Buildings · Paris, France · 2019–2024

Restoration of Notre-Dame de Paris after the 2019 fire

Notre-Dame de Paris reopened on December 7, 2024, about eight months after the five-year target, for about €703 million against phase budgets of €717 million.

-2%cost overrun
8 months lateagainst the first plan
$781 millionactual cost in 2025 dollars
Lateconfidence: medium

Notre-Dame restoration as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Emergency securing and consolidationApr 16, 2019 – ?Apr 16, 2019 – Sep 2021
Restoration: timber roof and spireSep 2021 – Apr 2024Sep 2021 – Mar 6, 2024
Restoration: interior, windows and organ? – Apr 2024Mar 2022 – Nov 29, 2024
Reopening? – Apr 2024Dec 7, 2024 – Dec 8, 2024

The plan

On April 15, 2019, fire destroyed the roof and spire of Notre-Dame de Paris.3 The next evening, in a televised address, President Emmanuel Macron said the cathedral would be rebuilt even more beautifully and that he wanted the work finished within five years, a timescale some restoration experts said would take decades.5 Reporters linked the April 2024 target to the Paris Olympics that summer.5

Parliament adopted a dedicated restoration law on July 16, 2019, 95 days after the fire.3 It created a single public body to run the project, led by General Jean-Louis Georgelin and, after his death in August 2023, by Philippe Jost.3 Donations to the national subscription passed €843 million, so funding was never the constraint.2

No single total budget was announced at the go-ahead. The money was set by phase: €165 million for emergency securing and €552 million for restoration, €717 million in all, which this page treats as the plan.1 The schedule baseline is the five-year promise, which pointed to April 2024.

What actually happened

Emergency securing and consolidation, 2019–2021

The first job was keeping the building standing. The site failed lead-safety inspections in 2019 and was temporarily shut, and the neighborhood was not decontaminated for four months.3 In June 2020, with the pandemic slowing work, crews removed the charred scaffolding that had surrounded the old spire.4 The structure was declared secure in September 2021, and bidding for the main reconstruction opened.4 This phase used €151 million of its €165 million budget.1

Roof and spire, 2021–2024

In March 2021 the first of about 1,000 oaks for the new spire was selected in the Bercé forest.4 Large oak trusses were lifted onto the cathedral from July 2023, and in December 2023 a golden rooster, redesigned as a phoenix and holding a time capsule of relics, returned to the top of the spire.4 The scaffolding came down in early 2024, revealing a roof and spire rebuilt largely in their original form and materials.43

Interior, windows and organ, 2020–2024

Restoration of the 8,000-pipe organ, coated in lead dust, began in August 2020.4 Workshops started cleaning and restoring the stained glass in spring 2022, with Cologne Cathedral restoring four windows.4 Macron unveiled the restored interior on November 29, 2024.3

Reopening, December 2024

The cathedral reopened on December 7, 2024.3 An AP report in March 2023 had already given December 2024 as the reopening date, so the public target had moved quietly from the five-year promise.3 On a planned versus actual schedule, that is about eight months late against April 2024, and on time against the date the project later set itself.

The final audit and the next phase, 2025–2028

In September 2025 France's Court of Audit (Cour des comptes) published its third and final report on the project and found that budget and timetable had been rigorously respected, with no overrun.21 About €140 million of donations remained for defects that predated the fire and for restoring the sacristy.1 Work continues in a further phase to 2028, starting with the chevet, already badly deteriorated before 2019.32

Why it went the way it did

One body, one law, one deadline

A special law passed within 95 days gave a single public body authority over the site.3 Under that structure, the Court of Audit found the work delivered on budget and on schedule, and the public five-year promise gave everyone a date to work back from.15

Money was not the constraint

With more than €843 million pledged, the project never waited for funding decisions, and roughly €140 million was left over after the fire-related work.21 Few public projects start with their money already in the bank.

The design question was settled by rebuilding as before

The roof and spire were rebuilt largely in their original form and materials, in oak and lead.3 Choosing a known design meant craft and supply risk, such as sourcing about 1,000 oaks, rather than open-ended design risk.4

What slipped: lead and the pandemic

The months lost came early. The lead-related shutdown in 2019 and the pandemic slowdown in 2020 both hit the securing phase, which ran to September 2021 before main restoration contracts could be let.34

Lessons for project managers

  1. Give a fixed deadline a dedicated delivery body. Notre-Dame's public body had its own law, one leader and one job. That clarity mattered more than the deadline itself.
  2. Secure the structure before letting the main contracts. Two and a half years of securing came before restoration bids opened. Treating it as a separate phase, as the five stages of project management suggest, kept unknowns out of the main contracts.
  3. Settle the design brief early. Rebuilding the spire and roof largely as before turned an open design question into a known craft task with a known schedule.
  4. Report against the original promise, too. On time against December 2024 is also eight months late against April 2024. Stating both is one of the plainer project management principles: name the baseline.

Notre-Dame restoration by the numbers

PlannedActualSource
Cost€717 million (securing €165m + restoration €552m)About €703 million (€151m spent on securing + €552m restoration budget)[1]
Securing and consolidation phase€165 million€151 million (to September 2021)[1]
DonationsNational subscriptionMore than €843 million[2]
Funds remaining after fire-related workNone plannedAbout €140 million[1]
StartApril 16, 2019April 16, 2019[3]
ReopeningApril 2024 (five-year target)December 7, 2024[3]
Delay against the five-year targetNoneAbout eight months[3]

From the history of managing work: How Big Things Get Done (2023).

Frequently asked questions about Notre-Dame restoration

How long did it take to restore Notre-Dame?
About five years and eight months. The fire was on April 15, 2019, and the cathedral reopened on December 7, 2024.3 The first phase, securing and consolidating the damaged structure, ran to September 2021; the roof, spire, interior, windows and organ followed.4 A further phase on older defects continues to 2028.3
How much did the Notre-Dame restoration cost?
About €703 million for the fire-related work: €151 million spent on securing the structure, against a €165 million budget, plus the €552 million restoration budget.1 France's Court of Audit reported no overrun.2 The total excludes the later phase on pre-fire defects, which is funded from the roughly €140 million of donations left over.1
Was Notre-Dame finished on time?
Against Macron's April 2019 promise of five years, it reopened about eight months late, on December 7, 2024.53 Against the December 2024 date that the project had been working to since at least 2023, it was on time, and the Court of Audit found the timetable rigorously respected.32
Who paid for the restoration of Notre-Dame?
Donors, from France and around the world. The national subscription raised more than €843 million, which covered both the emergency securing phase and the restoration phase and left about €140 million for further work, including the sacristy and defects that predated the fire.21 The money was managed by the dedicated public body set up by the July 2019 law.3
Who led the Notre-Dame restoration?
A public body created by the restoration law of July 16, 2019. It was led by General Jean-Louis Georgelin until his death in August 2023, and then by Philippe Jost.3 In its final report the Court of Audit described the project as a success, with budget and calendar rigorously respected.1

Sources

  1. Chantier de Notre-Dame de Paris : une gestion exemplaire, Batiweb (accessed October 25, 2026)
  2. Notre-Dame de Paris : publication du troisième rapport de la Cour des comptes sur le chantier de conservation et de restauration de la cathédrale, French Ministry of Culture (accessed October 25, 2026)
  3. Notre-Dame de Paris fire, Wikipedia (accessed October 25, 2026)
  4. Notre Dame Cathedral: A timeline of events in the restoration project (AP), Fox News / Associated Press (accessed October 25, 2026)
  5. Macron vows to rebuild a 'more beautiful' Notre-Dame in 5 years (AFP), Arab News, April 17, 2019 (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart

The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.

See Kanbanchi’s Gantt chart Start your free trial Back to all 100 great projects