Tokyo 2020 cost 1.42 trillion yen, nearly double the 734 billion yen in its 2013 bid, and opened on July 23, 2021, a year late, after a pandemic postponement.

+94%cost overrun
12 months lateagainst the first plan
$15.4 billionactual cost in 2025 dollars
Over budget and lateconfidence: medium

Tokyo 2020 as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Bid and award? – Sep 7, 20132011 – Sep 7, 2013
National Stadium redesignnot publishedJul 17, 2015 – Dec 2015
Venue construction (National Stadium)? – Mar 2019Dec 2016 – Nov 30, 2019
Postponementnot publishedMar 24, 2020 – Jul 23, 2021
GamesJul 24, 2020 – Aug 9, 2020Jul 23, 2021 – Aug 8, 2021
Final accountsnot publishedAug 9, 2021 – Jun 21, 2022

The plan

Tokyo was elected host of the 2020 Summer Olympics on September 7, 2013.2 Its bid file put the cost at 734 billion yen.1 The Games were scheduled to run from July 24 to August 9, 2020, giving the city almost seven years to prepare.2

The record carries one official schedule rebaseline. On March 24, 2020 the IOC and Japan postponed the Games because of the COVID-19 pandemic, and they were held from July 23 to August 8, 2021, the only postponement in Olympic history.2 No revised budget is used as a cost baseline here; instead, the organizers' estimate of what the delay added, about 294 billion yen, is shown separately.5

The final figure has its own boundary. The organizing committee's 1.42 trillion yen covers the cost of hosting the Olympics and Paralympics.1 In October 2018 Japan's Board of Audit had warned that total Olympic-related spending could exceed $25 billion once wider government outlays were counted, so the full public cost was probably higher.2

Official rebaseline: March 2020 postponement to 2021, revised finish Jul 23, 2021.

What actually happened

Bid and award, 2013

Tokyo's 734 billion yen bid figure became the public reference point for everything that followed.1 Like every Olympic host, Tokyo was committed to a fixed opening date years before detailed designs existed.4

The stadium reset, 2015

The first warning came from the centerpiece. By June 2015 the agreed cost of Zaha Hadid's design for the new National Stadium had reached around 250 billion yen. On July 17, 2015, Prime Minister Shinzo Abe announced that the plan would be scrapped and rebid, and the stadium would no longer be ready to host the 2019 Rugby World Cup.3 In December 2015 the Japan Sport Council chose a design by Kengo Kuma with Taisei Corporation.3

Building the venues, 2016–2019

The new National Stadium was built from December 2016 to November 30, 2019, at about 157 billion yen, and opened on December 21, 2019.3 Meanwhile the Board of Audit's 2018 report signaled that spending outside the organizers' budget was growing too.2

Postponement, March 2020 to July 2021

Four months before the opening, the plan broke. The postponement announced on March 24, 2020 moved the Games back by a year.2 In December 2020 the organizers estimated the delay would add about 294 billion yen, with the Tokyo Metropolitan Government expected to pay 120 billion yen, the organizing committee 103 billion yen and the national government 71 billion yen; a separate IOC contribution of $650 million was not included.5 Oxford researchers describe the pandemic as a black swan that added billions of dollars of overruns on top of billions already incurred.4

The Games without spectators, July–August 2021

On July 8, 2021, the prime minister declared a new state of emergency in the Tokyo area from July 12 to August 22 and announced that events there would be held behind closed doors.2 The Games opened on July 23, 2021, 364 days after the original date, and became the only Olympics held without official spectators.2 On a planned versus actual schedule, the whole Games bar simply shifts right by a year while scope stays the same.

Final accounts, June 2022

On June 21, 2022 the organizing committee said the cost of hosting the Olympics and Paralympics was set to total 1.42 trillion yen, about $10.5 billion at the time, nearly double the 734 billion yen in the 2013 bid file.1

Why it went the way it did

A pandemic on a fixed date

The postponement alone accounted for about 294 billion yen of extra cost, according to the organizers' December 2020 estimate.5 A one-year delay meant keeping venues, staff and contracts alive for another year, then adding infection controls. Flyvbjerg, Budzier and Lunn note that black swans of this kind can kill a plan outright, as COVID-19 did for a 2020 opening.4

Design costs escalated before construction

The original stadium design reached around 250 billion yen before Abe scrapped it; the replacement cost about 157 billion yen.3 Cancelling saved money but cost time, and the stadium lost its Rugby World Cup role.3

Long planning horizons widen the risk window

The Oxford team argues that the seven-to-11-year horizon between bid and Games is itself a cost driver: the longer the window, the more likely a large shock flies through it.4 Across all Games since 1960 they find an average real overrun of 172 percent, a reminder of how far estimates drift from reality.4

Lessons for project managers

  1. Hold real contingency for long horizons. A seven-year program needs a reserve sized for shocks, not for rounding errors. Tokyo's delay alone added about 294 billion yen.
  2. Kill an unaffordable design before construction starts. Tokyo cancelled the Hadid stadium at around 250 billion yen and built a replacement for about 157 billion yen. The decision was costly in time but cheaper than building the original.
  3. Report all public spending, not just the organizer's. The Board of Audit's warning of more than $25 billion in wider spending shows why a single organizer total can understate the public cost.
  4. Plan how a schedule shift ripples through contracts. When the opening moved by 364 days, every dependent venue, staffing and supply contract moved too. Good project planning maps those links before a crisis forces the exercise.

Tokyo 2020 by the numbers

PlannedActualSource
Cost734 billion yen (2013 bid file)1.42 trillion yen (organizers' final figure, June 2022)[1]
Overrun (nominal)Bid figureAbout 93% (nearly double)[1]
Extra cost of the postponementNoneAbout 294 billion yen (December 2020 estimate)[5]
Opening ceremonyJuly 24, 2020July 23, 2021[2]
DelayNone364 days (pandemic postponement)[2]
National Stadium costAround 250 billion yen (Hadid design, June 2015)About 157 billion yen (Kuma design)[3]
National Stadium completionIn time for the 2019 Rugby World Cup (original scheme)November 30, 2019[3]

From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979).

Frequently asked questions about Tokyo 2020

How much did the Tokyo 2020 Olympics cost?
The organizing committee put the cost of hosting the Olympics and Paralympics at 1.42 trillion yen, about $10.5 billion at the June 2022 exchange rate.1 That may not capture all public spending: in 2018 Japan's Board of Audit warned that total Olympic-related costs could exceed $25 billion.2
How much over budget was Tokyo 2020?
The final 1.42 trillion yen was nearly double the 734 billion yen quoted in the 2013 bid file, an increase of about 93 percent in nominal terms.1 About 294 billion yen of the increase came from the one-year postponement, according to the organizers' December 2020 estimate.5
Why was Tokyo 2020 postponed?
On March 24, 2020 the IOC and Japan postponed the Games because of the global COVID-19 pandemic, the only postponement in Olympic history.2 They were held from July 23 to August 8, 2021, under a state of emergency and still branded Tokyo 2020. The delay was 364 days against the original July 24, 2020 opening.2
How much did the postponement cost?
In December 2020 the organizers estimated that the delay would add about 294 billion yen, or about $2.8 billion. The Tokyo Metropolitan Government was expected to pay 120 billion yen, the organizing committee 103 billion yen and the national government 71 billion yen. The IOC's separate $650 million contribution was not included.5
Why was Tokyo 2020 held without spectators?
Overseas spectators were barred, and in July 2021 a new state of emergency in the Tokyo area led the government to announce that events there would be held behind closed doors.2 Tokyo 2020 became the only Olympic Games held without official spectators.2

Sources

  1. Olympics: Tokyo Games cost totals 1.42 tril. yen, twice bid figure, Kyodo News, June 21, 2022 (accessed October 25, 2026)
  2. 2020 Summer Olympics, Wikipedia (accessed October 25, 2026)
  3. Japan National Stadium, Wikipedia (accessed October 25, 2026)
  4. Regression to the Tail: Why the Olympics Blow Up (Flyvbjerg, Budzier & Lunn, Environment and Planning A, 2021), arXiv / University of Oxford (accessed October 25, 2026)
  5. Japanese organizers say 2020 Games delay to cost them $2.8b, The Jakarta Post, December 4, 2020 (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart

The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.

See Kanbanchi’s Gantt chart Start your free trial Back to all 100 great projects