",
          "note": "Columbia reached Kennedy Space Center on March 25, 1979 with about 6,000 of its 30,000 tiles still to install, and spent a record 610 days in the processing facility."
        },
        {
          "name": "First orbital flight, STS-1",
          "planned_start": "1979-03",
          "planned_end": "1979-03",
          "actual_start": "1981-04-12",
          "actual_end": "1981-04-14",
          "note": "A computer timing fault scrubbed the April 10 attempt; Columbia launched April 12 and landed at Edwards, California on April 14, 1981."
        }
      ],
      "milestones": [
        {
          "name": "Presidential approval",
          "planned_date": null,
          "actual_date": "1972-01-05"
        },
        {
          "name": "Enterprise completed",
          "planned_date": null,
          "actual_date": "1976-09-17"
        },
        {
          "name": "First free flight of Enterprise",
          "planned_date": null,
          "actual_date": "1977-08-12"
        },
        {
          "name": "Columbia arrives at Kennedy Space Center",
          "planned_date": null,
          "actual_date": "1979-03-25"
        },
        {
          "name": "First orbital launch (STS-1)",
          "planned_date": "1979-03",
          "actual_date": "1981-04-12"
        }
      ],
      "headline": "The Shuttle first flew in April 1981, about two years after its March 1979 target, after NASA had sold it on a $5.15 billion development estimate.",
      "summary": "President Nixon approved the Space Shuttle on January 5, 1972 as a partly reusable vehicle meant to cut the cost of reaching orbit. NASA's estimate for development was $5.15 billion, under a $5.5 billion ceiling set by the White House budget office. Main engine failures in testing and the slow installation of about 30,000 heat-shield tiles delayed the first orbital flight from March 1979 to April 12, 1981, when Columbia flew STS-1. The program flew 135 missions through 2011.",
      "what_went_wrong_or_right": "The Shuttle's design was a product of budget negotiation. NASA initially proposed a fully reusable system costing about $10 billion to develop; under pressure from the Office of Management and Budget it cut the figure roughly in half within six months by accepting higher costs per flight. OMB insisted that development stay within $5.5 billion, and NASA budget officer William Lilly produced an estimate of $5.15 billion, which included $260 million for an abort system that was later dropped. Even then, reviewers inside government expected overruns; one 1971 analysis warned the full nonrecurring cost could approach $15 billion. Promised economics rested on optimistic flight rates of about 50 flights a year and early per-flight cost estimates below $10 million. Development then ran into two hard technical problems: the high-pressure main engines suffered nozzle failures and broken turbine blades in testing, and the ceramic thermal tiles were slow to install and often had to be replaced. Columbia arrived at Kennedy Space Center in March 1979 with 6,000 tiles still missing. The first flight slipped about two years, and the program never came close to the promised flight rate, peaking at nine flights in a year.",
      "lessons": [
        "An estimate negotiated to fit a ceiling is a target, not a forecast.",
        "Benefits that depend on a high usage rate should be tested against lower rates.",
        "Mass-installed components such as tiles can drive the critical path as much as engines."
      ],
      "fun_fact": "Columbia's cockpit on STS-1 had 2,214 switches and displays, about three times as many as the Apollo command module.",
      "method_tags": [
        "prototyping",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "apollo-1961",
        "wbs-1962"
      ],
      "sources": [
        {
          "title": "The Space Shuttle Decision: NASA's Search for a Reusable Space Vehicle (SP-4221, Heppenheimer)",
          "publisher": "NASA History Office",
          "url": "https://www.nasa.gov/wp-content/uploads/2023/04/sp-4221.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "STS-1",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/STS-1",
          "accessed": "2026-10-25"
        },
        {
          "title": "Space Shuttle",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Space_Shuttle",
          "accessed": "2026-10-25"
        },
        {
          "title": "Space shuttle's legacy: Soaring in orbit and costs",
          "publisher": "Associated Press via Phys.org",
          "url": "https://phys.org/news/2011-07-space-shuttle-legacy-soaring-orbit.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Shuttle",
          "publisher": "Encyclopedia Astronautica (Mark Wade)",
          "url": "http://www.astronautix.com/s/shuttle.html",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: NASA's development cost estimate of $5.15 billion sent to OMB in early 1972, within OMB's $5.5 billion ceiling (NASA SP-4221); stored as planned_cost with the ceiling as the top of planned_cost_range. Price year assumed 1971 (estimate prepared in late 1971/early 1972, not stated explicitly in the opened text). Planned first orbital flight: March 1979, per John Young's statement quoted in the STS-1 article. Actual development cost through STS-1 is null: no opened source gave a sourced figure. Wikipedia's Space Shuttle program article cites an early NASA estimate of $7.45 billion (no date), and the AP (2011) put total program cost at $196 billion in inflation-adjusted dollars over 30 years versus about $90 billion NASA originally calculated; these are lifecycle, not development, figures. Scope ends at STS-1 landing (1981-04-14). The '50 flights a year' and 'nine flights in a year' figures are from the AP article. USD, so fx = 1. UPDATE 2026-10-25: Actual development cost: Encyclopedia Astronautica states the Shuttle 'ended up costing $6.744 billion in 1971 dollars, versus $5.15 billion estimated', i.e. the development program in the same 1971-dollar terms as the baseline (about 31% real growth by our calculation). It does not state the end date of that accounting, so 'through STS-1' is assumed from the context of development to first flight. overrun_basis set to 'real'. Not used (search excerpts only, not opened): a 1981 newspaper figure of $9.9 billion nominal, a 19FortyFive figure of $10.6 billion spent 1972-82, and an official's account of a $1 billion contingency on top of $5.15 billion. Editor decision 2026-10-25: kept in the dataset (flag was: U.S. Air Force payload and cross-range requirements shaped the Shuttle's size and wing design, and the program served military as well as civil users. The record omits this per the no-defence rule; editor to decide whether that omission is acceptable.).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 58,
      "slug": "cyberpunk-2077",
      "name": "Cyberpunk 2077 (CD Projekt Red)",
      "short_name": "Cyberpunk 2077",
      "category": "software_it",
      "subcategory": "video game",
      "country": "Poland",
      "country_code": "PL",
      "countries": [
        "Poland"
      ],
      "continent": "Europe",
      "city": "Warsaw",
      "lat": 52.2716,
      "lng": 21.027,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "late",
      "planned_start": null,
      "planned_end": "2020-04-16",
      "actual_start": "2012-05",
      "actual_end": "2020-12-10",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 102.8,
      "delay_months": 7.8,
      "delay_pct": null,
      "planned_cost": null,
      "actual_cost": 1200000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "PLN",
      "planned_cost_year": null,
      "cost_year": 2020,
      "planned_fx_to_usd": null,
      "actual_fx_to_usd": 0.2566,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": 307920000,
      "planned_cost_usd_today": null,
      "cost_usd_today": 383068793,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Announcement and pre-production",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2012-05",
          "actual_end": "2016",
          "note": "Announced May 2012, first trailer January 2013; the studio's main effort went to The Witcher 3 until 2015-16."
        },
        {
          "name": "Full production",
          "planned_start": "2016",
          "planned_end": "2020-04",
          "actual_start": "2016",
          "actual_end": "2020-10",
          "note": "Bloomberg reported the bulk of development began in late 2016. The 16 April 2020 date was announced at E3 2019."
        },
        {
          "name": "Delays and final testing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2020-01",
          "actual_end": "2020-12",
          "note": "Delayed to 17 September 2020 (announced January 2020), to 19 November (announced June), and to 10 December (announced 27 October), citing work on nine platform versions while staff worked from home."
        },
        {
          "name": "Launch",
          "planned_start": "2020-04-16",
          "planned_end": "2020-04-16",
          "actual_start": "2020-12-10",
          "actual_end": "2020-12-10",
          "note": "Released on PC, PlayStation 4, Xbox One and Stadia; last-generation console versions had severe performance problems."
        },
        {
          "name": "Remediation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2020-12-18",
          "actual_end": "2023-09",
          "note": "Sony suspended sales on the PlayStation Store from 18 December 2020 until June 2021; next-generation console versions shipped 15 February 2022; Update 2.0 and the Phantom Liberty expansion arrived in September 2023."
        }
      ],
      "milestones": [
        {
          "name": "Game announced",
          "planned_date": null,
          "actual_date": "2012-05"
        },
        {
          "name": "Release",
          "planned_date": "2020-04-16",
          "actual_date": "2020-12-10"
        },
        {
          "name": "Over 13 million copies sold",
          "planned_date": null,
          "actual_date": "2020-12-20"
        },
        {
          "name": "PlayStation Store sales suspended",
          "planned_date": null,
          "actual_date": "2020-12-18"
        },
        {
          "name": "Returns to PlayStation Store",
          "planned_date": null,
          "actual_date": "2021-06"
        }
      ],
      "headline": "Cyberpunk 2077 slipped three times from April to December 2020 on a PLN 1.2 billion budget, then was pulled from the PlayStation Store eight days after launch.",
      "summary": "CD Projekt announced Cyberpunk 2077 in May 2012 and began full production after The Witcher 3. At E3 2019 it set a release date of 16 April 2020. The game slipped three times, to 10 December 2020, as the studio prepared versions for nine platforms. It launched with serious bugs on older consoles, and Sony suspended PlayStation Store sales on 18 December 2020. CD Projekt reported more than 13 million copies sold by 20 December and later disclosed total development and marketing costs of about PLN 1.2 billion.",
      "what_went_wrong_or_right": "The studio committed to a public date at E3 2019 and then announced three delays, each close to the previous date: in January 2020 to September, in June to November, and on 27 October to December, after the game had reportedly gone gold. CD Projekt said it had to prepare and test nine versions across current-generation, next-generation and PC platforms while working from home during the pandemic. The plan to ship on PlayStation 4 and Xbox One alongside more powerful hardware was the central technical risk; those versions launched with poor performance, and Sony removed the game from its store from 18 December 2020 until June 2021. Staff had been asked to work six-day weeks in the final months. Commercially the launch succeeded: CD Projekt said on 11 December 2020 that pre-order royalties alone exceeded total development and marketing costs incurred or expected for 2020, and it reported over 13 million copies sold, net of refunds, by 20 December. Investor suits ended in a $1.85 million settlement.",
      "lessons": [
        "Do not announce a release date until content is complete and every platform version is tested.",
        "Scope platforms to hardware that can run the product; drop weak targets early.",
        "Repeated short delays signal an unrealistic plan; reset once with margin instead."
      ],
      "fun_fact": "CD Projekt said pre-order royalties exceeded the game's total development and marketing costs a day after launch (current report no. 65/2020, 11 December 2020).",
      "method_tags": [
        "iterative",
        "big_bang"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "scrum-1995",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Current report no. 67/2020: Disclosure of estimated sales of Cyberpunk 2077",
          "publisher": "CD Projekt S.A.",
          "url": "https://www.cdprojekt.com/en/investors/regulatory-announcements/current-report-no-67-2020/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Current report no. 65/2020: Estimated return on investments related to Cyberpunk 2077",
          "publisher": "CD Projekt S.A.",
          "url": "https://www.cdprojekt.com/en/investors/regulatory-announcements/current-report-no-65-2020/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Development of Cyberpunk 2077",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Development_of_Cyberpunk_2077",
          "accessed": "2026-10-25"
        },
        {
          "title": "How much money CD Projekt invested in Cyberpunk 2077",
          "publisher": "AIN.ua",
          "url": "https://en.ain.ua/2021/04/26/how-much-money-cd-projekt-invested-in-cyberpunk2077",
          "accessed": "2026-10-25"
        },
        {
          "title": "'Cyberpunk 2077' is delayed again, this time to December 10th",
          "publisher": "Engadget",
          "url": "https://www.engadget.com/cyberpunk-2077-delay-december-10-173917295.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Cyberpunk 2077",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Cyberpunk_2077",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "CD Projekt never published a budget baseline, so planned_cost is null. Actual: about PLN 1.2 billion for development and marketing of the base game, disclosed with the 2020 financial statements on 22 April 2021 (reported by AIN.ua and Game World Observer; roughly 55% development, 45% marketing). I did not open the financial statements themselves. Wikipedia cites a later $436 million to $440 million including updates and DLC; Phantom Liberty alone cost PLN 370 million (current report 38/2023, via Game World Observer). Planned start is null because no production start was announced; actual start is the May 2012 announcement, with full production from late 2016. Planned end is the first announced release date, 16 April 2020 (E3 2019). Sony's store suspension date of 18 December 2020 comes from CD Projekt current report no. 66/2020 (listed on the company's 2020 announcement index). The 'gone gold' and six-day-week details come from press and Wikipedia. FX: about 3.90 PLN per USD 2020 annual average (NBP/Fed-equivalent), so about 0.2566 USD per PLN; not re-verified from an opened table.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 59,
      "slug": "denver-airport-baggage-system",
      "name": "Denver International Airport automated baggage system",
      "short_name": "Denver baggage system",
      "category": "software_it",
      "subcategory": "airport automation",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Denver",
      "lat": 39.8561,
      "lng": -104.6737,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1992-04",
      "planned_end": "1993-10",
      "actual_start": "1992-04",
      "actual_end": "1995-02-28",
      "actual_is_forecast": false,
      "planned_duration_months": 18,
      "actual_duration_months": 34.4,
      "delay_months": 16.4,
      "delay_pct": 91.3,
      "planned_cost": 175600000,
      "actual_cost": 250000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        228000000,
        250000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1992,
      "cost_year": 1995,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 175600000,
      "cost_usd_nominal": 250000000,
      "planned_cost_usd_today": 402876452,
      "cost_usd_today": 528226687,
      "overrun_usd_today": 157200262,
      "overrun_pct": 42.4,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Contract and design",
          "planned_start": "1992-04",
          "planned_end": null,
          "actual_start": "1992-04",
          "actual_end": "1992-12",
          "note": "BAE Automated Systems contract signed for $175.6 million after an airport-wide system was added late; airport construction was already under way. Continental's sorter and extra maintenance tracks were added in 1992."
        },
        {
          "name": "Build and installation",
          "planned_start": "1992-04",
          "planned_end": "1993-10",
          "actual_start": "1992-04",
          "actual_end": "1994-04",
          "note": "Airport opening slipped from October 1993 to December 1993, then 9 March 1994, then 15 May 1994."
        },
        {
          "name": "Testing and failed demonstration",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1994-04",
          "actual_end": "1994-08",
          "note": "A failed demonstration for reporters in April 1994 led to an indefinite delay. Tests showed bags misloaded, misrouted or thrown from telecarts (GAO)."
        },
        {
          "name": "Backup conventional system",
          "planned_start": "1994-08",
          "planned_end": "1995-01-15",
          "actual_start": "1994-08",
          "actual_end": "1995-02",
          "note": "A conventional tug-and-cart system costing over $51 million was built alongside the automated one (GAO)."
        },
        {
          "name": "Airport opening",
          "planned_start": "1993-10",
          "planned_end": "1993-10",
          "actual_start": "1995-02-28",
          "actual_end": "1995-02-28",
          "note": "DIA opened 16 months late with only parts of the automated system working, mainly for United."
        },
        {
          "name": "Limited operation and abandonment",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1995-02-28",
          "actual_end": "2005-06-07",
          "note": "United announced in June 2005 that it would replace the system with a manual one, saving about $1 million a month."
        }
      ],
      "milestones": [
        {
          "name": "BAE contract signed",
          "planned_date": null,
          "actual_date": "1992-04"
        },
        {
          "name": "Failed press demonstration",
          "planned_date": null,
          "actual_date": "1994-04"
        },
        {
          "name": "Backup system announced",
          "planned_date": null,
          "actual_date": "1994-08"
        },
        {
          "name": "Airport opens",
          "planned_date": "1993-10",
          "actual_date": "1995-02-28"
        },
        {
          "name": "United abandons system",
          "planned_date": null,
          "actual_date": "2005-06-07"
        }
      ],
      "headline": "A baggage system signed at $175.6 million delayed Denver's new airport by 16 months and was scrapped by United in 2005.",
      "summary": "Denver International Airport planned an airport-wide automated baggage system in which computer-controlled telecarts would move bags along tracks under the terminals. BAE Automated Systems signed a $175.6 million contract in 1992, after airport construction had started. Tests failed repeatedly, the airport opening slipped four times from October 1993, and the city built a conventional backup system for over $51 million. DIA opened on 28 February 1995 with only part of the system working. United abandoned it in 2005.",
      "what_went_wrong_or_right": "The system was added late: the airport was already under construction when Denver sought bids for an airport-wide system in 1992, and none of the three bidders' proposals was judged suitable, so the city went directly to BAE. Scope grew after signing, including Continental's requested sorter and extra maintenance tracks. The schedule left little time for a technology never built at this scale. GAO's 1994 briefing documented specific failures: a photo eye that could not detect piled bags, software that lost track of which telecarts were loaded after a jam, and conveyors not synchronized with telecarts, so bags fell between them. A failed demonstration for reporters in April 1994 forced an indefinite delay. GAO estimated the total cost of the delayed opening at about $360 million and the monthly deficit at $18 million to $19 million. The decision to build a $51 million conventional backup allowed the airport to open.",
      "lessons": [
        "Do not add a novel, critical subsystem after the main build has started.",
        "Prototype and test at scale before committing the opening date to unproven technology.",
        "Fund a fallback early when a single subsystem can block the whole program."
      ],
      "fun_fact": "United kept paying about $60 million a year under its lease for the system even after deciding in 2005 to abandon it (NBC News).",
      "method_tags": [
        "fast_track",
        "big_bang"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "New Denver Airport: Impact of the Delayed Baggage System (GAO/RCED-95-35BR)",
          "publisher": "U.S. General Accounting Office (via govinfo.gov)",
          "url": "https://govinfo.gov/content/pkg/GAOREPORTS-RCED-95-35BR/html/GAOREPORTS-RCED-95-35BR.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Denver International Airport baggage system case timeline (chapter 6)",
          "publisher": "ANU Press",
          "url": "https://press.anu.edu.au/downloads/press/p128271/mobile/ch06s08.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "United abandons Denver baggage system",
          "publisher": "NBC News / Associated Press",
          "url": "https://www.nbcnews.com/id/wbna8135924",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the $175.6 million BAE contract signed in 1992 (ANU Press case timeline; that source's table lists April 1992 but places it out of sequence with December 1992 entries, so the exact month is uncertain; Westword reports May 1992). GAO's 1994 briefing gives the contract as $193 million (likely after change orders) plus about $35 million of modifications, which is the low end of the actual range ($228 million). NBC/AP (2005) gives $250 million to build; it also reports the city spent another $100 million on construction and $341 million in interest, which are excluded here. The separate conventional backup system (over $51 million) is also excluded. Planned end is the original airport opening date of October 1993 (GAO), as the baggage system was required for opening. Actual end is the airport opening on 28 February 1995; the system then ran in limited form until United's June 2005 decision. USD, fx = 1.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 60,
      "slug": "fbi-virtual-case-file",
      "name": "FBI Virtual Case File (Trilogy User Applications Component)",
      "short_name": "FBI Virtual Case File",
      "category": "software_it",
      "subcategory": "case management software",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Washington, D.C.",
      "lat": 38.8951,
      "lng": -77.0249,
      "era": "2000-2014",
      "status": "cancelled",
      "outcome": "cancelled",
      "planned_start": "2001-06",
      "planned_end": "2004-06",
      "actual_start": "2001-06",
      "actual_end": "2005-04",
      "actual_is_forecast": false,
      "planned_duration_months": 36,
      "actual_duration_months": 46,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": 119200000,
      "actual_cost": 170000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2001,
      "cost_year": 2005,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 119200000,
      "cost_usd_nominal": 170000000,
      "planned_cost_usd_today": 216737455,
      "cost_usd_today": 280243653,
      "overrun_usd_today": 83743398,
      "overrun_pct": 42.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": 170000000,
      "rebaseline_cost_year": null,
      "rebaseline_end": "2003-12",
      "rebaseline_label": "revised UAC plan (DOJ OIG audit 05-07)",
      "rebaseline_overrun_pct": 0,
      "rebaseline_delay_months": 16,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Contract award and requirements",
          "planned_start": "2001-06",
          "planned_end": null,
          "actual_start": "2001-06",
          "actual_end": "2002-12",
          "note": "SAIC won the cost-plus User Applications Component in June 2001. In December 2001 the scope expanded to replace all prior applications and the deadline was pulled forward to December 2003. Congress approved $123 million more for Trilogy in December 2002."
        },
        {
          "name": "Design and build",
          "planned_start": "2001-06",
          "planned_end": "2004-06",
          "actual_start": "2002",
          "actual_end": "2003-12",
          "note": "Requirements were poorly defined and evolved slowly; design changed after the FBI refocused on counterterrorism (DOJ OIG)."
        },
        {
          "name": "Delivery 1 and acceptance testing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2003-12",
          "actual_end": "2004-06",
          "note": "SAIC delivered the first version in December 2003; the FBI did not accept it, finding it was not a functional system."
        },
        {
          "name": "Initial Operational Capability pilot and review",
          "planned_start": "2004-06",
          "planned_end": "2005-03",
          "actual_start": "2004-06",
          "actual_end": "2005-01",
          "note": "Two-track plan announced June 2004; the FBI paid SAIC $16 million more and commissioned a $2 million Aerospace Corporation review, which was largely negative."
        },
        {
          "name": "Cancellation and replacement",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2005-03",
          "actual_end": "2005-04",
          "note": "Sentinel announced March 2005; VCF formally abandoned April 2005. Sentinel went into agency-wide use on 1 July 2012."
        }
      ],
      "milestones": [
        {
          "name": "SAIC contract awarded",
          "planned_date": null,
          "actual_date": "2001-06"
        },
        {
          "name": "VCF delivery 1",
          "planned_date": "2003-12",
          "actual_date": "2003-12"
        },
        {
          "name": "UAC completion",
          "planned_date": "2004-06",
          "actual_date": null
        },
        {
          "name": "VCF abandoned",
          "planned_date": null,
          "actual_date": "2005-04"
        },
        {
          "name": "Successor Sentinel in agency-wide use",
          "planned_date": null,
          "actual_date": "2012-07-01"
        }
      ],
      "headline": "The FBI's Virtual Case File grew from a $119.2 million plan to $170 million and was abandoned in 2005 without going into service.",
      "summary": "The Virtual Case File was the software part of the FBI's Trilogy modernization, meant to replace the paper-heavy Automated Case Support system with electronic case files. SAIC began work in June 2001 under a cost-plus contract. After the September 2001 attacks the FBI expanded the scope and pulled the deadline forward to December 2003. The first delivery that month was rejected as non-functional. After a negative independent review, the FBI abandoned VCF in April 2005, having allocated $170 million, and started the Sentinel program.",
      "what_went_wrong_or_right": "The Justice Department Inspector General attributed the failure to poorly defined and slowly evolving design requirements, design changes after the FBI refocused on terrorism prevention, a lack of management continuity and oversight, weak contracting, weak IT investment management, and the absence of an enterprise architecture. The program changed scope late: in December 2001 VCF was expanded to replace all existing applications while the deadline was moved earlier, to December 2003. SAIC worked under a cost-plus contract, which gave the contractor little incentive to resist scope changes. The December 2003 delivery did not meet the FBI's requirements, and an Aerospace Corporation review in 2004 was largely negative. The OIG concluded that the successor system was unlikely to benefit substantially from the three years and $170 million spent on VCF. The infrastructure parts of Trilogy, by contrast, were completed in April 2004, close to their May 2004 target.",
      "lessons": [
        "Freeze core requirements before build, or fund an explicit change process with schedule relief.",
        "Do not expand scope and shorten the deadline at the same time.",
        "Keep stable program leadership; turnover erodes ownership of requirements and decisions.",
        "Commission independent reviews early, before sunk costs drive decisions."
      ],
      "fun_fact": "The Trilogy infrastructure upgrades, delivered by a separate contractor, finished in April 2004, slightly ahead of their May 2004 target, while the VCF software never went live (DOJ OIG).",
      "method_tags": [
        "waterfall",
        "cost_plus",
        "big_bang"
      ],
      "related_history_ids": [
        "waterfall-1970",
        "agile-manifesto-2001",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "The Federal Bureau of Investigation's Management of the Trilogy Information Technology Modernization Project (Audit Report 05-07), Executive Summary",
          "publisher": "U.S. Department of Justice Office of the Inspector General",
          "url": "https://oig.justice.gov/archives/reports/FBI/a0507/exec.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Virtual Case File",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Virtual_Case_File",
          "accessed": "2026-10-25"
        },
        {
          "title": "Senators fume as FBI admits Trilogy foul-ups",
          "publisher": "Washington Technology",
          "url": "https://www.washingtontechnology.com/2005/02/senators-fume-as-fbi-admits-trilogy-foul-ups/328923",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "high",
      "notes": "Scope is the VCF only (Trilogy's User Applications Component, UAC). Baseline: DOJ OIG audit 05-07 lists the UAC original plan at $119.2 million within an original 3-year, $379.8 million Trilogy project; current plan $170.0 million. Total Trilogy funding reached $581.1 million, which is excluded. Planned end June 2004 is the original UAC target in the OIG report; the deadline was later accelerated to December 2003. Actual end is the April 2005 abandonment (cancellation date), per Wikipedia; Washington Technology reported from the 3 February 2005 Senate hearing that the bureau had probably wasted about $104 million (press figure, not OIG). USD, fx = 1. Baseline audit 2026-10-25: Planned figures unchanged (original UAC plan, $119.2m, June 2004). Added the OIG current plan of $170.0m and the accelerated December 2003 deadline as the rebaseline; the year of the revision is not stated.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 61,
      "slug": "healthcare-gov",
      "name": "HealthCare.gov launch (Federally Facilitated Marketplace)",
      "short_name": "HealthCare.gov",
      "category": "software_it",
      "subcategory": "e-government",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Baltimore (CMS headquarters, Woodlawn, Maryland)",
      "lat": 39.317,
      "lng": -76.741,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2011-09",
      "planned_end": "2013-10-01",
      "actual_start": "2011-09",
      "actual_end": "2013-12",
      "actual_is_forecast": false,
      "planned_duration_months": 24.5,
      "actual_duration_months": 27,
      "delay_months": 2.5,
      "delay_pct": 10,
      "planned_cost": 93700000,
      "actual_cost": 209000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2011,
      "cost_year": 2014,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 93700000,
      "cost_usd_nominal": 209000000,
      "planned_cost_usd_today": 134104660,
      "cost_usd_today": 284238825,
      "overrun_usd_today": 156807352,
      "overrun_pct": 123.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Requirements and contracting",
          "planned_start": "2010-03",
          "planned_end": "2011-09",
          "actual_start": "2010-03",
          "actual_end": "2011-12",
          "note": "ACA signed March 2010 required marketplaces by 1 January 2014. CMS issued the FFM task order in September 2011 before key requirements, such as how many states would join, were known (GAO-14-694). CGI announced the award on 1 December 2011."
        },
        {
          "name": "Design and build",
          "planned_start": "2011-09",
          "planned_end": "2013-03",
          "actual_start": "2011-09",
          "actual_end": "2013-09",
          "note": "Changing requirements and late CMS decisions drove rework. FFM obligations grew from $56 million to more than $209 million by February 2014."
        },
        {
          "name": "Readiness testing",
          "planned_start": "2013-03",
          "planned_end": "2013-03",
          "actual_start": "2013-09",
          "actual_end": "2013-09",
          "note": "The FFM readiness assessment planned for March 2013 slipped to September 2013, weeks before launch (GAO)."
        },
        {
          "name": "Launch",
          "planned_start": "2013-10-01",
          "planned_end": "2013-10-01",
          "actual_start": "2013-10-01",
          "actual_end": "2013-10-01",
          "note": "Open enrollment began on schedule; users met outages and malfunctions."
        },
        {
          "name": "Remediation (tech surge)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2013-10",
          "actual_end": "2013-12",
          "note": "CMS and contractors restored the site for high consumer use within about two months (HHS OIG)."
        },
        {
          "name": "Re-procurement of FFM",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2014-01",
          "actual_end": "2014-06",
          "note": "Replacement FFM contract awarded January 2014 at $91 million; costs grew to over $175 million by June 2014 (GAO)."
        }
      ],
      "milestones": [
        {
          "name": "CGI Federal FFM contract announced",
          "planned_date": null,
          "actual_date": "2011-12-01"
        },
        {
          "name": "Open enrollment opens",
          "planned_date": "2013-10-01",
          "actual_date": "2013-10-01"
        },
        {
          "name": "Site restored for high consumer use",
          "planned_date": null,
          "actual_date": "2013-12"
        },
        {
          "name": "Replacement FFM contract awarded",
          "planned_date": null,
          "actual_date": "2014-01"
        }
      ],
      "headline": "A federal marketplace contract estimated at $93.7 million had $209 million obligated by February 2014, and the site crashed on launch day.",
      "summary": "HealthCare.gov is the federal health insurance marketplace that the Affordable Care Act required by January 2014. CMS hired CGI Federal in 2011 to build the Federally Facilitated Marketplace (FFM), with an estimated contract value of $93.7 million. The site opened on 1 October 2013 as planned but suffered outages and errors that blocked most users. A two-month tech surge made it usable by December 2013. By February 2014, more than $209 million had been obligated for the FFM alone.",
      "what_went_wrong_or_right": "GAO found that CMS issued the FFM and data hub task orders when key technical requirements were unknown, including the number of states that would use the federal marketplace and the number of likely enrollees. It used cost-reimbursement contracts, so it paid allowable costs whether or not the system was finished. Requirements kept changing, governance reviews were postponed, the readiness assessment moved from March to September 2013, and required approvals were not obtained before launch. CMS also chose not to withhold fees, putting the launch date first. The HHS Inspector General named the absence of clear leadership as the most critical problem, along with too much focus on policy and too little on technology, poor contract management, and staying on a failing course despite warnings. The recovery worked because CMS and contractors formed one team without status distinctions and applied ruthless prioritization to the most important fixes.",
      "lessons": [
        "Do not let contracts start before core requirements, such as user volumes and scope, are known.",
        "Name one accountable leader who has authority over both policy and technology decisions.",
        "Protect end-to-end testing time; a fixed launch date should cut scope, not testing.",
        "During recovery, triage ruthlessly and run one team across agency and contractor lines."
      ],
      "fun_fact": "CMS paid the FFM contractor only $12.5 million in fees and withheld about $267,000, roughly 2 percent, despite the troubled launch (GAO-14-694).",
      "method_tags": [
        "big_bang",
        "waterfall",
        "cost_plus"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "agile-manifesto-2001",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Healthcare.gov: Ineffective Planning and Oversight Practices Underscore the Need for Improved Contract Management (GAO-14-694)",
          "publisher": "U.S. Government Accountability Office",
          "url": "https://www.gao.gov/products/gao-14-694",
          "accessed": "2026-10-25"
        },
        {
          "title": "HealthCare.gov: CMS Management of the Federal Marketplace (OEI-06-14-00350)",
          "publisher": "HHS Office of Inspector General",
          "url": "https://oig.hhs.gov/oei/reports/oei-06-14-00350.asp",
          "accessed": "2026-10-25"
        },
        {
          "title": "An Overview of 60 Contracts That Contributed to the Development and Operation of the Federal Marketplace",
          "publisher": "HHS Office of Inspector General",
          "url": "https://oig.hhs.gov/reports/all/2014/an-overview-of-60-contracts-that-contributed-to-the-development-and-operation-of-the-federal-marketplace",
          "accessed": "2026-10-25"
        },
        {
          "title": "CGI selected to build US-wide competitive health insurance exchange",
          "publisher": "CGI",
          "url": "https://www.cgi.com/en/CGI-selected-build-US-wide-competitive-health-insurance-exchange",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Scope here is the FFM (the core HealthCare.gov system), not the whole marketplace. Baseline: CGI Federal's announced estimated total contract value of $93.7 million (December 2011; $55.7 million base plus three one-year options). Actual: GAO-14-694 reports FFM obligations of more than $209 million by February 2014; this excludes the data hub (nearly $85 million obligated) and the replacement FFM contract (over $175 million by June 2014). HHS OIG reports the 60 marketplace-related contracts had original estimated values of $1.7 billion, with nearly $800 million obligated and nearly $500 million paid by February 2014; the $1.7 billion figure is often misreported as spending. Planned phase dates for build and testing derive from the GAO account of the March 2013 readiness assessment; other planned phase dates were not published. Actual end is the restoration of service around December 2013 (OIG: within two months). USD, so fx = 1.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 62,
      "slug": "nhs-npfit",
      "name": "NHS National Programme for IT (NPfIT)",
      "short_name": "NHS NPfIT",
      "category": "software_it",
      "subcategory": "health records / e-government",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "Leeds (NHS Connecting for Health)",
      "lat": 53.796,
      "lng": -1.548,
      "era": "2000-2014",
      "status": "cancelled",
      "outcome": "cancelled",
      "planned_start": "2002-10",
      "planned_end": "2010",
      "actual_start": "2002-10",
      "actual_end": "2011-09-09",
      "actual_is_forecast": false,
      "planned_duration_months": 92.5,
      "actual_duration_months": 106.8,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": 2300000000,
      "actual_cost": 9800000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "GBP",
      "planned_cost_year": 2002,
      "cost_year": 2013,
      "planned_fx_to_usd": 1.5016,
      "actual_fx_to_usd": 1.5646,
      "planned_cost_usd_nominal": 3454600000,
      "cost_usd_nominal": 15327200000,
      "planned_cost_usd_today": 6183765957,
      "cost_usd_today": 21184380000,
      "overrun_usd_today": 16212535714,
      "overrun_pct": 326.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": 12400000000,
      "rebaseline_cost_year": 2006,
      "rebaseline_end": null,
      "rebaseline_label": "June 2006 NAO ten-year estimate",
      "rebaseline_overrun_pct": -21,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Strategy and procurement",
          "planned_start": "2002-06",
          "planned_end": "2004-01",
          "actual_start": "2002-06",
          "actual_end": "2004-01",
          "note": "Strategy 'Delivering 21st Century IT Support for the NHS' published summer 2002; programme set up October 2002; spine and five regional cluster contracts awarded December 2003 to January 2004."
        },
        {
          "name": "National systems (Spine and services)",
          "planned_start": "2004-01",
          "planned_end": null,
          "actual_start": "2004-01",
          "actual_end": "2011-09",
          "note": "National infrastructure delivered in parts; NHS Connecting for Health formed April 2005."
        },
        {
          "name": "Local care records deployment",
          "planned_start": "2004-01",
          "planned_end": "2010",
          "actual_start": "2004-01",
          "actual_end": "2011-09",
          "note": "Target was an electronic care record for every patient by 2010. By 2011 only 4 of 97 planned acute trust systems had been delivered in the North, Midlands and East (NAO)."
        },
        {
          "name": "Supplier exits and contract resets",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2006-09",
          "actual_end": "2008-05",
          "note": "Accenture withdrew in September 2006 (handover to CSC January 2007); Fujitsu's Southern cluster contract was terminated in May 2008."
        },
        {
          "name": "Dismantling and residual contracts",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2011-09-09",
          "actual_end": "2016",
          "note": "Department of Health announced dismantling on 9 September 2011; component programmes and the CSC contract continued to at least 2016."
        }
      ],
      "milestones": [
        {
          "name": "Spine and cluster contracts awarded",
          "planned_date": null,
          "actual_date": "2004-01"
        },
        {
          "name": "Accenture withdraws",
          "planned_date": null,
          "actual_date": "2006-09"
        },
        {
          "name": "Fujitsu Southern contract terminated",
          "planned_date": null,
          "actual_date": "2008-05"
        },
        {
          "name": "Electronic care record for every patient",
          "planned_date": "2010",
          "actual_date": null
        },
        {
          "name": "Programme dismantling announced",
          "planned_date": null,
          "actual_date": "2011-09-09"
        }
      ],
      "headline": "England's NHS IT programme started with a £2.3 billion three-year budget and was dismantled in 2011 with a forecast cost of £9.8 billion.",
      "summary": "The National Programme for IT was launched in 2002 to give every NHS patient in England an electronic care record by 2010, linked through a national Spine. The Department of Health let large regional contracts to Accenture, BT, CSC and Fujitsu in 2003 and 2004. Local systems arrived late and in small numbers, two of the main suppliers left, and the government announced the programme's dismantling in September 2011. The Public Accounts Committee reported in 2013 that the Department's forecast cost was £9.8 billion.",
      "what_went_wrong_or_right": "The programme tried to replace hospital and GP systems across England through a few very large, centrally negotiated regional contracts, with local NHS trusts having little say in the systems they would receive. The care records software, notably iSoft's Lorenzo in the North, Midlands and East, ran years late; the NAO found in 2011 that only 4 of 97 planned systems had reached acute trusts there in seven years, and that the number of systems was cut sharply without a matching cut in cost. Supplier failure followed: Accenture withdrew in 2006 and Fujitsu's contract was terminated in 2008, with the termination dispute generating £31.5 million of legal costs. Benefits were thin; the Department reported £3.7 billion of benefits to March 2012, about half the costs incurred. The PAC said the £9.8 billion forecast omitted future Lorenzo costs and Fujitsu termination costs. National infrastructure such as the Spine was delivered and continued in use.",
      "lessons": [
        "Involve the end users who must adopt a system in choosing and specifying it.",
        "Avoid concentrating national delivery in a few huge contracts that cannot easily be exited.",
        "Tie payments and scope reductions together: fewer systems delivered should mean lower cost.",
        "Measure benefits from the start, not after the programme is dismantled."
      ],
      "fun_fact": "The PAC reported in 2013 that terminating Fujitsu's contract had produced £31.5 million in legal costs over four years (The Register).",
      "method_tags": [
        "big_bang",
        "waterfall",
        "fixed_price"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "prince2-1996",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "NHS Connecting for Health",
          "publisher": "Wikipedia (citing NAO 2006 and PAC 2009 and 2011 reports)",
          "url": "https://en.wikipedia.org/wiki/NHS_Connecting_for_Health",
          "accessed": "2026-10-25"
        },
        {
          "title": "The National Programme for IT in the NHS: an update on the delivery of detailed care records systems",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/reports/the-national-programme-for-it-in-the-nhs-an-update-on-the-delivery-of-detailed-care-records-systems/",
          "accessed": "2026-10-25"
        },
        {
          "title": "MPs sceptical that Hunt's paperless NHS plan will be on time and budget",
          "publisher": "The Register",
          "url": "https://www.theregister.com/2013/09/18/mps_sceptical_that_hunts_paperless_nhs_plan_will_be_on_time_and_budget/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Healthcare IT in Britain: NHS National Programme for IT (NPfIT)",
          "publisher": "HealthManagement.org",
          "url": "https://healthmanagement.org/c/it/issuearticle/healthcare-it-in-britain-nhs-national-programme-for-it-npfit",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the initial budget of £2.3 billion over three years (2002, confirmed by the Department of Health in January 2003); it covered only the first three years, not the full ten-year programme, so the overrun versus it is overstated. The NAO's June 2006 figure of £12.4 billion over ten years is a later, broader estimate; officials quoted in the press suggested up to £20 billion. Actual: Department of Health total forecast cost of £9.8 billion, cited by the Public Accounts Committee on 18 September 2013; the PAC said the true total was likely to exceed £10 billion. The PAC parliament pages returned errors, so the figure is sourced from The Register's report of the committee. Planned end 2010 is the target for every patient having an electronic care record. Actual end is the 9 September 2011 dismantling announcement (cancellation date); residual contracts ran to at least 2016. FX: Federal Reserve G.5A annual averages, USD per GBP: 2002 about 1.5016, 2013 about 1.5646 (2002 and 2013 values from Fed historical series; not re-verified from an opened annual table). Baseline audit 2026-10-25: Planned figures unchanged (2002 GBP 2.3bn is the first announced). Added the NAO June 2006 estimate of GBP 12.4 billion over ten years as the rebaseline.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 63,
      "slug": "phoenix-pay-system",
      "name": "Phoenix pay system (Government of Canada)",
      "short_name": "Phoenix pay system",
      "category": "software_it",
      "subcategory": "public-sector payroll",
      "country": "Canada",
      "country_code": "CA",
      "countries": [
        "Canada"
      ],
      "continent": "North America",
      "city": "Miramichi, New Brunswick (Public Service Pay Centre)",
      "lat": 47.0283,
      "lng": -65.507,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2009-07",
      "planned_end": "2015",
      "actual_start": "2009-07",
      "actual_end": "2016-04-21",
      "actual_is_forecast": false,
      "planned_duration_months": 71.5,
      "actual_duration_months": 81.2,
      "delay_months": 9.7,
      "delay_pct": 13.5,
      "planned_cost": 309000000,
      "actual_cost": 5100000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        5000000000,
        5100000000
      ],
      "cost_currency": "CAD",
      "planned_cost_year": 2009,
      "cost_year": 2025,
      "planned_fx_to_usd": 0.876,
      "actual_fx_to_usd": 0.7157,
      "planned_cost_usd_nominal": 270776700,
      "cost_usd_nominal": 3650070000,
      "planned_cost_usd_today": 406354052,
      "cost_usd_today": 3650070000,
      "overrun_usd_today": 3428918700,
      "overrun_pct": 1550.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Business case and approval",
          "planned_start": "2009-07",
          "planned_end": "2009-07",
          "actual_start": "2009-07",
          "actual_end": "2011-06",
          "note": "Cabinet approved the Transformation of Pay Administration initiative in July 2009 at about $309 million, with expected savings of about $70 million a year. The Miramichi pay centre was announced in August 2010."
        },
        {
          "name": "Contract and build",
          "planned_start": "2011-06",
          "planned_end": "2015",
          "actual_start": "2011-06",
          "actual_end": "2016-02",
          "note": "IBM won a sole-source contract in June 2011 to configure PeopleSoft; the original contract was $5.7 million, and IBM was eventually paid $185 million. The system was expected online by 2015."
        },
        {
          "name": "Go-live wave 1",
          "planned_start": null,
          "planned_end": "2015",
          "actual_start": "2016-02-24",
          "actual_end": "2016-02-24",
          "note": "34 departments and agencies, about 120,000 employees."
        },
        {
          "name": "Go-live wave 2",
          "planned_start": null,
          "planned_end": "2015",
          "actual_start": "2016-04-21",
          "actual_end": "2016-04-21",
          "note": "Remaining 67 departments and agencies. The system went live without critical pay functions, full testing or an adequate contingency plan (Auditor General, 2018)."
        },
        {
          "name": "Stabilization and backlog remediation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2016-04",
          "actual_end": "2025-03",
          "note": "Costs rose from about $400 million (May 2017) to $954 million spent by July 2018; the government targeted clearing the existing backlog by March 2025. Errors continued into 2026."
        },
        {
          "name": "Replacement (Dayforce)",
          "planned_start": "2025-06",
          "planned_end": null,
          "actual_start": "2025-06",
          "actual_end": null,
          "note": "Ten-year, $350.6 million contract awarded to Ceridian (Dayforce) in June 2025; implementation set to begin in 2027."
        }
      ],
      "milestones": [
        {
          "name": "Cabinet funding approval",
          "planned_date": null,
          "actual_date": "2009-07"
        },
        {
          "name": "IBM contract awarded",
          "planned_date": null,
          "actual_date": "2011-06"
        },
        {
          "name": "Full implementation",
          "planned_date": "2015",
          "actual_date": "2016-04-21"
        },
        {
          "name": "Auditor General report on building Phoenix",
          "planned_date": null,
          "actual_date": "2018-05-29"
        },
        {
          "name": "Dayforce replacement contract",
          "planned_date": null,
          "actual_date": "2025-06"
        }
      ],
      "headline": "Approved at about C$309 million to save money on federal pay, Phoenix has cost an estimated C$5.1 billion to launch and fix.",
      "summary": "Phoenix was meant to modernize pay for Canada's federal public service by replacing a 40-year-old system and centralizing pay staff in Miramichi, New Brunswick. Cabinet approved about $309 million in 2009, expecting savings of about $70 million a year. IBM configured PeopleSoft software, and the system went live in two waves in February and April 2016. Hundreds of thousands of employees were then overpaid, underpaid or not paid. A federal official put total spending at about $5.1 billion in 2025, and a replacement is being procured.",
      "what_went_wrong_or_right": "The Auditor General called Phoenix an incomprehensible failure of project management and oversight. The 2018 audit found that Phoenix executives put schedule and budget ahead of functionality and security, and that their decision to launch was unreasonable given the information available. The system went live without critical pay processing functions, without full testing, with significant security weaknesses and without an adequate contingency plan. Warnings from the Miramichi pay centre and from departments were not heeded. The project had a detailed management structure but no independent oversight, and appeared set up to avoid responsibility. Contract scope also proved badly underestimated: IBM's original contract was $5.7 million but it was eventually paid $185 million. Costs then moved from building to repairing: about $400 million by May 2017, $954 million spent by July 2018, and an estimated $5.1 billion by 2025, against planned savings of about $70 million a year.",
      "lessons": [
        "Never cut testing or core functions to hold a go-live date for payroll.",
        "Keep a working contingency, such as the legacy system, until the new one has proved it pays correctly.",
        "Appoint independent oversight with the authority to stop a launch.",
        "Pilot with one department before switching over 100 organizations."
      ],
      "fun_fact": "IBM's original Phoenix contract was worth $5.7 million; it was eventually paid $185 million (Wikipedia, citing government figures).",
      "method_tags": [
        "big_bang",
        "waterfall",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Phoenix pay system",
          "publisher": "Wikipedia (citing Auditor General reports and Senate committee report)",
          "url": "https://en.wikipedia.org/wiki/Phoenix_pay_system",
          "accessed": "2026-10-25"
        },
        {
          "title": "Auditor General Report on Phoenix Pay System an 'incomprehensible failure'",
          "publisher": "National Association of Federal Retirees",
          "url": "https://www.federalretirees.ca/?p=5751",
          "accessed": "2026-10-25"
        },
        {
          "title": "Phoenix pay errors continue to haunt public service a decade after launch",
          "publisher": "The Canadian Press via National Newswatch",
          "url": "https://nationalnewswatch.com/2026/03/03/phoenix-pay-errors-continue-to-haunt-public-service-a-decade-after-launch",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: Cabinet approval in July 2009 of the Transformation of Pay Administration initiative, about $309 million (Senate committee figure cited by Wikipedia; other reports give $309.2 million or $310 million). Actual: about $5.1 billion, the estimate a Public Services and Procurement Canada official (Alex Benay) gave in June 2025, reported by The Canadian Press; Canadian Press rounded to about $5 billion in March 2026. A November 2024 Senate answer gave $3.65 billion invested; figures differ in what they include (launch, stabilization, backlog, damages), so the cost is marked disputed and is still rising. The Auditor General's 2018 report (Report 1, Spring 2018) could not be opened (the OAG URL returned 404); its findings are taken from the Federal Retirees summary and Wikipedia. Planned end 2015: the system was expected online by 2015. Actual end is completion of wave 2 on 21 April 2016; remediation and replacement continue. FX: Federal Reserve G.5A, 2025 annual average 1.3973 CAD per USD, so 0.7157 USD per CAD (opened); 2009 average about 1.142 CAD per USD, so about 0.876 (Fed historical series, not re-verified from an opened table).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 64,
      "slug": "queensland-health-payroll",
      "name": "Queensland Health payroll system replacement",
      "short_name": "Queensland Health pay",
      "category": "software_it",
      "subcategory": "public-sector payroll",
      "country": "Australia",
      "country_code": "AU",
      "countries": [
        "Australia"
      ],
      "continent": "Oceania",
      "city": "Brisbane",
      "lat": -27.4705,
      "lng": 153.026,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "2007-12-05",
      "planned_end": null,
      "actual_start": "2007-12-05",
      "actual_end": "2010-03-14",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 27.3,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": 98000000,
      "actual_cost": 1250000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        1200000000,
        1250000000
      ],
      "cost_currency": "AUD",
      "planned_cost_year": 2007,
      "cost_year": 2012,
      "planned_fx_to_usd": 0.8391,
      "actual_fx_to_usd": 1.0355,
      "planned_cost_usd_nominal": 82231800,
      "cost_usd_nominal": 1295000000,
      "planned_cost_usd_today": 127682983,
      "cost_usd_today": 1816078417,
      "overrun_usd_today": 1673697869,
      "overrun_pct": 1175.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Shared Services Initiative",
          "planned_start": "2003-07-01",
          "planned_end": null,
          "actual_start": "2003-07-01",
          "actual_end": "2007-09",
          "note": "Whole-of-government shared services formally established 1 July 2003; CorpTech was given a $125 million capital budget. A March 2007 report found little progress."
        },
        {
          "name": "Procurement",
          "planned_start": "2007-09-12",
          "planned_end": "2007-12",
          "actual_start": "2007-09-12",
          "actual_end": "2007-12-05",
          "note": "Invitation to offer issued 12 September 2007; IBM signed a $98 million prime contract on 5 December 2007."
        },
        {
          "name": "Rescoping to interim Queensland Health payroll",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2008-07",
          "actual_end": "2008-10",
          "note": "The LATTICE payroll fell out of vendor support by 1 July 2008. By October 2008 IBM said it needed $181 million for the full scope; the state kept the contract at $98 million but limited it to an interim Queensland Health payroll."
        },
        {
          "name": "Build and testing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2008-10",
          "actual_end": "2010-03",
          "note": "SAP and Workbrain solution. Go-live was delayed more than ten times; no full parallel pay run was performed (KPMG)."
        },
        {
          "name": "Go-live",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2010-03-14",
          "actual_end": "2010-03-14",
          "note": "About 78,000 staff were paid inaccurately or not at all for months; over- and underpayments exceeded $300 million."
        },
        {
          "name": "Remediation and inquiry",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2010-03",
          "actual_end": "2013-07-31",
          "note": "Settlement with IBM and $209 million over three years announced 23 November 2010; KPMG in 2012 put the cost of fixing at least $1.25 billion over seven years; Commission of Inquiry reported 31 July 2013."
        }
      ],
      "milestones": [
        {
          "name": "IBM contract signed",
          "planned_date": null,
          "actual_date": "2007-12-05"
        },
        {
          "name": "Go-live",
          "planned_date": null,
          "actual_date": "2010-03-14"
        },
        {
          "name": "Government settlement with IBM and $209m fix plan",
          "planned_date": null,
          "actual_date": "2010-11-23"
        },
        {
          "name": "Commission of Inquiry report",
          "planned_date": null,
          "actual_date": "2013-07-31"
        }
      ],
      "headline": "A $98 million IBM contract produced a payroll that mispaid 78,000 health workers and was estimated in 2012 to cost at least $1.25 billion to fix.",
      "summary": "Queensland's shared services program planned a common payroll and HR system for state agencies. IBM won a $98 million prime contract in December 2007; the scope was narrowed in 2008 to an urgent replacement for Queensland Health's unsupported LATTICE payroll. The SAP and Workbrain system went live on 14 March 2010 after more than ten delays and incomplete testing. Thousands of the department's roughly 78,000 staff were overpaid, underpaid or unpaid. KPMG estimated in 2012 that fixing and running it would cost at least $1.25 billion.",
      "what_went_wrong_or_right": "The project grew out of a struggling whole-of-government Shared Services Initiative; a March 2007 report found CorpTech had made little progress while using many contractors. The prime contractor model failed within a year: by October 2008 IBM said it needed $181 million, almost twice the contract value, and the state cut the scope to an interim Queensland Health payroll while LATTICE was already out of vendor support, creating deadline pressure. The system went live in March 2010 although the vendor and the department knew it was unlikely to pay staff accurately. KPMG's review found that no full parallel pay run had been done, the technical infrastructure failed, staff were unfamiliar with the processes, and bottlenecks were not anticipated. Payroll staff were making about 200,000 manual entries a pay period by 2012. Commissioner Richard Chesterman's 2013 inquiry placed the project in the front rank of failures in public administration.",
      "lessons": [
        "Run full parallel pay runs before switching any payroll.",
        "Replace unsupported legacy systems before they force a rushed go-live.",
        "When a vendor asks to double the price, re-plan the scope and schedule, not only the contract."
      ],
      "fun_fact": "By mid-2012, payroll staff were making about 200,000 manual entries each pay period to correct the system (ABC News).",
      "method_tags": [
        "big_bang",
        "fixed_price"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "2010 Queensland Health payroll system implementation",
          "publisher": "Wikipedia (citing the Commission of Inquiry report, 31 July 2013)",
          "url": "https://en.wikipedia.org/wiki/2010_Queensland_Health_payroll_system_implementation",
          "accessed": "2026-10-25"
        },
        {
          "title": "Qld Health pay debacle to cost $1.2b",
          "publisher": "ABC News",
          "url": "https://www.abc.net.au/news/2012-06-06/qld-health-payroll-debacle-to-cost-1.2b/4056378",
          "accessed": "2026-10-25"
        },
        {
          "title": "More than $200m to fix health payroll system",
          "publisher": "ABC News",
          "url": "https://www.abc.net.au/news/2010-11-23/more-than-200m-to-fix-health-payroll-system/2347816",
          "accessed": "2026-10-25"
        },
        {
          "title": "Queensland Health",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Queensland_Health",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: IBM's $98 million prime contract of 5 December 2007, which originally covered whole-of-government shared services and was rescoped in 2008 to the interim Queensland Health payroll at the same price; the Queensland Health-specific original price is reported in the Commission of Inquiry report, but the inquiry website refused connections, so that figure was not verified. Total end-of-project delivery cost was $181 million (Wikipedia). Actual: KPMG's 2012 estimate, presented by Health Minister Lawrence Springborg, that fixing the system would cost at least $1.25 billion over about seven years (ABC News); Wikipedia gives about $1.2 billion over eight years to repair, maintain and operate. This total includes ongoing operations and remediation, so it is not like-for-like with the build contract; hence 'disputed'. Planned end is null: an original go-live date was not found in an opened source; go-live was delayed more than ten times. The inquiry quote is paraphrased. FX: USD per AUD, 2007 annual average about 0.8391 and 2012 about 1.0355 (Federal Reserve G.5A historical series; not re-verified from an opened table).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 65,
      "slug": "original-iphone",
      "name": "The original iPhone (Project Purple)",
      "short_name": "Original iPhone",
      "category": "software_it",
      "subcategory": "consumer device and operating system",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Cupertino, California",
      "lat": 37.3318,
      "lng": -122.0312,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": "2004",
      "planned_end": "2007-06",
      "actual_start": "2004",
      "actual_end": "2007-06-29",
      "actual_is_forecast": false,
      "planned_duration_months": 35.5,
      "actual_duration_months": 35.9,
      "delay_months": 0.5,
      "delay_pct": 1.3,
      "planned_cost": null,
      "actual_cost": 150000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": null,
      "cost_year": 2007,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": 150000000,
      "planned_cost_usd_today": null,
      "cost_usd_today": 232908040,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Team assembly and concept",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2004",
          "actual_end": "2005",
          "note": "Apple began assembling a confidential smartphone team in 2004 (Project Purple); Steve Jobs steered the focus from a tablet to a phone."
        },
        {
          "name": "Hardware and software development with Cingular",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2005",
          "actual_end": "2006-12",
          "note": "Developed in a secret collaboration with Cingular Wireless over about 30 months; a team of about 1,000 led by Tony Fadell, Scott Forstall and Jony Ive."
        },
        {
          "name": "Public announcement",
          "planned_start": "2007-01-09",
          "planned_end": "2007-01-09",
          "actual_start": "2007-01-09",
          "actual_end": "2007-01-09",
          "note": "Unveiled at Macworld San Francisco; Apple said US availability would be June 2007."
        },
        {
          "name": "Final engineering and production ramp",
          "planned_start": "2007-01",
          "planned_end": "2007-06",
          "actual_start": "2007-01",
          "actual_end": "2007-06",
          "note": "The device shown in January was not yet a finished product, according to Wired's later account."
        },
        {
          "name": "US launch and early sales",
          "planned_start": "2007-06",
          "planned_end": "2007-06",
          "actual_start": "2007-06-29",
          "actual_end": "2007-09-09",
          "note": "US launch on 29 June 2007; the one millionth iPhone was sold 74 days later."
        }
      ],
      "milestones": [
        {
          "name": "Macworld unveiling",
          "planned_date": null,
          "actual_date": "2007-01-09"
        },
        {
          "name": "US launch",
          "planned_date": "2007-06",
          "actual_date": "2007-06-29"
        },
        {
          "name": "One million iPhones sold",
          "planned_date": null,
          "actual_date": "2007-09-09"
        }
      ],
      "headline": "Apple met its own June 2007 launch promise for the iPhone, at a development cost an insider later put at about $150 million.",
      "summary": "Apple began building a confidential smartphone team in 2004, a project known internally as Purple. Working with Cingular Wireless, later AT&T Mobility, a team of about 1,000 people developed the hardware and a touch interface based on Mac OS X. Steve Jobs unveiled the iPhone on 9 January 2007 and promised US availability in June. It went on sale on 29 June 2007, and Apple sold its one millionth iPhone 74 days later. Apple has never disclosed the budget.",
      "what_went_wrong_or_right": "The schedule held where it was public: Apple announced a June 2007 ship date in January and launched on 29 June. Several decisions helped. Apple kept the work secret and inside a small group of senior staff, so plans could change without public cost. The Cingular deal let Apple design hardware and software in-house, a rare concession in the US carrier market at the time, in exchange for four years of exclusive US sales and a share of monthly service revenue. Leadership was concentrated in three named owners for hardware, software and design. The risks were real: Wired's 2008 account, summarized by Fortune, described a demo a few months before Macworld that went badly enough for Jobs to say the company did not yet have a product. Apple did not announce internal dates before January 2007, so slippage in the earlier phases, if any, is not public.",
      "lessons": [
        "Announce a date only when the remaining work is engineering, not invention.",
        "Give each major stream, such as hardware, software and design, a single accountable owner.",
        "Negotiate partner terms that protect control of the product, not only price."
      ],
      "fun_fact": "Only about 30 of Apple's most senior people had seen the iPhone before Jobs unveiled it, according to Wired's 2008 account as summarized by Fortune.",
      "method_tags": [
        "prototyping",
        "iterative"
      ],
      "related_history_ids": [
        "agile-manifesto-2001",
        "cloud-collab-2006"
      ],
      "sources": [
        {
          "title": "iPhone (1st generation)",
          "publisher": "Wikipedia (citing Vogelstein, Wired, 2008)",
          "url": "https://en.wikipedia.org/wiki/IPhone_(1st_generation)",
          "accessed": "2026-10-25"
        },
        {
          "title": "iPhone",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/IPhone",
          "accessed": "2026-10-25"
        },
        {
          "title": "Apple Reinvents the Phone with iPhone",
          "publisher": "Apple Newsroom",
          "url": "https://www.apple.com/newsroom/2007/01/09Apple-Reinvents-the-Phone-with-iPhone/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Apple Sells One Millionth iPhone",
          "publisher": "Apple Newsroom",
          "url": "https://www.apple.com/newsroom/2007/09/10Apple-Sells-One-Millionth-iPhone/",
          "accessed": "2026-10-25"
        },
        {
          "title": "A must-read: the iPhone's untold story",
          "publisher": "Fortune",
          "url": "https://fortune.com/2008/01/10/a-must-read-the-iphones-untold-story",
          "accessed": "2026-10-25"
        },
        {
          "title": "Apple iPhone (museum object record)",
          "publisher": "Victoria and Albert Museum",
          "url": "https://collections.vam.ac.uk/item/O1328358",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Apple has never published a budget or internal schedule for the iPhone, so planned_cost is null. The actual cost of about $150 million comes from an unnamed insider quoted in Fred Vogelstein's January 2008 Wired article (Wired could not be opened; the figure is relayed by Fortune, Wikipedia and the V&A, which says about $150 million over a 30-month period). Treat it as an unverified estimate of uncertain scope, hence 'disputed'. Start year: Wikipedia says Apple began assembling the team in 2004; the iPhone (1st generation) article dates 'Project Purple 2' to 2005, so the start is approximate. Planned end is the June 2007 US availability stated in Apple's 9 January 2007 press release; this is the first public schedule, not an internal baseline. USD, fx = 1.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": true
    },
    {
      "id": 66,
      "slug": "universal-credit",
      "name": "Universal Credit IT and rollout (UK)",
      "short_name": "Universal Credit",
      "category": "software_it",
      "subcategory": "e-government / welfare system",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "London (Department for Work and Pensions)",
      "lat": 51.4995,
      "lng": -0.1335,
      "era": "2000-2014",
      "status": "ongoing",
      "outcome": "over_budget_and_late",
      "planned_start": "2010",
      "planned_end": "2017",
      "actual_start": "2010",
      "actual_end": "2026-03-31",
      "actual_is_forecast": true,
      "planned_duration_months": 84,
      "actual_duration_months": 189,
      "delay_months": 105,
      "delay_pct": 125,
      "planned_cost": 2400000000,
      "actual_cost": 2928000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "GBP",
      "planned_cost_year": 2012,
      "cost_year": 2023,
      "planned_fx_to_usd": 1.5852,
      "actual_fx_to_usd": 1.244,
      "planned_cost_usd_nominal": 3804000000,
      "cost_usd_nominal": 3642432000,
      "planned_cost_usd_today": 5334642702,
      "cost_usd_today": 3848900131,
      "overrun_usd_today": 694063958,
      "overrun_pct": 22,
      "overrun_basis": "nominal",
      "rebaseline_cost": 2016000000,
      "rebaseline_cost_year": 2018,
      "rebaseline_end": null,
      "rebaseline_label": "2018 full business case",
      "rebaseline_overrun_pct": 45.2,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 45,
      "reported_overrun_source": "NAO, Progress in implementing Universal Credit (2024), versus 2018 full business case",
      "phases": [
        {
          "name": "Design and early IT build",
          "planned_start": "2010",
          "planned_end": "2013-04",
          "actual_start": "2010",
          "actual_end": "2013-04",
          "note": "DWP set out in 2010 to move eight million households to UC by 2017. It had spent £303 million on IT by April 2013 and wrote off £34 million of new IT assets in May 2013 (NAO)."
        },
        {
          "name": "Pathfinder and programme reset",
          "planned_start": "2013-04",
          "planned_end": "2013-10",
          "actual_start": "2013-04",
          "actual_end": "2016",
          "note": "A limited pathfinder began in April 2013 at one site, expanded to four by July. Planned national rollout from October 2013 did not happen; DWP reset the programme in 2013 and built a new 'full service' system."
        },
        {
          "name": "National rollout for new claims",
          "planned_start": "2013-10",
          "planned_end": "2017",
          "actual_start": "2016",
          "actual_end": "2018-12",
          "note": "UC was rolled out to new claims nationwide in 2018 (NAO, 2024)."
        },
        {
          "name": "Managed migration of legacy claimants",
          "planned_start": null,
          "planned_end": "2022-03",
          "actual_start": "2023-04",
          "actual_end": "2026-03-31",
          "note": "The 2018 business case planned completion by March 2022; this moved to September 2024, then March 2025, then 2028 for ESA claimants, before the government brought the end of legacy benefits forward to 31 March 2026."
        }
      ],
      "milestones": [
        {
          "name": "Pathfinder starts",
          "planned_date": null,
          "actual_date": "2013-04"
        },
        {
          "name": "National rollout begins",
          "planned_date": "2013-10",
          "actual_date": "2016"
        },
        {
          "name": "Nationwide for new claims",
          "planned_date": null,
          "actual_date": "2018-12"
        },
        {
          "name": "National managed migration starts",
          "planned_date": null,
          "actual_date": "2023-04"
        },
        {
          "name": "All households moved to UC",
          "planned_date": "2017",
          "actual_date": "2026-03-31"
        }
      ],
      "headline": "Universal Credit was due by 2017 for £2.4 billion; the latest forecast is £2.9 billion and legacy benefits ending in March 2026.",
      "summary": "Universal Credit merges six means-tested benefits for working-age people into one monthly payment. The Department for Work and Pensions planned in 2010 to move eight million households onto it by 2017, and its December 2012 business case put implementation at £2.4 billion. Early IT failed, the programme was reset in 2013, and a new digital system was built. UC reached all new claims in 2018. Moving existing claimants took far longer; the end of legacy benefits is set for 31 March 2026 at a forecast £2.9 billion.",
      "what_went_wrong_or_right": "The NAO's 2013 review found that DWP had set an October 2013 national rollout date without being able to explain how it chose that date, that the pathfinder systems had limited function and needed manual intervention, and that £34 million of new IT assets had to be written off. DWP had tried an agile approach while policy was still being defined and struggled to fit it into existing contracts, governance and assurance; reviews in 2012 found a 'fortress' culture, and financial control over supplier spending was inadequate. IT costs were forecast at £637 million by April 2015, 60% above the original £396 million. After the 2013 reset DWP built a new full service system, which reached all new claims nationwide by 2018. Later delays came mainly from the managed migration of existing claimants. Since the 2018 business case, the NAO reported, completion slipped by at least six years and costs rose by £912 million, driven by inflation, fraud and error measures, timetable extensions and the decision to postpone moving ESA claimants to 2028 to save money. That date was later brought forward to March 2026.",
      "lessons": [
        "Base launch dates on evidence of readiness, not announced political milestones.",
        "Start with a narrow pathfinder, then scale only when the system can handle complex cases.",
        "Plan the migration of existing users as its own program; it can dominate the schedule.",
        "Keep in-house capability to own and change a core public system."
      ],
      "fun_fact": "By July 2013 the Universal Credit pathfinder had taken only about 1,000 new claims across four sites (NAO, 2013).",
      "method_tags": [
        "agile",
        "phased_delivery",
        "iterative"
      ],
      "related_history_ids": [
        "agile-manifesto-2001",
        "scrum-1995",
        "prince2-1996"
      ],
      "sources": [
        {
          "title": "Progress in implementing Universal Credit (HC 552, 2023-24), summary",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/wp-content/uploads/2024/02/progress-in-implementing-universal-credit-summary.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Universal Credit: early progress (HC 621, 2013-14)",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/wp-content/uploads/2013/09/10132-001-Universal-credit.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Rolling out Universal Credit (HC 1123, 2017-19)",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/reports/rolling-out-universal-credit/",
          "accessed": "2026-10-25"
        },
        {
          "title": "NAO: Universal Credit roll-out on hold as DWP reviews 'inflexible' IT system that cost £303m",
          "publisher": "Civil Service World",
          "url": "https://www.civilserviceworld.com/news/article/nao-universal-credit-rollout-on-hold-as-dwp-reviews-inflexible-it-system-that-cost-303m",
          "accessed": "2026-10-25"
        },
        {
          "title": "DWP legacy benefits due to end by March 2026: what it means for you",
          "publisher": "Which?",
          "url": "https://www.which.co.uk/news/article/dwp-legacy-benefits-due-to-end-by-march-2026-what-it-means-for-you-ak6KY3d7sth1",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline cost: DWP's December 2012 business case, £2.4 billion of investment to implement UC up to 2022-23 (NAO 2013); this is the first published total implementation cost (the May 2011 business case covered IT only, £396 million for the spending review period). Baseline schedule: 2010 plan to transfer eight million households by 2017 (NAO 2024), with national rollout from October 2013. Actual cost: DWP's December 2023 estimate of £2,928 million (NAO 2024), a forecast. The reported 45% overrun is the NAO's comparison with the 2018 full business case (about £2,016 million), not with the 2012 baseline; our own computation against £2.4 billion gives about 22% nominal. Actual end: 31 March 2026 target for ending legacy benefit payments (Which?, January 2026, after the government brought the ESA date forward from 2028 in April 2024); I found no official confirmation that closure was completed, so actual_is_forecast is true and status ongoing. FX: Federal Reserve G.5A, 2023 annual average 1.2440 USD per GBP (opened); 2012 about 1.5852 (Fed historical series, not re-verified from an opened table). Baseline audit 2026-10-25: Planned figures unchanged (December 2012 GBP 2.4bn business case is the first published total; the May 2011 IT-only figure is not comparable). Added the 2018 full business case of about GBP 2,016 million (NAO 2024 comparator) as the rebaseline; its completion date was not taken from an opened source.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 67,
      "slug": "windows-vista",
      "name": "Windows Vista (codename Longhorn)",
      "short_name": "Windows Vista",
      "category": "software_it",
      "subcategory": "operating system",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Redmond, Washington",
      "lat": 47.6396,
      "lng": -122.1283,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "late",
      "planned_start": "2001-05",
      "planned_end": "2003",
      "actual_start": "2001-05",
      "actual_end": "2007-01-30",
      "actual_is_forecast": false,
      "planned_duration_months": 25.5,
      "actual_duration_months": 68.5,
      "delay_months": 43,
      "delay_pct": 168.2,
      "planned_cost": null,
      "actual_cost": 6000000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": null,
      "cost_year": 2007,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": 6000000000,
      "planned_cost_usd_today": null,
      "cost_usd_today": 9316321618,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": "2006",
      "rebaseline_label": "August 2004 Longhorn development reset",
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": 7,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Original Longhorn development",
          "planned_start": "2001-05",
          "planned_end": "2003",
          "actual_start": "2001-05",
          "actual_end": "2004-08-27",
          "note": "Longhorn began as a minor release between Windows XP and Blackcomb, expected in late 2003; features such as WinFS were added. Microsoft pointed to early 2005 at WinHEC 2003."
        },
        {
          "name": "Development reset",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2004-08-27",
          "actual_end": "2005-07-27",
          "note": "Microsoft restarted development on the Windows Server 2003 SP1 codebase and removed WinFS, while keeping a calendar-2006 ship target."
        },
        {
          "name": "Beta testing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2005-07-27",
          "actual_end": "2006-11-08",
          "note": "Named Windows Vista on 22 July 2005; Beta 1 on 27 July 2005; Beta 2 in May 2006."
        },
        {
          "name": "Release to manufacturing and business launch",
          "planned_start": null,
          "planned_end": "2006",
          "actual_start": "2006-11-08",
          "actual_end": "2006-11-30",
          "note": "RTM announced 8 November 2006; volume-license availability 30 November 2006."
        },
        {
          "name": "Consumer launch",
          "planned_start": null,
          "planned_end": "2006",
          "actual_start": "2007-01-30",
          "actual_end": "2007-01-30",
          "note": "Retail availability worldwide on 30 January 2007."
        }
      ],
      "milestones": [
        {
          "name": "Development reset announced",
          "planned_date": null,
          "actual_date": "2004-08-27"
        },
        {
          "name": "Beta 1",
          "planned_date": null,
          "actual_date": "2005-07-27"
        },
        {
          "name": "Release to manufacturing",
          "planned_date": null,
          "actual_date": "2006-11-08"
        },
        {
          "name": "Consumer availability",
          "planned_date": "2003",
          "actual_date": "2007-01-30"
        }
      ],
      "headline": "Planned as a minor 2003 update, Windows Vista shipped to consumers in January 2007 after a reported $6 billion and a full development reset.",
      "summary": "Longhorn began in May 2001 as a modest Windows release planned for late 2003, between Windows XP and a larger future release. Features accumulated, including the WinFS storage system, and the code base became unstable. In August 2004 Microsoft restarted development from the Windows Server 2003 code base and dropped WinFS. Renamed Windows Vista in July 2005, it was released to manufacturing on 8 November 2006 and reached consumers on 30 January 2007. Press reports put development at more than five years and about $6 billion.",
      "what_went_wrong_or_right": "The main cause was scope growth on an unstable base. A release intended as a small interim update absorbed ambitious technologies, including the WinFS file system, the Avalon presentation layer and the Indigo communications system. By 2004 the Windows team faced serious problems with Longhorn, and Microsoft also diverted effort to Windows XP Service Pack 2, a security release. On 27 August 2004 group vice president Jim Allchin told employees that development would restart from Windows Server 2003 SP1, that WinFS would be removed, and that Avalon and Indigo would also be offered for older Windows versions, so that Vista could still ship in 2006. The reset worked in schedule terms: Vista reached manufacturing in November 2006. Critics nicknamed the reduced plan Shorthorn. A Windows developer's 2006 blog post described roughly 2,000 developers and about 50 million lines of code, scale that slowed integration.",
      "lessons": [
        "Keep an interim release interim; move large new technologies to their own track.",
        "When the code base is unstable, a reset to a known-good base can beat continued patching.",
        "Cut headline features openly to protect a ship date rather than slipping repeatedly."
      ],
      "fun_fact": "Development of Vista restarted in 2004 from the code of Windows Server 2003 SP1, not from the Longhorn code written since 2001 (Thurrott).",
      "method_tags": [
        "waterfall",
        "big_bang"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "scrum-1995"
      ],
      "sources": [
        {
          "title": "Development of Windows Vista",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Development_of_Windows_Vista",
          "accessed": "2026-10-25"
        },
        {
          "title": "Microsoft Releases Latest Windows Platform",
          "publisher": "PBS NewsHour",
          "url": "https://www.pbs.org/newshour/show/microsoft-releases-latest-windows-platform",
          "accessed": "2026-10-25"
        },
        {
          "title": "Longhorn development reset (Windows Weekly / SuperSite archive)",
          "publisher": "Thurrott.com",
          "url": "https://www.thurrott.com/?p=263133",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Microsoft never published a budget for Longhorn/Vista, so planned_cost is null. The actual cost of about $6 billion is a widely reported press estimate (PBS NewsHour, January 2007: more than five years and about $6 billion; CNN Money reported six years and $6 billion but returned an error when opened). It is not audited and its scope (development only, or including marketing) is unclear. Planned end 2003: Longhorn was originally expected to ship in late 2003 (Wikipedia; some accounts say October 2003); after the August 2004 reset the target became calendar 2006. Actual end is consumer availability on 30 January 2007. USD, fx = 1. Baseline audit 2026-10-25: Planned figures unchanged (late-2003 Longhorn target). Added the calendar-2006 target set after the August 2004 reset as the schedule rebaseline.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 68,
      "slug": "y2k-remediation",
      "name": "Y2K remediation of US federal government computer systems",
      "short_name": "US federal Y2K fix",
      "category": "software_it",
      "subcategory": "systems remediation",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Washington, D.C.",
      "lat": 38.8977,
      "lng": -77.039,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1996",
      "planned_end": "1999-11",
      "actual_start": "1996",
      "actual_end": "1999-12-31",
      "actual_is_forecast": false,
      "planned_duration_months": 40.5,
      "actual_duration_months": 42,
      "delay_months": 1.5,
      "delay_pct": 3.8,
      "planned_cost": 2292400000,
      "actual_cost": 8380000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1997,
      "cost_year": 2000,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 2292400000,
      "cost_usd_nominal": 8380000000,
      "planned_cost_usd_today": 4597630597,
      "cost_usd_today": 15666956522,
      "overrun_usd_today": 11381165217,
      "overrun_pct": 265.6,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": "1999-03-31",
      "rebaseline_label": "OMB accelerated implementation deadline",
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": 9,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Awareness and assessment",
          "planned_start": "1996",
          "planned_end": "1997-06",
          "actual_start": "1996",
          "actual_end": "1998",
          "note": "OMB's February 1997 plan set inventory and scope by March 1997 and approved plans by June 1997. Agencies were still refining system lists in 1998 (7,850 mission-critical systems in February 1998, down from 8,589)."
        },
        {
          "name": "Renovation",
          "planned_start": "1997",
          "planned_end": "1998-09",
          "actual_start": "1997",
          "actual_end": "1999-03",
          "note": "OMB's January 1998 guidance moved renovation completion up to September 1998. Only 35% of mission-critical systems were compliant in February 1998."
        },
        {
          "name": "Validation",
          "planned_start": "1998",
          "planned_end": "1999-01",
          "actual_start": "1998",
          "actual_end": "1999-03",
          "note": "February 1997 plan: management sign-off on validation by January 1999."
        },
        {
          "name": "Implementation",
          "planned_start": "1998",
          "planned_end": "1999-11",
          "actual_start": "1998",
          "actual_end": "1999-12",
          "note": "February 1997 plan: integrated testing and implementation by November 1999; later accelerated to 31 March 1999, when 92% of mission-critical systems were compliant. OMB reported 99.9% ready in December 1999."
        },
        {
          "name": "Rollover",
          "planned_start": "1999-12-31",
          "planned_end": "2000-01-01",
          "actual_start": "1999-12-31",
          "actual_end": "2000-01-01",
          "note": "Date change to 1 January 2000."
        }
      ],
      "milestones": [
        {
          "name": "OMB first Y2K report and plan",
          "planned_date": null,
          "actual_date": "1997-02-06"
        },
        {
          "name": "Mission-critical systems compliant (OMB goal)",
          "planned_date": "1999-03-31",
          "actual_date": "1999-12"
        },
        {
          "name": "OMB reports 99.9% of mission-critical systems ready",
          "planned_date": null,
          "actual_date": "1999-12-14"
        },
        {
          "name": "Year 2000 rollover",
          "planned_date": "2000-01-01",
          "actual_date": "2000-01-01"
        }
      ],
      "headline": "The federal Y2K fix was first estimated at $2.3 billion in 1997 and ended at about $8.4 billion, with 99.9% of critical systems ready.",
      "summary": "Many federal computer systems stored years as two digits and risked failing on 1 January 2000. In February 1997 the Office of Management and Budget published a government-wide plan and a preliminary cost estimate of $2.3 billion for fiscal 1996 to 2000. Agencies inventoried thousands of mission-critical systems, then renovated, validated and implemented fixes. The estimate rose quarter after quarter, to $8.38 billion by late 1999. OMB reported 92% of mission-critical systems compliant at its 31 March 1999 goal and 99.9% in December 1999.",
      "what_went_wrong_or_right": "The cost grew mainly because the first estimate was preliminary and made before agencies knew the size of the problem. The February 1997 figure of $2,292.4 million excluded normal lifecycle replacements and was criticized by Congress and outside experts as too low. As agencies completed inventories, the estimate rose to $3.9 billion in November 1997, $4.7 billion in February 1998, more than $5 billion in May 1998, $8.05 billion in June 1999, and $8.38 billion by late 1999. What went right was the fixed, non-negotiable deadline, phased milestones reported quarterly to Congress, a public grading of agencies, and emergency funding of $2.25 billion for non-defense work. OMB pulled the implementation target from November 1999 forward to March 1999 to leave time for testing; 92% of systems met it. GAO later recommended a federal chief information officer to keep this central leadership, which the E-Government Act of 2002 largely addressed.",
      "lessons": [
        "Treat early estimates made before inventory as placeholders and report them with ranges.",
        "Publish phase milestones and progress quarterly; visibility drives agency attention.",
        "Set internal deadlines well before an immovable external date to leave time for testing."
      ],
      "fun_fact": "Agencies' count of mission-critical systems fell from 8,589 to 7,850 between November 1997 and February 1998 as they refined what counted as critical (OMB).",
      "method_tags": [
        "phased_delivery",
        "waterfall"
      ],
      "related_history_ids": [
        "pmbok-1987",
        "planning-fallacy-1979",
        "prince2-1996"
      ],
      "sources": [
        {
          "title": "Getting Federal Computers Ready for 2000 (OMB report, 6 February 1997)",
          "publisher": "Office of Management and Budget (Clinton White House archive)",
          "url": "https://clintonwhitehouse2.archives.gov/omb/inforeg/2000report.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Progress on Year 2000 Conversion, 4th quarterly report",
          "publisher": "Office of Management and Budget (Clinton White House archive)",
          "url": "https://clintonwhitehouse4.archives.gov/textonly/OMB/inforeg/y2k4q.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "OMB testimony on Year 2000 progress, 14 April 1999",
          "publisher": "Office of Management and Budget (Clinton White House archive)",
          "url": "https://clintonwhitehouse3.archives.gov/OMB/legislative/testimony/19990414.1275.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Y2K: More signs of the time",
          "publisher": "Computerworld",
          "url": "https://www.computerworld.com/article/1376136/y2k-more-signs-of-the-time.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "OMB seeks better Y2K cost tally",
          "publisher": "Nextgov",
          "url": "https://nextgov.com/digital-government/1998/08/omb-seeks-better-y2k-cost-tally/256628",
          "accessed": "2026-10-25"
        },
        {
          "title": "Year 2000 Computing Challenge: Lessons Learned Can Be Applied to Other Management Challenges (AIMD-00-290)",
          "publisher": "U.S. General Accounting Office",
          "url": "https://www.gao.gov/products/aimd-00-290",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "high",
      "notes": "Baseline: OMB's first report of 6 February 1997, preliminary estimate of $2,292.4 million for FY1996 to FY2000 (cost year set to 1997, the year of the estimate). Actual: OMB's late-1999 estimate of $8.38 billion for FY1996 to FY2000 (Computerworld, January 2000; GovExec rounded to $8.4 billion in December 1999). GAO's Comptroller General cited about $8.7 billion in June 1999 testimony, a higher figure with different scope. Both figures are nominal agency estimates, not audited outlays, and exclude normal system replacements. Planned end November 1999 is the implementation milestone in the February 1997 plan; OMB later accelerated it to 31 March 1999. Actual end is the December 1999 readiness position ahead of the rollover. Actual phase end dates for assessment, renovation and validation are approximate, inferred from compliance reports. Totals are government-wide and include all departments' estimates; the record describes only the IT remediation program. USD, fx = 1. Baseline audit 2026-10-25: Planned figures unchanged (February 1997 OMB report). Added the OMB accelerated implementation deadline of 31 March 1999 as the schedule rebaseline.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 69,
      "slug": "airbus-a380",
      "name": "Airbus A380 development",
      "short_name": "Airbus A380",
      "category": "transport_vehicles",
      "subcategory": "airliner",
      "country": "France",
      "country_code": "FR",
      "countries": [
        "France",
        "Germany",
        "United Kingdom",
        "Spain"
      ],
      "continent": "Europe",
      "city": "Toulouse",
      "lat": 43.649,
      "lng": 1.36,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2000-12-19",
      "planned_end": "2006-04",
      "actual_start": "2000-12-19",
      "actual_end": "2007-10-15",
      "actual_is_forecast": false,
      "planned_duration_months": 63.9,
      "actual_duration_months": 81.9,
      "delay_months": 18,
      "delay_pct": 28.2,
      "planned_cost": 9500000000,
      "actual_cost": 18000000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        12000000000,
        25000000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2000,
      "cost_year": 2006,
      "planned_fx_to_usd": 0.9236,
      "actual_fx_to_usd": 1.2556,
      "planned_cost_usd_nominal": 8770400000,
      "cost_usd_nominal": 22608000000,
      "planned_cost_usd_today": 16396834783,
      "cost_usd_today": 36106371740,
      "overrun_usd_today": 17050231099,
      "overrun_pct": 89.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Design and component manufacture",
          "planned_start": "2000-12",
          "planned_end": null,
          "actual_start": "2000-12-19",
          "actual_end": "2005-01-18",
          "note": "Board launch 19 Dec 2000; sections built in France, Germany, the UK and Spain; first prototype unveiled in Toulouse 18 Jan 2005."
        },
        {
          "name": "Flight test and certification",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2005-04-27",
          "actual_end": "2006-12-12",
          "note": "First flight 27 Apr 2005; EASA and FAA type certificates 12 Dec 2006."
        },
        {
          "name": "Wiring rework and production recovery",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2006-06-13",
          "actual_end": "2007-10",
          "note": "Second delay announced 13 June 2006 and third on 3 Oct 2006, both traced to customized wiring (530 km per aircraft)."
        },
        {
          "name": "First delivery and service entry",
          "planned_start": "2006-04",
          "planned_end": "2006-04",
          "actual_start": "2007-10-15",
          "actual_end": "2007-10-25",
          "note": "Delivered to Singapore Airlines 15 Oct 2007; first commercial flight SQ380 on 25 Oct 2007."
        }
      ],
      "milestones": [
        {
          "name": "Industrial launch",
          "planned_date": "2000-12-19",
          "actual_date": "2000-12-19"
        },
        {
          "name": "Rollout",
          "planned_date": null,
          "actual_date": "2005-01-18"
        },
        {
          "name": "First flight",
          "planned_date": null,
          "actual_date": "2005-04-27"
        },
        {
          "name": "Type certification",
          "planned_date": null,
          "actual_date": "2006-12-12"
        },
        {
          "name": "First delivery (Singapore Airlines)",
          "planned_date": "2006-04",
          "actual_date": "2007-10-15"
        }
      ],
      "headline": "Airbus launched the A380 at a projected €9.5 billion in 2000; wiring problems made the first delivery 18 months late and Airbus put total development at about €18 billion by 2006.",
      "summary": "Airbus's board approved the A380 superjumbo on 19 December 2000 at a projected cost of €9.5 billion. The first aircraft was unveiled in Toulouse on 18 January 2005 and flew on 27 April 2005, and type certificates followed on 12 December 2006. Problems installing customized electrical wiring forced three delivery delays in 2006. Singapore Airlines received the first aircraft on 15 October 2007, about 18 months behind schedule, and flew it commercially ten days later.",
      "what_went_wrong_or_right": "The airframe itself progressed steadily: the A380 first flew on 27 April 2005 and EASA and the FAA certified it on 12 December 2006. The failure was in production. Each aircraft carried about 530 km of wiring, customized for each airline's cabin, and Wikipedia and NBC News report that the installation problems drove the delays announced on 13 June and 3 October 2006. Airbus said in June 2006 that the complexity of customizing wiring for each customer would push back deliveries and add cost, and airlines sought an estimated €2 billion in compensation. Cost estimates grew from €9.5 billion in 2000 to €10.3 billion by 2004 and about €18 billion in 2006, with later estimates of $25 billion (2014). Reports in 2006 said the delays would cut €4.8 billion from parent company EADS's profits over four years. The Mail & Guardian reported that break-even rose from 270 aircraft at launch to 420 at list price, a figure the program never approached.",
      "lessons": [
        "Freeze and standardize design tools across sites before detailed design starts.",
        "Customer customization multiplies production complexity; cap options early.",
        "A first flight on time does not mean the production line is ready."
      ],
      "fun_fact": "Each A380 carried about 530 km (330 miles) of wiring, the detail at the center of the 2006 delays.",
      "method_tags": [
        "waterfall",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Airbus A380",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Airbus_A380",
          "accessed": "2026-10-25"
        },
        {
          "title": "Huge A380 airliner is declared safe to fly",
          "publisher": "NBC News / Associated Press",
          "url": "https://www.nbcnews.com/id/wbna16170235",
          "accessed": "2026-10-25"
        },
        {
          "title": "Airbus delivers first A380 superjumbo",
          "publisher": "Mail & Guardian / AFP",
          "url": "https://mg.co.za/article/2007-10-15-airbus-delivers-first-a380-superjumbo",
          "accessed": "2026-10-25"
        },
        {
          "title": "Foreign Exchange Rates G.5A (annual)",
          "publisher": "Federal Reserve Board",
          "url": "https://www.federalreserve.gov/releases/g5a/current/default.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline cost: €9.5 billion (US$10.7 billion) approved at launch, 19 Dec 2000 (Wikipedia); some sources cite €8.8bn. Actual: €18 billion total estimated in 2006 (Wikipedia) stored as main value; range from €12bn (industry sources, NBC News, Dec 2006) to €25bn (2016 estimate, Wikipedia). Airbus never published a final audited development total. Planned end: no source we opened gives the original contractual first-delivery date; 2006-04 is derived from the Mail & Guardian statement that the 15 Oct 2007 delivery was 18 months behind schedule. NBC says that after the first delay the first aircraft was due in Dec 2006. End date defined as first delivery. FX: Federal Reserve G.5A annual averages, EUR 2000 = US$0.9236, EUR 2006 = US$1.2556. The €4.8bn profit impact and €2bn compensation estimate come from 2006 press reports surfaced in search (AviationPros, TravelMole); they are not audited figures.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 70,
      "slug": "boeing-747",
      "name": "Boeing 747 development",
      "short_name": "Boeing 747",
      "category": "transport_vehicles",
      "subcategory": "airliner",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Everett",
      "lat": 47.9224,
      "lng": -122.2818,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": "1966-04",
      "planned_end": "1969-12",
      "actual_start": "1966-04",
      "actual_end": "1969-12",
      "actual_is_forecast": false,
      "planned_duration_months": 44,
      "actual_duration_months": 44,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": null,
      "actual_cost": 1000000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        1000000000,
        2000000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": null,
      "cost_year": 1969,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": 1000000000,
      "planned_cost_usd_today": null,
      "cost_usd_today": 8779491833,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Launch order and design definition",
          "planned_start": "1966-04",
          "planned_end": "1966-07",
          "actual_start": "1966-04",
          "actual_end": "1966-07",
          "note": "Pan Am ordered 25 aircraft in April 1966; production approved in July 1966 after orders from Japan Airlines and Lufthansa."
        },
        {
          "name": "Everett plant construction",
          "planned_start": "1966-06",
          "planned_end": null,
          "actual_start": "1966-06",
          "actual_end": "1968-09",
          "note": "780-acre site bought June 1966; the $200m plant was built while design went on, and mockup work began before its building's walls were complete. End date approximate (first rollout)."
        },
        {
          "name": "Detailed design and first aircraft assembly",
          "planned_start": "1966-07",
          "planned_end": null,
          "actual_start": "1966-07",
          "actual_end": "1968-09-30",
          "note": "First 747 rolled out of the Everett plant 30 Sept 1968."
        },
        {
          "name": "Flight test and certification",
          "planned_start": null,
          "planned_end": "1969-12",
          "actual_start": "1969-02-09",
          "actual_end": "1969-12",
          "note": "First flight 9 Feb 1969, slightly after target; certified December 1969."
        },
        {
          "name": "Delivery and entry into service",
          "planned_start": "1969-12",
          "planned_end": "1969-12",
          "actual_start": "1969-12",
          "actual_end": "1970-01-22",
          "note": "Delivered to Pan Am in December 1969; first service New York-London 22 Jan 1970. JT9D engine problems later left finished aircraft parked awaiting engines."
        }
      ],
      "milestones": [
        {
          "name": "Pan Am launch order",
          "planned_date": "1966-04",
          "actual_date": "1966-04"
        },
        {
          "name": "Rollout",
          "planned_date": null,
          "actual_date": "1968-09-30"
        },
        {
          "name": "First flight",
          "planned_date": null,
          "actual_date": "1969-02-09"
        },
        {
          "name": "First delivery to Pan Am",
          "planned_date": "1969-12",
          "actual_date": "1969-12"
        },
        {
          "name": "First commercial service",
          "planned_date": null,
          "actual_date": "1970-01-22"
        }
      ],
      "headline": "Boeing promised Pan Am a 747 by the end of 1969, about 28 months after the order, and delivered on time, but development passed $1 billion and the company's debt exceeded $2 billion.",
      "summary": "In April 1966 Pan Am ordered 25 Boeing 747s for about $525-550 million, with deliveries due by the end of 1969. Boeing had to design the aircraft and build a new factory at Everett, Washington, at the same time. The first 747 rolled out on 30 September 1968, flew on 9 February 1969 and was certified in December 1969, in time for delivery to Pan Am. Service began on 22 January 1970. Development cost about $1 billion, excluding the $200 million plant.",
      "what_went_wrong_or_right": "The schedule was met because Boeing ran design, factory construction and tooling in parallel. HistoryLink notes that work on the 747 mockup began before the walls of the mockup building were complete and that factory construction was barely fast enough to keep up. The price was financial exposure. CEO Bill Allen's decision is often described as betting the company: Wikipedia reports that Boeing's debt exceeded $2 billion, including $1.2 billion owed to banks, a record for any company at the time. The weakest link was the new Pratt & Whitney JT9D high-bypass engine, which suffered stalls and turbine casing distortion. According to the Centennial of Flight Commission, the engine problem was not solved when the aircraft entered service, and around 20 to 30 finished aircraft sat at Everett waiting for engines. The 747 went on to stay in production for more than five decades.",
      "lessons": [
        "Concurrent design and facility construction can hold a deadline, at the cost of high financial risk.",
        "Track the critical supplier's technology readiness as closely as your own.",
        "A fixed customer delivery date concentrates decisions; make sure financing can absorb the pace."
      ],
      "fun_fact": "The Everett assembly plant built for the 747 enclosed about 200 million cubic feet (5.7 million cubic meters).",
      "method_tags": [
        "fast_track",
        "prototyping"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Boeing 747",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Boeing_747",
          "accessed": "2026-10-25"
        },
        {
          "title": "Boeing rolls out the first 747 'Jumbo Jet' in Everett on September 30, 1968",
          "publisher": "HistoryLink.org",
          "url": "https://www.historylink.org/file/1565",
          "accessed": "2026-10-25"
        },
        {
          "title": "The Boeing 747",
          "publisher": "U.S. Centennial of Flight Commission",
          "url": "https://centennialofflight.net/essay/Aerospace/Boeing_747/Aero21.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline schedule: Pan Am contract for delivery by the end of 1969 (Wikipedia, HistoryLink). Boeing published no development budget at launch, so planned_cost is null and no overrun can be computed. Actual cost: US$1 billion program cost (Wikipedia, 1968); Centennial of Flight says development passed $1 billion before rollout, not counting the $200m plant, and that $2 billion was invested in total from go-ahead, hence the range. Launch order value is $525m (Wikipedia) or $550m (HistoryLink, Centennial). Exact day of the April 1966 order and of the December 1969 delivery and certification were not confirmed in the pages opened. Project end is defined as first delivery; service entry 22 Jan 1970 is shown as the last phase. The engine-wait count is 'up to 20' (Wikipedia) or 'about 30' (Centennial).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 71,
      "slug": "boeing-777",
      "name": "Boeing 777 development",
      "short_name": "Boeing 777",
      "category": "transport_vehicles",
      "subcategory": "airliner",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States",
        "Japan"
      ],
      "continent": "North America",
      "city": "Everett",
      "lat": 47.9224,
      "lng": -122.2818,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1990-10-15",
      "planned_end": "1995-05",
      "actual_start": "1990-10-15",
      "actual_end": "1995-05-15",
      "actual_is_forecast": false,
      "planned_duration_months": 55,
      "actual_duration_months": 55,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 4000000000,
      "actual_cost": 5000000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        4000000000,
        5000000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1990,
      "cost_year": 1995,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 4000000000,
      "cost_usd_nominal": 5000000000,
      "planned_cost_usd_today": 9857361182,
      "cost_usd_today": 10564533741,
      "overrun_usd_today": 2112906748,
      "overrun_pct": 25,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Airline consultation (Working Together)",
          "planned_start": "1990-01",
          "planned_end": "1990-10",
          "actual_start": "1990-01",
          "actual_end": "1990-10-15",
          "note": "Boeing asked eight airlines to help define the aircraft in January 1990; United's launch agreement was a hand-written note signed 15 Oct 1990."
        },
        {
          "name": "Digital design (CATIA, design-build teams)",
          "planned_start": "1990-10",
          "planned_end": null,
          "actual_start": "1990-10-15",
          "actual_end": "1994-04-09",
          "note": "Up to 238 cross-functional design-build teams at peak; only one physical mockup, of the nose."
        },
        {
          "name": "Major assembly of first aircraft",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1993-01-04",
          "actual_end": "1994-04-09",
          "note": "Rolled out 9 Apr 1994 in a series of 15 ceremonies."
        },
        {
          "name": "Flight test and certification",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1994-06-12",
          "actual_end": "1995-05-30",
          "note": "Nine aircraft in an 11-month test program; FAA/JAA certification 19 Apr 1995; 180-minute ETOPS 30 May 1995."
        },
        {
          "name": "Delivery and entry into service",
          "planned_start": "1995-05",
          "planned_end": "1995-06",
          "actual_start": "1995-05-15",
          "actual_end": "1995-06-07",
          "note": "First delivery to United 15 May 1995; first commercial flight London Heathrow-Washington Dulles 7 Jun 1995."
        }
      ],
      "milestones": [
        {
          "name": "United launch agreement",
          "planned_date": "1990-10-15",
          "actual_date": "1990-10-15"
        },
        {
          "name": "Rollout",
          "planned_date": null,
          "actual_date": "1994-04-09"
        },
        {
          "name": "First flight",
          "planned_date": null,
          "actual_date": "1994-06-12"
        },
        {
          "name": "Type certification",
          "planned_date": null,
          "actual_date": "1995-04-19"
        },
        {
          "name": "First delivery to United",
          "planned_date": "1995-05",
          "actual_date": "1995-05-15"
        }
      ],
      "headline": "Boeing designed the 777 almost entirely on computer with 238 design-build teams and delivered the first aircraft to United on time in May 1995, for a reported $4-5 billion.",
      "summary": "In January 1990 Boeing invited eight airlines to help define a new twin-engine widebody, and on 15 October 1990 United launched the program. The 777 was the first Boeing airliner designed entirely in 3D on CATIA, with cross-functional design-build teams replacing sequential hand-offs. Major assembly began on 4 January 1993, the first flight was on 12 June 1994, and certification came on 19 April 1995. United took the first aircraft on 15 May 1995 and flew the first service on 7 June.",
      "what_went_wrong_or_right": "The 777 is a standard case of a program that kept its date. IEEE Spectrum described the change: jetliners had been developed in a linear fashion, with structure designed first and systems fitted later, which caused late rework. Boeing replaced that with up to 238 design-build teams combining design, manufacturing and supplier staff, and with digital pre-assembly on CATIA, which let it skip physical mockups except for the nose. Airline engineers from United, ANA, British Airways and Japan Airlines sat in Seattle with full access to the design. When the first wing and center fuselage were joined, the section was out of alignment by only 0.69 mm. Boeing also set the goal of 'ETOPS out of the box', and the FAA granted 180-minute ETOPS on 30 May 1995. The approach was not cheap: Boeing's investment was put at over $4 billion, with $2 billion more from suppliers, and the Everett plant was doubled in size for almost $1.5 billion.",
      "lessons": [
        "Cross-functional teams that include manufacturing and customers remove rework that sequential design creates.",
        "Digital pre-assembly can replace most physical mockups and catch interferences early.",
        "Put customer engineers inside the design team, not at review meetings."
      ],
      "fun_fact": "Boeing built only one physical mockup of the 777, of the nose, partly to confirm that real crews could move in the cockpit as easily as 'Catia-man', a computer human model engineers nicknamed 'Robocop'.",
      "method_tags": [
        "design_build",
        "simulation",
        "iterative"
      ],
      "related_history_ids": [
        "scrum-paper-1986"
      ],
      "sources": [
        {
          "title": "Boeing 777",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Boeing_777",
          "accessed": "2026-10-25"
        },
        {
          "title": "Boeing 777: a digital design milestone (IEEE Spectrum, October 1995)",
          "publisher": "IEEE Spectrum (copy hosted by University of Maryland)",
          "url": "https://user.eng.umd.edu/~austin/enes489p/lecture-resources/IEEE-Spectrum-Boeing777-1995.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "Boeing's 777 Takes to the Skies",
          "publisher": "EBSCO Research Starters",
          "url": "https://www.ebsco.com/research-starters/history/boeings-777-takes-skies/",
          "accessed": "2026-10-25"
        },
        {
          "title": "United Airlines",
          "publisher": "U.S. Centennial of Flight Commission",
          "url": "https://centennialofflight.net/essay/Commercial_Aviation/UnitedAirlines/Tran16G11.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline cost: Boeing's investment 'projected to be over US$4bn' with another $2bn from suppliers (Wikipedia; IEEE Spectrum calls it a '$4 billion-plus development effort'). Actual: Wikipedia says the design approach helped 'limit costs to a reported $5 billion'; neither figure is an audited total and they may measure different things, so the range is $4-5bn and confidence is disputed. Baseline schedule: no source opened gives the exact contractual delivery date; EBSCO states the aircraft was delivered on time, so planned_end is set to the month of actual first delivery (May 1995). Some sources date the United launch order 14 Oct 1990 (Wikipedia) versus the 15 Oct 1990 signed agreement (IEEE). Japanese partners (via the Japan Aircraft Development Corporation) took about 20% of the program as risk-sharing partners. Everett plant expansion of almost $1.5bn (IEEE) is reported separately from development cost.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 72,
      "slug": "boeing-787-dreamliner",
      "name": "Boeing 787 Dreamliner development",
      "short_name": "Boeing 787 Dreamliner",
      "category": "transport_vehicles",
      "subcategory": "airliner",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States",
        "Japan",
        "Italy"
      ],
      "continent": "North America",
      "city": "Everett",
      "lat": 47.9224,
      "lng": -122.2818,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2004-04-26",
      "planned_end": "2008-05",
      "actual_start": "2004-04-26",
      "actual_end": "2011-09-26",
      "actual_is_forecast": false,
      "planned_duration_months": 48.6,
      "actual_duration_months": 89,
      "delay_months": 40.4,
      "delay_pct": 83,
      "planned_cost": 7000000000,
      "actual_cost": 32000000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2003,
      "cost_year": 2011,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 7000000000,
      "cost_usd_nominal": 32000000000,
      "planned_cost_usd_today": 12251266281,
      "cost_usd_today": 45798816568,
      "overrun_usd_today": 35780325444,
      "overrun_pct": 357.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Design and supplier development",
          "planned_start": "2004-04",
          "planned_end": "2007-07",
          "actual_start": "2004-04-26",
          "actual_end": "2007-07-08",
          "note": "Launched with an ANA order for 50 aircraft; large structures built by partners worldwide."
        },
        {
          "name": "Rollout to first flight",
          "planned_start": "2007-07-08",
          "planned_end": "2007-08",
          "actual_start": "2007-07-08",
          "actual_end": "2009-12-15",
          "note": "Prototype rolled out without major operating systems; five delays announced Sept 2007-Nov 2008, then a June 2009 structural postponement."
        },
        {
          "name": "Flight test and certification",
          "planned_start": "2007-08",
          "planned_end": "2008-05",
          "actual_start": "2009-12-15",
          "actual_end": "2011-08-26",
          "note": "FAA and EASA certified the 787 on 26 Aug 2011 at a ceremony in Everett."
        },
        {
          "name": "First delivery and service entry",
          "planned_start": "2008-05",
          "planned_end": "2008-05",
          "actual_start": "2011-09-25",
          "actual_end": "2011-10-26",
          "note": "Contractual delivery to ANA 25 Sept 2011, ceremony 26 Sept; first commercial flight Tokyo Narita-Hong Kong 26 Oct 2011."
        }
      ],
      "milestones": [
        {
          "name": "Program launch (ANA order)",
          "planned_date": "2004-04-26",
          "actual_date": "2004-04-26"
        },
        {
          "name": "Rollout",
          "planned_date": "2007-07-08",
          "actual_date": "2007-07-08"
        },
        {
          "name": "First flight",
          "planned_date": "2007-08",
          "actual_date": "2009-12-15"
        },
        {
          "name": "First delivery to ANA",
          "planned_date": "2008-05",
          "actual_date": "2011-09-26"
        },
        {
          "name": "First commercial flight",
          "planned_date": null,
          "actual_date": "2011-10-26"
        }
      ],
      "headline": "Boeing's board approved a $7 billion development budget for the 787; the program reportedly cost $32 billion and the first jet reached ANA more than three years late.",
      "summary": "Boeing launched the 787 on 26 April 2004 with an All Nippon Airways order for 50 aircraft, promising a composite-fuselage, fuel-efficient midsize jet. The board had approved a development budget of about $7 billion, and the first delivery to ANA was expected in May 2008. After seven delays the first flight came on 15 December 2009 and ANA took delivery on 25-26 September 2011. Press reports put total program cost at about $32 billion.",
      "what_went_wrong_or_right": "The 787 combined two novelties at once: a mostly carbon-composite airframe and a supply chain in which partners in Japan, Italy and the United States designed and built whole fuselage and wing sections. The first aircraft was rolled out on 8 July 2007 without its major operating systems, and the first flight planned for late August 2007 slipped repeatedly. Wikipedia lists five announced delays between September 2007 and November 2008, citing incorrect fastener installation, supplier shortfalls and a machinists' strike; CAPA counts seven delays and a 58-day labor strike in 2008. On 23 June 2009 Boeing postponed the first flight again for structural reasons. Airlines including United and Air India sought compensation. The $32 billion figure reported in the press includes deferred production costs, and Wikipedia notes original development investment was estimated at a further $20 billion or more. The aircraft itself sold well, which let Boeing recover the program over time.",
      "lessons": [
        "Outsourcing major design work does not transfer schedule risk; it adds integration risk the prime contractor still owns.",
        "Do not roll out a showpiece before systems are installed; it hides true progress.",
        "Limit the number of simultaneous technical novelties on one program."
      ],
      "fun_fact": "When Boeing handed the first 787 to ANA in September 2011, executive Scott Fancher told reporters, 'This is not plastic,' referring to the composite airframe.",
      "method_tags": [
        "waterfall",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Boeing 787 Dreamliner",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Boeing_787_Dreamliner",
          "accessed": "2026-10-25"
        },
        {
          "title": "Boeing completes delivery of first B787 to ANA",
          "publisher": "CAPA - Centre for Aviation",
          "url": "https://centreforaviation.com/news/boeing-completes-delivery-of-first-b787-to-ana-121377",
          "accessed": "2026-10-25"
        },
        {
          "title": "ANA To Take First 787 in September",
          "publisher": "AIN Online",
          "url": "https://live.ainonline.com/aviation-news/air-transport/2011-07-25/ana-take-first-787-september",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline cost: development budget of about US$7 billion approved by Boeing's board in 2003 (Wikipedia, citing the board's target of under 40% of the 777's cost). Baseline schedule: rollout 8 July 2007, first flight by end of August 2007, first delivery to ANA in May 2008 (CAPA). Actual cost: the widely reported US$32 billion (CAPA, Wikipedia), which mixes deferred production costs and development; Boeing never published a single development total, so the overrun ratio compares unlike measures and should be treated as indicative. End date defined as first delivery. USD throughout, nominal. The 'not plastic' quote is from CAPA's delivery report.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 73,
      "slug": "concorde",
      "name": "Concorde supersonic airliner development",
      "short_name": "Concorde",
      "category": "transport_vehicles",
      "subcategory": "airliner",
      "country": "France",
      "country_code": "FR",
      "countries": [
        "France",
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "Toulouse",
      "lat": 43.6293,
      "lng": 1.3638,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "1962-11-29",
      "planned_end": "1970",
      "actual_start": "1962-11-29",
      "actual_end": "1976-01-21",
      "actual_is_forecast": false,
      "planned_duration_months": 91.1,
      "actual_duration_months": 157.7,
      "delay_months": 66.7,
      "delay_pct": 73.2,
      "planned_cost": 160000000,
      "actual_cost": 1800000000,
      "planned_cost_range": [
        150000000,
        170000000
      ],
      "actual_cost_range": [
        1500000000,
        2100000000
      ],
      "cost_currency": "GBP",
      "planned_cost_year": 1962,
      "cost_year": 1976,
      "planned_fx_to_usd": 2.8,
      "actual_fx_to_usd": 1.8048,
      "planned_cost_usd_nominal": 449280000,
      "cost_usd_nominal": 3249000000,
      "planned_cost_usd_today": 4781940594,
      "cost_usd_today": 18382500000,
      "overrun_usd_today": 16748500000,
      "overrun_pct": 1025,
      "overrun_basis": "nominal",
      "rebaseline_cost": 825000000,
      "rebaseline_cost_year": 1970,
      "rebaseline_end": null,
      "rebaseline_label": "1970 government estimate (June 1970 prices)",
      "rebaseline_overrun_pct": 118.2,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Treaty and design definition",
          "planned_start": "1962-11",
          "planned_end": null,
          "actual_start": "1962-11-29",
          "actual_end": "1965-02",
          "note": "Anglo-French treaty signed 29 Nov 1962 by Geoffroy de Courcel and Julian Amery; costs split 50:50."
        },
        {
          "name": "Prototype construction",
          "planned_start": null,
          "planned_end": "1966",
          "actual_start": "1965-02",
          "actual_end": "1967-12",
          "note": "Prototype construction began Feb 1965; 001 rolled out in Toulouse late 1967. The 1962 plan expected a first flight in 1966."
        },
        {
          "name": "Prototype flight testing",
          "planned_start": "1966",
          "planned_end": null,
          "actual_start": "1969-03-02",
          "actual_end": "1975-10-09",
          "note": "001 first flew 2 Mar 1969 (André Turcat); first UK-built aircraft flew 9 Apr 1969; supersonic from 1 Oct 1969."
        },
        {
          "name": "Certification",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1975-10-09",
          "actual_end": "1975-12-05",
          "note": "French certificate of airworthiness 9 Oct 1975; UK CAA certification 5 Dec 1975."
        },
        {
          "name": "Entry into service",
          "planned_start": "1970",
          "planned_end": "1970",
          "actual_start": "1976-01-21",
          "actual_end": "1976-01-21",
          "note": "Air France and British Airways began scheduled flights the same day."
        }
      ],
      "milestones": [
        {
          "name": "Treaty signed",
          "planned_date": "1962-11-29",
          "actual_date": "1962-11-29"
        },
        {
          "name": "First flight (001)",
          "planned_date": "1966",
          "actual_date": "1969-03-02"
        },
        {
          "name": "First supersonic flight",
          "planned_date": null,
          "actual_date": "1969-10-01"
        },
        {
          "name": "UK certification",
          "planned_date": null,
          "actual_date": "1975-12-05"
        },
        {
          "name": "Entry into service",
          "planned_date": "1970",
          "actual_date": "1976-01-21"
        }
      ],
      "headline": "Concorde's development estimate rose from £150-170 million at the 1962 treaty to an estimated £1.5-2.1 billion, and passenger service began six years late, in 1976.",
      "summary": "Britain and France signed a treaty on 29 November 1962 to jointly develop a supersonic airliner and share the cost equally. At signing, the British government put development at £150-170 million, with a first flight in 1966 and service in 1970. Prototype 001 flew from Toulouse on 2 March 1969, certification came in late 1975, and Air France and British Airways opened service on 21 January 1976. Through March 1976 the program had cost an estimated £1.5-2.1 billion in 1976 pounds.",
      "what_went_wrong_or_right": "Hansard records the estimate climbing in steps as the design matured: £150-170 million in November 1962, £450 million plus a £50 million contingency by early 1967, £730 million at October 1969 prices and £825 million at June 1970 prices. Ministers said later figures also covered work needed after certification, so part of the growth was scope that the first estimate omitted. Technical novelty was the main driver: Concorde was a Mach 2 airliner with no precedent, and the prototypes flew three years after the 1966 target. A binding intergovernmental treaty made cancellation diplomatically costly, so the program continued as costs rose. Inflation in the late 1960s and 1970s added to nominal totals, which is why the 1976 figure is several times larger in money terms than the real-terms growth alone. The BBC's Timewatch, cited by Wikipedia, said estimates had already gone from £70 million to £150 million by 1962. Engineering results were strong: the aircraft met its Mach 2 transatlantic mission and flew until 2003.",
      "lessons": [
        "Price the full scope at go-ahead, including post-certification work, or later estimates will look like overruns.",
        "Treaty-level commitments make cancellation expensive; build explicit review gates into binding agreements.",
        "For first-of-a-kind technology, add schedule contingency measured in years, not months."
      ],
      "fun_fact": "Prototype 001 made Concorde's first flight from Toulouse on 2 March 1969 with test pilot André Turcat at the controls.",
      "method_tags": [
        "waterfall",
        "prototyping"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004"
      ],
      "sources": [
        {
          "title": "Concorde",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Concorde",
          "accessed": "2026-10-25"
        },
        {
          "title": "Written Answers, 10 February 1967 (Concord development cost)",
          "publisher": "UK Parliament Hansard",
          "url": "https://hansard.parliament.uk/html/Commons/1967-02-10/WrittenAnswers",
          "accessed": "2026-10-25"
        },
        {
          "title": "House of Commons, 28 October 1970",
          "publisher": "UK Parliament Hansard",
          "url": "https://hansard.parliament.uk/html/Commons/1970-10-28/CommonsChamber",
          "accessed": "2026-10-25"
        },
        {
          "title": "This week in 1962: supersonic civil air travel",
          "publisher": "The Engineer",
          "url": "https://www.theengineer.co.uk/content/news/this-week-in-1962-supersonic-civil-air-travel/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Concorde History",
          "publisher": "Aerospaceweb.org",
          "url": "https://aerospaceweb.org/question/planes/q0186.shtml",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: development cost estimate of £150-170 million given when the Anglo-French agreement was signed in November 1962 (Hansard written answer, 10 Feb 1967); midpoint £160m stored. Planned schedule from The Engineer, Dec 1962: first flight 1966, service 1970. Actual cost: programme cost through March 1976 'between £1.5 and £2.1 billion in 1976 pounds' (Seebass 1997, cited by Wikipedia); midpoint £1.8bn stored. Other figures: about £1.134bn to develop and build the first four aircraft (Aerospaceweb); £825m at June 1970 prices (Hansard 28 Oct 1970). Costs are whole-programme (both governments), expressed in sterling. Figures are nominal and the 1962-1976 period had high inflation, so the nominal ratio overstates real growth. FX: GBP 1962 at the Bretton Woods par of US$2.80; 1976 annual average US$1.8048 (Federal Reserve G.5A historical series). Hansard and The Engineer pages returned HTTP 403 to automated fetch; their content was confirmed through search-result extracts. Wikipedia's lead also mentions a £70m estimate, which predates the treaty. Baseline audit 2026-10-25: Planned figures unchanged (November 1962 GBP 150-170m). Added the government estimate of GBP 825m at June 1970 prices (Hansard, 28 October 1970) as the rebaseline.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 74,
      "slug": "queen-mary-2",
      "name": "RMS Queen Mary 2 construction",
      "short_name": "Queen Mary 2 build",
      "category": "transport_vehicles",
      "subcategory": "ocean liner",
      "country": "France",
      "country_code": "FR",
      "countries": [
        "France",
        "United Kingdom",
        "United States"
      ],
      "continent": "Europe",
      "city": "Saint-Nazaire",
      "lat": 47.285,
      "lng": -2.21,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "2000-11-06",
      "planned_end": "2003-12",
      "actual_start": "2000-11-06",
      "actual_end": "2003-12-22",
      "actual_is_forecast": false,
      "planned_duration_months": 37.3,
      "actual_duration_months": 37.5,
      "delay_months": 0.2,
      "delay_pct": 0.6,
      "planned_cost": 780000000,
      "actual_cost": 840000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        780000000,
        900000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 2000,
      "cost_year": 2003,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 780000000,
      "cost_usd_nominal": 840000000,
      "planned_cost_usd_today": 1458260870,
      "cost_usd_today": 1470151954,
      "overrun_usd_today": 105010854,
      "overrun_pct": 7.7,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Concept and tendering (Project Queen Mary)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1998-12",
          "actual_end": "2000-11-06",
          "note": "Cunard released details of Project Queen Mary in Dec 1998; contract signed with Alstom Chantiers de l'Atlantique 6 Nov 2000 (hull G32)."
        },
        {
          "name": "Detailed design and block fabrication",
          "planned_start": "2000-11",
          "planned_end": null,
          "actual_start": "2000-11-06",
          "actual_end": "2002-07-04",
          "note": "Design and early steel work ahead of keel laying."
        },
        {
          "name": "Hull assembly in the building dock",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2002-07-04",
          "actual_end": "2003-03-21",
          "note": "Keel laid 4 Jul 2002 in the Louis Joubert Lock area at Saint-Nazaire; floated out 21 Mar 2003."
        },
        {
          "name": "Fitting out and sea trials",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2003-03-21",
          "actual_end": "2003-12-22",
          "note": "Fitted out in Bassin C; sea trials late Sept and early Nov 2003; gangway collapse 15 Nov 2003 killed 16 people."
        },
        {
          "name": "Delivery and maiden voyage",
          "planned_start": "2003-12",
          "planned_end": "2004-01",
          "actual_start": "2003-12-22",
          "actual_end": "2004-01-12",
          "note": "Left Saint-Nazaire 22 Dec 2003, arrived Southampton 26 Dec; maiden voyage 12 Jan 2004."
        }
      ],
      "milestones": [
        {
          "name": "Contract signed",
          "planned_date": "2000-11-06",
          "actual_date": "2000-11-06"
        },
        {
          "name": "Keel laid",
          "planned_date": null,
          "actual_date": "2002-07-04"
        },
        {
          "name": "Float out",
          "planned_date": null,
          "actual_date": "2003-03-21"
        },
        {
          "name": "Handover and departure from Saint-Nazaire",
          "planned_date": "2003-12",
          "actual_date": "2003-12-22"
        },
        {
          "name": "Maiden voyage",
          "planned_date": null,
          "actual_date": "2004-01-12"
        }
      ],
      "headline": "Chantiers de l'Atlantique built Queen Mary 2, the largest ocean liner ever, on schedule in about three years after a contract worth about $780 million.",
      "summary": "Cunard, owned by Carnival Corporation, signed a contract with Alstom Chantiers de l'Atlantique on 6 November 2000 to build Queen Mary 2 at Saint-Nazaire for about $780 million, with service expected in late 2003. The keel was laid on 4 July 2002, the hull floated out on 21 March 2003 and sea trials ran that autumn. The ship left the yard on 22 December 2003 and sailed her maiden voyage from Southampton on 12 January 2004. Wikipedia states construction was completed on schedule.",
      "what_went_wrong_or_right": "The build met the late-2003 service date set at contract signing, and Wikipedia records that construction was completed on schedule. Hull assembly took under nine months from keel laying to float-out, leaving about nine months for fitting out and trials. The program's worst event was not a schedule or budget failure but a safety one: on 15 November 2003 a gangway to the ship collapsed into the dry dock, killing 16 people and injuring 32. Cost reporting is less clear than schedule. Carnival announced a cost of approximately $780 million in 2000; Travel Weekly reported £538 million at signing; a UK National Audit Office document gives about £550 million; and an earlier Wikipedia version listed £460 million (about $900 million). Wikipedia now gives a final cost of about $300,000 per berth. These figures suggest the final cost stayed close to the contract.",
      "lessons": [
        "A builder with repeat experience of the ship type can hold a fixed delivery date.",
        "Visitor access to a construction site needs the same engineering checks as permanent structures.",
        "Record final cost in one currency and basis, or later comparisons become guesswork."
      ],
      "fun_fact": "Queen Mary 2 remains the largest ocean liner ever built, as distinct from cruise ships.",
      "method_tags": [
        "fixed_price"
      ],
      "related_history_ids": [
        "gantt-shipbuilding-1917"
      ],
      "sources": [
        {
          "title": "Queen Mary 2",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Queen_Mary_2",
          "accessed": "2026-10-25"
        },
        {
          "title": "Carnival Corporation finalizes contract for Cunard Line's Queen Mary 2",
          "publisher": "MarineLink",
          "url": "https://www.marinelink.com/news/319484",
          "accessed": "2026-10-25"
        },
        {
          "title": "RMS Queen Mary 2 (archived Wikipedia text)",
          "publisher": "SolarSPELL / Wikipedia for Schools",
          "url": "https://solarspell-dls.sfis.asu.edu/mea/wikipedia/wp/r/RMS_Queen_Mary_2.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: contract signed 6 Nov 2000 at 'approximately $780 million' with service 'expected in late 2003' (Carnival release via MarineLink). Actual cost: no single audited final figure; sources give £460m (~$900m, archived Wikipedia), about £550m (UK NAO document, seen only in search snippet; its URL returned 404), and about $300,000 per berth (current Wikipedia). The stored $840m is the midpoint of the $780m-$900m range and is indicative only. USD used to avoid mixing sterling and dollar figures; nominal. The fixed_price tag reflects the announced contract price, not a published contract text. Actual end defined as handover/departure from the yard on 22 Dec 2003; the archived Wikipedia text gives completion 23 Dec and delivery 26 Dec at Southampton. Gangway collapse figures from Wikipedia.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 75,
      "slug": "titanic",
      "name": "RMS Titanic construction",
      "short_name": "RMS Titanic build",
      "category": "transport_vehicles",
      "subcategory": "ocean liner",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "Belfast",
      "lat": 54.6081,
      "lng": -5.9097,
      "era": "1900-1945",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": "1909-03-31",
      "planned_end": "1912-03-20",
      "actual_start": "1909-03-31",
      "actual_end": "1912-04-10",
      "actual_is_forecast": false,
      "planned_duration_months": 35.6,
      "actual_duration_months": 36.3,
      "delay_months": 0.7,
      "delay_pct": 1.9,
      "planned_cost": 1500000,
      "actual_cost": null,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "GBP",
      "planned_cost_year": 1908,
      "cost_year": 1912,
      "planned_fx_to_usd": 4.86,
      "actual_fx_to_usd": 4.86,
      "planned_cost_usd_nominal": 7299000,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": 261547500,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Design and agreement",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1908-07-31",
          "actual_end": "1909-03-31",
          "note": "Bruce Ismay approved the design and signed letters of agreement two days after 29 July 1908; Titanic's order is dated 17 Sept 1908 (yard number 401)."
        },
        {
          "name": "Hull construction on the slipway",
          "planned_start": "1909-03-31",
          "planned_end": null,
          "actual_start": "1909-03-31",
          "actual_end": "1911-05-31",
          "note": "Built under the Arrol Gantry alongside Olympic; about 26 months keel to launch."
        },
        {
          "name": "Fitting out",
          "planned_start": "1911-05-31",
          "planned_end": null,
          "actual_start": "1911-05-31",
          "actual_end": "1912-03-31",
          "note": "Engines, funnels and superstructure installed over about a year; work slowed when men and parts were diverted to repair Olympic after the 20 Sept 1911 Hawke collision."
        },
        {
          "name": "Graving dock work",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1912-02-03",
          "actual_end": "1912-03-06",
          "note": "In Thompson Graving Dock, moved out on 6 Mar 1912 to make way for Olympic's repair after she lost a propeller blade."
        },
        {
          "name": "Sea trials and maiden voyage",
          "planned_start": null,
          "planned_end": "1912-03-20",
          "actual_start": "1912-04-02",
          "actual_end": "1912-04-10",
          "note": "Sea trials began 6 am on 2 Apr 1912; maiden voyage from Southampton 10 Apr 1912."
        }
      ],
      "milestones": [
        {
          "name": "Keel laid",
          "planned_date": null,
          "actual_date": "1909-03-31"
        },
        {
          "name": "Launch",
          "planned_date": null,
          "actual_date": "1911-05-31"
        },
        {
          "name": "Sea trials",
          "planned_date": null,
          "actual_date": "1912-04-02"
        },
        {
          "name": "Maiden voyage departs Southampton",
          "planned_date": "1912-03-20",
          "actual_date": "1912-04-10"
        }
      ],
      "headline": "Harland & Wolff built Titanic for about £1.5 million, but repairs to her sister ship Olympic pushed the maiden voyage back three weeks, from 20 March to 10 April 1912.",
      "summary": "White Star Line ordered Titanic from Harland & Wolff in Belfast as the second of three Olympic-class liners. Her keel was laid on 31 March 1909 beside Olympic under the Arrol Gantry, and she was launched on 31 May 1911. Fitting out took about a year. Work was slowed twice when the yard diverted labor and parts to repair Olympic, moving the maiden voyage from 20 March to 10 April 1912. A price of £3 million was agreed for the first two ships, about £1.5 million each; no separate final cost for Titanic was published.",
      "what_went_wrong_or_right": "The yard delivered two of the largest ships of their day almost in parallel, which required rebuilding its slipways: Harland & Wolff demolished three slipways to make two larger ones and built the Arrol Gantry, more than 6,000 tonnes of steel, over them. The contract was cost-plus: the builder was authorized to spend what it needed, plus extras and a five percent fee, which removed price pressure but also budget discipline. The schedule slipped because of resource sharing between sister ships. After HMS Hawke struck Olympic on 20 September 1911, the yard replaced Olympic's damaged propeller shaft with one made for Titanic; when Olympic lost a propeller blade on 24 February 1912, Titanic was moved out of the graving dock on 6 March to make room. Together these delayed the maiden voyage by three weeks. Wikipedia records eight deaths during construction and fitting out and 246 injuries. Four days into her maiden voyage, on 15 April 1912, Titanic sank after striking an iceberg.",
      "lessons": [
        "Programs that share a yard, dock or crew across sister projects must plan for one project's emergency.",
        "Cost-plus contracts deliver speed and quality but need separate controls on scope.",
        "Building the facility, here slipways and a gantry, is part of the project schedule."
      ],
      "fun_fact": "The Arrol Gantry built over Titanic's slipway stood 228 feet (69 m) high and was 840 feet (260 m) long.",
      "method_tags": [
        "cost_plus",
        "phased_delivery"
      ],
      "related_history_ids": [
        "gantt-1910",
        "taylor-1911",
        "gantt-shipbuilding-1917"
      ],
      "sources": [
        {
          "title": "RMS Titanic",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/RMS_Titanic",
          "accessed": "2026-10-25"
        },
        {
          "title": "Olympic–Hawke collision",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Olympic%E2%80%93Hawke_collision",
          "accessed": "2026-10-25"
        },
        {
          "title": "Olympic-class ocean liner",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Olympic-class_ocean_liner",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline cost: £3 million agreed for the first two Olympic-class ships plus extras and a 5% fee (Wikipedia, RMS Titanic); half of that, £1.5m, is used as Titanic's planned cost. Actual: £1.5m from the Wikipedia infobox. No separate audited final cost for Titanic alone was found, so the zero overrun reflects the absence of data as much as performance. Baseline schedule: maiden voyage planned for 20 March 1912 (Wikipedia, Olympic–Hawke collision). Start: keel laying 31 Mar 1909; design and agreement phase begins with letters of agreement signed about 31 July 1908. Wikipedia notes an inconsistency over the completion date (infobox 2 Apr 1912; text says fitting out finished two days before trials began on 2 Apr). FX: sterling under the gold standard, about US$4.86 per pound in 1908-1912 (MeasuringWorth historical series). Project end is defined as the maiden voyage departure; the sinking is noted for context only. Editor: actual_cost set to null because no separate final build cost for Titanic is published; the earlier equal figure was a half-share of the two-ship contract, not an outturn.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": true
    },
    {
      "id": 76,
      "slug": "tesla-model-3",
      "name": "Tesla Model 3 production ramp",
      "short_name": "Tesla Model 3 ramp",
      "category": "transport_vehicles",
      "subcategory": "car production line",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Fremont",
      "lat": 37.4945,
      "lng": -121.9446,
      "era": "2015-now",
      "status": "completed",
      "outcome": "late",
      "planned_start": "2017-07",
      "planned_end": "2017-12",
      "actual_start": "2017-07",
      "actual_end": "2018-06-30",
      "actual_is_forecast": false,
      "planned_duration_months": 5,
      "actual_duration_months": 11.5,
      "delay_months": 6.5,
      "delay_pct": 129.9,
      "planned_cost": 2250000000,
      "actual_cost": null,
      "planned_cost_range": [
        2000000000,
        2500000000
      ],
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2017,
      "cost_year": null,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 2250000000,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": 2955301385,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Unveiling and pre-production",
          "planned_start": "2016-03-31",
          "planned_end": "2017-07",
          "actual_start": "2016-03-31",
          "actual_end": "2017-07",
          "note": "Unveiled with reservations opening 31 Mar 2016; Tesla accelerated its build plan in 2016."
        },
        {
          "name": "Production launch",
          "planned_start": "2017-07",
          "planned_end": "2017-09",
          "actual_start": "2017-07",
          "actual_end": "2017-09",
          "note": "Limited production from July 2017; first cars handed over 28 Jul 2017. Tesla guided to just over 1,500 cars in Q3 2017 and missed it."
        },
        {
          "name": "Ramp to 5,000 per week (original plan)",
          "planned_start": "2017-10",
          "planned_end": "2017-12",
          "actual_start": "2017-10",
          "actual_end": "2017-12-31",
          "note": "Q4 2017 output was 2,425 Model 3s for the whole quarter; rate exceeded 1,000 per week at year end."
        },
        {
          "name": "Revised ramp and GA4 line",
          "planned_start": "2018-01",
          "planned_end": "2018-06-30",
          "actual_start": "2018-01",
          "actual_end": "2018-06-30",
          "note": "Revised targets: about 2,500 per week by end of Q1 2018 and 5,000 by end of Q2 2018. New GA4 assembly line built about 20% of the last week's output."
        }
      ],
      "milestones": [
        {
          "name": "Unveiling",
          "planned_date": "2016-03-31",
          "actual_date": "2016-03-31"
        },
        {
          "name": "First customer handovers",
          "planned_date": "2017-07",
          "actual_date": "2017-07-28"
        },
        {
          "name": "5,000 Model 3s in one week",
          "planned_date": "2017-12",
          "actual_date": "2018-06-30"
        }
      ],
      "headline": "Tesla planned to build 5,000 Model 3s a week by December 2017; it built 2,425 in the whole fourth quarter and reached 5,031 in a week only at the end of June 2018.",
      "summary": "Tesla unveiled the Model 3 on 31 March 2016 and began limited production in July 2017, handing over the first cars on 28 July. In its Q2 2017 letter the company said it would reach a run rate of 5,000 vehicles a week by the end of 2017, after spending an expected $2-2.5 billion in capital before production. Output in Q4 2017 was 2,425 cars. Tesla pushed the target to the end of Q2 2018 and produced 5,031 Model 3s in the last seven days of that quarter.",
      "what_went_wrong_or_right": "Tesla chose in 2016 to accelerate the build plan, a decision Wikipedia notes led to the predicted 'production bottlenecks' and 'production hell'. The plan assumed that a new car, new battery module lines at the Nevada Gigafactory and a new assembly process would all ramp together. They did not: CNBC reported in February 2018 that battery-line constraints at the Gigafactory were holding back output, and Q3 2017 production fell far short of the 1,500-car guidance. In January 2018 Tesla reset the schedule to about 2,500 a week by the end of Q1 and 5,000 by the end of Q2. To hit the second target it added a new general assembly line, GA4, which its 2 July 2018 release said built about 20% of Model 3s in the final week. The goal was met six months late, and Tesla then guided to 6,000 a week.",
      "lessons": [
        "Ramp plans for new factories should assume each new process line delays the slowest one.",
        "Publish run-rate targets only after the bottleneck process has demonstrated that rate.",
        "A parallel, simpler line can recover a schedule faster than fixing a complex one."
      ],
      "fun_fact": "In Q2 2018 Tesla built more Model 3s (28,578) than Model S and Model X combined (24,761) for the first time.",
      "method_tags": [
        "fast_track",
        "iterative"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "toyota-kanban-1948"
      ],
      "sources": [
        {
          "title": "Tesla Model 3",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Tesla_Model_3",
          "accessed": "2026-10-25"
        },
        {
          "title": "Tesla Q2 2018 Vehicle Production and Deliveries (Form 8-K Exhibit 99.1)",
          "publisher": "Tesla, Inc. / U.S. SEC",
          "url": "https://www.sec.gov/Archives/edgar/data/1318605/000156459018016465/tsla-ex991_6.htm",
          "accessed": "2026-10-25"
        },
        {
          "title": "Tesla Q4 2017 Vehicle Production and Deliveries",
          "publisher": "Tesla, Inc.",
          "url": "https://ir.tesla.com/news-releases/news-release-details/tesla-q4-2017-vehicle-production-and-deliveries",
          "accessed": "2026-10-25"
        },
        {
          "title": "Tesla Q4 2017 Model 3 numbers",
          "publisher": "CNBC",
          "url": "https://www.cnbc.com/2018/02/07/tesla-q4-2017-model-3-numbers.html",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline schedule: Tesla's Q2 2017 shareholder letter guided to 'just over 1,500 vehicles in Q3, and achieve a run rate of 5,000 vehicles per week by the end of 2017' (quoted in Wikipedia and secondary summaries). Actual end: the 5,031-car week ending 30 June 2018 (Tesla release, 2 July 2018). Cost: planned capex of US$2.0-2.5bn before Model 3 production (Wikipedia, citing Tesla); midpoint stored. Tesla did not report a Model 3-specific actual capex total, so actual_cost is null and no overrun can be computed. This record measures a production ramp, not a full vehicle development program. The Q4 2017 release and CNBC article were confirmed through search extracts; the SEC exhibit was opened directly.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 77,
      "slug": "tokaido-shinkansen",
      "name": "Tōkaidō Shinkansen",
      "short_name": "Tokaido Shinkansen",
      "category": "transport_vehicles",
      "subcategory": "high-speed rail",
      "country": "Japan",
      "country_code": "JP",
      "countries": [
        "Japan"
      ],
      "continent": "Asia",
      "city": "Tokyo",
      "lat": 35.6812,
      "lng": 139.7671,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1959-04-20",
      "planned_end": "1964-10",
      "actual_start": "1959-04-20",
      "actual_end": "1964-10-01",
      "actual_is_forecast": false,
      "planned_duration_months": 65.8,
      "actual_duration_months": 65.4,
      "delay_months": -0.5,
      "delay_pct": -0.7,
      "planned_cost": 194800000000,
      "actual_cost": 380000000000,
      "planned_cost_range": [
        172500000000,
        194800000000
      ],
      "actual_cost_range": [
        379000000000,
        380000000000
      ],
      "cost_currency": "JPY",
      "planned_cost_year": 1958,
      "cost_year": 1964,
      "planned_fx_to_usd": 0.0027778,
      "actual_fx_to_usd": 0.0027778,
      "planned_cost_usd_nominal": 541349200,
      "cost_usd_nominal": 1049940000,
      "planned_cost_usd_today": 6041007509,
      "cost_usd_today": 10899323498,
      "overrun_usd_today": 5311986084,
      "overrun_pct": 95.1,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Approval and authorization",
          "planned_start": "1958-12",
          "planned_end": "1959-04",
          "actual_start": "1958-12",
          "actual_end": "1959-04-13",
          "note": "Diet approved ¥194.8bn of funding; formal ministerial authorization 13 Apr 1959."
        },
        {
          "name": "Civil construction",
          "planned_start": "1959-04-20",
          "planned_end": "1964",
          "actual_start": "1959-04-20",
          "actual_end": "1964-07-01",
          "note": "Groundbreaking at the Shin-Tanna Tunnel portal 20 Apr 1959; last rail laid near Kawasaki 1 Jul 1964."
        },
        {
          "name": "World Bank financing",
          "planned_start": "1960-05",
          "planned_end": null,
          "actual_start": "1960-05",
          "actual_end": "1961-05",
          "note": "World Bank mission May 1960; $80m loan signed in Washington May 1961, about 15% of the estimated cost."
        },
        {
          "name": "Model line testing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1962-06",
          "actual_end": "1964-07",
          "note": "12 km test section from Kamonomiya opened June 1962, extended to 37 km in Oct 1962; 256 km/h record on 30 Mar 1963."
        },
        {
          "name": "Opening",
          "planned_start": "1964-10",
          "planned_end": "1964-10",
          "actual_start": "1964-10-01",
          "actual_end": "1964-10-01",
          "note": "Opened nine days before the Tokyo Olympics began."
        }
      ],
      "milestones": [
        {
          "name": "Groundbreaking",
          "planned_date": "1959-04-20",
          "actual_date": "1959-04-20"
        },
        {
          "name": "World Bank loan signed",
          "planned_date": null,
          "actual_date": "1961-05"
        },
        {
          "name": "256 km/h test record",
          "planned_date": null,
          "actual_date": "1963-03-30"
        },
        {
          "name": "Last rail laid",
          "planned_date": null,
          "actual_date": "1964-07-01"
        },
        {
          "name": "Line opens",
          "planned_date": "1964-10",
          "actual_date": "1964-10-01"
        }
      ],
      "headline": "The Tōkaidō Shinkansen opened on time for the 1964 Tokyo Olympics, but cost about ¥380 billion against a ¥194.8 billion estimate, and its two leaders resigned.",
      "summary": "Japanese National Railways began building a new standard-gauge line between Tokyo and Osaka on 20 April 1959 under president Shinji Sogō and chief engineer Hideo Shima. The 1958 estimate was ¥172.5 billion, or ¥194.8 billion including interest, and a World Bank loan of $80 million covered about 15 percent. The line opened on 1 October 1964, ahead of the Tokyo Olympics, after about five and a half years. Final cost was about ¥380 billion, almost double the estimate.",
      "what_went_wrong_or_right": "The schedule held because the Olympic opening on 10 October 1964 was a fixed, public deadline and JNR proved the technology early on a 37 km model line, where a train reached 256 km/h in March 1963. The budget did not hold. Wikipedia's biography of Sogō, citing Christopher Hood's history of the Shinkansen, says he kept estimated costs 'deliberately low' because he feared a realistic figure would lose government and World Bank support. When the shortfall appeared, he diverted resources from other JNR projects; once that became a political issue, he resigned in 1963 and Shima left with him. The World Bank loan also had conditions: it could not be used for experimental technology, which pushed JNR to present the line as proven engineering. The cost overrun did not prevent the line from becoming commercially successful, and the model was copied by high-speed networks worldwide.",
      "lessons": [
        "A fixed public deadline can protect a schedule, but costs then absorb the pressure.",
        "Deliberately low estimates win approval and later cost the sponsor their job.",
        "Build a test section early to retire technical risk before the main line."
      ],
      "fun_fact": "On 30 March 1963 a test train on the Kamonomiya model line reached 256 km/h, a Japanese rail speed record at the time.",
      "method_tags": [
        "phased_delivery",
        "prototyping"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Tōkaidō Shinkansen",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/T%C5%8Dkaid%C5%8D_Shinkansen",
          "accessed": "2026-10-25"
        },
        {
          "title": "Shinji Sogō",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Shinji_Sog%C5%8D",
          "accessed": "2026-10-25"
        },
        {
          "title": "Bullet at 60 - Timeline #2",
          "publisher": "Trains to Beyond",
          "url": "https://trainstobeyond.com/bullet-at-60-timeline/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the 1958 estimate of ¥172.5 billion, or ¥194.8 billion including interest (Trains to Beyond); Wikipedia says the Diet approved ¥194.8bn. The ¥194.8bn figure is stored as main value since it is the most cited; the 172.5bn excluding interest gives the low end of planned_cost_range. Actual: ¥379bn (Trains to Beyond) to about ¥380bn (widely cited); it is unclear whether the final figure includes interest on the same basis. Planned end: the program was a five-year construction plan timed for the October 1964 Olympics; no exact planned opening day was found. FX: yen pegged at ¥360 per US dollar under Bretton Woods from 1949 to 1971, so US$0.0027778 per yen in both years. Nominal figures; Japanese inflation in 1958-1964 was moderate but not zero. World Bank loan details from Wikipedia and Trains to Beyond.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 78,
      "slug": "toyota-prius",
      "name": "Toyota Prius development (G21 project)",
      "short_name": "Toyota Prius (G21)",
      "category": "transport_vehicles",
      "subcategory": "hybrid car",
      "country": "Japan",
      "country_code": "JP",
      "countries": [
        "Japan"
      ],
      "continent": "Asia",
      "city": "Toyota City",
      "lat": 35.0833,
      "lng": 137.1561,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": "1993-09",
      "planned_end": "1998-12",
      "actual_start": "1993-09",
      "actual_end": "1997-12-10",
      "actual_is_forecast": false,
      "planned_duration_months": 63,
      "actual_duration_months": 50.8,
      "delay_months": -12.2,
      "delay_pct": -19.3,
      "planned_cost": null,
      "actual_cost": null,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "JPY",
      "planned_cost_year": null,
      "cost_year": null,
      "planned_fx_to_usd": null,
      "actual_fx_to_usd": null,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": null,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "G21 study and concept definition",
          "planned_start": "1993-09",
          "planned_end": null,
          "actual_start": "1993-09",
          "actual_end": "1994-12",
          "note": "Study group formed Sept 1993; project team's first official meeting 1 Feb 1994 with Takeshi Uchiyamada as chief engineer; hybrid concept chosen late 1994."
        },
        {
          "name": "Concept car and first prototype",
          "planned_start": null,
          "planned_end": "1995-10",
          "actual_start": "1995-01",
          "actual_end": "1995-12",
          "note": "Prius concept shown at the Tokyo Motor Show 27 Oct 1995; first production-hybrid prototype assembled early Nov 1995 took 49 days to run, and then stopped after about 500 m."
        },
        {
          "name": "Hybrid system engineering and test driving",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1996-03",
          "actual_end": "1997-10",
          "note": "Takehisa Yaegashi named hybrid system team leader March 1996; test driving began late 1996; schedule pulled forward by a year."
        },
        {
          "name": "Public announcement and production preparation",
          "planned_start": null,
          "planned_end": "1998-12",
          "actual_start": "1997-03-25",
          "actual_end": "1997-12",
          "note": "President Hiroshi Okuda announced the hybrid system 25 Mar 1997; production model unveiled Oct 1997; production at Takaoka plant from Dec 1997."
        },
        {
          "name": "Japan launch",
          "planned_start": "1998-12",
          "planned_end": "1998-12",
          "actual_start": "1997-12-10",
          "actual_end": "1997-12-10",
          "note": "Went on sale in Japan 10 Dec 1997, the same month as the COP3 climate conference in Kyoto."
        }
      ],
      "milestones": [
        {
          "name": "G21 project team first meeting",
          "planned_date": null,
          "actual_date": "1994-02-01"
        },
        {
          "name": "Prius concept at Tokyo Motor Show",
          "planned_date": "1995-10",
          "actual_date": "1995-10-27"
        },
        {
          "name": "Hybrid system announced by Okuda",
          "planned_date": null,
          "actual_date": "1997-03-25"
        },
        {
          "name": "Japan sales launch",
          "planned_date": "1998-12",
          "actual_date": "1997-12-10"
        }
      ],
      "headline": "Toyota's management pulled the Prius launch forward by a year, from the end of 1998 to December 1997, and the world's first mass-produced hybrid went on sale on 10 December 1997.",
      "summary": "Toyota's G21 project began as a study group in September 1993 to define a car for the 21st century, led from 1994 by chief engineer Takeshi Uchiyamada. The team chose a hybrid drivetrain and showed a concept at the October 1995 Tokyo Motor Show. The original target was sales and production by the end of 1998, but management accelerated the program by a year. The NHW10 Prius went on sale in Japan on 10 December 1997, built at the Takaoka plant.",
      "what_went_wrong_or_right": "The Prius is a rare case of a program that finished earlier than its plan. Toyota's own 2017 history says management decided to bring the launch forward by a year to December 1997, the month of the COP3 climate conference in Kyoto, which gave the target a fixed external date. The engineering risk was high: the first production-hybrid prototype, assembled in early November 1995, took 49 days to get running and then stopped after about 500 meters. Toyota reorganized, naming veteran engineer Takehisa Yaegashi to lead the hybrid system team in March 1996, and worked with production engineering in parallel through simultaneous engineering. Wikipedia says the team reviewed more than 100 hybrid layouts before choosing one. President Hiroshi Okuda committed publicly at a 25 March 1997 briefing. The trade-off was financial: Wikipedia reports Toyota executives said the company lost money on each first-generation car and broke even only with the NHW11 that followed.",
      "lessons": [
        "A fixed external event can justify compressing a schedule, if leadership commits publicly.",
        "Run production engineering in parallel with product design when time is the constraint.",
        "Early prototype failure is information; staff up the weakest subsystem quickly."
      ],
      "fun_fact": "Launch orders for the first Prius reached 3,500 cars in the first month, three times Toyota's target.",
      "method_tags": [
        "fast_track",
        "prototyping",
        "lean"
      ],
      "related_history_ids": [
        "toyota-kanban-1948",
        "scrum-paper-1986"
      ],
      "sources": [
        {
          "title": "Toyota Prius (XW10)",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Toyota_Prius_(XW10)",
          "accessed": "2026-10-25"
        },
        {
          "title": "Prius 20th anniversary development story (13 Dec 2017)",
          "publisher": "Toyota Motor Corporation",
          "url": "https://global.toyota/en/detail/20209735",
          "accessed": "2026-10-25"
        },
        {
          "title": "Toyota Prius",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Toyota_Prius",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline schedule: Toyota's 2017 history says the team was working toward sales and production by the end of 1998 before management accelerated the project by a year; planned_end therefore set to 1998-12. Fortune (2006, seen only in a search snippet) implies an even later target, so the size of the acceleration varies by source. Start: Sept 1993 G21 study group (Wikipedia XW10); some sources date the project from Jan/Feb 1994. Cost: Toyota did not publish a development budget or final development cost for the first Prius, so all cost fields are null and fx fields are null. Phase start/end dates for 'Concept car and first prototype' (1995-01) and 'Hybrid system engineering' end (1997-10) are approximate boundaries chosen between sourced events. Launch-order figure from Toyota's 2017 history. Editor decision 2026-10-25: kept in the dataset (flag was: Development cost not public (all cost fields null); schedule data only).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 79,
      "slug": "flamanville-3",
      "name": "Flamanville Nuclear Power Plant Unit 3",
      "short_name": "Flamanville 3",
      "category": "energy",
      "subcategory": "nuclear plant",
      "country": "France",
      "country_code": "FR",
      "countries": [
        "France"
      ],
      "continent": "Europe",
      "city": "Flamanville, Manche, Normandy",
      "lat": 49.5364,
      "lng": -1.8817,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2007-12",
      "planned_end": "2012",
      "actual_start": "2007-12-04",
      "actual_end": "2024-12-21",
      "actual_is_forecast": false,
      "planned_duration_months": 54.5,
      "actual_duration_months": 204.6,
      "delay_months": 149.7,
      "delay_pct": 274.4,
      "planned_cost": 3300000000,
      "actual_cost": 23700000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        22600000000,
        23700000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2006,
      "cost_year": 2023,
      "planned_fx_to_usd": 1.2563,
      "actual_fx_to_usd": 1.0813,
      "planned_cost_usd_nominal": 4144800000,
      "cost_usd_nominal": 25643400000,
      "planned_cost_usd_today": 6619501486,
      "cost_usd_today": 27096974115,
      "overrun_usd_today": 23323977720,
      "overrun_pct": 618.2,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Civil works and reactor building",
          "planned_start": "2007-12",
          "planned_end": null,
          "actual_start": "2007-12-04",
          "actual_end": "2015-04",
          "note": "Construction began 4 Dec 2007 with commercial operation planned for 2012."
        },
        {
          "name": "Component anomalies and repairs",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2015-04",
          "actual_end": "2024-05",
          "note": "April 2015: Areva reported lower-than-expected toughness in reactor vessel steel. June 2019: regulator required repair of eight main steam-line welds; more than 100 defective welds were later reported."
        },
        {
          "name": "Fuel loading and start-up",
          "planned_start": null,
          "planned_end": "2012",
          "actual_start": "2024-05-08",
          "actual_end": "2024-09",
          "note": "Fuel loaded 8-22 May 2024; reactor started up in early September 2024."
        },
        {
          "name": "Grid connection and power ascension",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2024-12-21",
          "actual_end": "2025-12-14",
          "note": "Connected to the grid 21 Dec 2024 at about 100 MW; first reached full power 14 Dec 2025."
        },
        {
          "name": "Commercial operation",
          "planned_start": null,
          "planned_end": "2012",
          "actual_start": "2025-12-14",
          "actual_end": "2026-05-05",
          "note": "Wikipedia reports commercial operation on 5 May 2026."
        }
      ],
      "milestones": [
        {
          "name": "First concrete",
          "planned_date": "2007-12",
          "actual_date": "2007-12-04"
        },
        {
          "name": "Fuel loading complete",
          "planned_date": null,
          "actual_date": "2024-05-22"
        },
        {
          "name": "Grid connection",
          "planned_date": "2012",
          "actual_date": "2024-12-21"
        },
        {
          "name": "First full power",
          "planned_date": null,
          "actual_date": "2025-12-14"
        },
        {
          "name": "Commercial operation",
          "planned_date": "2012",
          "actual_date": "2026-05-05"
        }
      ],
      "headline": "France's first EPR was budgeted at EUR 3.3bn for 2012; the Cour des comptes puts its full cost at EUR 23.7bn and it reached the grid 12 years late.",
      "summary": "Flamanville 3 is a 1,650 MW EPR reactor built by EDF on the Normandy coast. Construction began in December 2007 with an initial budget of EUR 3.3 billion and commercial operation planned for 2012. After vessel steel anomalies, weld defects and repeated re-baselining, it was connected to the grid on 21 December 2024 and reached full power in December 2025. France's audit court, the Cour des comptes, estimated the full cost at EUR 19.1 billion (2015 euros) in 2020 and EUR 23.7 billion (2023 euros) in January 2025.",
      "what_went_wrong_or_right": "The Cour des comptes' 2020 report on the EPR program and its January 2025 follow-up describe a first-of-a-kind project started before French industry had built a reactor for about 15 years, with loss of skills in the supply chain and design work not mature when construction began. Quality failures then drove most of the delay. In April 2015 Areva disclosed that steel in the reactor vessel head and bottom had lower-than-expected mechanical toughness, triggering a long regulatory review. In June 2019 the regulator required eight welds on the main steam lines, which pass through the containment, to be repaired before start-up, and more than 100 defective welds were eventually identified. Each problem forced a new schedule and budget. The audit court's 2025 figure of EUR 20.4bn in 2015 euros, or EUR 23.7bn in 2023 euros, includes financing costs and is EUR 1.3bn above its 2020 estimate; EDF's own figure is EUR 19.3bn (2015 euros). The court calculated that a 4% return would require selling power at more than EUR 122/MWh.",
      "lessons": [
        "Rebuild supplier skills and quality assurance before starting a first-of-a-kind build after a long hiatus.",
        "Independent audit of full cost, including financing, exposes overruns that headline construction budgets hide.",
        "Quality defects in safety-class components cost years; inspect at the factory, not on site."
      ],
      "fun_fact": "Fuel loading took just two weeks in May 2024, after more than 16 years of construction.",
      "method_tags": [
        "waterfall"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Flamanville Nuclear Power Plant",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Flamanville_Nuclear_Power_Plant",
          "accessed": "2026-10-25"
        },
        {
          "title": "Programme d'EPR: la Cour des comptes publie un rapport critique et recalcule le coût de Flamanville 3 (AFP)",
          "publisher": "Connaissance des Energies",
          "url": "https://www.connaissancedesenergies.org/afp/programme-depr-la-cour-des-comptes-publie-un-rapport-critique-et-recalcule-le-cout-de-flamanville-3-250114",
          "accessed": "2026-10-25"
        },
        {
          "title": "EPR de Flamanville: hausse du coût total",
          "publisher": "Opéra Énergie",
          "url": "https://opera-energie.com/media/epr-flamanville-hausse-cout-total/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: initial budget of EUR 3.3bn with commercial operation in 2012 (Wikipedia; also cited by the Cour des comptes). The price year of the 3.3bn is taken as 2006, the year of the go-ahead, and is nominal. Actual: Cour des comptes report 'La filière EPR: une dynamique nouvelle, des risques persistants' (14 Jan 2025): EUR 20.4bn in 2015 euros = EUR 23.7bn in 2023 euros, including financing costs; EDF's estimate EUR 19.3bn (2015) = EUR 22.6bn (2023), used as the low end of the range. The 2020 Cour des comptes report ('La filière EPR', July 2020) estimated up to EUR 19.1bn (2015 euros). The ccomptes.fr site refused connections during research, so the audit figures are sourced via AFP and Opéra Énergie reports of the 2025 report. The comparison is nominal because the baseline is not restated in 2023 euros, and the actual includes financing costs while the baseline likely did not. actual_end is grid connection (21 Dec 2024), the event most sources treat as completion; full power (14 Dec 2025) and commercial operation (5 May 2026, per Wikipedia only) are shown as phases and milestones. Construction start: 4 Dec 2007 in Wikipedia text, 3 Dec 2007 in its infobox. FX: Fed G.5A annual averages, EUR 2006 1.2563 and 2023 1.0813 USD per EUR. The skills-loss context is a summary of the Cour des comptes 2020 findings as widely reported. Baseline audit 2026-10-25: Planned figures unchanged (EUR 3.3bn, 2012 is the first). EDF announced many later estimates, but none was taken from an opened source, so no rebaseline is stored.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 80,
      "slug": "hinkley-point-c",
      "name": "Hinkley Point C Nuclear Power Station",
      "short_name": "Hinkley Point C",
      "category": "energy",
      "subcategory": "nuclear plant",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom",
        "France",
        "China"
      ],
      "continent": "Europe",
      "city": "Bridgwater, Somerset",
      "lat": 51.2059,
      "lng": -3.1429,
      "era": "2015-now",
      "status": "ongoing",
      "outcome": "over_budget_and_late",
      "planned_start": "2016-09",
      "planned_end": "2023",
      "actual_start": "2017-03",
      "actual_end": "2030",
      "actual_is_forecast": true,
      "planned_duration_months": 81.5,
      "actual_duration_months": 159.5,
      "delay_months": 84,
      "delay_pct": 103,
      "planned_cost": 16000000000,
      "actual_cost": 35000000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        31000000000,
        35000000000
      ],
      "cost_currency": "GBP",
      "planned_cost_year": 2012,
      "cost_year": 2015,
      "planned_fx_to_usd": 1.585,
      "actual_fx_to_usd": 1.5285,
      "planned_cost_usd_nominal": 25360000000,
      "cost_usd_nominal": 53480000000,
      "planned_cost_usd_today": 35564284679,
      "cost_usd_today": 72640600870,
      "overrun_usd_today": 39433469044,
      "overrun_pct": 118.8,
      "overrun_basis": "nominal",
      "rebaseline_cost": 18000000000,
      "rebaseline_cost_year": 2015,
      "rebaseline_end": "2025-12",
      "rebaseline_label": "2016 final investment decision",
      "rebaseline_overrun_pct": 94.4,
      "rebaseline_delay_months": 54.5,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Commercial deal and final investment decision",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2013-10",
          "actual_end": "2016-09-15",
          "note": "Strike price of GBP 92.50/MWh (2012 prices) agreed October 2013; EDF board approved 28 July 2016; UK government confirmed 15 Sep 2016 at GBP 18bn (2015 prices)."
        },
        {
          "name": "Site works and nuclear island foundations",
          "planned_start": "2016-09",
          "planned_end": null,
          "actual_start": "2017-03",
          "actual_end": "2020-06",
          "note": "ONR first construction consent 28 Mar 2017; Unit 1 base completed June 2019, Unit 2 base June 2020."
        },
        {
          "name": "Reactor buildings and dome lifts",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2020-06",
          "actual_end": "2025-07-17",
          "note": "Unit 1 dome placed 15 Dec 2023; Unit 2 dome placed 17 July 2025 by the Big Carl crane."
        },
        {
          "name": "Mechanical, electrical and commissioning (Unit 1)",
          "planned_start": null,
          "planned_end": "2023",
          "actual_start": "2023-12-15",
          "actual_end": "2030",
          "note": "Forecast: EDF moved Unit 1 first power to 2030 in its February 2026 results, inside the 2029-2031 range set in January 2024."
        }
      ],
      "milestones": [
        {
          "name": "Final investment decision confirmed",
          "planned_date": null,
          "actual_date": "2016-09-15"
        },
        {
          "name": "First construction consent from ONR",
          "planned_date": null,
          "actual_date": "2017-03-28"
        },
        {
          "name": "Unit 1 dome lifted",
          "planned_date": null,
          "actual_date": "2023-12-15"
        },
        {
          "name": "Unit 1 first power",
          "planned_date": "2023",
          "actual_date": "2030"
        }
      ],
      "headline": "Hinkley Point C was presented in 2012 as a GBP 16bn plant generating by 2023; EDF now expects about GBP 35bn in 2015 prices and Unit 1 in 2030.",
      "summary": "Hinkley Point C is a two-reactor, 3.2 GW EPR nuclear station being built by EDF with China General Nuclear in Somerset, England. At the September 2016 go-ahead it was priced at GBP 18 billion in 2015 money, with first power from Unit 1 expected at the end of 2025. Successive updates raised the estimate to GBP 22-23bn (2021), GBP 25-26bn (2022), GBP 31-35bn (2024) and GBP 35bn (February 2026), with Unit 1 now forecast for 2030. Construction costs are borne by EDF and CGN, not taxpayers.",
      "what_went_wrong_or_right": "Hinkley Point C is the UK's first new nuclear station in a generation and uses the EPR design, which had already overrun at Olkiluoto 3 and Flamanville 3. EDF has attributed the increases to first-of-a-kind engineering in a UK regulatory context, the scale of design adaptation, Covid-19 disruption to labor and supply chains, and inflation in materials and labor. In September 2019 EDF said ground conditions and the cost of reaching design maturity would add up to GBP 2.9bn. A 15-month risk to Unit 1 followed in 2023. The National Audit Office concluded in June 2017 that the government had locked consumers into 'a high cost and risky deal', with expected top-up payments under the contract for difference rising from GBP 6bn to GBP 30bn as wholesale price forecasts fell; it could not say the department had maximized value for money. Because construction risk sits with EDF and CGN, the overruns have hit EDF's balance sheet, including a EUR 2.5bn write-down announced in February 2026. Progress milestones have still been met: both reactor domes are in place.",
      "lessons": [
        "Use the outturn of earlier units of the same design as the reference class, not the vendor's estimate.",
        "Adapting a reactor design to a new regulator is scope; budget and schedule it explicitly.",
        "State the price base of every estimate so stakeholders can separate inflation from overrun."
      ],
      "fun_fact": "Once running, the two reactors are expected to supply about 7% of the UK's electricity consumption.",
      "method_tags": [
        "phased_delivery",
        "reference_class"
      ],
      "related_history_ids": [
        "rcf-2004",
        "big-things-2023",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Hinkley Point C (HC 40, 2017-18)",
          "publisher": "National Audit Office",
          "url": "https://www.nao.org.uk/reports/hinkley-point-c/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Hinkley Point C nuclear power station",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Hinkley_Point_C_nuclear_power_station",
          "accessed": "2026-10-25"
        },
        {
          "title": "UK's Hinkley Point nuclear plant costs raised to GBP 35 billion - EDF",
          "publisher": "AJ Bell / Reuters",
          "url": "https://www.ajbell.co.uk/news/articles/uks-hinkley-point-nuclear-plant-costs-raised-ps35-billion-edf",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: GBP 18bn in 2015 prices at the final investment decision (EDF board 28 July 2016, UK government 15 Sep 2016), with Unit 1 first power at end-2025 as announced at go-ahead (later reported as 'end-2025 first announced' alongside the 2021 revision). The 2013 deal had expected completion in 2023; that pre-FID date is not used as the baseline. Actual: EDF February 2026 estimate of GBP 35bn in 2015 prices (about GBP 48bn in 2026 prices per Wikipedia); range reflects the January 2024 scenarios of GBP 31bn to 35bn. Both figures are in 2015 money, so overrun_basis is real. actual_end is the Unit 1 first-power forecast (2030); no firm Unit 2 date was published in the sources consulted. FX: Fed G.5A 2015 annual average, 1.5285 USD per GBP, applied to both since both are 2015 prices. Energy Intelligence reported a higher GBP 46bn figure in current money; not used. The commissioning phase start is set to the Unit 1 dome lift as a proxy; EDF has not published a commissioning start date in the sources consulted. Baseline audit 2026-10-25: Planned changed from the 2016 FID figure (GBP 18bn in 2015 prices, end-2025) to the first announced figures: GBP 16bn given by EDF in 2012 (2012 prices) and completion expected in 2023 under the October 2013 contract for difference (Wikipedia). The FID figure is now the rebaseline. Wikipedia also gives the January 2021 revision (GBP 22-23bn, 2015 prices, June 2026) and the January 2024 revision (GBP 31-35bn, 2015 prices, Unit 1 in 2029-2031). Commissioning phase and first-power milestone planned dates moved to 2023. planned_fx_to_usd 1.585 is the 2012 Fed G.5A average (tools/fx.json). Because the planned figure is now in 2012 prices and the actual in 2015 prices, overrun_basis \"real\" is no longer strictly accurate; left unchanged for the editor to decide. Editor 2026-10-25: overrun_basis set to nominal because the 2012 baseline and the 2015-prices forecast are in different price bases.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 81,
      "slug": "hoover-dam",
      "name": "Hoover Dam (Boulder Canyon Project)",
      "short_name": "Hoover Dam",
      "category": "energy",
      "subcategory": "hydroelectric dam",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Boulder City, Nevada / Black Canyon",
      "lat": 36.0156,
      "lng": -114.7378,
      "era": "1900-1945",
      "status": "completed",
      "outcome": "on_time_on_budget",
      "planned_start": "1931-04-20",
      "planned_end": "1938-04-20",
      "actual_start": "1931-04-20",
      "actual_end": "1936-03-01",
      "actual_is_forecast": false,
      "planned_duration_months": 84,
      "actual_duration_months": 58.4,
      "delay_months": -25.6,
      "delay_pct": -30.5,
      "planned_cost": 165000000,
      "actual_cost": 140000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 1928,
      "cost_year": 1939,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 165000000,
      "cost_usd_nominal": 140000000,
      "planned_cost_usd_today": 3093750000,
      "cost_usd_today": 3240430622,
      "overrun_usd_today": -578648325,
      "overrun_pct": -15.2,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Authorization and contract award",
          "planned_start": "1928-12-21",
          "planned_end": null,
          "actual_start": "1928-12-21",
          "actual_end": "1931-03",
          "note": "Boulder Canyon Project Act signed 21 Dec 1928 with a $165m appropriation; Six Companies won the dam contract in March 1931 with a bid of about $48.9m."
        },
        {
          "name": "River diversion tunnels",
          "planned_start": "1931-04-20",
          "planned_end": "1933-10-01",
          "actual_start": "1931",
          "actual_end": "1932-11-13",
          "note": "Contract required diversion by 1 Oct 1933; the Colorado River was turned into the Arizona tunnels on 13 Nov 1932."
        },
        {
          "name": "Cofferdams and foundation excavation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1932-09",
          "actual_end": "1933-06-06",
          "note": "Upper cofferdam work began September 1932; the riverbed was dewatered and excavated to bedrock."
        },
        {
          "name": "Concrete placement",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1933-06-06",
          "actual_end": "1935-05-29",
          "note": "First concrete on 6 June 1933; last on 29 May 1935. Peak of 10,462 cubic yards in one day."
        },
        {
          "name": "Dedication and completion of all features",
          "planned_start": null,
          "planned_end": "1938-04-20",
          "actual_start": "1935-09-30",
          "actual_end": "1936-03-01",
          "note": "Dedicated by President Roosevelt 30 Sep 1935; all features finished and accepted by Interior Secretary Ickes on 1 Mar 1936, about two years inside the seven-year contract allowance."
        },
        {
          "name": "Power generation start",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1936-03-01",
          "actual_end": "1936-09-11",
          "note": "First generator produced power on 11 Sep 1936."
        }
      ],
      "milestones": [
        {
          "name": "Boulder Canyon Project Act signed",
          "planned_date": "1928-12-21",
          "actual_date": "1928-12-21"
        },
        {
          "name": "River diverted",
          "planned_date": "1933-10-01",
          "actual_date": "1932-11-13"
        },
        {
          "name": "First concrete",
          "planned_date": null,
          "actual_date": "1933-06-06"
        },
        {
          "name": "Dam accepted by government",
          "planned_date": "1938-04-20",
          "actual_date": "1936-03-01"
        },
        {
          "name": "First power",
          "planned_date": null,
          "actual_date": "1936-09-11"
        }
      ],
      "headline": "Six Companies had seven years to build Hoover Dam and handed it over in under five, about two years early.",
      "summary": "Hoover Dam, built in Black Canyon on the Colorado River between Nevada and Arizona, was authorized by the Boulder Canyon Project Act of December 1928 with a $165 million appropriation. The Six Companies consortium won the dam contract in 1931 with a bid of about $48.9 million and seven years to finish. The river was diverted in November 1932, concrete placement ran from June 1933 to May 1935, and the government accepted the completed works on 1 March 1936, roughly two years ahead of the contract deadline.",
      "what_went_wrong_or_right": "The schedule was beaten mainly through contractor incentives and an aggressive, highly organized work plan. The contract gave Six Companies seven years from 20 April 1931 and imposed penalties for delay, so every month saved reduced the consortium's overhead and raised its margin. The Great Depression supplied an abundant labor pool: about 21,000 people worked on the job in total, with an average of 3,500 a day and a peak of 5,218 in June 1934. Construction was also accelerated deliberately to create jobs. The river was diverted almost a year before the contractual date of October 1933, which let foundation work and concrete placement start early. Concrete was poured in interlocking columns cooled by embedded pipes, allowing placement rates of up to 275,000 cubic yards in a month. The speed came at a human cost: 112 deaths were reported in connection with the project, and the camp conditions in 1931 led to a strike. Cost comparisons are approximate because the $165 million appropriation covered the wider Boulder Canyon Project, including the All-American Canal.",
      "lessons": [
        "Tie contractor profit to schedule with clear penalties; Six Companies gained directly from every month saved.",
        "Pull critical-path enablers forward: early river diversion unlocked all downstream work.",
        "Engineer the process, not only the product: cooled concrete columns made record pour rates possible."
      ],
      "fun_fact": "On its busiest day the project placed 10,462 cubic yards of concrete, according to the US Bureau of Reclamation.",
      "method_tags": [
        "gantt",
        "critical_path",
        "fixed_price",
        "fast_track"
      ],
      "related_history_ids": [
        "hoover-gantt-1931",
        "gantt-1910",
        "taylor-1911"
      ],
      "sources": [
        {
          "title": "Hoover Dam - Frequently Asked Questions",
          "publisher": "US Bureau of Reclamation",
          "url": "https://www.usbr.gov/lc/hooverdam/faqs/damfaqs.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Hoover Dam",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Hoover_Dam",
          "accessed": "2026-10-25"
        },
        {
          "title": "Hoover Dam - Boulder City NV",
          "publisher": "The Living New Deal",
          "url": "https://livingnewdeal.org/sites/hoover-dam-boulder-city-nv/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the Boulder Canyon Project Act of 21 Dec 1928 appropriated $165m for the whole project (dam, power plant and the All-American Canal), so the planned and actual figures are project-level, not dam-only. The Six Companies dam contract bid was about $48.9m (sources give $48,890,955 or $48,890,995.50). Actual cost uses the 1939 Public Works Administration survey quoted by the Living New Deal ('nearly $140,000,000', of which $38m came from the PWA); scope coverage of that figure is not fully clear, and a 1969 Reclamation figure put total estimated project cost at about $176m. Planned schedule: seven years from 20 Apr 1931 (USBR FAQ). USD only, so fx = 1. Figures are nominal.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 82,
      "slug": "itaipu-dam",
      "name": "Itaipu Dam",
      "short_name": "Itaipu Dam",
      "category": "energy",
      "subcategory": "hydroelectric dam",
      "country": "Brazil",
      "country_code": "BR",
      "countries": [
        "Brazil",
        "Paraguay"
      ],
      "continent": "South America",
      "city": "Foz do Iguaçu / Hernandarias",
      "lat": -25.4078,
      "lng": -54.5886,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1975",
      "planned_end": null,
      "actual_start": "1975-01",
      "actual_end": "1991",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 197.5,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": 2700000000,
      "actual_cost": 19600000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        19600000000,
        27000000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 1973,
      "cost_year": 1991,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 2700000000,
      "cost_usd_nominal": 19600000000,
      "planned_cost_usd_today": 19582083958,
      "cost_usd_today": 46330320059,
      "overrun_usd_today": 39948082091,
      "overrun_pct": 625.9,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Treaty and binational entity",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1973-04-26",
          "actual_end": "1975-01",
          "note": "Brazil and Paraguay signed the Itaipu Treaty on 26 Apr 1973, creating Itaipu Binacional with US$100m share capital split equally."
        },
        {
          "name": "River diversion and excavation",
          "planned_start": "1975",
          "planned_end": null,
          "actual_start": "1975-01",
          "actual_end": "1978-10-14",
          "note": "The Paraná was diverted through a bypass channel on 14 Oct 1978 to dry the main riverbed."
        },
        {
          "name": "Main dam and powerhouse construction",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1978-10-14",
          "actual_end": "1982-10-13",
          "note": "About 40,000 people worked on construction."
        },
        {
          "name": "Reservoir filling",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1982-10-13",
          "actual_end": "1982-10-27",
          "note": "Water reached the spillway gates on 27 Oct 1982; the reservoir flooded the Guaíra (Sete Quedas) falls. About 10,000 families were displaced."
        },
        {
          "name": "Installation of first 18 generating units",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1984-05-05",
          "actual_end": "1991",
          "note": "First unit started 5 May 1984; units added two to three per year; the 18th entered service in 1991. Energy sales began March 1985."
        },
        {
          "name": "Units 19 and 20",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2006-09",
          "actual_end": "2007-03",
          "note": "Two additional units, originally planned as reserves, started September 2006 and March 2007."
        }
      ],
      "milestones": [
        {
          "name": "Itaipu Treaty signed",
          "planned_date": null,
          "actual_date": "1973-04-26"
        },
        {
          "name": "River diverted",
          "planned_date": null,
          "actual_date": "1978-10-14"
        },
        {
          "name": "First generating unit",
          "planned_date": null,
          "actual_date": "1984-05-05"
        },
        {
          "name": "18th unit in service",
          "planned_date": null,
          "actual_date": "1991"
        },
        {
          "name": "Construction debt fully repaid",
          "planned_date": null,
          "actual_date": "2023-02-28"
        }
      ],
      "headline": "Itaipu was first costed at about US$2.7bn; it ended up at roughly US$19.6bn, and its debt took 50 years and US$63.5bn to repay.",
      "summary": "Itaipu is a 14 GW hydroelectric dam on the Paraná River, owned equally by Brazil and Paraguay through Itaipu Binacional under a treaty signed in April 1973. Construction started in 1975, the river was diverted in 1978, the reservoir filled in October 1982 and the first unit ran in May 1984. The 18th unit entered service in 1991 and two more followed in 2006-2007. An early estimate of about US$2.7 billion grew to a reported US$19.6 billion; debt service totaled US$63.5 billion by February 2023.",
      "what_went_wrong_or_right": "The main driver of cost growth was scope change. According to former Itaipu director Jorge Ayala Kunzle, the pre-1973 estimate of about US$2.7bn assumed 14 smaller turbines; the design grew to 18 large units with provision for two reserves, because planners judged that water, materials and energy demand justified it, and the plant finished with 20 units. Financing was the second driver: the binational entity was built almost entirely on borrowed money, raised through more than 300 financing contracts with about 70 creditors and guaranteed by Brazil's Treasury, during the high-interest, high-inflation 1970s and 1980s. Of the US$63.5bn eventually paid, about US$27.9bn was financial charges. The scheme was technically successful: units were commissioned at two to three per year and the plant became one of the world's largest producers of electricity. The debt calculations were never officially audited, and some Paraguayan groups dispute part of it. Resettlement of about 10,000 families and the flooding of the Guaíra falls were part of the project scope.",
      "lessons": [
        "Re-baseline cost formally when capacity scope grows; comparing against the original estimate then misleads.",
        "Financing structure can cost as much as construction; model interest and currency risk explicitly.",
        "Treaty-based ownership needs an agreed, audited cost record to avoid decades of dispute."
      ],
      "fun_fact": "Itaipu made its final construction-debt payment, US$115 million, in February 2023, almost 50 years after the treaty was signed.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Itaipu Dam",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Itaipu_Dam",
          "accessed": "2026-10-25"
        },
        {
          "title": "Justifican costo final de central",
          "publisher": "ABC Color",
          "url": "https://www.abc.com.py/edicion-impresa/economia/justifican-costo-final-de-central-1745095.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Itaipu pays off debt from the construction of the hydroelectric plant",
          "publisher": "Canal Solar",
          "url": "https://canalsolar.com.br/en/itaipu-quita-divida-da-construcao-da-usina-hidreletrica",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the pre-1973 estimate of about US$2.7bn cited by former director Jorge Ayala Kunzle (ABC Color, 23 Apr 2019); no officially published baseline budget or completion date was found, so planned_end is null and planned_start uses the 1975 start. Scope grew from 14 to 20 units, so the comparison is not like-for-like. Actual: US$19.6bn nominal from the Wikipedia infobox; Ayala Kunzle put the final cost near US$27bn including financial charges (upper end of range). Total debt service of US$63.5bn (US$35.6bn principal, US$27.9bn financial charges) is reported by Canal Solar and is not a construction cost. actual_end is 1991 (18th unit); units 19-20 (2006-2007) are shown as a later phase. Wikipedia's infobox gives a construction start of January 1971, inconsistent with its text (January 1975); 1975 is used. Coordinates are those commonly given for the dam and were not confirmed in the pages fetched. Itaipu Binacional's own site returned an error during research. Figures in USD, so fx = 1; nominal. Installed capacity of about 14 GW (20 units of 700 MW) is general knowledge and was not re-verified in the pages fetched.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 83,
      "slug": "iter",
      "name": "ITER (International Thermonuclear Experimental Reactor)",
      "short_name": "ITER",
      "category": "energy",
      "subcategory": "fusion reactor",
      "country": "France",
      "country_code": "FR",
      "countries": [
        "France",
        "China",
        "India",
        "Japan",
        "South Korea",
        "United States"
      ],
      "continent": "Europe",
      "city": "Saint-Paul-lès-Durance",
      "lat": 43.7083,
      "lng": 5.7775,
      "era": "2000-2014",
      "status": "ongoing",
      "outcome": "over_budget_and_late",
      "planned_start": "2007",
      "planned_end": "2016",
      "actual_start": "2007-10-24",
      "actual_end": "2034",
      "actual_is_forecast": true,
      "planned_duration_months": 108,
      "actual_duration_months": 320.2,
      "delay_months": 216,
      "delay_pct": 200,
      "planned_cost": 5900000000,
      "actual_cost": 20000000000,
      "planned_cost_range": [
        5000000000,
        5900000000
      ],
      "actual_cost_range": [
        20000000000,
        25000000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2008,
      "cost_year": 2016,
      "planned_fx_to_usd": 1.4726,
      "actual_fx_to_usd": 1.1069,
      "planned_cost_usd_nominal": 8690700000,
      "cost_usd_nominal": 22140000000,
      "planned_cost_usd_today": 12995753091,
      "cost_usd_today": 29701123128,
      "overrun_usd_today": 20939291805,
      "overrun_pct": 239,
      "overrun_basis": "nominal",
      "rebaseline_cost": 20000000000,
      "rebaseline_cost_year": 2016,
      "rebaseline_end": null,
      "rebaseline_label": "April 2016 ITER Council cost assessment",
      "rebaseline_overrun_pct": 0,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Agreement and organization set-up",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2006-11-21",
          "actual_end": "2007-10-24",
          "note": "ITER Agreement signed in Paris 21 Nov 2006; ITER Organization established 24 Oct 2007 after ratification by all members."
        },
        {
          "name": "Site preparation and excavation",
          "planned_start": "2007",
          "planned_end": null,
          "actual_start": "2008",
          "actual_end": "2013",
          "note": "Site clearing from 2007-2008; excavation of the tokamak pit started 2010."
        },
        {
          "name": "Tokamak complex construction and component manufacturing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2013",
          "actual_end": "2020-07-28",
          "note": "Tokamak building construction from 2013; components manufactured in kind by the seven members."
        },
        {
          "name": "Machine assembly",
          "planned_start": null,
          "planned_end": "2016",
          "actual_start": "2020-07-28",
          "actual_end": "2033",
          "note": "Assembly launched 28 July 2020. Cracks in thermal shield cooling pipes and vacuum vessel issues forced repairs; the French regulator briefly halted assembly in early 2022."
        },
        {
          "name": "Start of research operation (forecast)",
          "planned_start": "2016",
          "planned_end": null,
          "actual_start": "2034",
          "actual_end": null,
          "note": "Forecast under Baseline 2024: start of research operation 2034, full plasma current 2036, deuterium-deuterium 2035."
        },
        {
          "name": "Deuterium-tritium operation (forecast)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2039",
          "actual_end": null,
          "note": "Forecast: D-T operation 2039, versus 2035 in the 2016 baseline."
        }
      ],
      "milestones": [
        {
          "name": "ITER Agreement signed",
          "planned_date": null,
          "actual_date": "2006-11-21"
        },
        {
          "name": "Machine assembly launched",
          "planned_date": null,
          "actual_date": "2020-07-28"
        },
        {
          "name": "First plasma / start of research operation",
          "planned_date": "2016",
          "actual_date": "2034"
        },
        {
          "name": "Deuterium-tritium operation",
          "planned_date": null,
          "actual_date": "2039"
        }
      ],
      "headline": "Signed in 2006 at an estimated EUR 5.9bn with first plasma due in 2016, ITER now expects research operation in 2034 after cost estimates passed EUR 20bn.",
      "summary": "ITER is a seven-member international fusion experiment under construction at Saint-Paul-lès-Durance in southern France, hosted by the EU and funded largely through in-kind component contributions. The 2006 agreement was based on an estimated EUR 5.9 billion (2008 prices) over ten years and first plasma in 2016. The 2016 re-baseline put the cost at about EUR 20 billion and first plasma at December 2025. The 2024 baseline moved start of research operation to 2034 and deuterium-tritium operation to 2039, adding about EUR 5 billion.",
      "what_went_wrong_or_right": "The European Parliament's research service records three resets: a 2008 design review raised the estimate to about EUR 19bn and moved first plasma to 2019; the April 2016 Council baseline set about EUR 20bn and December 2025; and Baseline 2024, presented by Director-General Pietro Barabaschi, moved research operation to 2034. Causes include technical novelty, since ITER is a first-of-a-kind machine; an immature design at the time of the agreement; and a procurement model in which members supply components in kind from factories in many countries, making integration and quality control hard and total cost difficult to state. In 2022, cracks were found in cooling pipes of the thermal shields and dimensional problems in vacuum vessel sectors, requiring repairs, and the French nuclear safety authority briefly halted assembly over radiological shielding. Covid-19 disrupted supply chains. The European Court of Auditors found the EU's post-2020 construction funding need was EUR 5.4bn above the amount already committed. Barabaschi declined in 2024 to give a total cost because of the in-kind funding structure.",
      "lessons": [
        "In-kind procurement spreads political ownership but multiplies interfaces; budget heavily for integration and quality control.",
        "Do not commit to dates before the design of a first-of-a-kind machine is mature.",
        "Keep a single, published total cost; without one, sponsors cannot judge overruns."
      ],
      "fun_fact": "Europe, as host, pays almost half of ITER's construction cost; the other six members share the rest equally.",
      "method_tags": [
        "phased_delivery",
        "waterfall"
      ],
      "related_history_ids": [
        "wbs-1962",
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "MFF: The International Thermonuclear Experimental Reactor (ITER) project",
          "publisher": "European Parliament Legislative Train",
          "url": "https://www.europarl.europa.eu/legislative-train/theme-a-european-green-deal/file-mff-the-international-thermonuclear-experimental-reactor-(iter)-project",
          "accessed": "2026-10-25"
        },
        {
          "title": "ITER fusion reactor hit by massive decade-long delay and EUR 5bn price hike",
          "publisher": "Physics World",
          "url": "https://physicsworld.com/a/iter-fusion-reactor-hit-by-massive-decade-long-delay-and-e5bn-price-hike/",
          "accessed": "2026-10-25"
        },
        {
          "title": "ITER Council press release, 34th meeting (20 June 2024)",
          "publisher": "ITER Organization",
          "url": "https://www.iter.org/node/28293",
          "accessed": "2026-10-25"
        },
        {
          "title": "ITER",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/ITER",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the 2006 ITER Agreement estimate of EUR 5.9bn (2008 prices) over ten years with first plasma in 2016 (European Parliament); the commonly quoted round figure of EUR 5bn is the low end of planned_cost_range. Actual: no official total exists because members contribute mostly in kind. The main value is the April 2016 ITER Council assessment of about EUR 20bn; the upper end of the range adds the roughly EUR 5bn extra cost announced with Baseline 2024 (Physics World, 3 July 2024). This simple sum is an editorial range, not an official figure. Physics World reports a 2010 estimate of about EUR 15bn. Some outside estimates of USD 45-65bn (disputed by ITER) are not used. actual_end is the forecast start of research operation (2034) under Baseline 2024; deuterium-deuterium operation is targeted for 2035 and D-T for 2039. Original target dates differ by source (2016 per European Parliament, 2020 in parts of Wikipedia). FX: Fed G.5A annual averages, EUR 2008 1.4726 and 2016 1.1069 USD per EUR. ITER has seven members; per the dataset's no-Russia rule, one member is deliberately not named in the text or the countries list. The vacuum vessel sector repair detail is from ITER's 2022 public statements as summarized in Wikipedia; Physics World cites the thermal shield pipe cracks, Covid-19 and the 2022 regulatory halt. Baseline audit 2026-10-25: Planned figures unchanged (2006 ITER Agreement, EUR 5.9bn in 2008 prices, first plasma 2016). Added the April 2016 ITER Council assessment of about EUR 20bn as the rebaseline; Baseline 2024 (research operation 2034) is reflected in actual_end.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 84,
      "slug": "olkiluoto-3",
      "name": "Olkiluoto Nuclear Power Plant Unit 3",
      "short_name": "Olkiluoto 3",
      "category": "energy",
      "subcategory": "nuclear plant",
      "country": "Finland",
      "country_code": "FI",
      "countries": [
        "Finland",
        "France",
        "Germany"
      ],
      "continent": "Europe",
      "city": "Eurajoki",
      "lat": 61.2369,
      "lng": 21.4408,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2005",
      "planned_end": "2009-05",
      "actual_start": "2005-08-12",
      "actual_end": "2023-05-01",
      "actual_is_forecast": false,
      "planned_duration_months": 46.5,
      "actual_duration_months": 212.6,
      "delay_months": 167.5,
      "delay_pct": 360.6,
      "planned_cost": 3000000000,
      "actual_cost": 11000000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "EUR",
      "planned_cost_year": 2003,
      "cost_year": 2023,
      "planned_fx_to_usd": 1.1321,
      "actual_fx_to_usd": 1.0813,
      "planned_cost_usd_nominal": 3396000000,
      "cost_usd_nominal": 11902000000,
      "planned_cost_usd_today": 5943614327,
      "cost_usd_today": 12576654653,
      "overrun_usd_today": 9146657929,
      "overrun_pct": 266.7,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Contract and licensing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2003-12-19",
          "actual_end": "2005-02-07",
          "note": "Fixed-price turnkey contract signed with the Areva-Siemens consortium 19 Dec 2003; construction license issued 7 Feb 2005."
        },
        {
          "name": "Civil construction and installation",
          "planned_start": "2005",
          "planned_end": "2009-05",
          "actual_start": "2005-08-12",
          "actual_end": "2021-03",
          "note": "Construction started August 2005 against a May 2009 commercial operation target; repeated slips through the 2010s."
        },
        {
          "name": "Fuel loading and first criticality",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2021-03",
          "actual_end": "2021-12-21",
          "note": "Fuel loading permit March 2021; all 241 assemblies loaded April 2021; first criticality 21 Dec 2021."
        },
        {
          "name": "Test production",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2022-03-12",
          "actual_end": "2023-04-16",
          "note": "Grid connection 12 Mar 2022; delayed in 2022 by foreign material found in the turbine steam reheater in May 2022."
        },
        {
          "name": "Regular and commercial operation",
          "planned_start": null,
          "planned_end": "2009-05",
          "actual_start": "2023-04-16",
          "actual_end": "2023-05-01",
          "note": "Regular electricity production began 16 Apr 2023; commercial operation 1 May 2023."
        }
      ],
      "milestones": [
        {
          "name": "Turnkey contract signed",
          "planned_date": null,
          "actual_date": "2003-12-19"
        },
        {
          "name": "Construction start",
          "planned_date": null,
          "actual_date": "2005-08-12"
        },
        {
          "name": "First criticality",
          "planned_date": null,
          "actual_date": "2021-12-21"
        },
        {
          "name": "Grid connection",
          "planned_date": null,
          "actual_date": "2022-03-12"
        },
        {
          "name": "Commercial operation",
          "planned_date": "2009-05",
          "actual_date": "2023-05-01"
        }
      ],
      "headline": "Finland's first EPR was sold as a EUR 3bn fixed-price turnkey job due in 2009; it entered commercial operation in 2023 at an estimated EUR 11bn.",
      "summary": "Olkiluoto 3 is a 1,600 MWe EPR reactor at Eurajoki on Finland's west coast, ordered by utility TVO from an Areva-Siemens consortium under a fixed-price turnkey contract of about EUR 3 billion signed in December 2003. Construction began in August 2005 with commercial operation planned for May 2009. First criticality came in December 2021, grid connection in March 2022, and commercial operation on 1 May 2023, 14 years late. Total cost is estimated at about EUR 11 billion, split roughly equally between TVO's investment and Areva's losses.",
      "what_went_wrong_or_right": "Olkiluoto 3 was the first EPR to start construction anywhere, and Finland's nuclear regulator STUK identified the core causes in a 2010 review. The original schedule was overly ambitious for a first-of-a-kind plant larger than any previous reactor; design and engineering were not sufficiently complete when construction began; there was a shortage of experienced designers; the parties lacked experience managing a project of this size; and there was a worldwide shortage of qualified nuclear equipment suppliers. The fixed-price turnkey contract did not stop the delays but moved most of the overrun onto the vendor: Areva is reported to have absorbed about EUR 5.5bn in losses while TVO invested about EUR 5.5bn. Years of disputes ended in a 2018 settlement under which Areva paid TVO EUR 450m in compensation. Late-stage commissioning added further slippage, including foreign material found in the turbine steam reheater in May 2022. Regular production finally began on 16 April 2023, about 18 years after construction started.",
      "lessons": [
        "Freeze design and complete detailed engineering before pouring safety-class concrete.",
        "A fixed price shifts losses to the vendor but does not prevent delay; owners still bear lost output.",
        "Check that the supply chain for first-of-a-kind components exists before committing to dates."
      ],
      "fun_fact": "Regular electricity production began on 16 April 2023, almost exactly 14 years after the original May 2009 target.",
      "method_tags": [
        "fixed_price",
        "design_build"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Olkiluoto Nuclear Power Plant",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Olkiluoto_Nuclear_Power_Plant",
          "accessed": "2026-10-25"
        },
        {
          "title": "Finnish nuclear plant under construction since 2005 faces yet another delay",
          "publisher": "POWER Magazine",
          "url": "https://www.powermag.com/finnish-nuclear-plant-under-construction-since-2005-faces-yet-another-delay/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Finnish EPR enters regular electricity production",
          "publisher": "World Nuclear News",
          "url": "https://world-nuclear-news.org/articles/finnish-epr-enters-regular-electricity-production",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the EUR 3bn fixed-price turnkey contract signed 19 Dec 2003, with commercial operation planned for May 2009. Actual cost is the widely reported total of about EUR 11bn (TVO about EUR 5.5bn plus Areva losses about EUR 5.5bn) from Wikipedia; TVO has not published a single all-in figure in the sources consulted, so the overrun is approximate and nominal (contract-year versus completion-year euros). The 2018 EUR 450m settlement is a transfer between the parties, not additional cost. Construction start: Wikipedia infobox gives 12 Aug 2005, POWER gives 11 Aug 2005. FX: Fed G.5A annual averages, EUR 2003 1.1321 and 2023 1.0813 USD per EUR. Coordinates converted from 61 14 13 N, 21 26 27 E. Siemens later exited the consortium; Germany is listed for its role in the original contract. Baseline audit 2026-10-25: Planned figures unchanged (EUR 3bn turnkey contract, May 2009, is the first). TVO revised the schedule many times, but no single formal rebaseline was sourced, so none is stored.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 85,
      "slug": "snowy-2",
      "name": "Snowy 2.0 Pumped Hydro Project",
      "short_name": "Snowy 2.0",
      "category": "energy",
      "subcategory": "pumped hydro storage",
      "country": "Australia",
      "country_code": "AU",
      "countries": [
        "Australia"
      ],
      "continent": "Oceania",
      "city": "Kosciuszko National Park, Snowy Mountains, NSW",
      "lat": -35.7864,
      "lng": 148.4444,
      "era": "2015-now",
      "status": "ongoing",
      "outcome": "over_budget_and_late",
      "planned_start": "2018",
      "planned_end": "2024",
      "actual_start": "2019",
      "actual_end": "2028-12",
      "actual_is_forecast": true,
      "planned_duration_months": 72,
      "actual_duration_months": 113.5,
      "delay_months": 53.5,
      "delay_pct": 74.2,
      "planned_cost": 2000000000,
      "actual_cost": 12000000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "AUD",
      "planned_cost_year": 2017,
      "cost_year": 2023,
      "planned_fx_to_usd": 0.7669,
      "actual_fx_to_usd": 0.6644,
      "planned_cost_usd_nominal": 1534200000,
      "cost_usd_nominal": 7972800000,
      "planned_cost_usd_today": 2015121504,
      "cost_usd_today": 8424731324,
      "overrun_usd_today": 7020609436,
      "overrun_pct": 500,
      "overrun_basis": "nominal",
      "rebaseline_cost": 12000000000,
      "rebaseline_cost_year": 2023,
      "rebaseline_end": "2028-12",
      "rebaseline_label": "August 2023 Snowy Hydro project reset",
      "rebaseline_overrun_pct": 0,
      "rebaseline_delay_months": 0,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Announcement and feasibility study",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2017-03",
          "actual_end": "2017-12-21",
          "note": "Announced by Prime Minister Malcolm Turnbull in early 2017 at about A$2bn; feasibility study released 21 Dec 2017 put the cost at A$3.8-4.5bn."
        },
        {
          "name": "Contract award and approvals",
          "planned_start": "2018",
          "planned_end": null,
          "actual_start": "2018",
          "actual_end": "2019",
          "note": "Main civil and electro-mechanical contract (about A$5.1bn) awarded to Future Generation JV (Clough and Salini Impregilo, now Webuild); federal government bought out NSW and Victorian shares in Snowy Hydro."
        },
        {
          "name": "Early works and tunneling",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2019",
          "actual_end": "2024-07-11",
          "note": "TBM Florence launched March 2022, hit soft ground near Tantangara and was stuck for about 19 months; a sinkhole opened above the tunnel in December 2022. It was clear by 11 July 2024."
        },
        {
          "name": "Project reset",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2023-05",
          "actual_end": "2023-08-31",
          "note": "Snowy Hydro reset the project on 31 Aug 2023: A$12bn cost to complete, A$4.3bn spent to June 2023, capacity raised to 2,200 MW."
        },
        {
          "name": "Power station, waterways and first power (forecast)",
          "planned_start": null,
          "planned_end": "2024",
          "actual_start": "2023-08-31",
          "actual_end": "2027-12",
          "note": "Forecast first power in the second half of 2027 per the 2023 reset."
        },
        {
          "name": "Commercial operation of all units (forecast)",
          "planned_start": null,
          "planned_end": "2024",
          "actual_start": "2027-12",
          "actual_end": "2028-12",
          "note": "Forecast December 2028; press reports in October 2025 said the scheme was about 67% complete and could not be finished within A$12bn."
        }
      ],
      "milestones": [
        {
          "name": "Feasibility study released",
          "planned_date": null,
          "actual_date": "2017-12-21"
        },
        {
          "name": "TBM Florence launched",
          "planned_date": null,
          "actual_date": "2022-03"
        },
        {
          "name": "Project reset to A$12bn",
          "planned_date": null,
          "actual_date": "2023-08-31"
        },
        {
          "name": "First power",
          "planned_date": "2024",
          "actual_date": "2027-12"
        },
        {
          "name": "All units in commercial operation",
          "planned_date": "2024",
          "actual_date": "2028-12"
        }
      ],
      "headline": "Snowy 2.0 was floated at about A$2bn in 2017; the official cost to complete is now A$12bn and full operation has slipped to at least December 2028.",
      "summary": "Snowy 2.0 links the Tantangara and Talbingo reservoirs in Kosciuszko National Park with tunnels and an underground power station to create a 2,200 MW pumped-storage scheme. Announced in early 2017 at a rough A$2 billion, it was costed at A$3.8-4.5 billion in the December 2017 feasibility study and awarded as a A$5.1 billion main contract. Snowy Hydro's August 2023 reset set a A$12 billion cost to complete, first power in late 2027 and all units operating by December 2028. Transmission is extra.",
      "what_went_wrong_or_right": "Snowy Hydro itself named the causes when it reset the project on 31 August 2023. Project-specific: the design was immature at final investment decision, complex elements cost more to build than estimated, and site and geological conditions varied, most notably the soft ground that trapped tunnel boring machine Florence near Tantangara for about 19 months and opened a sinkhole above the tunnel in December 2022. External: pandemic disruption, labor shortages worsened by quarantine and movement restrictions, shipping and supply-chain delays, and rising material and labor costs. The initial A$2bn figure was a political estimate made before a feasibility study; that study, released in December 2017, already put the cost at A$3.8-4.5bn, and the main contract alone came in about 35 percent above the top of that range, partly because it included escalation over eight years. The completion date has been reset several times. By October 2025 the scheme was reported to be about 67 percent complete and unlikely to finish within the A$12bn forecast.",
      "lessons": [
        "Never announce a megaproject number before a feasibility study; the first figure becomes the public baseline.",
        "Invest in geotechnical investigation along the full tunnel route before awarding a fixed-scope tunneling contract.",
        "Report costs with and without connecting transmission so the true system cost is visible."
      ],
      "fun_fact": "Tunnel boring machine Florence, named after Florence Violet McKenzie, spent about 19 months stuck in soft ground near Tantangara.",
      "method_tags": [
        "design_build",
        "phased_delivery"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Securing the future of critical energy transformation: resets",
          "publisher": "Snowy Hydro",
          "url": "https://www.snowyhydro.com.au/news/securing-the-future-of-critical-energy-transformation-resets/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Snowy 2.0 project pushed back to late 2029, costs to blow out again",
          "publisher": "RenewEconomy",
          "url": "https://reneweconomy.com.au/snowy-2-0-project-pushed-back-to-late-2029-costs-to-blow-out-again/amp/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Snowy 2.0 Pumped Storage Power Station",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Snowy_2.0_Pumped_Storage_Power_Station",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the roughly A$2bn figure announced by Prime Minister Turnbull in early 2017, which was the first public number (pre-feasibility). The December 2017 feasibility study (A$3.8-4.5bn, December 2017 real) and the ~A$5.1bn main contract are alternative baselines; using either would show a smaller overrun. Planned end of 2024 is from Wikipedia ('originally expected by 2024'). Actual: Snowy Hydro's 31 Aug 2023 reset of A$12bn total cost to complete, first power second half 2027 and all units by December 2028; this is the latest official forecast found. Reports in October 2025 (via Wikipedia) say it cannot be finished within A$12bn, and a May 2023 report cited a possible December 2029 full operation, so both cost and date carry upside risk. Transmission connections are excluded. The ANAO website was not consulted because web search budget ran out. FX: Fed G.5A annual averages, AUD 2017 0.7669 and 2023 0.6644 USD per AUD. The contractor name (Future Generation JV) is from general project reporting; the RenewEconomy and Wikipedia sources name Clough and Salini Impregilo. Baseline audit 2026-10-25: Planned figures unchanged (early-2017 A$2bn announcement is the first public number). Added the 31 August 2023 Snowy Hydro reset (A$12bn, all units by December 2028) as the rebaseline; it is also the current actual forecast. The December 2017 feasibility study (A$3.8-4.5bn) and A$5.1bn main contract are intermediate figures.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 86,
      "slug": "three-gorges-dam",
      "name": "Three Gorges Dam",
      "short_name": "Three Gorges Dam",
      "category": "energy",
      "subcategory": "hydroelectric dam",
      "country": "China",
      "country_code": "CN",
      "countries": [
        "China"
      ],
      "continent": "Asia",
      "city": "Sandouping, Yichang, Hubei",
      "lat": 30.8233,
      "lng": 111.0028,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "late",
      "planned_start": "1994-12-14",
      "planned_end": "2009",
      "actual_start": "1994-12-14",
      "actual_end": "2012-07",
      "actual_is_forecast": false,
      "planned_duration_months": 174.6,
      "actual_duration_months": 211,
      "delay_months": 36.5,
      "delay_pct": 20.9,
      "planned_cost": 203900000000,
      "actual_cost": 203000000000,
      "planned_cost_range": [
        180000000000,
        203900000000
      ],
      "actual_cost_range": [
        180000000000,
        203000000000
      ],
      "cost_currency": "CNY",
      "planned_cost_year": 1994,
      "cost_year": 2012,
      "planned_fx_to_usd": 0.116,
      "actual_fx_to_usd": 0.1585,
      "planned_cost_usd_nominal": 23591230000,
      "cost_usd_nominal": 32175500000,
      "planned_cost_usd_today": 51244982095,
      "cost_usd_today": 45122186186,
      "overrun_usd_today": -200049101,
      "overrun_pct": -0.4,
      "overrun_basis": "nominal",
      "rebaseline_cost": 180000000000,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": "revised official estimate (cited 2000-2001)",
      "rebaseline_overrun_pct": 12.8,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Approval and preparation",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1992-04-03",
          "actual_end": "1994-12-14",
          "note": "National People's Congress approved the project in 1992 (1,767 for, 177 against, 664 abstaining)."
        },
        {
          "name": "Main works to first power",
          "planned_start": "1994-12-14",
          "planned_end": null,
          "actual_start": "1994-12-14",
          "actual_end": "2003-07-10",
          "note": "Official start 14 Dec 1994; reservoir impounding and first generator (No. 2) in 2003."
        },
        {
          "name": "Dam body completion",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2003-07-10",
          "actual_end": "2006-05-20",
          "note": "Dam body completed in 2006 and officially opened 20 May 2006."
        },
        {
          "name": "Remaining generating units",
          "planned_start": null,
          "planned_end": "2009",
          "actual_start": "2006-05-20",
          "actual_end": "2012-07",
          "note": "Full operation was planned for 2009; the last of 32 main units (No. 27) finished testing 23 May 2012 and the plant was fully operational in July 2012."
        },
        {
          "name": "Ship lift",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2007-10",
          "actual_end": "2016-01",
          "note": "Ship lift construction began October 2007; tested December 2015 and announced complete January 2016."
        },
        {
          "name": "Resettlement and final acceptance",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1993",
          "actual_end": "2020-11-01",
          "note": "About 1.24 million residents had been relocated by June 2008 (estimates range 1.13m to 1.4m). Overall completion acceptance announced 1 Nov 2020."
        }
      ],
      "milestones": [
        {
          "name": "NPC approval",
          "planned_date": null,
          "actual_date": "1992-04-03"
        },
        {
          "name": "Construction start",
          "planned_date": "1994-12-14",
          "actual_date": "1994-12-14"
        },
        {
          "name": "First generator online",
          "planned_date": null,
          "actual_date": "2003-07-10"
        },
        {
          "name": "Full operation",
          "planned_date": "2009",
          "actual_date": "2012-07"
        },
        {
          "name": "Overall completion acceptance",
          "planned_date": null,
          "actual_date": "2020-11-01"
        }
      ],
      "headline": "The world's largest power station came in at about 203 billion yuan against an initial budget of 203.9 billion, but full operation slipped three years to 2012.",
      "summary": "The Three Gorges Dam on the Yangtze at Sandouping, Hubei, was approved by the National People's Congress in 1992 and officially started on 14 December 1994. Its 2003 reservoir filling and first generator were followed by dam-body completion in 2006 and full operation of all main units in July 2012, three years after the 2009 target. The initial budget was 203.9 billion yuan; reported final cost is about 203 billion yuan. Relocation of roughly 1.24 million or more residents was a major cost and scope item.",
      "what_went_wrong_or_right": "On cost, official figures show the project close to or under its initial budget. Xinhua reported in 2000 that the original 203.9 billion yuan budget assumed price inflation of 5 to 10 percent a year; when prices fell in the late 1990s, low inflation alone saved more than 14 billion yuan, and low interest rates also helped, so the developer said the dam would cost no more than 180 billion yuan. By the end of 2008, dynamic investment stood at 181.5 billion yuan. Later reported totals, around 203 billion yuan, include later works. On schedule, the main dam and first power in 2003 kept broadly to plan, but full operation of all generating units slipped from 2009 to 2012, and the ship lift was not complete until 2016. Resettlement was the largest non-engineering scope item: about 1.24 million people had been relocated by 2008, and a 2001 report noted 310 cases of misuse of relocation funds. Because official figures mix static and dynamic bases and several budgets were published, the true overrun is disputed, especially by foreign analysts who estimated much higher totals.",
      "lessons": [
        "State whether a budget is static or inflation-escalated; mixed bases make cost performance impossible to judge.",
        "Budget resettlement and land acquisition as core scope with its own controls and audits.",
        "Phase delivery so early units generate revenue while later works continue."
      ],
      "fun_fact": "At the 1992 National People's Congress vote, 664 delegates abstained and 177 voted against, an unusually large dissent for that body.",
      "method_tags": [
        "phased_delivery",
        "waterfall"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Three Gorges Dam",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Three_Gorges_Dam",
          "accessed": "2026-10-25"
        },
        {
          "title": "Foreign estimates of Three Gorges costs wrong: official (Xinhua, 3 May 2000)",
          "publisher": "Probe International",
          "url": "https://journal.probeinternational.org/2000/05/03/foreign-estimates-three-gorges-costs-wrong-official/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Government to audit gigantic Three Gorges project",
          "publisher": "Probe International",
          "url": "https://journal.probeinternational.org/2008/11/04/government-audit-gigantic-three-gorges-project/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Three Gorges project completes overall completion acceptance",
          "publisher": "People's Daily",
          "url": "https://paper.people.com.cn/rmrbwap/html/2020-11/02/nw.D110000renmrb_20201102_6-01.htm",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the initial budget of 203.9 billion yuan as reported by Xinhua (May 2000), which included assumed future inflation (a dynamic budget); the year 1994 is used as the price year for the go-ahead, but the figure is not in constant prices. The 180 billion yuan figure is the revised official estimate cited in 2000 and 2001 reports. Actual cost uses the Wikipedia infobox figure of 203 billion yuan (cited to Power Technology); Xinhua reported 181.5 billion yuan dynamic (122.9 billion static) spent by end 2008. No official final settlement figure was found in the 2020 acceptance notice. Actual end is taken as full operation of the main power plant (July 2012); the ship lift (2016) and final acceptance (2020) are shown as phases. FX: Fed G.5A annual averages, CNY 1994 about 8.62 per USD (0.1160) and 2012 about 6.31 per USD (0.1585). The NPC approval date of 3 April 1992 is the date of the vote at the Fifth Session of the Seventh NPC; the vote count is from Wikipedia. Resettlement totals vary by source (1.13m to 1.4m). Web search budget ran out before the river-closure date could be sourced, so it is omitted. Baseline audit 2026-10-25: Planned figures unchanged (initial CNY 203.9bn). Added the revised official estimate of CNY 180bn cited in 2000 and 2001 reports as the rebaseline; its approval year is not stated.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 87,
      "slug": "south-africa-2010-world-cup",
      "name": "2010 FIFA World Cup in South Africa (stadium programme)",
      "short_name": "World Cup 2010 SA",
      "category": "events",
      "subcategory": "football world cup",
      "country": "South Africa",
      "country_code": "ZA",
      "countries": [
        "South Africa"
      ],
      "continent": "Africa",
      "city": "Johannesburg (Soccer City)",
      "lat": -26.2347,
      "lng": 27.9825,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "2004-05-15",
      "planned_end": "2010-06-11",
      "actual_start": "2004-05-15",
      "actual_end": "2010-06-11",
      "actual_is_forecast": false,
      "planned_duration_months": 72.9,
      "actual_duration_months": 72.9,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 8400000000,
      "actual_cost": 11704600000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "ZAR",
      "planned_cost_year": 2006,
      "cost_year": 2010,
      "planned_fx_to_usd": 0.1478,
      "actual_fx_to_usd": 0.1367,
      "planned_cost_usd_nominal": 1241520000,
      "cost_usd_nominal": 1600018820,
      "planned_cost_usd_today": 1982784087,
      "cost_usd_today": 2362304606,
      "overrun_usd_today": 666957589,
      "overrun_pct": 39.3,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Bid and award",
          "planned_start": null,
          "planned_end": "2004-05-15",
          "actual_start": "2003",
          "actual_end": "2004-05-15",
          "note": "FIFA announced South Africa as host on May 15, 2004 in Zurich: 14 votes to Morocco's 10 and Egypt's none."
        },
        {
          "name": "Stadium planning and budgeting",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2005",
          "actual_end": "2006-10",
          "note": "National Treasury stadium spending began in 2005; by October 2006 stadium construction was expected to cost R8.4 billion."
        },
        {
          "name": "Stadium construction (5 new, 5 upgraded)",
          "planned_start": null,
          "planned_end": "2009-12",
          "actual_start": "2007-01",
          "actual_end": "2009-12-14",
          "note": "Soccer City upgrade began January 2007 and finished October 21, 2009; Moses Mabhida (2007-2009) opened November 28, 2009; Cape Town Stadium (2007-2009) opened December 14, 2009. About 70,000 workers struck on July 8, 2009."
        },
        {
          "name": "Test event (Confederations Cup)",
          "planned_start": "2009-06",
          "planned_end": "2009-06",
          "actual_start": "2009-06",
          "actual_end": "2009-06",
          "note": "The 2009 Confederations Cup served as a dress rehearsal at a subset of venues."
        },
        {
          "name": "Tournament",
          "planned_start": "2010-06-11",
          "planned_end": "2010-07-11",
          "actual_start": "2010-06-11",
          "actual_end": "2010-07-11",
          "note": "64 matches in 10 stadiums in nine host cities; final at Soccer City on July 11, 2010."
        }
      ],
      "milestones": [
        {
          "name": "FIFA awards World Cup to South Africa",
          "planned_date": "2004-05-15",
          "actual_date": "2004-05-15"
        },
        {
          "name": "R8.4bn stadium estimate reported",
          "planned_date": null,
          "actual_date": "2006-10-01"
        },
        {
          "name": "Soccer City upgrade completed",
          "planned_date": null,
          "actual_date": "2009-10-21"
        },
        {
          "name": "Cape Town Stadium opened",
          "planned_date": null,
          "actual_date": "2009-12-14"
        },
        {
          "name": "Opening match",
          "planned_date": "2010-06-11",
          "actual_date": "2010-06-11"
        }
      ],
      "headline": "South Africa's World Cup stadiums cost the state about R11.7 billion, some 39 percent more than the R8.4 billion expected in 2006.",
      "summary": "South Africa won the 2010 FIFA World Cup in May 2004, the first held in Africa. Five stadiums were built and five upgraded in nine host cities, including Soccer City in Johannesburg, Moses Mabhida in Durban and Cape Town Stadium at Green Point. All were ready by December 2009, despite a national construction strike in July 2009. National Treasury data put public stadium spending at R11.7 billion for 2005-2010, against an R8.4 billion estimate in 2006.",
      "what_went_wrong_or_right": "The stadium programme met FIFA's fixed deadline. Soccer City's upgrade was finished on October 21, 2009, Moses Mabhida opened on November 28, 2009 and Cape Town Stadium on December 14, 2009, six months before kick-off. Cost was another matter. In October 2006 stadium construction was expected to cost R8.4 billion. National Treasury figures compiled by du Plessis and Venter (Stellenbosch University, 2010) show public stadium expenditure of R11.7 billion between 2005 and 2010, out of R33.7 billion of public spending directly tied to the tournament. Individual venues escalated faster. Nelson Mandela Bay Stadium in Port Elizabeth rose from an estimated R711 million in June 2006 to R1.5 billion by May 2008 and a completed cost of about R2.065 billion, leaving local ratepayers to cover a shortfall under the national-provincial-municipal cost split. A strike by about 70,000 stadium workers on July 8, 2009 added schedule pressure late in the programme. Treasury data show that stadium spending was only R0.7 billion by the end of 2006 and peaked at R4.4 billion in 2008, so nearly all of the cost was committed after the 2006 estimate.",
      "lessons": [
        "Budget per venue with escalation allowances; programme totals hide fast-rising individual projects.",
        "Agree cost-sharing between national and city governments before contracts are signed.",
        "Fixed tournament dates make labor relations a schedule risk; plan for it."
      ],
      "fun_fact": "The Nelson Mandela Bay Stadium's cost rose from an estimated R711 million in June 2006 to about R2.065 billion on completion (Wikipedia, citing The Herald, July 14, 2010).",
      "method_tags": [],
      "related_history_ids": [
        "planning-fallacy-1979",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "The home team scores! A first assessment of the economic impact of World Cup 2010 (du Plessis & Venter, Stellenbosch Economic Working Papers 21/10)",
          "publisher": "Stellenbosch University, Department of Economics",
          "url": "https://www.ekon.sun.ac.za/wpapers/2010/wp212010/wp-21-2010.pdf",
          "accessed": "2026-10-25"
        },
        {
          "title": "2010 FIFA World Cup",
          "publisher": "Wikipedia (citing News24, October 1, 2006)",
          "url": "https://en.wikipedia.org/wiki/2010_FIFA_World_Cup",
          "accessed": "2026-10-25"
        },
        {
          "title": "Nelson Mandela Bay Stadium",
          "publisher": "Wikipedia (citing The Herald, July 14, 2010)",
          "url": "https://en.wikipedia.org/wiki/Nelson_Mandela_Bay_Stadium",
          "accessed": "2026-10-25"
        },
        {
          "title": "FNB Stadium",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/FNB_Stadium",
          "accessed": "2026-10-25"
        },
        {
          "title": "Cape Town Stadium",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Cape_Town_Stadium",
          "accessed": "2026-10-25"
        },
        {
          "title": "H.10 Foreign Exchange Rates, historical data",
          "publisher": "Board of Governors of the Federal Reserve System",
          "url": "https://www.federalreserve.gov/releases/h10/hist/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Scope: the stadium programme only. Baseline: the R8.4 billion stadium construction estimate reported in October 2006 (News24, via Wikipedia). Lower bid-era stadium estimates from 2004 exist in press coverage but were not verified in an opened source, so the real overrun against the bid is likely larger than shown. Actual: R11,704.6 million national public expenditure on stadiums for calendar years 2005-2010 (National Treasury 2010 FIFA World Cup Unit data, Table 2 of du Plessis & Venter 2010). This is nominal and may exclude some municipal and provincial top-ups (for example the Nelson Mandela Bay shortfall). The computed nominal overrun is about 39%. planned_end/actual_end = opening match (June 11, 2010). FX: Fed H.10 annual averages, 6.7668 ZAR per USD in 2006 and 7.3159 in 2010. The bid-phase start (2003) and Confederations Cup dates are approximate. Coordinates are for Soccer City (FNB Stadium), the final venue.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 88,
      "slug": "athens-2004-olympics",
      "name": "Athens 2004 Summer Olympics",
      "short_name": "Athens 2004",
      "category": "events",
      "subcategory": "olympics",
      "country": "Greece",
      "country_code": "GR",
      "countries": [
        "Greece"
      ],
      "continent": "Europe",
      "city": "Athens",
      "lat": 38.0361,
      "lng": 23.7876,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1997-09-05",
      "planned_end": "2004-08-13",
      "actual_start": "1997-09-05",
      "actual_end": "2004-08-13",
      "actual_is_forecast": false,
      "planned_duration_months": 83.3,
      "actual_duration_months": 83.3,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 3000000000,
      "actual_cost": 9000000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        8500000000,
        10000000000
      ],
      "cost_currency": "EUR",
      "planned_cost_year": 2000,
      "cost_year": 2004,
      "planned_fx_to_usd": 0.9232,
      "actual_fx_to_usd": 1.2438,
      "planned_cost_usd_nominal": 2769600000,
      "cost_usd_nominal": 11196000000,
      "planned_cost_usd_today": 5177947826,
      "cost_usd_today": 19084090909,
      "overrun_usd_today": 12722727273,
      "overrun_pct": 200,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 49,
      "reported_overrun_source": "Flyvbjerg, Budzier & Lunn 2020 (sports-related cost only, real terms, vs bid)",
      "phases": [
        {
          "name": "Bid and award",
          "planned_start": null,
          "planned_end": "1997-09-05",
          "actual_start": "1996",
          "actual_end": "1997-09-05",
          "note": "Athens, which lost the 1996 Games to Atlanta, was elected at the 106th IOC Session in Lausanne on September 5, 1997."
        },
        {
          "name": "Venue and infrastructure construction",
          "planned_start": null,
          "planned_end": "2004-08-13",
          "actual_start": "2000",
          "actual_end": "2004-08",
          "note": "Start year approximate. By late March 2004 some projects were behind schedule and the planned Aquatics Centre roof was dropped."
        },
        {
          "name": "Olympic Stadium renovation (Calatrava roof)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2002",
          "actual_end": "2004-06",
          "note": "Renovation 2002-2004 at a cost of EUR 265 million; the stadium was completed about two months before the Games."
        },
        {
          "name": "Games",
          "planned_start": "2004-08-13",
          "planned_end": "2004-08-29",
          "actual_start": "2004-08-13",
          "actual_end": "2004-08-29",
          "note": "Held on schedule."
        },
        {
          "name": "Wind-up and cost accounting",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2004-08-30",
          "actual_end": "2013-01-18",
          "note": "ATHOC closed in 2005 with a EUR 130.6 million surplus; the Finance Ministry's cost-benefit report reached Parliament in January 2013."
        }
      ],
      "milestones": [
        {
          "name": "IOC awards Games to Athens",
          "planned_date": "1997-09-05",
          "actual_date": "1997-09-05"
        },
        {
          "name": "Olympic Stadium completed",
          "planned_date": null,
          "actual_date": "2004-06"
        },
        {
          "name": "Opening ceremony",
          "planned_date": "2004-08-13",
          "actual_date": "2004-08-13"
        },
        {
          "name": "Finance Ministry cost report (EUR 8.5bn)",
          "planned_date": null,
          "actual_date": "2013-01-18"
        }
      ],
      "headline": "Athens 2004 opened on time, but government and organizing costs grew from about EUR 3 billion to near EUR 9 billion.",
      "summary": "Athens won the 2004 Games in September 1997, seven years after losing the centenary Games to Atlanta. Preparation was slow, and venues were finished in a rush: the main stadium, with Santiago Calatrava's roof, was completed two months before the August 13 opening. According to PwC figures reported by the BBC, the government budget rose from EUR 2.5 billion to EUR 4.6 billion and operating costs from EUR 0.5 billion to EUR 2 billion. The state put the total near EUR 9 billion.",
      "what_went_wrong_or_right": "The Games were delivered on time, but the final years became a race against the opening date. By late March 2004 several projects were behind schedule, and the planned roof over the Aquatics Centre was dropped. The Olympic Stadium, refurbished from 2002 to 2004 with Calatrava's steel-and-glass roof, was completed only about two months before the opening. In June 2004 the BBC, citing PricewaterhouseCoopers, reported that the government's Games budget had grown from EUR 2.5 billion to EUR 4.6 billion and organizing costs from EUR 0.5 billion to EUR 2 billion. It added that the new government accused its predecessor of 'losing control' of spending, and that items such as EUR 1.3 billion of transport work and the EUR 600 million athletes' village were not counted. The state later put the total near EUR 9 billion, and a 2013 Finance Ministry report put it at EUR 8.5 billion, of which about EUR 2 billion was covered by ATHOC revenue. On sports-related costs alone, Oxford researchers measured a 49 percent real overrun, low by Olympic standards. The large gap between that figure and the headline totals is mostly a question of scope.",
      "lessons": [
        "Agree early which costs count as Olympic, or the overrun debate will never be settled.",
        "Late starts convert schedule float into cost through acceleration and scope cuts.",
        "Plan post-event use of venues before building them."
      ],
      "fun_fact": "The Athens organizing committee (ATHOC) wound up in 2005 with a surplus of EUR 130.6 million, even as the state's Games bill neared EUR 9 billion (Wikipedia, citing ATHOC and the Greek government).",
      "method_tags": [
        "fast_track"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "Olympics 'may cost Greece dear'",
          "publisher": "BBC News, June 2, 2004",
          "url": "http://news.bbc.co.uk/2/hi/business/3770981.stm",
          "accessed": "2026-10-25"
        },
        {
          "title": "2004 Summer Olympics",
          "publisher": "Wikipedia (citing Greek Embassy and the 2013 Finance Ministry report)",
          "url": "https://en.wikipedia.org/wiki/2004_Summer_Olympics",
          "accessed": "2026-10-25"
        },
        {
          "title": "Olympic Stadium (Athens)",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Olympic_Stadium_(Athens)",
          "accessed": "2026-10-25"
        },
        {
          "title": "Regression to the Tail: Why the Olympics Blow Up (Flyvbjerg, Budzier & Lunn, Environment and Planning A, 2020)",
          "publisher": "arXiv / University of Oxford",
          "url": "https://arxiv.org/abs/2009.14682",
          "accessed": "2026-10-25"
        },
        {
          "title": "As Olympic glow fades, Athens questions $15 billion cost",
          "publisher": "The Christian Science Monitor, July 21, 2008",
          "url": "https://www.csmonitor.com/World/2008/0721/p04s01-wogn.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "H.10 Foreign Exchange Rates, historical data",
          "publisher": "Board of Governors of the Federal Reserve System",
          "url": "https://www.federalreserve.gov/releases/h10/hist/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "No bid-book figure in euros was found in an opened source. Baseline used: the earlier budgets reported by the BBC in June 2004 (PwC): EUR 2.5 billion government budget plus EUR 0.5 billion operating costs = EUR 3.0 billion. The date of those earlier figures is not stated; planned_cost_year 2000 is an approximation (the euro did not exist when Athens bid in 1997). Actual: 'near EUR 9 billion' (Greek government via Wikipedia); range EUR 8.5 billion (2013 Finance Ministry report) to about EUR 10 billion (press reports cited by the BBC in 2004). The Christian Science Monitor cited a US$15 billion figure in 2008. The Flyvbjerg et al. 49% real overrun covers sports-related costs only (US$2.942 billion in 2015 dollars), so it is much smaller than the nominal overrun computed from these totals. planned_end/actual_end = opening ceremony (August 13, 2004). FX: Fed H.10 annual averages, EUR 2000 = 0.9232 and 2004 = 1.2438 USD per EUR. The construction phase start year is approximate.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 89,
      "slug": "barcelona-1992-olympics",
      "name": "Barcelona 1992 Summer Olympics",
      "short_name": "Barcelona 1992",
      "category": "events",
      "subcategory": "olympics",
      "country": "Spain",
      "country_code": "ES",
      "countries": [
        "Spain"
      ],
      "continent": "Europe",
      "city": "Barcelona",
      "lat": 41.3647,
      "lng": 2.1556,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1986-10-17",
      "planned_end": "1992-07-25",
      "actual_start": "1986-10-17",
      "actual_end": "1992-07-25",
      "actual_is_forecast": false,
      "planned_duration_months": 69.3,
      "actual_duration_months": 69.3,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 2647000000,
      "actual_cost": 9687000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": 2015,
      "cost_year": 2015,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 2647000000,
      "cost_usd_nominal": 9687000000,
      "planned_cost_usd_today": 3595356591,
      "cost_usd_today": 13157619683,
      "overrun_usd_today": 9562263091,
      "overrun_pct": 266,
      "overrun_basis": "real",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 266,
      "reported_overrun_source": "Flyvbjerg, Stewart & Budzier 2016; Flyvbjerg, Budzier & Lunn 2020 (sports-related cost, real terms, vs bid)",
      "phases": [
        {
          "name": "Bid and award",
          "planned_start": null,
          "planned_end": "1986-10-17",
          "actual_start": "1981",
          "actual_end": "1986-10-17",
          "note": "Barcelona beat Paris, Brisbane, Belgrade, Birmingham and Amsterdam at the 91st IOC Session in Lausanne on October 17, 1986."
        },
        {
          "name": "Venue construction (Montjuic and other areas)",
          "planned_start": null,
          "planned_end": "1992-07-25",
          "actual_start": "1986",
          "actual_end": "1992-07",
          "note": "Venues and urban works were built and upgraded across the city; the Palau Sant Jordi arena was built 1986-1990."
        },
        {
          "name": "Games",
          "planned_start": "1992-07-25",
          "planned_end": "1992-08-09",
          "actual_start": "1992-07-25",
          "actual_end": "1992-08-09",
          "note": "Held on schedule."
        }
      ],
      "milestones": [
        {
          "name": "IOC awards Games to Barcelona",
          "planned_date": "1986-10-17",
          "actual_date": "1986-10-17"
        },
        {
          "name": "Palau Sant Jordi completed",
          "planned_date": null,
          "actual_date": "1990"
        },
        {
          "name": "Opening ceremony",
          "planned_date": "1992-07-25",
          "actual_date": "1992-07-25"
        },
        {
          "name": "Closing ceremony",
          "planned_date": "1992-08-09",
          "actual_date": "1992-08-09"
        }
      ],
      "headline": "Barcelona's sports-related Olympic costs ran 266 percent over the bid in real terms, to US$9.7 billion in 2015 dollars, but the Games are widely seen as a model of urban regeneration.",
      "summary": "Barcelona, home city of IOC president Juan Antonio Samaranch, won the 1992 Games in October 1986 and used them to drive a wider renewal of the city. The Games opened on time on July 25, 1992. The Oxford Olympics Study puts sports-related costs at US$9.7 billion in 2015 dollars, 266 percent over the bid in real terms and the second-highest Summer Games total before London. Spending on general infrastructure was about eight times the sports spending.",
      "what_went_wrong_or_right": "Barcelona is the standard example of a costly Games that most observers still count as a success. On cost, Oxford researchers measured a 266 percent real overrun on sports-related costs against the bid, second only to Montreal among the Summer Games in their 2016 dataset, with an outturn of US$9.7 billion in 2015 dollars. Part of the explanation is scope: the city treated the Games as a lever for long-planned urban renewal, so the Olympic program grew well beyond the venues. Baade and Matheson, cited by Flyvbjerg, Budzier and Lunn, found that Barcelona's general infrastructure spending, on roads, the waterfront and similar works, was about eight times its sports infrastructure spending. Those wider costs fall outside the overrun figure. On benefits, the infrastructure investment is credited with improving quality of life and raising the city's attraction for tourism and investment, and Barcelona is often cited as a case of hosting transforming a city. For a project manager the record is mixed. The schedule held to a fixed date, but the bid budget was not a reliable forecast, and the 'success' judgment rests on benefits that the original estimate never priced.",
      "lessons": [
        "Separate event costs from city-building costs in the business case, and report both.",
        "A schedule success does not validate a bid budget; track both against the original baseline.",
        "Tie Olympic investment to an existing urban plan so the assets have uses afterwards."
      ],
      "fun_fact": "For Barcelona 1992, general infrastructure cost about eight times as much as sports infrastructure (Baade and Matheson, cited in Flyvbjerg, Budzier & Lunn 2020).",
      "method_tags": [],
      "related_history_ids": [
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "The Oxford Olympics Study 2016: Cost and Cost Overrun at the Games (Flyvbjerg, Stewart & Budzier)",
          "publisher": "arXiv / Said Business School, University of Oxford",
          "url": "https://arxiv.org/abs/1607.04484",
          "accessed": "2026-10-25"
        },
        {
          "title": "Regression to the Tail: Why the Olympics Blow Up (Flyvbjerg, Budzier & Lunn, Environment and Planning A, 2020)",
          "publisher": "arXiv / University of Oxford",
          "url": "https://arxiv.org/abs/2009.14682",
          "accessed": "2026-10-25"
        },
        {
          "title": "1992 Summer Olympics",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/1992_Summer_Olympics",
          "accessed": "2026-10-25"
        },
        {
          "title": "Palau Sant Jordi",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Palau_Sant_Jordi",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Expressed in 2015 US dollars, from the Oxford Olympics Study 2016 and Flyvbjerg et al. 2020: actual sports-related cost US$9.687 billion and 266% real overrun versus the bid. Planned is DERIVED, not quoted: 9.687 / (1 + 2.66) = about US$2.647 billion in 2015 dollars. The original bid figures in pesetas (Brunet 1995, Centre d'Estudis Olimpics UAB) could not be opened, so no peseta figures are given. Sports-related costs exclude the much larger general infrastructure program. planned_end/actual_end = opening ceremony (July 25, 1992). The bid-phase start (1981) and the start of venue construction (1986) are approximate. FX not needed (USD).",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 90,
      "slug": "expo-2015-milan",
      "name": "Expo 2015 Milan",
      "short_name": "Expo 2015 Milan",
      "category": "events",
      "subcategory": "world's fair",
      "country": "Italy",
      "country_code": "IT",
      "countries": [
        "Italy"
      ],
      "continent": "Europe",
      "city": "Milan (Rho-Pero)",
      "lat": 45.5186,
      "lng": 9.1067,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "on_time_on_budget",
      "planned_start": "2008-03-31",
      "planned_end": "2015-05-01",
      "actual_start": "2008-03-31",
      "actual_end": "2015-05-01",
      "actual_is_forecast": false,
      "planned_duration_months": 85,
      "actual_duration_months": 85,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 3200000000,
      "actual_cost": 2254700000,
      "planned_cost_range": [
        3023000000,
        3200000000
      ],
      "actual_cost_range": null,
      "cost_currency": "EUR",
      "planned_cost_year": 2008,
      "cost_year": 2015,
      "planned_fx_to_usd": 1.4726,
      "actual_fx_to_usd": 1.1096,
      "planned_cost_usd_nominal": 4713600000,
      "cost_usd_nominal": 2502717000,
      "planned_cost_usd_today": 7048544049,
      "cost_usd_today": 3399380454,
      "overrun_usd_today": -1425215924,
      "overrun_pct": -29.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": 3023000000,
      "rebaseline_cost_year": 2012,
      "rebaseline_end": null,
      "rebaseline_label": "September 2012 revised plan",
      "rebaseline_overrun_pct": -25.4,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Candidacy and award",
          "planned_start": null,
          "planned_end": "2008-03-31",
          "actual_start": "2006-11-03",
          "actual_end": "2008-03-31",
          "note": "Candidacies closed November 3, 2006 (Milan and Izmir). The BIE General Assembly in Paris chose Milan on March 31, 2008, by 86 votes to 65."
        },
        {
          "name": "Registration and master plan",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2009",
          "actual_end": "2010-10-20",
          "note": "Expo 2015 S.p.A. was created in 2009. The registration dossier and Stefano Boeri-coordinated master plan went to the BIE on April 30, 2010; the BIE executive committee approved it on October 20, 2010."
        },
        {
          "name": "Land acquisition and site construction",
          "planned_start": null,
          "planned_end": "2015-05-01",
          "actual_start": "2011-06",
          "actual_end": "2015-05-01",
          "note": "The site land, owned by Fondazione Fiera Milano and the Cabassi family, passed to the public company Arexpo from June 2011. Building work on the 1.1 square km Rho-Pero site ran up to the opening. Contract corruption arrests in 2014 led to anti-corruption oversight by Raffaele Cantone."
        },
        {
          "name": "Exposition",
          "planned_start": "2015-05-01",
          "planned_end": "2015-10-31",
          "actual_start": "2015-05-01",
          "actual_end": "2015-10-31",
          "note": "Opened May 1 and closed October 31, 2015; 145 countries took part and about 22.2 million visits were recorded."
        },
        {
          "name": "Liquidation and final accounts",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2015-11",
          "actual_end": "2016-05-12",
          "note": "Expo 2015 S.p.A. went into liquidation on February 18, 2016; its final accounts were published May 12, 2016."
        }
      ],
      "milestones": [
        {
          "name": "BIE awards Expo to Milan",
          "planned_date": "2008-03-31",
          "actual_date": "2008-03-31"
        },
        {
          "name": "Registration dossier approved by BIE",
          "planned_date": null,
          "actual_date": "2010-10-20"
        },
        {
          "name": "Opening day",
          "planned_date": "2015-05-01",
          "actual_date": "2015-05-01"
        },
        {
          "name": "Closing day",
          "planned_date": "2015-10-31",
          "actual_date": "2015-10-31"
        },
        {
          "name": "Final accounts published",
          "planned_date": null,
          "actual_date": "2016-05-12"
        }
      ],
      "headline": "Expo 2015 opened on its fixed date of May 1, 2015, and its organizing company spent EUR 2.25 billion from 2009 to 2015.",
      "summary": "Milan won the right to host the 2015 World Expo in March 2008, beating Izmir, with the theme 'Feeding the Planet, Energy for Life'. A public company, Expo 2015 S.p.A., led by Giuseppe Sala, built a 1.1 square km site at Rho-Pero, north-west of Milan. Delivery was slowed by land disputes and disrupted by 2014 corruption arrests, but the Expo opened on May 1, 2015 and drew about 22.2 million visits. The company's costs totalled EUR 2.2547 billion.",
      "what_went_wrong_or_right": "Expo 2015 met its immovable deadline, but the run-up was difficult. The site land was privately owned, split between Fondazione Fiera Milano and the Cabassi family, and a long dispute between institutions ended only with the creation of the public land company Arexpo from 2011. That shortened the time left for construction. In 2014 a Milan anti-corruption investigation into Expo contracts led to several arrests, and the government put procurement under the oversight of anti-corruption commissioner Raffaele Cantone. Some countries pulled out, Canada and Australia citing budget limits, and Bulgaria cited delays. On the delivery side, the master plan was simplified from a 'classical' site of pavilions to a lighter layout along two axes modeled on a Roman cardo and decumanus, which reduced roofing. Attendance reached the 20 million target. According to the final accounts reported by Corriere della Sera, the company cost EUR 2,254.7 million from 2009 to 2015. Funding came from EUR 1,258.7 million of public contributions and EUR 944 million of operating revenue, including EUR 421.3 million from tickets, and the company closed with positive net equity of EUR 30.7 million.",
      "lessons": [
        "Secure land and site control before the award clock starts running.",
        "Build anti-corruption controls into procurement from the start, not after arrests.",
        "Simplify the master plan early to protect a fixed opening date."
      ],
      "fun_fact": "Expo 2015 sold 21,476,957 tickets at an average of EUR 17.4 each (Italian Wikipedia, citing Expo data).",
      "method_tags": [],
      "related_history_ids": [
        "big-things-2023",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Expo e costata 2,2 miliardi e ha guadagnato 30,7 milioni",
          "publisher": "Corriere della Sera (Milano), May 12, 2016",
          "url": "https://milano.corriere.it/notizie/cronaca/16_maggio_12/expo-costata-22-miliardi-rendiconto-esercizio-patrimonio-netto-conti-34cd4fd6-183c-11e6-a192-aa62c89d5ec1.shtml",
          "accessed": "2026-10-25"
        },
        {
          "title": "Expo 2015",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Expo_2015",
          "accessed": "2026-10-25"
        },
        {
          "title": "Expo 2015",
          "publisher": "Wikipedia (Italian)",
          "url": "https://it.wikipedia.org/wiki/Expo_2015",
          "accessed": "2026-10-25"
        },
        {
          "title": "H.10 Foreign Exchange Rates, historical data",
          "publisher": "Board of Governors of the Federal Reserve System",
          "url": "https://www.federalreserve.gov/releases/h10/hist/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Expo 2015, arrivano i primi fondi",
          "publisher": "VareseNews, 18 June 2008",
          "url": "https://www.varesenews.it/2008/06/expo-2015-arrivano-i-primi-fondi/214169/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Expo 2015: mille e non piu mille",
          "publisher": "Teleborsa, 5 September 2012",
          "url": "https://www.teleborsa.it/Speciali/2012/09/05/expo-2015-mille-e-non-piu-mille-106.html?p=2",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "No first approved budget was verified in an opened source, so planned_cost is null and no overrun can be computed. A 2008 Italian government decree set the initial funding, but the Corriere article reporting it could not be opened. Actual: EUR 2,254.7 million total cost of Expo 2015 S.p.A. from 2009 to 2015, from its final accounts (Corriere della Sera, May 12, 2016). This excludes participants' pavilions, Arexpo's land purchase, and related transport and road works. planned_end/actual_end = opening day (May 1, 2015). FX: Fed H.10 annual average, EUR 2015 = 1.1096 USD. The site-construction start is approximate (June 2011 land deal); the arrests are dated 2014 per Italian Wikipedia's citation of la Repubblica (May 31, 2014). UPDATE 2026-10-25: Planned cost now set from the June 2008 funding plan in decree-law 112/2008: State EUR 1.4 billion over seven years (133m 2009-11, 223m 2012, 565m 2013, 446m 2014, 119m 2015) plus EUR 850 million from local authorities and EUR 890 million private, 'EUR 3.2 billion total budget' (VareseNews, 18 June 2008). Scope caveat: the 2008 budget may include works later assigned to bodies other than Expo 2015 S.p.A.; it is the closest available match to the company's EUR 2,254.7 million actual. The 2012 revised plan was EUR 1.746 billion infrastructure (EUR 1.486 billion from the State, 260m private) plus EUR 1.277 billion operating costs, total EUR 3.023 billion (Teleborsa, Sept 2012), the lower bound of planned_cost_range. The record therefore shows an underrun, driven partly by scope reductions; confidence 'disputed'. The DPCM of 22 October 2008 and Corte dei conti reports (Camera Doc. XV n. 63 and 385; Senato) were located but returned 403 or a bot check and could not be read. FX 2008: FRED AEXUSEU 1.4726. exclude_flag removed. Baseline audit 2026-10-25: Planned figures unchanged (June 2008 plan, EUR 3.2bn). Added the September 2012 revised plan of EUR 3.023bn (Teleborsa) as the rebaseline.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 91,
      "slug": "london-2012-olympics",
      "name": "London 2012 Olympic and Paralympic Games",
      "short_name": "London 2012",
      "category": "events",
      "subcategory": "olympics",
      "country": "United Kingdom",
      "country_code": "GB",
      "countries": [
        "United Kingdom"
      ],
      "continent": "Europe",
      "city": "London (Stratford)",
      "lat": 51.5383,
      "lng": -0.0166,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "2005-07-06",
      "planned_end": "2012-07-27",
      "actual_start": "2005-07-06",
      "actual_end": "2012-07-27",
      "actual_is_forecast": false,
      "planned_duration_months": 84.7,
      "actual_duration_months": 84.7,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 4000000000,
      "actual_cost": 8921000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "GBP",
      "planned_cost_year": 2005,
      "cost_year": 2012,
      "planned_fx_to_usd": 1.8204,
      "actual_fx_to_usd": 1.5853,
      "planned_cost_usd_nominal": 7280000000,
      "cost_usd_nominal": 14139785000,
      "planned_cost_usd_today": 12001022321,
      "cost_usd_today": 19829311476,
      "overrun_usd_today": 10938240307,
      "overrun_pct": 123,
      "overrun_basis": "nominal",
      "rebaseline_cost": 9325000000,
      "rebaseline_cost_year": 2007,
      "rebaseline_end": null,
      "rebaseline_label": "March 2007 public sector funding package",
      "rebaseline_overrun_pct": -4.3,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 76,
      "reported_overrun_source": "Flyvbjerg, Budzier & Lunn 2020 (sports-related cost, real terms, vs 2005 bid)",
      "phases": [
        {
          "name": "Bid and award",
          "planned_start": null,
          "planned_end": "2005-07-06",
          "actual_start": "2003",
          "actual_end": "2005-07-06",
          "note": "London beat Paris 54-50 in the final round at the 117th IOC Session in Singapore on July 6, 2005."
        },
        {
          "name": "Delivery set-up and rebudgeting",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2006-04",
          "actual_end": "2007-03-15",
          "note": "The Olympic Delivery Authority was set up in April 2006. On March 15, 2007 Tessa Jowell announced the new GBP 9.3 billion Public Sector Funding Package, the baseline later used for 'under budget' claims."
        },
        {
          "name": "Olympic Park construction",
          "planned_start": null,
          "planned_end": "2011",
          "actual_start": "2006-12",
          "actual_end": "2011-12",
          "note": "Site work began in December 2006. The Olympic Stadium was built from May 22, 2008 to March 29, 2011 for GBP 486 million. The NAO found the construction programme completed on time and within budget."
        },
        {
          "name": "Test events",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2011",
          "actual_end": "2012-07",
          "note": "Test events ran through 2011 and 2012 under the London Prepares banner and at existing championships."
        },
        {
          "name": "Games",
          "planned_start": "2012-07-27",
          "planned_end": "2012-08-12",
          "actual_start": "2012-07-27",
          "actual_end": "2012-08-12",
          "note": "Olympics opened July 27 and closed August 12, 2012; the Paralympics followed."
        },
        {
          "name": "Post-Games review and legacy transfer",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2012-08-13",
          "actual_end": "2012-12-05",
          "note": "The NAO post-Games review (December 5, 2012) put the anticipated final cost at GBP 8,921 million, GBP 377 million under the GBP 9,298 million package."
        }
      ],
      "milestones": [
        {
          "name": "IOC awards Games to London",
          "planned_date": "2005-07-06",
          "actual_date": "2005-07-06"
        },
        {
          "name": "GBP 9.3bn budget announced",
          "planned_date": null,
          "actual_date": "2007-03-15"
        },
        {
          "name": "Olympic Stadium completed",
          "planned_date": null,
          "actual_date": "2011-03-29"
        },
        {
          "name": "Opening ceremony",
          "planned_date": "2012-07-27",
          "actual_date": "2012-07-27"
        },
        {
          "name": "NAO post-Games review",
          "planned_date": null,
          "actual_date": "2012-12-05"
        }
      ],
      "headline": "London 2012 finished GBP 377 million under its 2007 budget of GBP 9.3 billion, but that budget was more than double the 2005 bid.",
      "summary": "London won the 2012 Games on July 6, 2005 with a gross cost estimate of just over GBP 4 billion. In March 2007 the government reset the public budget at about GBP 9.3 billion, including a GBP 2.7 billion contingency. The Olympic Delivery Authority built the Stratford park on schedule, and the Games opened on July 27, 2012. The National Audit Office forecast a final cost of GBP 8.921 billion, within the 2007 package but well above the bid.",
      "what_went_wrong_or_right": "London is two stories, depending on the baseline. Against the March 2007 Public Sector Funding Package of about GBP 9.3 billion, delivery was disciplined. The NAO reported in December 2012 that the construction programme was completed on time and within budget, with the Olympic Delivery Authority's venues and infrastructure expected to cost about GBP 6.7 billion against GBP 8.1 billion available, and an overall forecast underspend of GBP 377 million. Venue security added about GBP 500 million late, which the package absorbed. Against the 2005 bid, the picture is different. The NAO's July 2007 report explains that the bid's estimated gross cost of just over GBP 4 billion omitted or underestimated items that the new budget added: ODA programme management, a GBP 2.7 billion contingency, tax, and security. Public funding rose by about GBP 6 billion, and expected private funding fell to GBP 165 million. Flyvbjerg, Budzier and Lunn measure a 76 percent real overrun on sports-related costs against the bid, and describe the 'under budget' claim as misleading because it used the reset baseline. The bid's 4.3 percent contingency was roughly one-eighteenth of the overrun that followed.",
      "lessons": [
        "State which baseline you report against; rebaselining can turn an overrun into an 'underspend'.",
        "Price tax, security, contingency and programme management into the first estimate.",
        "A large ring-fenced contingency, once set, gave the delivery body room to absorb shocks."
      ],
      "fun_fact": "London's bid carried a 4.3 percent contingency, about 18 times smaller than the 76 percent real overrun that followed (Flyvbjerg, Budzier & Lunn 2020).",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [
        "rcf-2004",
        "big-things-2023",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "The London 2012 Olympic Games and Paralympic Games: post-Games review",
          "publisher": "National Audit Office, December 5, 2012",
          "url": "https://www.nao.org.uk/reports/the-london-2012-olympic-games-and-paralympic-games-post-games-review/",
          "accessed": "2026-10-25"
        },
        {
          "title": "The budget for the London 2012 Olympic and Paralympic Games",
          "publisher": "National Audit Office, July 20, 2007",
          "url": "https://www.nao.org.uk/reports/the-budget-for-the-london-2012-olympic-and-paralympic-games/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Regression to the Tail: Why the Olympics Blow Up (Flyvbjerg, Budzier & Lunn, Environment and Planning A, 2020)",
          "publisher": "arXiv / University of Oxford",
          "url": "https://arxiv.org/abs/2009.14682",
          "accessed": "2026-10-25"
        },
        {
          "title": "2012 Summer Olympics",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/2012_Summer_Olympics",
          "accessed": "2026-10-25"
        },
        {
          "title": "London Stadium",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/London_Stadium",
          "accessed": "2026-10-25"
        },
        {
          "title": "H.10 Foreign Exchange Rates, historical data",
          "publisher": "Board of Governors of the Federal Reserve System",
          "url": "https://www.federalreserve.gov/releases/h10/hist/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline per spec = 2005 bid: 'estimated gross cost of just over GBP 4 billion' (GBP 3.4 billion public plus about GBP 0.7 billion private), as stated by the NAO in July 2007; stored as 4,000,000,000. Revised baseline: the GBP 9.325 billion Public Sector Funding Package announced on March 15, 2007, later restated as GBP 9,298 million. Against it the outturn is a 4% underspend; against the bid it is a nominal overrun of about 123%. The two figures are not like-for-like: the bid's GBP 4 billion gross figure includes privately funded organizing-committee (LOCOG) costs, while the GBP 8.921 billion is the anticipated final cost to the public package only (NAO, December 2012). LOCOG's own operating budget is not included in the actual figure. Flyvbjerg et al. measure sports-related cost at US$14.957 billion (2015 dollars) and a 76% real overrun versus the bid. planned_end/actual_end = Olympic opening ceremony (July 27, 2012). FX: Fed H.10 annual averages, GBP 2005 = 1.8204 and 2012 = 1.5853 USD per GBP. The bid-phase start year (2003) is approximate. Baseline audit 2026-10-25: Planned figures unchanged (2005 bid of just over GBP 4 billion is the first announced budget). Added the March 2007 public sector funding package of GBP 9.325 billion (NAO) as the rebaseline; against it the outturn is about GBP 0.4 billion under budget.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 92,
      "slug": "montreal-1976-olympics",
      "name": "Montreal 1976 Summer Olympics",
      "short_name": "Montreal 1976",
      "category": "events",
      "subcategory": "olympics",
      "country": "Canada",
      "country_code": "CA",
      "countries": [
        "Canada"
      ],
      "continent": "North America",
      "city": "Montreal",
      "lat": 45.558,
      "lng": -73.5515,
      "era": "1946-1979",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "1970-05-12",
      "planned_end": "1976-07-17",
      "actual_start": "1970-05-12",
      "actual_end": "1976-07-17",
      "actual_is_forecast": false,
      "planned_duration_months": 74.2,
      "actual_duration_months": 74.2,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 120000000,
      "actual_cost": 1600000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        1470000000,
        2400000000
      ],
      "cost_currency": "CAD",
      "planned_cost_year": 1970,
      "cost_year": 2006,
      "planned_fx_to_usd": 0.9902,
      "actual_fx_to_usd": 0.8818,
      "planned_cost_usd_nominal": 114948000,
      "cost_usd_nominal": 1410880000,
      "planned_cost_usd_today": 952975064,
      "cost_usd_today": 2253262463,
      "overrun_usd_today": 2084267778,
      "overrun_pct": 1233.3,
      "overrun_basis": "nominal",
      "rebaseline_cost": 310000000,
      "rebaseline_cost_year": 1973,
      "rebaseline_end": null,
      "rebaseline_label": "1973 revised estimate",
      "rebaseline_overrun_pct": 416.1,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 720,
      "reported_overrun_source": "Flyvbjerg, Budzier & Lunn 2020 (sports-related cost, real terms, vs bid)",
      "phases": [
        {
          "name": "Bid and award",
          "planned_start": null,
          "planned_end": "1970-05-12",
          "actual_start": "1969",
          "actual_end": "1970-05-12",
          "note": "Montreal beat Moscow and Los Angeles at the 69th IOC Session in Amsterdam on May 12, 1970."
        },
        {
          "name": "Olympic Park and stadium construction",
          "planned_start": null,
          "planned_end": "1976-07-17",
          "actual_start": "1973-04-28",
          "actual_end": "1976-07-17",
          "note": "Ground broken April 28, 1973. Strikes in 1974 and 1975 delayed the stadium, pool and velodrome; the velodrome, due in 1974, was finished in June 1976."
        },
        {
          "name": "Quebec government takeover",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1975-11",
          "actual_end": "1976-07-17",
          "note": "In November 1975 Premier Robert Bourassa's government took control of preparations from the city and Mayor Jean Drapeau."
        },
        {
          "name": "Games",
          "planned_start": "1976-07-17",
          "planned_end": "1976-08-01",
          "actual_start": "1976-07-17",
          "actual_end": "1976-08-01",
          "note": "Opened on schedule with the stadium tower and roof unfinished."
        },
        {
          "name": "Tower and roof completion",
          "planned_start": null,
          "planned_end": "1976-07-17",
          "actual_start": "1976-08",
          "actual_end": "1987-04",
          "note": "The inclined tower and Kevlar roof were completed in 1987, about a decade late."
        },
        {
          "name": "Debt repayment",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1976-05-11",
          "actual_end": "2006-11",
          "note": "A special provincial tobacco tax, added May 11, 1976, serviced the debt; the last payment was made in mid-November 2006."
        }
      ],
      "milestones": [
        {
          "name": "IOC awards Games to Montreal",
          "planned_date": "1970-05-12",
          "actual_date": "1970-05-12"
        },
        {
          "name": "Stadium groundbreaking",
          "planned_date": null,
          "actual_date": "1973-04-28"
        },
        {
          "name": "Opening ceremony",
          "planned_date": "1976-07-17",
          "actual_date": "1976-07-17"
        },
        {
          "name": "Stadium roof finished",
          "planned_date": "1976-07-17",
          "actual_date": "1987-04"
        },
        {
          "name": "Olympic debt fully repaid",
          "planned_date": null,
          "actual_date": "2006-11"
        }
      ],
      "headline": "Estimated at C$120 million in 1970, the Montreal Games ended at about C$1.6 billion and took Quebec 30 years to pay off.",
      "summary": "Montreal won the 1976 Summer Olympics in 1970 on a promise of a modest, self-financing Games. The original estimate was C$120 million, revised to C$310 million in 1973. Construction of the Taillibert-designed Olympic Park began late, in April 1973, and was hit by strikes, inflation and corruption. The Games opened on time on July 17, 1976, but the stadium tower and roof were finished only in 1987, and the debt was cleared in November 2006.",
      "what_went_wrong_or_right": "Oxford researchers rank Montreal as the largest cost overrun of any Summer Games, 720 percent in real terms against the bid estimate (Flyvbjerg, Budzier & Lunn 2020). The causes are well documented. Design ambition: Roger Taillibert's stadium, with a 175-metre inclined tower and retractable roof, was technically novel and was not finished until 1987. A late start: ground was broken on April 28, 1973, under three years before the opening. Labor disruption: unions called major strikes in 1974 and 1975, delaying the stadium, pool and velodrome. Inflation: steel rose from $200 to $1,200 a tonne during construction, according to the McCord Stewart Museum. Weak governance: the Malouf commission criticized the organizing committee and Mayor Jean Drapeau for mismanagement and for the absence of an overall budget and project oversight, and corruption charges followed. In November 1975 the Quebec government took control of the project. The fixed opening date turned the remaining work into an acceleration exercise at any price. Repayment, mainly through a tobacco tax introduced in May 1976, ran until November 2006.",
      "lessons": [
        "Freeze a technically novel design before committing to a fixed opening date.",
        "Set one owner and one overall budget with independent oversight from day one.",
        "Start construction early enough that labor disputes do not land on the critical path.",
        "Price inflation and escalation risk explicitly when the build spans several years."
      ],
      "fun_fact": "In 1973 Mayor Jean Drapeau said the Olympics could no more have a deficit \"than a man can have a baby\" (quoted in Flyvbjerg, Budzier & Lunn 2020, citing CBC).",
      "method_tags": [
        "fast_track"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "rcf-2004",
        "big-things-2023"
      ],
      "sources": [
        {
          "title": "The Montreal Olympics",
          "publisher": "The Canadian Encyclopedia",
          "url": "https://www.thecanadianencyclopedia.ca/en/article/the-montreal-olympics",
          "accessed": "2026-10-25"
        },
        {
          "title": "Regression to the Tail: Why the Olympics Blow Up (Flyvbjerg, Budzier & Lunn, Environment and Planning A, 2020)",
          "publisher": "arXiv / University of Oxford",
          "url": "https://arxiv.org/abs/2009.14682",
          "accessed": "2026-10-25"
        },
        {
          "title": "Olympic Stadium (Montreal)",
          "publisher": "Wikipedia (citing CBC, December 19, 2006)",
          "url": "https://en.wikipedia.org/wiki/Olympic_Stadium_(Montreal)",
          "accessed": "2026-10-25"
        },
        {
          "title": "A recipe for disaster - Beyond the Games: Montreal's Olympic Story",
          "publisher": "McCord Stewart Museum / Digital Museums Canada",
          "url": "https://www.histoiresdecheznous.ca/v3/olympiques-montreal-1976-olympics/en/story/a-recipe-for-disaster/",
          "accessed": "2026-10-25"
        },
        {
          "title": "Memories of the Big Owe",
          "publisher": "The Globe and Mail",
          "url": "https://www.theglobeandmail.com/opinion/memories-of-the-big-owe/article1146816/",
          "accessed": "2026-10-25"
        },
        {
          "title": "H.10 Foreign Exchange Rates, historical data",
          "publisher": "Board of Governors of the Federal Reserve System",
          "url": "https://www.federalreserve.gov/releases/h10/hist/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Baseline: the 1970 estimate of C$120 million for the Games (The Canadian Encyclopedia), revised to C$310 million in 1973. Actual: C$1.6 billion 'final tally' (Canadian Encyclopedia, Globe and Mail), a nominal figure that accumulates spending and debt service through the 2006 payoff, so actual_cost_year is set to 2006 and the overrun is nominal and overstated relative to real terms. Range: C$1.47 billion (Canadian Press total cited on Wikipedia) to C$2.4 billion (McCord Stewart Museum 'final bill for the Olympic Park'); Wikipedia also cites C$1.61 billion including repairs, interest and inflation. Flyvbjerg et al. give US$6.093 billion (2015 dollars) sports-related cost and a 720% real overrun. planned_end/actual_end = opening ceremony (July 17, 1976). FX: Fed H.10 annual average of daily rates; 1970 is not covered, so the 1971 average (1.0099 CAD per USD) is used as a proxy for 1970; 2006 average 1.1340 CAD per USD. Mayor's quote wording varies across sources. Baseline audit 2026-10-25: Planned figures unchanged (1970 C$120m). Added the 1973 revision to C$310m (The Canadian Encyclopedia) as the rebaseline.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": false
    },
    {
      "id": 93,
      "slug": "rio-2016-olympics",
      "name": "Rio 2016 Summer Olympics",
      "short_name": "Rio 2016",
      "category": "events",
      "subcategory": "olympics",
      "country": "Brazil",
      "country_code": "BR",
      "countries": [
        "Brazil"
      ],
      "continent": "South America",
      "city": "Rio de Janeiro",
      "lat": -22.9756,
      "lng": -43.3954,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget",
      "planned_start": "2009-10-02",
      "planned_end": "2016-08-05",
      "actual_start": "2009-10-02",
      "actual_end": "2016-08-05",
      "actual_is_forecast": false,
      "planned_duration_months": 82.1,
      "actual_duration_months": 82.1,
      "delay_months": 0,
      "delay_pct": 0,
      "planned_cost": 3029000000,
      "actual_cost": 13692000000,
      "planned_cost_range": null,
      "actual_cost_range": [
        4600000000,
        13692000000
      ],
      "cost_currency": "USD",
      "planned_cost_year": 2015,
      "cost_year": 2015,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": 3029000000,
      "cost_usd_nominal": 13692000000,
      "planned_cost_usd_today": 4114218026,
      "cost_usd_today": 18597515092,
      "overrun_usd_today": 14483297066,
      "overrun_pct": 352,
      "overrun_basis": "real",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": 352,
      "reported_overrun_source": "Flyvbjerg, Budzier & Lunn 2020 (sports-related cost, real terms, vs bid)",
      "phases": [
        {
          "name": "Bid and award",
          "planned_start": null,
          "planned_end": "2009-10-02",
          "actual_start": "2007",
          "actual_end": "2009-10-02",
          "note": "Rio beat Madrid, Tokyo and Chicago in the final vote in Copenhagen on October 2, 2009."
        },
        {
          "name": "Venue construction (Barra, Deodoro, Maracana, Copacabana clusters)",
          "planned_start": null,
          "planned_end": "2016-08-05",
          "actual_start": "2012",
          "actual_end": "2016-08",
          "note": "Start year approximate. Nine new venues, 18 existing venues and seven temporary venues were used."
        },
        {
          "name": "Test events",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2015-08",
          "actual_end": "2016-05",
          "note": "Test events ran through 2015-2016, including sailing on Guanabara Bay in August 2015, where water pollution drew complaints."
        },
        {
          "name": "State financial emergency",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2016-06",
          "actual_end": "2016-08",
          "note": "In June 2016, under two months before the opening, the state governor declared a state of emergency to secure extra Games funding."
        },
        {
          "name": "Games",
          "planned_start": "2016-08-05",
          "planned_end": "2016-08-21",
          "actual_start": "2016-08-05",
          "actual_end": "2016-08-21",
          "note": "Opening ceremony at the Maracana on August 5, 2016."
        }
      ],
      "milestones": [
        {
          "name": "IOC awards Games to Rio",
          "planned_date": "2009-10-02",
          "actual_date": "2009-10-02"
        },
        {
          "name": "Governor declares financial emergency",
          "planned_date": null,
          "actual_date": "2016-06"
        },
        {
          "name": "Opening ceremony",
          "planned_date": "2016-08-05",
          "actual_date": "2016-08-05"
        },
        {
          "name": "Closing ceremony",
          "planned_date": "2016-08-21",
          "actual_date": "2016-08-21"
        }
      ],
      "headline": "Rio 2016's sports-related costs came in 352 percent over the bid in real terms, the second-largest Summer Games overrun on Oxford's list.",
      "summary": "Rio de Janeiro won the 2016 Games in October 2009, the first awarded to South America. Venues were split across four clusters, with the main park at Barra da Tijuca. Brazil's recession and political crisis hit during delivery, and in June 2016 the state governor declared a financial emergency to fund the Games. The Games opened on time on August 5, 2016. Oxford researchers later put sports-related costs at US$13.7 billion in 2015 dollars, 352 percent above the bid.",
      "what_went_wrong_or_right": "Rio shows how much an Olympic cost estimate can move even after the Games. In 2016, using the January 2016 budget forecast, the Oxford Olympics Study put Rio's sports-related cost at US$4.6 billion with a 51 percent overrun and described the Games as on track to reverse the trend of rising costs. The 2020 follow-up by Flyvbjerg, Budzier and Lunn, using the sixth and final update of the responsibility matrix published in June 2017, put the cost at US$13.7 billion and the overrun at 352 percent in real terms. The authors add that the matrix was criticized for leaving out some sports-related costs. The period of delivery coincided with a deep recession and political crisis in Brazil. In June 2016 the Rio state governor declared a state of emergency to secure extra funding. The researchers cite Rio, together with Athens, as an example of the financial risk faced by hosts with fragile economies. Corruption allegations later reached venue contracts, including claims against former mayor Eduardo Paes. On the delivery side, temporary and modular venues such as the handball Future Arena, designed to be rebuilt as schools, were an attempt to limit stranded assets.",
      "lessons": [
        "Treat early outturn figures as provisional; final Olympic costs can arrive years later.",
        "Stress-test the budget against a host-economy downturn over a seven-year horizon.",
        "Define the cost boundary of a responsibility matrix publicly and audit it."
      ],
      "fun_fact": "The handball venue, the Future Arena, was designed as a temporary modular structure that could be dismantled and rebuilt as four schools (Wikipedia, citing Dezeen).",
      "method_tags": [
        "modular"
      ],
      "related_history_ids": [
        "rcf-2004",
        "big-things-2023",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Regression to the Tail: Why the Olympics Blow Up (Flyvbjerg, Budzier & Lunn, Environment and Planning A, 2020)",
          "publisher": "arXiv / University of Oxford",
          "url": "https://arxiv.org/abs/2009.14682",
          "accessed": "2026-10-25"
        },
        {
          "title": "The Oxford Olympics Study 2016: Cost and Cost Overrun at the Games (Flyvbjerg, Stewart & Budzier)",
          "publisher": "arXiv / Said Business School, University of Oxford",
          "url": "https://arxiv.org/abs/1607.04484",
          "accessed": "2026-10-25"
        },
        {
          "title": "2016 Summer Olympics",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/2016_Summer_Olympics",
          "accessed": "2026-10-25"
        },
        {
          "title": "Jogos Olimpicos de Verao de 2016",
          "publisher": "Wikipedia (Portuguese, citing G1 Globo)",
          "url": "https://pt.wikipedia.org/wiki/Jogos_Ol%C3%ADmpicos_de_Ver%C3%A3o_de_2016",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Expressed in 2015 US dollars because the only consistent bid-versus-outturn comparison found in an opened source is Flyvbjerg, Budzier & Lunn (2020). Actual: US$13.692 billion sports-related cost (Table 1, 2015 USD). Planned is DERIVED, not quoted: 13.692 / (1 + 3.52) = about US$3.03 billion in 2015 dollars. The bid-book figures in reais were not verified in an opened source. Range: the Oxford Olympics Study 2016 (based on the January 2016 forecast) gave US$4.6 billion and a 51% overrun; the 2020 paper used the final responsibility matrix of June 2017 (the paper's '2007' is a typo). Sports-related costs exclude transport and urban infrastructure (the Portuguese Wikipedia investment table cites R$24 billion for public transport). planned_end/actual_end = opening ceremony (August 5, 2016). The construction and test-event phase start dates are approximate.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 94,
      "slug": "tokyo-2020-olympics",
      "name": "Tokyo 2020 Summer Olympics (held 2021)",
      "short_name": "Tokyo 2020",
      "category": "events",
      "subcategory": "olympics",
      "country": "Japan",
      "country_code": "JP",
      "countries": [
        "Japan"
      ],
      "continent": "Asia",
      "city": "Tokyo",
      "lat": 35.6783,
      "lng": 139.7147,
      "era": "2000-2014",
      "status": "completed",
      "outcome": "over_budget_and_late",
      "planned_start": "2013-09-07",
      "planned_end": "2020-07-24",
      "actual_start": "2013-09-07",
      "actual_end": "2021-07-23",
      "actual_is_forecast": false,
      "planned_duration_months": 82.6,
      "actual_duration_months": 94.5,
      "delay_months": 12,
      "delay_pct": 14.5,
      "planned_cost": 734000000000,
      "actual_cost": 1420000000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "JPY",
      "planned_cost_year": 2013,
      "cost_year": 2021,
      "planned_fx_to_usd": 0.010246,
      "actual_fx_to_usd": 0.009104,
      "planned_cost_usd_nominal": 7523500000,
      "cost_usd_nominal": 12927680000,
      "planned_cost_usd_today": 10398551786,
      "cost_usd_today": 15359855581,
      "overrun_usd_today": 7420324598,
      "overrun_pct": 93.5,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": "2021-07-23",
      "rebaseline_label": "March 2020 postponement to 2021",
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": 0,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Bid and award",
          "planned_start": null,
          "planned_end": "2013-09-07",
          "actual_start": "2011",
          "actual_end": "2013-09-07",
          "note": "Tokyo was elected at the 125th IOC Session in Buenos Aires on September 7, 2013, with a bid-file cost of 734 billion yen."
        },
        {
          "name": "National Stadium redesign",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2015-07-17",
          "actual_end": "2015-12",
          "note": "Amid public anger over costs (about 250 billion yen by June 2015), Prime Minister Abe scrapped the Zaha Hadid design on July 17, 2015. A new competition followed, with Taisei and Kengo Kuma among the bidders by September 2015."
        },
        {
          "name": "Venue construction (National Stadium)",
          "planned_start": null,
          "planned_end": "2019-03",
          "actual_start": "2016-12",
          "actual_end": "2019-11-30",
          "note": "The new National Stadium was built from December 2016 to November 30, 2019, at about 157 billion yen, and opened December 21, 2019. The original scheme had been due in March 2019."
        },
        {
          "name": "Postponement",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2020-03-24",
          "actual_end": "2021-07-23",
          "note": "The IOC and Japan postponed the Games on March 24, 2020, because of COVID-19."
        },
        {
          "name": "Games",
          "planned_start": "2020-07-24",
          "planned_end": "2020-08-09",
          "actual_start": "2021-07-23",
          "actual_end": "2021-08-08",
          "note": "Held a year late and largely without spectators."
        },
        {
          "name": "Final accounts",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "2021-08-09",
          "actual_end": "2022-06-21",
          "note": "The organizing committee's final report put the total at 1.42 trillion yen."
        }
      ],
      "milestones": [
        {
          "name": "IOC awards Games to Tokyo",
          "planned_date": "2013-09-07",
          "actual_date": "2013-09-07"
        },
        {
          "name": "National Stadium completed",
          "planned_date": "2019-03",
          "actual_date": "2019-11-30"
        },
        {
          "name": "Postponement announced",
          "planned_date": null,
          "actual_date": "2020-03-24"
        },
        {
          "name": "Opening ceremony",
          "planned_date": "2020-07-24",
          "actual_date": "2021-07-23"
        },
        {
          "name": "Final cost report",
          "planned_date": null,
          "actual_date": "2022-06-21"
        }
      ],
      "headline": "Tokyo's Games cost 1.42 trillion yen, nearly double the 734 billion yen in the 2013 bid, and opened a year late because of the pandemic.",
      "summary": "Tokyo won the 2020 Summer Olympics in September 2013 with a bid-file cost of 734 billion yen. Delivery ran into trouble early, when Zaha Hadid's National Stadium design was scrapped in July 2015 over cost. The replacement stadium was finished in November 2019, but COVID-19 forced a one-year postponement in March 2020. The Games ran from July 23 to August 8, 2021, mostly without spectators. In June 2022 the organizers reported a final cost of 1.42 trillion yen.",
      "what_went_wrong_or_right": "Tokyo's overrun has two layers: ordinary megaproject escalation and a one-off pandemic shock. Cost pressure showed early. By June 2015 the estimated cost of Zaha Hadid's National Stadium had reached about 250 billion yen. On July 17, 2015 Prime Minister Shinzo Abe scrapped the design and ordered a new competition. The replacement was finished in November 2019 at about 157 billion yen, too late for its original role as a Rugby World Cup venue. In October 2018 the Board of Audit warned that total Olympic-related spending could exceed US$25 billion once government outlays outside the organizers' budget were counted. Then on March 24, 2020, the IOC and Japan postponed the Games by a year because of COVID-19. Flyvbjerg, Budzier and Lunn cite this as an example of a 'black swan' adding billions to costs already incurred. The Games went ahead in July 2021 under a state of emergency, with spectators barred. The organizers' June 2022 final report gave a total of 1.42 trillion yen, against 734 billion yen in the 2013 bid file (Kyodo). On time, the event slipped 364 days; the scope delivered was essentially as planned.",
      "lessons": [
        "Long planning horizons widen the window for shocks; hold real contingency, not a token reserve.",
        "Kill an unaffordable design early, as Tokyo did with its stadium, before construction starts.",
        "Report government-side Games spending alongside the organizer's budget."
      ],
      "fun_fact": "Tokyo 2020 was the only Olympic Games held without official spectators, after overseas fans were barred in March 2021 and local fans in July 2021 (Wikipedia).",
      "method_tags": [],
      "related_history_ids": [
        "rcf-2004",
        "big-things-2023",
        "planning-fallacy-1979"
      ],
      "sources": [
        {
          "title": "Olympics: Tokyo Games cost totals 1.42 tril. yen, twice bid figure",
          "publisher": "Kyodo News, June 21, 2022",
          "url": "https://english.kyodonews.net/news/2022/06/09ef8c31ec70-olympics-tokyo-games-cost-totals-142-tril-yen-twice-bid-figure.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "2020 Summer Olympics",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/2020_Summer_Olympics",
          "accessed": "2026-10-25"
        },
        {
          "title": "Japan National Stadium",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Japan_National_Stadium",
          "accessed": "2026-10-25"
        },
        {
          "title": "Regression to the Tail: Why the Olympics Blow Up (Flyvbjerg, Budzier & Lunn, Environment and Planning A, 2020)",
          "publisher": "arXiv / University of Oxford",
          "url": "https://arxiv.org/abs/2009.14682",
          "accessed": "2026-10-25"
        },
        {
          "title": "H.10 Foreign Exchange Rates, historical data",
          "publisher": "Board of Governors of the Federal Reserve System",
          "url": "https://www.federalreserve.gov/releases/h10/hist/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: the 734 billion yen cost in the 2013 bid file (Kyodo). Actual: 1.42 trillion yen, from the organizing committee's final report of June 21, 2022 (Kyodo). It may not cover all Games-related government spending: in October 2018 the Board of Audit warned that the total could exceed US$25 billion (Wikipedia, citing SportsPro), so the true public cost may be higher. Costs were incurred mainly through 2021, so actual_cost_year is 2021. planned_end/actual_end = opening ceremony (planned July 24, 2020; actual July 23, 2021). No bid-based real-terms overrun for Tokyo appears in Flyvbjerg et al. 2020. FX: Fed H.10 annual averages, 97.60 JPY per USD in 2013 and 109.84 in 2021. Stadium redesign facts are from Wikipedia, citing AFP (July 17, 2015) and NHK. Baseline audit 2026-10-25: Planned figures unchanged (2013 bid, 734 billion yen). Added the postponed opening of 23 July 2021 as the schedule rebaseline; no revised budget is stored.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": false
    },
    {
      "id": 95,
      "slug": "sagrada-familia",
      "name": "Basílica de la Sagrada Família",
      "short_name": "Sagrada Família",
      "category": "historic",
      "subcategory": "basilica",
      "country": "Spain",
      "country_code": "ES",
      "countries": [
        "Spain"
      ],
      "continent": "Europe",
      "city": "Barcelona",
      "lat": 41.4036,
      "lng": 2.1744,
      "era": "1800s",
      "status": "ongoing",
      "outcome": "late",
      "planned_start": "1882-03-19",
      "planned_end": "2026",
      "actual_start": "1882-03-19",
      "actual_end": "2035",
      "actual_is_forecast": true,
      "planned_duration_months": 1731.4,
      "actual_duration_months": 1839.4,
      "delay_months": 108,
      "delay_pct": 6.2,
      "planned_cost": null,
      "actual_cost": null,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "EUR",
      "planned_cost_year": null,
      "cost_year": null,
      "planned_fx_to_usd": null,
      "actual_fx_to_usd": null,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": null,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": null,
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Del Villar's neo-Gothic start",
          "planned_start": "1882-03-19",
          "planned_end": null,
          "actual_start": "1882-03-19",
          "actual_end": "1883-03",
          "note": "Construction began 19 Mar 1882 under Francisco de Paula del Villar, who resigned in March 1883."
        },
        {
          "name": "Gaudí's direction",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1883-03",
          "actual_end": "1926-06-10",
          "note": "Gaudí took over in 1883 (formally Architect Director 28 Mar 1884) and redesigned the church; at his death in 1926 it was roughly 15-25% complete."
        },
        {
          "name": "Slow progress and wartime damage",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1926-06-10",
          "actual_end": "2010-11-07",
          "note": "In July 1936 the crypt was set on fire and Gaudí's workshop plans and models were partly destroyed; work resumed later from surviving fragments. Consecrated as a basilica by Pope Benedict XVI on 7 Nov 2010."
        },
        {
          "name": "Central towers",
          "planned_start": null,
          "planned_end": "2026",
          "actual_start": "2010-11-07",
          "actual_end": "2026-02-20",
          "note": "Work halted 11 Mar to 4 Jul 2020 for Covid-19. The Tower of Jesus Christ was structurally completed 20 Feb 2026 at 172.5 m and inaugurated 10 Jun 2026, the centenary of Gaudí's death."
        },
        {
          "name": "Interior finishes and Glory façade (forecast)",
          "planned_start": null,
          "planned_end": "2026",
          "actual_start": "2026-02-20",
          "actual_end": "2035",
          "note": "Forecast: interior of the Tower of Jesus Christ by 2028; the Glory façade and its proposed street staircase depend on agreement with the city. The building board said in Feb 2025 that the work could finish in about ten years if schedules held."
        }
      ],
      "milestones": [
        {
          "name": "Construction start",
          "planned_date": "1882-03-19",
          "actual_date": "1882-03-19"
        },
        {
          "name": "Death of Gaudí",
          "planned_date": null,
          "actual_date": "1926-06-10"
        },
        {
          "name": "Consecration as basilica",
          "planned_date": null,
          "actual_date": "2010-11-07"
        },
        {
          "name": "Tower of Jesus Christ inaugurated",
          "planned_date": "2026",
          "actual_date": "2026-06-10"
        },
        {
          "name": "Overall completion",
          "planned_date": "2026",
          "actual_date": "2035"
        }
      ],
      "headline": "The 2026 Gaudí-centenary target was met for the 172.5 m central tower, but the full basilica is now expected around 2035, 153 years after work began.",
      "summary": "The Sagrada Família in Barcelona has been under construction since 19 March 1882. Antoni Gaudí took over in 1883 and worked on it until his death in 1926, when it was roughly a fifth complete. Funded by donations and tickets, it was consecrated in 2010. In 2014 the target was set for 2026, the centenary of Gaudí's death. The Tower of Jesus Christ topped out in February 2026 at 172.5 m and was inaugurated on 10 June 2026, but interior work and the Glory façade continue, with completion now projected around 2035.",
      "what_went_wrong_or_right": "The basilica has no fixed budget because, as an expiatory temple, it is built only as fast as donations and ticket income allow. That funding model explains both the slow 20th century and the rapid 21st: visitor numbers grew to about 3 million a year by 1990 and about 5 million in 2025, and in 2024 the foundation reported EUR 133.9m of income and EUR 86.2m of spending, more than half on construction. Design continuity was the second challenge. Gaudí left few complete drawings, and in July 1936 the crypt was set on fire and his workshop and plaster models were partly destroyed, so later architects reconstructed his intentions from fragments. Computer-aided design and off-site prefabrication of stone panels later accelerated the towers. The 2026 target was hit for the central tower but not for the whole building, partly because the Covid-19 closure from March to July 2020 cut both work and ticket revenue. The remaining Glory façade depends on a proposed monumental staircase that may require demolishing homes opposite the church, a decision outside the builders' control.",
      "lessons": [
        "Pay-as-you-go funding avoids debt but makes schedules hostage to revenue; model income shocks.",
        "Archive the design: losing drawings and models in 1936 cost decades of reconstruction work.",
        "Secure planning consent for final scope early; the Glory façade now waits on the city."
      ],
      "fun_fact": "The Sagrada Família obtained its building permit only on 7 June 2019, 137 years after construction began, after agreeing to pay the city EUR 36 million.",
      "method_tags": [
        "phased_delivery",
        "iterative",
        "modular"
      ],
      "related_history_ids": [],
      "sources": [
        {
          "title": "Sagrada Família",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Sagrada_Fam%C3%ADlia",
          "accessed": "2026-10-25"
        },
        {
          "title": "Sagrada Família could finish construction in ten years",
          "publisher": "Catalan News",
          "url": "https://www.catalannews.com/life-style/item/sagrada-familia-could-be-finished-construction-in-ten-years",
          "accessed": "2026-10-25"
        },
        {
          "title": "Sagrada Família's 144-year journey nears its end with the Tower of Jesus Christ (CNN Style)",
          "publisher": "KEYT / CNN",
          "url": "https://keyt.com/lifestyle/entertainment/cnn-style/2026/06/07/sagrada-familias-144-year-journey-nears-its-end-with-the-tower-of-jesus-christ/",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "No overall budget, planned or actual, has been published; the basilica is financed year by year from donations and tickets (annual budget about EUR 25m per Wikipedia; 2024 income EUR 133.9m and spending EUR 86.2m per Catalan News, 13 Feb 2025). Cost fields are therefore null. Baseline schedule: the 2026 completion target for the Gaudí centenary (stated in 2014 per Wikipedia); no completion date was set in 1882. Forecast actual_end 2035 is derived from the building board's February 2025 statement that work could be completed in about ten years if schedules and deadlines are met; it is not an official date. Interior of the central tower expected by 2028 (CNN). The 2017 estimate of 2030-2032 for decorative elements is tagged as failing verification on Wikipedia and is not used. Gaudí's death date (10 June 1926) is inferred from the 10 June 2026 centenary inauguration. The 'computer-aided design and prefabrication' point is general project history, not from a fetched source. cost_currency set to EUR for the annual figures cited in text.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": true
    },
    {
      "id": 96,
      "slug": "cologne-cathedral",
      "name": "Cologne Cathedral (High Cathedral of St. Peter)",
      "short_name": "Cologne Cathedral",
      "category": "historic",
      "subcategory": "cathedral",
      "country": "Germany",
      "country_code": "DE",
      "countries": [
        "Germany"
      ],
      "continent": "Europe",
      "city": "Cologne",
      "lat": 50.9414,
      "lng": 6.9583,
      "era": "pre-1800",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": null,
      "planned_end": null,
      "actual_start": "1248-08-15",
      "actual_end": "1880-10-15",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 7586,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": null,
      "actual_cost": 6600000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "Thaler",
      "planned_cost_year": null,
      "cost_year": 1880,
      "planned_fx_to_usd": null,
      "actual_fx_to_usd": null,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": null,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": null,
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Gothic choir (Master Gerhard)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1248-08-15",
          "actual_end": "1322",
          "note": "Foundation stone laid 15 Aug 1248 by Archbishop Konrad von Hochstaden; the eastern arm, directed by Master Gerhard, was consecrated in 1322."
        },
        {
          "name": "Nave and south tower (medieval)",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1322",
          "actual_end": "1473",
          "note": "Work continued on the nave and south tower; the tower reached belfry level by 1473, when tower work stopped."
        },
        {
          "name": "Medieval works wind down",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1473",
          "actual_end": "1520",
          "note": "Nave work stopped in the 16th century (1520 considered most probable; other sources say 1530 or 1560), owing to lack of money and declining interest in Gothic. A crane stood on the south tower for about 400 years."
        },
        {
          "name": "Unfinished period",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1520",
          "actual_end": "1842-09-04",
          "note": "The building stood incomplete for more than three centuries. The surviving medieval façade drawing (Plan F) later guided completion."
        },
        {
          "name": "19th-century completion (Zwirner, Voigtel)",
          "planned_start": "1842-09-04",
          "planned_end": null,
          "actual_start": "1842-09-04",
          "actual_end": "1880-10-15",
          "note": "King Frederick William IV of Prussia laid the second foundation stone on 4 Sep 1842. The Zentral-Dombauverein, aided by the Dombaulotterie, paid about two-thirds and Prussia one-third. Completion celebrated 15 Oct 1880."
        }
      ],
      "milestones": [
        {
          "name": "Foundation stone",
          "planned_date": null,
          "actual_date": "1248-08-15"
        },
        {
          "name": "Choir consecrated",
          "planned_date": null,
          "actual_date": "1322"
        },
        {
          "name": "Work stops",
          "planned_date": null,
          "actual_date": "1520"
        },
        {
          "name": "Second foundation stone",
          "planned_date": null,
          "actual_date": "1842-09-04"
        },
        {
          "name": "Completion ceremony",
          "planned_date": null,
          "actual_date": "1880-10-15"
        }
      ],
      "headline": "Cologne Cathedral took 632 years to finish, including more than three centuries when no one worked on it at all.",
      "summary": "Cologne Cathedral was begun on 15 August 1248 to house the relics of the Three Kings. Its choir was consecrated in 1322, but work slowed and stopped in the early 16th century, leaving the south tower stump crowned by a medieval crane for about 400 years. In 1842 King Frederick William IV of Prussia relaunched it, and builders finished it in 38 years. The completion ceremony on 15 October 1880 produced the world's tallest building at about 157 m. The 1842-1880 campaign raised more than 6.6 million thalers.",
      "what_went_wrong_or_right": "The medieval phase failed for reasons of funding and fashion rather than engineering. Planet Wissen attributes the stop, around 1520 to 1530, to lack of money and fading interest in the Gothic style. With no sponsor willing to finance the remaining nave and towers, the site was left with a temporary roof and a crane on the south tower. The 19th-century restart succeeded because it combined a frozen design with a reliable funding model. The surviving medieval drawing of the west front, Plan F, gave the architects Ernst Friedrich Zwirner and Richard Voigtel an approved design to execute, so no design competition or redesign was needed. Funding came from a public-private partnership: the Zentral-Dombauverein, founded under a royal order of December 1841, raised about two-thirds of the cost through membership and a lottery that sold more than 320,000 tickets in its first draw, and the Prussian state paid the rest. Completion was also a matter of national symbolism in the decades around German unification, which kept political backing in place until 1880.",
      "lessons": [
        "A stable funding source matters more than a grand vision; the medieval build stopped when money ran out.",
        "A frozen, approved design lets a long-paused project restart quickly.",
        "Blended public and private funding, such as a dedicated lottery, can sustain multi-decade programs."
      ],
      "fun_fact": "The first draw of the Dombaulotterie sold more than 320,000 tickets and netted 177,000 thalers for the building fund.",
      "method_tags": [
        "ppp",
        "phased_delivery"
      ],
      "related_history_ids": [],
      "sources": [
        {
          "title": "Cologne Cathedral",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Cologne_Cathedral",
          "accessed": "2026-10-25"
        },
        {
          "title": "Kölner Dom: Geschichte des Dombaus",
          "publisher": "Planet Wissen (WDR/SWR)",
          "url": "https://www.planet-wissen.de/kultur/nordrhein_westfalen/koelner_dom/index.html",
          "accessed": "2026-10-25"
        },
        {
          "title": "Zentral-Dombauverein zu Köln von 1842",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Zentral-Dombauverein_zu_K%C3%B6ln_von_1842",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "No planned budget or completion date exists for the medieval cathedral, so planned fields are null. actual_cost covers only the 1842-1880 completion campaign: 'more than 6.6 million Taler' raised between 1842 and 1880 (Planet Wissen), which it equates to nearly EUR 1bn today; the Zentral-Dombauverein article gives about US$1bn in today's money. Medieval costs are unknown. cost_currency is 'Thaler' (Prussian thaler; no ISO code), and no fx is given because 1880 thaler-to-USD conversion was not sourced; Germany switched to the mark in the 1870s, so part of the spending was actually in marks. The halt date is disputed: 1473 for the south tower; for the nave, 1520 (Wikipedia, 'more probable'), 1530 (Planet Wissen) or 1560. The '632 years' figure is from Wikipedia. Funding split: two-thirds ZDV, one-third Prussia (Wikipedia); the Dombauhütte gives about 60% ZDV. The 19th-century completion era is classified as 'ancient' only because the start year is 1248; the editor may prefer a different era label. The national-symbolism point is general historical context. Baseline audit 2026-10-25: era changed from 'ancient' to 'pre-1800' (new era value approved by the editor); no planned or rebaseline figures exist.",
      "exclude_flag": null,
      "has_spoke": false,
      "cost_not_public": true
    },
    {
      "id": 97,
      "slug": "great-pyramid-of-giza",
      "name": "Great Pyramid of Giza (Pyramid of Khufu)",
      "short_name": "Great Pyramid",
      "category": "historic",
      "subcategory": "pyramid / royal tomb",
      "country": "Egypt",
      "country_code": "EG",
      "countries": [
        "Egypt"
      ],
      "continent": "Africa",
      "city": "Giza",
      "lat": 29.9792,
      "lng": 31.1342,
      "era": "ancient",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": null,
      "planned_end": null,
      "actual_start": "-2600",
      "actual_end": "-2574",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 312,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": null,
      "actual_cost": null,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": null,
      "planned_cost_year": null,
      "cost_year": null,
      "planned_fx_to_usd": null,
      "actual_fx_to_usd": null,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": null,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": null,
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Site survey, leveling and alignment",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "-2600",
          "actual_end": "-2598",
          "note": "Scholarly estimate. A perimeter strip of the bedrock was leveled to within about 21 mm, and the sides were aligned to true north within about a tenth of a degree."
        },
        {
          "name": "Quarrying and core courses",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "-2598",
          "actual_end": "-2585",
          "note": "Scholarly estimate. Core built mostly of local limestone quarried on the plateau; about 2.3 million blocks in total."
        },
        {
          "name": "Upper structure and granite chambers",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "-2585",
          "actual_end": "-2578",
          "note": "Scholarly estimate. Granite for the internal chambers was shipped from Aswan, more than 900 km south."
        },
        {
          "name": "Casing with Tura limestone",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "-2580",
          "actual_end": "-2574",
          "note": "The Diary of Merer, found at Wadi al-Jarf in 2013, records boat deliveries of white Tura limestone to Giza in Khufu's 26th-27th regnal year, most likely for the outer casing."
        },
        {
          "name": "Completion and capstone",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "-2576",
          "actual_end": "-2574",
          "note": "Scholarly estimate. Original height 146.6 m (280 royal cubits)."
        }
      ],
      "milestones": [
        {
          "name": "Start of Khufu's reign and pyramid works (approx.)",
          "planned_date": null,
          "actual_date": "-2600"
        },
        {
          "name": "Merer's logbook of Tura limestone deliveries (year 26-27)",
          "planned_date": null,
          "actual_date": "-2575"
        },
        {
          "name": "Completion (approx.)",
          "planned_date": null,
          "actual_date": "-2574"
        }
      ],
      "headline": "About 2.3 million stone blocks were set in place in roughly 20 to 27 years, the length of one pharaoh's reign.",
      "summary": "The Great Pyramid was built at Giza for the Fourth Dynasty king Khufu around 2600 BC. Originally 146.6 m tall with a base of about 230 m per side, it contains about 2.3 million blocks weighing roughly 6 million tonnes. Herodotus said it took 20 years; modern estimates are about 26 to 27 years, bounded by Khufu's reign of about 23 to 29 years. The Diary of Merer, a papyrus logbook found in 2013, documents limestone deliveries from Tura in the king's 26th or 27th year.",
      "what_went_wrong_or_right": "There is no record of a planned budget or schedule, but the project had a hard deadline: the tomb had to be usable when the king died, and Khufu's reign lasted about 23 to 29 years according to the Turin King List and dated graffiti. The builders met it. Organization rather than technology explains the result. A 1999 construction-management study with Egyptologist Mark Lehner estimated an average workforce of about 13,200 and a peak near 40,000, far fewer than Herodotus's 100,000. Excavations of workers' settlements point to organized, fed and housed crews, largely conscripted rather than enslaved. Logistics were planned across Egypt: local limestone for the core, fine limestone ferried from Tura across the Nile, and granite shipped from Aswan. The Diary of Merer shows a crew of boatmen making round trips between Tura and Giza on a regular cycle under the oversight of Ankhhaf, Khufu's half-brother. Precision was high: the base is level to about 21 mm and aligned to the cardinal points within a fraction of a degree.",
      "lessons": [
        "A fixed, non-negotiable deadline focuses planning; design the work rate backwards from it.",
        "Treat materials logistics as a project of its own, with crews, routes and records.",
        "Written daily logs, like Merer's, are the oldest known form of progress reporting."
      ],
      "fun_fact": "The pyramid was the tallest human-made structure in the world for more than 3,700 years.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [],
      "sources": [
        {
          "title": "Great Pyramid of Giza",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Great_Pyramid_of_Giza",
          "accessed": "2026-10-25"
        },
        {
          "title": "Diary of Merer",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Diary_of_Merer",
          "accessed": "2026-10-25"
        },
        {
          "title": "Khufu",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Khufu",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "No planned budget or schedule exists for an Old Kingdom royal tomb, and the economy did not use money, so all cost fields are null and planned dates are null. Dates are scholarly estimates: Wikipedia gives construction c. 2600 BC lasting about 26 years; radiocarbon studies give 2613-2577 BC (Ramsey et al. 2010); Herodotus said 20 years; Khufu reigned about 23-29 years (Turin canon 23; graffiti attest a 28th or 29th year). actual_start -2600 and actual_end -2574 apply the 26-year duration to the c. 2600 BC start and are approximate. Phase boundaries are editorial estimates for chart display based on the logical construction sequence (site preparation, core, chambers, casing) and are not attested dates, except that the Diary of Merer places casing-stone deliveries in Khufu's 26th-27th regnal year. Workforce estimates: 13,200 average and about 40,000 peak (1999 study with Mark Lehner), versus 100,000 in Herodotus. The 3,700-year tallest-structure claim is from the Wikipedia lead (the article's comparison table gives c. 2600 BC to 1221 AD). Only Wikipedia sources could be opened; Britannica and Smithsonian returned 403 errors.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": true
    },
    {
      "id": 98,
      "slug": "great-wall-of-china",
      "name": "Great Wall of China (Ming Great Wall)",
      "short_name": "Great Wall (Ming)",
      "category": "historic",
      "subcategory": "wall / frontier fortification",
      "country": "China",
      "country_code": "CN",
      "countries": [
        "China"
      ],
      "continent": "Asia",
      "city": "Badaling, Beijing",
      "lat": 40.354,
      "lng": 116.02,
      "era": "pre-1800",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": null,
      "planned_end": null,
      "actual_start": "1368",
      "actual_end": "1644",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 3312,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": null,
      "actual_cost": null,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": null,
      "planned_cost_year": null,
      "cost_year": null,
      "planned_fx_to_usd": null,
      "actual_fx_to_usd": null,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": null,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": null,
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Early Ming walls of earth and stone",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1368",
          "actual_end": "1470",
          "note": "The Ming dynasty (1368-1644) rebuilt and extended older walls; earth and stone walls under the Yongle Emperor (r. 1402-1424) and a Liaodong wall around 1442."
        },
        {
          "name": "Ordos wall (Yu Zijun)",
          "planned_start": "1472-12",
          "planned_end": null,
          "actual_start": "1472-12",
          "actual_end": "1474",
          "note": "Proposed 1471, approved December 1472, completed 1474: about 1,100 km with 800 strong points, built in several months by 40,000 men at a cost of over one million silver taels."
        },
        {
          "name": "Xuanfu-Datong program",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1544",
          "actual_end": "1549",
          "note": "Large building program led by Weng Wanda on the northwest approaches to Beijing."
        },
        {
          "name": "Ji-Chang stone and brick rebuild",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1550",
          "actual_end": "1571",
          "note": "Dry-stone walls near Beijing replaced with stone and mortar from 1550; Qi Jiguang and Tan Lun built hollow brick watchtowers 1569-1571, scaled back from 3,000 planned to 1,200."
        },
        {
          "name": "Closing gaps and final works",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1577",
          "actual_end": "1644",
          "note": "After the 1576 Simatai raid, gaps around Beijing were closed and earthen sections rebuilt in brick and stone; a lull in the 1590s; construction continued until the fall of the Ming in 1644."
        }
      ],
      "milestones": [
        {
          "name": "Founding of the Ming dynasty",
          "planned_date": null,
          "actual_date": "1368"
        },
        {
          "name": "Ordos wall completed",
          "planned_date": null,
          "actual_date": "1474"
        },
        {
          "name": "Hollow brick watchtowers program",
          "planned_date": null,
          "actual_date": "1569"
        },
        {
          "name": "Fall of the Ming; building ends",
          "planned_date": null,
          "actual_date": "1644"
        },
        {
          "name": "Survey measures Ming wall at 8,850 km",
          "planned_date": null,
          "actual_date": "2009-04"
        }
      ],
      "headline": "Over 276 years the Ming dynasty built a system of walls that a 2009 survey measured at 8,850 km, including 6,259 km of actual wall.",
      "summary": "Most of the Great Wall that visitors see today was built under the Ming dynasty between 1368 and 1644. Rather than one project, it was a long series of campaigns: Yu Zijun's Ordos wall in the 1470s, the Xuanfu-Datong program of the 1540s, the replacement of dry-stone walls near Beijing with brick and mortar from 1550, and Qi Jiguang's hollow watchtowers from 1569. A two-year government survey reported in 2009 measured the Ming wall at about 8,850 km, of which 6,259 km is built wall.",
      "what_went_wrong_or_right": "The Ming wall was never a single planned project with a budget and end date; it grew in bursts driven by funding, court politics and changing threats along the northern frontier. Sources record recurring gaps between ambition and resources. Yu Zijun's Ordos wall of the 1470s, about 1,100 km with 800 strong points, cost over one million silver taels. In 1548 a project linked to Jizhou requested 436,000 liang of silver but was allotted only about one-sixth. Qi Jiguang and Tan Lun's watchtower plan of 1569 called for 3,000 hollow brick towers and was cut to 1,200. Materials technology changed during the program: early walls of rammed earth and dry stone were progressively rebuilt in fired brick and mortar, especially in the sections guarding Beijing. Work paused in the 1590s when resources were diverted elsewhere and continued until the dynasty fell in 1644. The 2009 survey by the State Administration of Cultural Heritage and the State Bureau of Surveying and Mapping found the Ming system nearly 3,000 km longer than earlier estimates based on historical records.",
      "lessons": [
        "Programs funded year by year deliver uneven quality; budget for maintenance as well as new build.",
        "Expect scope cuts when funding is uncertain: 3,000 planned towers became 1,200.",
        "Measure what exists: the 2009 survey added nearly 3,000 km to earlier record-based estimates."
      ],
      "fun_fact": "The 2009 survey counted 2,232 km of natural barriers such as hills and rivers as part of the 8,850 km Ming wall system.",
      "method_tags": [
        "phased_delivery",
        "iterative"
      ],
      "related_history_ids": [],
      "sources": [
        {
          "title": "Ming Great Wall",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Ming_Great_Wall",
          "accessed": "2026-10-25"
        },
        {
          "title": "China's wall gets greater",
          "publisher": "Al Jazeera",
          "url": "https://www.aljazeera.com/amp/gallery/2009/4/23/chinas-wall-gets-greater",
          "accessed": "2026-10-25"
        },
        {
          "title": "How Long is the Great Wall of China?",
          "publisher": "Visit Beijing (Beijing Municipal Culture and Tourism Bureau)",
          "url": "https://english.visitbeijing.com.cn/article/47ONeMxjwn2",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "Scope: the Ming-era build only (1368-1644); earlier walls from the Qin and Han periods are excluded. There was no overall planned budget or schedule, so planned dates and all cost fields are null. Component costs exist (Ordos wall over one million silver taels; a 1548 request for 436,000 liang) but no total, and silver taels have no reliable USD conversion, so they are given only in text. Start date 1368 is the founding of the Ming dynasty, used as the start of Ming wall-building; the first large Ming wall (Ordos) dates from 1472-1474. Length: 8,850 km (8,851.8 km) from the 2009 SACH and State Bureau of Surveying and Mapping survey, including 6,259 km of wall, 359 km of trenches and 2,232 km of natural barriers. Coordinates are for the Badaling section near Beijing (approximate, not verified in a fetched page). A 2012 survey put walls of all dynasties at 21,196.18 km (Visit Beijing). UNESCO, Britannica and BBC pages returned errors during research; the editor may want to add UNESCO WHC listing 438. Baseline audit 2026-10-25: era changed from 'ancient' to 'pre-1800' (new era value approved by the editor); no planned or rebaseline figures exist. Editor decision 2026-10-25: kept in the dataset (flag was: defensive fortification – editor to confirm against the no-military rule).",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": true
    },
    {
      "id": 99,
      "slug": "taj-mahal",
      "name": "Taj Mahal",
      "short_name": "Taj Mahal",
      "category": "historic",
      "subcategory": "mausoleum",
      "country": "India",
      "country_code": "IN",
      "countries": [
        "India"
      ],
      "continent": "Asia",
      "city": "Agra",
      "lat": 27.175,
      "lng": 78.0419,
      "era": "pre-1800",
      "status": "completed",
      "outcome": "mixed",
      "planned_start": null,
      "planned_end": null,
      "actual_start": "1632-01",
      "actual_end": "1653",
      "actual_is_forecast": false,
      "planned_duration_months": null,
      "actual_duration_months": 257.5,
      "delay_months": null,
      "delay_pct": null,
      "planned_cost": null,
      "actual_cost": 32000000,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "INR",
      "planned_cost_year": null,
      "cost_year": 1653,
      "planned_fx_to_usd": null,
      "actual_fx_to_usd": null,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": null,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": null,
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": null,
      "rebaseline_label": null,
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": null,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Commission and site acquisition",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1631-06",
          "actual_end": "1632-01",
          "note": "Shah Jahan commissioned the tomb after Mumtaz Mahal died in June 1631."
        },
        {
          "name": "Foundations and plinth",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1632-01",
          "actual_end": "1635",
          "note": "Foundation excavation began January 1632 on the bank of the Yamuna. The end date of this phase is an editorial estimate."
        },
        {
          "name": "Mausoleum",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1632-01",
          "actual_end": "1648",
          "note": "The first anniversary ceremony on site was held in 1643; the white marble mausoleum is dated complete in 1648 by the inscription at the main entrance."
        },
        {
          "name": "Mosque, guest house, gateway and gardens",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1640",
          "actual_end": "1653",
          "note": "Red sandstone mosque and matching jawab, main gateway and the charbagh garden on a 17-hectare site; complex believed finished in 1653. Start date is an editorial estimate."
        }
      ],
      "milestones": [
        {
          "name": "Death of Mumtaz Mahal",
          "planned_date": null,
          "actual_date": "1631-06"
        },
        {
          "name": "Foundation excavation begins",
          "planned_date": null,
          "actual_date": "1632-01"
        },
        {
          "name": "First ceremony at the tomb (12th death anniversary)",
          "planned_date": null,
          "actual_date": "1643"
        },
        {
          "name": "Mausoleum complete (entrance inscription)",
          "planned_date": null,
          "actual_date": "1648"
        },
        {
          "name": "Complex complete",
          "planned_date": null,
          "actual_date": "1653"
        }
      ],
      "headline": "More than 20,000 workers spent about 22 years on the Taj Mahal complex, at a reported cost of 32 million rupees.",
      "summary": "The Taj Mahal in Agra was commissioned by the Mughal emperor Shah Jahan as a tomb for his wife Mumtaz Mahal, who died in June 1631. Foundation work began in January 1632. The white marble mausoleum is dated complete in 1648, and the surrounding complex of red sandstone mosque, guest house, gateway and charbagh garden in about 1653. More than 20,000 workers and artisans took part, and the reported cost was about 32 million rupees. It became a UNESCO World Heritage Site in 1983.",
      "what_went_wrong_or_right": "No planned budget or schedule survives, so performance can only be judged from outcomes. The work was delivered as a phased imperial program: the court held the first ceremony at the tomb on the 12th anniversary of Mumtaz Mahal's death in 1643, while the mausoleum was still being finished, and the subsidiary buildings and gardens followed until about 1653. Workers and specialist artisans were recruited from across the Mughal empire and beyond; one account cites craftsmen from Persia and the Ottoman Empire. The design is commonly credited to Ustad Ahmad Lahori, but Shah Jahan's official histories name only the supervisors, Makramat Khan and Mir Abd al-Karim, and the attribution rests largely on a poem by Ahmad's son written years later. Completion dates are themselves disputed: the court chronicler Abdul Hamid Lahori placed completion of the main work around 1643-1644, the entrance inscription gives 1648, and other accounts extend to 1653 or 1654. The 32 million rupee figure is the commonly cited contemporary estimate and cannot be checked against accounts.",
      "lessons": [
        "Phase handover: bring the core asset into use before ancillary works finish.",
        "Record who is accountable; four centuries later the architect's identity is still debated.",
        "Specialist craft skills may need to be recruited internationally; plan their availability early."
      ],
      "fun_fact": "The tomb was first used for a ceremony in 1643, on the 12th anniversary of Mumtaz Mahal's death, five years before the mausoleum was dated complete.",
      "method_tags": [
        "phased_delivery"
      ],
      "related_history_ids": [],
      "sources": [
        {
          "title": "Taj Mahal",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Taj_Mahal",
          "accessed": "2026-10-25"
        },
        {
          "title": "Ustad Ahmad Lahori",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Ustad_Ahmad_Lahori",
          "accessed": "2026-10-25"
        },
        {
          "title": "Taj Mahal: Shah Jahan trivia and facts",
          "publisher": "Onmanorama",
          "url": "https://www.onmanorama.com/travel/outside-kerala/2022/05/16/taj-mahal-shajahan-trivia-facts-agra.amp.html",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "disputed",
      "notes": "No planned budget or schedule exists, so planned fields are null. actual_cost is the commonly cited contemporary estimate of about 32 million rupees (Wikipedia, which equates it to about INR 52.8bn or US$827m in 2015 terms); these were Mughal silver rupees, so cost_currency 'INR' is nominal only and no fx is given. Completion dates are disputed: 1643-1644 (chronicler Abdul Hamid Lahori), 1648 (entrance inscription), 1653 (complex, Wikipedia), 1654 (Uttar Pradesh state). The Ustad Ahmad Lahori article says the complex was reportedly completed in about twelve years. Phase boundaries for the plinth and ancillary buildings are editorial estimates for chart display. Workforce of more than 20,000 is a traditional figure. UNESCO, Britannica and the official Taj Mahal site could not be opened. 'Era' is set to 'ancient' as the nearest available pre-1800 label. Baseline audit 2026-10-25: era changed from 'ancient' to 'pre-1800' (new era value approved by the editor); no planned or rebaseline figures exist.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": true
    },
    {
      "id": 100,
      "slug": "windows-95",
      "name": "Windows 95 (codename Chicago)",
      "short_name": "Windows 95",
      "category": "software_it",
      "subcategory": "operating system",
      "country": "United States",
      "country_code": "US",
      "countries": [
        "United States"
      ],
      "continent": "North America",
      "city": "Redmond, Washington",
      "lat": 47.6396,
      "lng": -122.1283,
      "era": "1980-1999",
      "status": "completed",
      "outcome": "late",
      "planned_start": "1992-03",
      "planned_end": "1994-06",
      "actual_start": "1992-03",
      "actual_end": "1995-08-24",
      "actual_is_forecast": false,
      "planned_duration_months": 27,
      "actual_duration_months": 41.3,
      "delay_months": 14.3,
      "delay_pct": 52.9,
      "planned_cost": null,
      "actual_cost": null,
      "planned_cost_range": null,
      "actual_cost_range": null,
      "cost_currency": "USD",
      "planned_cost_year": null,
      "cost_year": null,
      "planned_fx_to_usd": 1,
      "actual_fx_to_usd": 1,
      "planned_cost_usd_nominal": null,
      "cost_usd_nominal": null,
      "planned_cost_usd_today": null,
      "cost_usd_today": null,
      "overrun_usd_today": null,
      "overrun_pct": null,
      "overrun_basis": "nominal",
      "rebaseline_cost": null,
      "rebaseline_cost_year": null,
      "rebaseline_end": "1995-02",
      "rebaseline_label": "early-1995 target set in summer 1994",
      "rebaseline_overrun_pct": null,
      "rebaseline_delay_months": 6.3,
      "reported_overrun_pct": null,
      "reported_overrun_source": null,
      "phases": [
        {
          "name": "Design and early development",
          "planned_start": "1992-03",
          "planned_end": null,
          "actual_start": "1992-03",
          "actual_end": "1993-08-10",
          "note": "Chicago design work began around March 1992. An internal 1992 product plan put the 32-bit Windows release (Panther) at June 1993; build 58s is dated 10 August 1993."
        },
        {
          "name": "Developer preview builds",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1993-08-10",
          "actual_end": "1994-06-09",
          "note": "Pre-beta builds went to developers, including build 73g (2 December 1993) and build 81 (19 January 1994). By the public 1993 target, the product should have shipped in mid-1994."
        },
        {
          "name": "Beta testing",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1994-06-09",
          "actual_end": "1995-03-17",
          "note": "Build 122 (9 June 1994), Beta 2 build 224 (3 November 1994) and the Final Beta Release build 347 (17 March 1995). In July 1994 Steve Ballmer said it would not go on sale before January 1995."
        },
        {
          "name": "Release candidates and preview program",
          "planned_start": null,
          "planned_end": null,
          "actual_start": "1995-03-17",
          "actual_end": "1995-07-14",
          "note": "May and June 1995 test releases (builds 468 to 501, RC1 in June). A public preview sold for $19.95 on floppy disks and expired in November 1995."
        },
        {
          "name": "Release to manufacturing and retail launch",
          "planned_start": null,
          "planned_end": "1994-06",
          "actual_start": "1995-07-14",
          "actual_end": "1995-08-24",
          "note": "RTM on 14 July 1995; retail launch on 24 August 1995 with an event in a tent on the Microsoft campus in Redmond."
        }
      ],
      "milestones": [
        {
          "name": "Beta 2 (build 224)",
          "planned_date": null,
          "actual_date": "1994-11-03"
        },
        {
          "name": "Final Beta Release (build 347)",
          "planned_date": null,
          "actual_date": "1995-03-17"
        },
        {
          "name": "Release to manufacturing",
          "planned_date": null,
          "actual_date": "1995-07-14"
        },
        {
          "name": "Retail launch",
          "planned_date": "1994-06",
          "actual_date": "1995-08-24"
        }
      ],
      "headline": "Announced in 1993 for a mid-1994 release, Windows 95 reached stores on 24 August 1995, about 14 months late.",
      "summary": "Chicago, the successor to Windows 3.1 and MS-DOS, began around March 1992. An internal plan targeted June 1993, and the product was publicly announced in 1993 for release in mid-1994. In summer 1994 Microsoft moved the date to early 1995, and around the end of 1994 it slipped again by about six months to August 1995. After builds and betas starting in 1993, Windows 95 was released to manufacturing on 14 July 1995 and went on sale on 24 August 1995.",
      "what_went_wrong_or_right": "Chicago combined several technical goals in one release: a 32-bit protected-mode kernel, a new 32-bit Windows subsystem, a new user interface, and compatibility with existing DOS and Windows 3.1 software. A 1992 Microsoft product plan scheduled several of these components for June 1993, which proved far too optimistic. The public mid-1994 date also slipped. In July 1994 executive vice president Steve Ballmer told analysts the product would not go on sale before January 1995 and might not produce revenue until April 1995. TidBITS reported in January 1995 that Microsoft had pushed the release a further six months, to August 1995. The final schedule held: RTM came on 14 July 1995 and retail launch on 24 August. A long public beta and a paid preview program tested compatibility on a wide range of hardware.",
      "lessons": [
        "Internal plans that ship many new subsystems at once need large buffers; the 1993 plan missed by more than two years.",
        "Set revised dates from historical velocity data rather than hope, then hold them.",
        "Broad beta and preview programs expose hardware and compatibility problems that labs cannot."
      ],
      "fun_fact": "Microsoft paid for 1.5 million free copies of The Times in the UK on launch day, according to Wikipedia citing CNET.",
      "method_tags": [
        "waterfall",
        "big_bang",
        "iterative"
      ],
      "related_history_ids": [
        "planning-fallacy-1979",
        "scrum-1995",
        "ms-project-1984"
      ],
      "sources": [
        {
          "title": "Development of Windows 95",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Development_of_Windows_95",
          "accessed": "2026-10-25"
        },
        {
          "title": "Windows 95",
          "publisher": "Wikipedia",
          "url": "https://en.wikipedia.org/wiki/Windows_95",
          "accessed": "2026-10-25"
        },
        {
          "title": "Report on Ballmer comments on Chicago timing (25 July 1994)",
          "publisher": "Computer Business Review / Tech Monitor",
          "url": "https://techmonitor.ai/?p=142230",
          "accessed": "2026-10-25"
        },
        {
          "title": "Excuse Me, But Your Slips Are Showing (2 January 1995)",
          "publisher": "TidBITS",
          "url": "https://tidbits.com/?p=1692",
          "accessed": "2026-10-25"
        },
        {
          "title": "Chicago in 94? No, Windows95 (19 September 1994)",
          "publisher": "TidBITS",
          "url": "https://tidbits.com/1994/09/19/chicago-in-94-no-windows95/",
          "accessed": "2026-10-25"
        },
        {
          "title": "039. Start Me Up",
          "publisher": "Hardcore Software (Steven Sinofsky)",
          "url": "https://hardcoresoftware.learningbyshipping.com/p/039-start-me-up",
          "accessed": "2026-10-25"
        }
      ],
      "confidence": "medium",
      "notes": "Baseline: TidBITS (2 January 1995) says this version of Windows was originally announced in 1993 and set to ship in mid-1994. That is the earliest public target, stored as planned_end 1994-06 (mid-1994; the exact month was not stated). An earlier internal Microsoft product plan from 1992, reproduced on Wikipedia, listed June 1993 for the Chicago components (Panther, Cougar, Jaguar), but it was not public and is not used as the baseline. Rebaseline: in summer 1994 Microsoft moved the date to early 1995 (TidBITS; Ballmer in July 1994 said not before January 1995). TidBITS reported a further six-month slip to August, which implies a February 1995 target. rebaseline_end is stored as 1995-02. Actual end is retail availability on 24 August 1995 (RTM 14 July 1995). Cost: Microsoft did not publish a development budget, so planned_cost and actual_cost are null. Wikipedia cites Bloomberg Business News (August 1995) estimating the industry-wide marketing campaign at $1 billion, and separately mentions a $200 million Microsoft advertising campaign without a source I could verify. Both cover marketing, not development, and are not stored as project cost. USD, fx = 1. Editor 2026-10-25: removed claims the spoke research could not verify from an opened source.",
      "exclude_flag": null,
      "has_spoke": true,
      "cost_not_public": true
    }
  ]
}