Energy · Sandouping, Yichang, Hubei, China · 1994–2012

Three Gorges Dam

Budgeted at 203.9 billion yuan with full operation due in 2009, the Three Gorges Dam came in at about 203 billion yuan but reached full operation in July 2012.

0%cost overrun
3 years lateagainst the first plan
$45.1 billionactual cost in 2025 dollars
Lateconfidence: disputed

Three Gorges Dam as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Approval and preparationnot publishedApr 3, 1992 – Dec 14, 1994
Main works to first powerDec 14, 1994 – ?Dec 14, 1994 – Jul 10, 2003
Dam body completionnot publishedJul 10, 2003 – May 20, 2006
Remaining generating units? – 2009May 20, 2006 – Jul 2012
Ship liftnot publishedOct 2007 – Jan 2016
Resettlement and final acceptancenot published1993 – Nov 1, 2020

The plan

China's National People's Congress approved the Three Gorges Project in April 1992. Of 2,633 delegates, 1,767 voted in favor, 177 voted against and 664 abstained1. Construction officially started at Sandouping in Hubei province on 14 December 19941.

The initial budget was 203.9 billion yuan. It was a dynamic budget, built on the assumption that prices would rise by 5 to 10 percent a year during construction, and it included interest2. The project was scheduled for completion in 20093. Its scope covered the dam, the power plants, the ship locks and the relocation of the people living in the area the reservoir would flood1.

In 2000 the developer revised its estimate downward: the general manager of the China Three Gorges Project Corporation said the project would cost no more than 180 billion yuan, about 20 billion below the initial budget2. That figure appears in later official statements as the expected total3.

Official rebaseline: revised official estimate (cited 2000-2001), CN¥180 billion (outturn +13% against it).

What actually happened

Approval and preparation, 1992–1994

The vote was followed by more than two years of preparation before the official start in December 19941. Resettlement was treated as part of the project rather than a separate program, and it was accounted for as its own spending line next to construction and financing1.

Main works to first power, 1994–2003

The first phase ran to 2003, when the reservoir began filling, trial navigation through the ship locks started in June, and generator No. 2 began producing power on 10 July 200341. This part of the schedule broadly held. Low inflation in the late 1990s also meant the dynamic budget was larger than needed: the developer reported savings of more than 14 billion yuan from lower price rises, plus further savings from low interest rates2.

Dam body and reservoir, 2003–2010

The dam body was completed in 20061. The reservoir was raised in steps, reaching 172.5 m by 2008 and its design level of 175 m on 26 October 20101. By the end of 2008, total spending stood at 148.4 billion yuan: 64.6 billion on construction, 68.6 billion on relocation and 15.2 billion on financing1.

Remaining generating units, 2006–2012

Full operation had been expected in 20093. Instead, units were brought into service over several more years. The last of the 32 main 700 MW generators finished testing on 23 May 2012, and the plant was fully operational in July 2012, giving an installed capacity of about 22,500 MW1. That year it produced a record 98.1 TWh1.

Ship lift and final acceptance, 2007–2020

Work on the ship lift, which raises smaller vessels past the dam faster than the locks, ran from 2007; it was announced complete in January 2016 and first used in regular operation on 18 September 20161. On 1 November 2020 the Ministry of Water Resources and the National Development and Reform Commission announced that the project had passed its overall completion acceptance4.

Why it went the way it did

A budget that assumed high inflation

The 203.9 billion yuan budget built in price rises of 5 to 10 percent a year. When prices fell instead, the same scope cost less in money terms, and the developer cut its estimate to 180 billion yuan2. Part of the cost performance therefore reflects the economy, not only project control. The total usually reported today, about 203 billion yuan, is close to the initial budget, although the sources do not state its price basis1.

Resettlement as a cost and scope item

Relocation was the largest single spending category by the end of 2008, at 68.6 billion yuan of 148.4 billion, ahead of construction1. The original plan called for relocating 1.13 million people. By the end of 2006 about 1.2 million had moved, an increase officials attributed to population growth and migration, and 47,300 more were scheduled for 2007 at a cost of 5.5 billion yuan5. About 1.24 million had been moved by June 20081. Its scale required oversight of its own: an official audit program found 310 cases of misused relocation funds, totaling 58.67 million yuan, of which 43 million had been recovered3.

Generating units commissioned in sequence

The schedule slip was concentrated at the end. First power in 2003 kept to plan, but the remaining generators came online one at a time over nine years, and the last finished testing in 2012, three years after the 2009 target13. The ship lift then added four more years beyond that1.

Several budgets on different bases

Official figures mix dynamic budgets that include inflation and interest with spending totals reported at different dates21. That makes the overrun, or underrun, hard to pin down, and foreign analysts published much higher estimates, which the developer disputed in 20002.

Lessons for project managers

  1. Label every budget static or dynamic. Three Gorges published budgets with and without inflation and interest. Stating the basis is the only way to compare estimates with outcomes fairly.
  2. Budget resettlement as core scope. Relocation cost more than construction by 2008 and needed its own audits. Give land and resettlement work its own budget, schedule and controls.
  3. Phase delivery so early parts earn revenue. Generators produced power from 2003 while later units, the ship lift and other works continued. Plan phases on a project schedule so that each one delivers value on its own.
  4. Schedule the closing stage, too. Full operation came in 2012, but final acceptance took until 2020. Closing is one of the five stages of project management and deserves a date in the plan.

Three Gorges Dam by the numbers

PlannedActualSource
Cost203.9 billion yuan (initial dynamic budget)About 203 billion yuan (reported total)[1]
Revised estimate180 billion yuan (2000)148.4 billion yuan spent by end 2008[2]
Construction start14 December 199414 December 1994[1]
Full operation2009July 2012[3]
Installed capacity32 main units of 700 MWAbout 22,500 MW[1]
People relocated1.13 million (original plan)About 1.24 million by June 2008[5]
Final acceptanceNot statedAnnounced 1 November 2020[4]

From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023).

Frequently asked questions about Three Gorges Dam

How much did the Three Gorges Dam cost?
The initial budget was 203.9 billion yuan, which assumed annual inflation of 5 to 10 percent2. In 2000 the developer cut its estimate to no more than 180 billion yuan after prices fell2. By the end of 2008, spending stood at 148.4 billion yuan, and the total usually reported today is about 203 billion yuan1. On these official figures the project came in at or under its initial budget.
How long did the Three Gorges Dam take to build?
Construction started on 14 December 1994. The first generator produced power in July 2003, the dam body was finished in 2006, and the power plant was fully operational in July 2012, about 17 and a half years after the start1. The ship lift followed in 2016, and final acceptance was announced in November 202014.
Was the Three Gorges Dam finished on time?
Partly. First power in 2003 broadly met the plan, but full operation, expected in 2009, came in July 2012, about three years late31. The ship lift was not complete until January 2016, and the formal overall completion acceptance was announced only on 1 November 2020, more than 25 years after construction began14.
How many people were relocated for the Three Gorges Dam?
The original plan was to relocate 1.13 million people, and by the end of 2006 about 1.2 million had moved, according to the State Council's Three Gorges office5. About 1.24 million residents had been relocated by June 2008, and estimates of the final total run to about 1.4 million1. Relocation was also the largest spending item by the end of 2008, at 68.6 billion yuan of 148.4 billion spent1.
How big is the Three Gorges Dam?
The dam is about 181 m high and roughly 2.3 km long, and its 32 main generators of 700 MW each give an installed capacity of about 22,500 MW, the largest of any power station14. It used 27.2 million cubic meters of concrete and 463,000 tonnes of steel1.

Sources

  1. Three Gorges Dam, Wikipedia (accessed October 25, 2026)
  2. Foreign estimates of Three Gorges costs wrong: official (Xinhua, 3 May 2000), Probe International (accessed October 25, 2026)
  3. Government to audit gigantic Three Gorges project, Probe International (accessed October 25, 2026)
  4. Three Gorges project completes overall completion acceptance, People's Daily (accessed October 25, 2026)
  5. Three Gorges official says relocated residents will exceed 1.2 million (Xinhua, 12 February 2007), Probe International (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart