Skip to content

Space and science · Greenbelt, Maryland (Goddard Space Flight Center), United States · 1977–1993

Hubble Space Telescope

Planned at $600 million for a 1983 launch, Hubble reached orbit in April 1990 at about $1.5 billion, then needed a December 1993 servicing mission to correct a flawed mirror.

+150%cost overrun
10 years lateagainst the first plan
$3.7 billionactual cost in 2025 dollars
Over budget and lateconfidence: medium

Hubble as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Approval and design1977 – 19791977 – 1979
Primary mirror grinding and polishingnot published1979 – May 1981
Assembly, testing and launch slips1981 – 19831981 – Jan 28, 1986
Storage after the Challenger accidentnot publishedJan 28, 1986 – Apr 24, 1990
Mirror flaw discovery and investigationnot publishedApr 24, 1990 – Nov 1990
Corrective optics and first servicing missionnot publishedOct 1991 – Dec 13, 1993

The plan

The Space Telescope, later named for Edwin Hubble, won its first construction money in 1977, when Congress approved $36 million for fiscal 1978 after a lobbying campaign by astronomers.6 Marshall Space Flight Center managed development, with Lockheed as the main spacecraft contractor and Perkin-Elmer building the optical telescope assembly.6 The European Space Agency joined in exchange for at least 15 percent of observing time.6

The telescope was originally estimated to cost $600 million to build, with a Space Shuttle launch planned for 1983.1 Auditors doubted the number from the start. In May 1977 GAO reported that NASA's estimates left out $227.2 million in development costs and $709.4 million in operations, which together would have put the life-cycle cost near $1.4 billion.4 In January 1980 GAO again asked NASA to give Congress more complete cost information, while noting the project was then on budget and on schedule for 1983.3

There was no formal rebaseline. The launch date simply moved, and the cost grew with it.

What actually happened

Approval and design, 1977–1979

Funding and schedule uncertainty marked the period from 1977 to the planned 1983 launch, a pattern that a 2012 review by Matthew Lallo compared directly to Webb's.1 GAO's two reviews in 1977 and 1980 both focused on incomplete cost reporting rather than on technical risk.43

Grinding the primary mirror, 1979–1981

Perkin-Elmer had won the optics work as the low bidder at $64.2 million, against $99.8 million from Kodak and Itek.2 It polished the 2.4-meter primary mirror to a precise shape, but the wrong one: the outer edge was too flat by about 2,200 nanometers, because one lens in the reflective null corrector used to test it was 1.3 millimeters out of position.6 The error was made in 1981 and stayed hidden for nine years.2

Assembly, testing and launch slips, 1981–1986

By 1980 it was already clear the telescope would not launch before 1986, and by 1985 the construction cost had roughly doubled to about $1.2 billion.1 Wikipedia's account traces the launch moving to 1985 and then into 1986, with the project budget reaching $1.175 billion.6

Storage after Challenger, 1986–1990

The loss of Challenger in January 1986 grounded the Shuttle fleet. The finished telescope waited in a clean room at about $6 million a month.6 Discovery finally carried it to orbit on STS-31 on April 24, 1990, by which time Hubble had cost about $1.5 billion.62 Ground systems used the four-year wait to mature.1

The mirror flaw, 1990

On June 24, 1990, Hubble failed a focusing test and the problem was diagnosed as spherical aberration.2 Senator Barbara Mikulski called the telescope a 'techno-turkey'. The failure board led by JPL director Lew Allen reported in November 1990: it traced the error to the flawed null corrector and blamed poor communication and weak oversight by both NASA and Perkin-Elmer.2

Corrective optics and the first servicing mission, 1991–1993

Because Hubble had been designed to be serviced by astronauts, the fix could go to the telescope. STS-61 launched on December 2, 1993, and over five spacewalks totaling 35 hours and 28 minutes the crew installed COSTAR, which put corrective mirrors in front of the existing instruments, and the new Wide Field and Planetary Camera 2, with correction built in.5 Hubble then reached its intended performance, about 16 years after approval.5

Why it went the way it did

An estimate that left out known costs

The $600 million figure covered construction only.1 GAO identified more than $900 million of development and operations costs outside NASA's estimate in 1977, so the program started with a baseline that was incomplete by design.4 Growth to about $1.2 billion by 1985 and $1.5 billion at launch followed.12

One unchecked test instrument

The mirror was ground to match a single reflective null corrector, and that instrument was wrong.6 The Allen board found that communication and oversight between NASA and its low-bid contractor were not strong enough to catch it.2 A single independent cross-check of the mirror's shape would have exposed the 2.2-micrometer error on the ground.

Total dependence on the Shuttle

Hubble could only launch on the Shuttle, so the Challenger accident added four years of storage at about $6 million a month to a project that was already late.61 The schedule risk sat in another program entirely.

Lessons for project managers

  1. Verify critical measurements with an independent method. Hubble's mirror passed every test made with the one instrument that was wrong.6 Anything that cannot be fixed later deserves a second, independent check.
  2. Put every known cost in the baseline. GAO flagged the missing costs in 1977, years before the overrun appeared.4 An estimate that excludes known items is a classic source of the gap between estimates and outcomes.
  3. Map dependencies outside your own project. Hubble's launch depended on the Shuttle, and the Shuttle's grounding held it for four years.6 Tracking task dependencies across organizations shows where someone else's delay becomes yours.
  4. Design for maintenance. In-orbit servicing turned a flawed telescope into a working one in five spacewalks.5 Building in a way to repair or upgrade is cheap insurance against the failure nobody predicted.

Hubble by the numbers

PlannedActualSource
Cost$600 million (construction estimate)About $1.5 billion (at launch, 1990)[2]
Cost by 1985n/aAbout $1.2 billion[1]
Cost at launch, inflation-adjustedn/aAbout $4.7 billion (2010 dollars)[6]
Start19771977[1]
Launch1983April 24, 1990 (STS-31)[1]
Design performance reached1983December 1993 (STS-61)[5]
DurationAbout 6 yearsAbout 16.5 years (to the end of STS-61)[5]
Mirror errorn/aAbout 2.2 micrometers too flat at the edge[6]

From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), PMI publishes the Project Management Body of Knowledge (1987).

Frequently asked questions about Hubble

How much over budget was the Hubble Space Telescope?
Hubble was originally estimated at $600 million to build and cost about $1.5 billion by its 1990 launch, roughly 150 percent more in nominal dollars.12 That figure excludes the 1993 repair mission. In inflation-adjusted 2010 dollars, NASA had spent about $4.7 billion at launch, and much more once servicing missions are counted.6
Why was Hubble launched seven years late?
Funding and technical problems had pushed the planned 1983 launch to 1986 before the Challenger accident in January 1986 grounded the Shuttle fleet.1 The finished telescope then sat in a clean room for four years at about $6 million a month, launching on April 24, 1990.6
What was wrong with Hubble's mirror?
The primary mirror was polished very precisely to the wrong shape, about 2.2 micrometers too flat at its edge, which caused spherical aberration.6 The cause was a lens 1.3 millimeters out of position in the null corrector Perkin-Elmer used to test the mirror. The Allen board also blamed poor communication and oversight by NASA and the contractor.2
Who built the Hubble Space Telescope?
NASA's Marshall Space Flight Center managed development, Lockheed built the spacecraft and Perkin-Elmer built the optical telescope assembly, including the primary mirror.6 Perkin-Elmer won that work as the low bidder at $64.2 million.2 The European Space Agency contributed in exchange for at least 15 percent of observing time.6
How was Hubble fixed?
Astronauts on STS-61, launched December 2, 1993, made five spacewalks totaling 35 hours and 28 minutes.5 They installed COSTAR, which placed corrective mirrors in front of the existing instruments, and a replacement camera, WFPC2, with correction built in, along with new solar arrays and other repairs.5

Sources

  1. Experience with the Hubble Space Telescope: 20 years of an archetype (Lallo, 2012), arXiv / Optical Engineering (accessed October 25, 2026)
  2. Techno-turkey: Remembering Hubble's vision troubles, 30 years on, Astronomy Magazine (accessed October 25, 2026)
  3. NASA Should Provide the Congress Complete Cost Information on the Space Telescope Program (PSAD-80-15), U.S. Government Accountability Office (accessed October 25, 2026)
  4. Status and Issues Pertaining to the Proposed Development of the Space Telescope Project (PSAD-77-98), U.S. Government Accountability Office (via Justia) (accessed October 25, 2026)
  5. Servicing Mission 1, NASA (accessed October 25, 2026)
  6. Hubble Space Telescope, Wikipedia (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart

The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.

See Kanbanchi’s Gantt chart Start your free trial Back to all 100 great projects