Infrastructure · Schönefeld, near Berlin, Germany · 2006–2020
Berlin Brandenburg Airport Willy Brandt (BER)
Berlin's BER airport opened on October 31, 2020, nine years after its planned October 2011 date, at a cost of roughly €6.5 to 7.3 billion against about €2 billion.
Berlin BER Airport as a Gantt chart: planned vs actual
- Planned
- Actual
- Forecast
- Milestones (planned, actual)
- ↳ Dependency
- Today
| Phase | Planned | Actual |
|---|---|---|
| Construction of terminal and airfield | 2006 – Oct 2011 | 2006 – May 2012 |
| Opening cancelled; fire-protection failure | ? – Jun 2, 2012 | May 2012 – May 2014 |
| Remediation and rework | not published | 2014 – 2019 |
| Acceptance, licensing and trial operations | not published | 2019 – Oct 2020 |
| Opening and transfer from Tegel | Oct 2011 – Oct 2011 | Oct 31, 2020 – Nov 8, 2020 |
Open in the explorer of 100 projects · Compare with Heathrow T5 (a big European terminal that opened on its planned date) · What is a Gantt chart? A free lesson
The plan
Berlin Brandenburg Airport was built at Schönefeld to replace the city's Tegel and Schönefeld airports with a single hub, owned by the states of Berlin and Brandenburg and the federal government.1 The first groundbreaking took place on September 5, 2006, and the airport was due to open in October 2011.31 At the start of construction the cost was put at about €2 billion.2
The record carries one rebaseline built from two decisions. By 2009 the construction budget stood at €2.83 billion, and the opening was later moved to June 3, 2012, a date that was fully marketed and then cancelled four weeks out.13
The outturn is a range. The taxpayers' association Bund der Steuerzahler reported about €6.5 to 7 billion up to opening, more than three times the original figure, while German Wikipedia gives a total project cost of about €7.3 billion.23 This page uses the midpoint, €6.9 billion: about 245 percent over the €2 billion start figure, or about 144 percent over the 2009 budget. A 2018 estimate of €9.4 billion includes expansion work to 2030 and is not used.1
Official rebaseline: 2009 budget; opening moved to June 2012, €2.83 billion (outturn +144% against it), revised finish Jun 2012.
What actually happened
Construction of terminal and airfield, 2006–2012
Construction began in 2006 for an October 2011 opening, which slipped to June 2012.1 By late 2012, spending had already reached €4.3 billion.1 Brandenburg's audit office later found that between 2010 and 2013 the state's representatives did not adequately exercise oversight in the shareholders' meeting or the supervisory board, that there was no external controlling of the company or the construction project, and that new opening dates were announced hastily without intervention.5
The cancelled opening, May 2012
On May 8, 2012, about four weeks before the June 3 opening, the airport company announced a postponement because of problems with the fire-protection system.3 The fire alarm and smoke-extraction system had failed its mandatory acceptance test, and the building authority rejected a stopgap plan to station up to 700 people in the terminal as human fire spotters.1 Everything else in the terminal could be finished, and none of it could be used.
Diagnosis and dismissals, 2012–2014
Berlin's House of Representatives set up an inquiry committee on September 27, 2012 to examine the causes of the cost and schedule overruns.4 Investigators found a smoke-extraction design that routed smoke down through a shaft in the basement, against the natural rise of hot air, along with poor workmanship that included about 60 km of cooling pipes allegedly installed without insulation.1 The general planner, pg bbi, became insolvent and the architects were dismissed, and the system's designer, Alfredo di Mauro, turned out not to be a qualified engineer; he was dismissed in early May 2014 and his plans were discarded.1
Rework and refinancing, 2014–2019
Rebuilding the technical systems took years and new money. Total costs reached €5.4 billion in 2015, and a request that June for another €2.5 billion took the total to about €6.8 billion.1 In November 2015 the financial concept was judged fundamentally flawed because it assumed Berlin would become a major transfer hub, a role only Air Berlin could have filled; the airline became insolvent in August 2017.1 The EU approved €2.2 billion of state aid on August 3, 2016, and a €2.4 billion loan was signed on February 13, 2017.1 The inquiry committee's final report, Drucksache 17/3000, was debated in plenary on June 23, 2016.4
Licence, opening and the move from Tegel, 2020
BER received its operating licence in May 2020 and opened for commercial traffic on October 31, 2020, 14 years after construction began and in the middle of the COVID-19 pandemic.1 All remaining airlines had moved from Tegel by November 8, 2020.1
Why it went the way it did
One life-safety system sat on the critical path
An airport terminal cannot open without building-authority acceptance, and acceptance depends on the fire alarm and smoke-extraction system working as permitted.1 That made a single subsystem the gate for the whole project: shops, gates, baggage and runways were all downstream of it. It is the textbook case of one late task holding up everything that depends on it, and at BER it cost years rather than weeks.3
Design without a qualified owner
The smoke-extraction concept fought physics, and its designer was not a qualified engineer.1 When the general planner became insolvent and the architects were dismissed, responsibility for an integrated design that was already failing had no clear home.1
Weak owner oversight and hasty dates
Brandenburg's audit office found no external controlling of the company or the construction project between 2010 and 2013, and no intervention when new opening dates were announced hastily.5 It recommended external controlling and an in-depth review of the airport company's organization.5
A business case built on a hub
The financial plan assumed transfer traffic that only one airline could supply, and that airline did not survive to see the opening.1
Lessons for project managers
- Put life-safety acceptance on the critical path early. Model the fire-safety system as a predecessor of opening in the schedule, with acceptance testing well before launch. A dependency-linked Gantt chart, in Kanbanchi or any other tool, makes that gate visible to everyone who plans around it.
- Have safety design checked by qualified, independent engineers. BER's smoke-extraction design came from someone who was not a qualified engineer. Credential checks and independent review are cheap compared with eight years of rework.
- Plan for losing your general planner. When pg bbi became insolvent, design integration lost its owner. Keep design documentation, contracts and responsibilities clear enough that someone else can take over.
- Announce dates only after the evidence supports them. BER marketed a June 2012 opening and cancelled it four weeks out. Deadline realism means publishing a date only once the gating tests have been passed.
Berlin BER Airport by the numbers
| Planned | Actual | Source | |
|---|---|---|---|
| Cost | About €2 billion (2006) | About €6.5 to 7.3 billion (to 2020; midpoint €6.9 billion) | [2] |
| Revised budget | €2.83 billion (2009) | About €6.9 billion (about +144%) | [1] |
| Construction start | September 5, 2006 | September 5, 2006 | [3] |
| Opening | October 2011 | October 31, 2020 | [1] |
| Rescheduled opening | June 3, 2012 | Cancelled on May 8, 2012 | [3] |
| Delay | None | About nine years (108 months) | [1] |
| Duration, groundbreaking to opening | About 61 months | About 170 months | [1] |
From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), How Big Things Get Done (2023).
Frequently asked questions about Berlin BER Airport
- Why was Berlin Brandenburg Airport delayed?
- The fire alarm and smoke-extraction system failed its mandatory acceptance test weeks before the planned June 2012 opening.13 Its design pulled smoke downward against its natural rise, its designer was not a qualified engineer, and inspectors found widespread poor workmanship. Rebuilding the technical systems took until 2020.1
- How much over budget was BER?
- The cost rose from about €2 billion at the start of construction to roughly €6.5 to 7 billion up to opening, according to the Bund der Steuerzahler, or about €7.3 billion according to German Wikipedia.23 Using the €6.9 billion midpoint, that is about 245 percent over the original figure and about 144 percent over the 2009 budget of €2.83 billion.1
- When did Berlin's new airport finally open?
- BER opened for commercial traffic on October 31, 2020, after receiving its operating licence in May 2020.1 The original target was October 2011, so it opened about nine years late, and eight and a half years after the cancelled June 2012 opening. Airlines finished moving from Tegel by November 8, 2020.1
- What was wrong with BER's fire protection system?
- The smoke-extraction design routed smoke down a shaft through the basement, reversing the natural rise of hot air, and it did not work as planned.1 Inspectors also reported wiring and cable-routing problems. The designer was dismissed in May 2014 and his plans were discarded.1
- How long did BER take to build?
- About 14 years. The first groundbreaking was on September 5, 2006, and the airport opened on October 31, 2020.31 The plan had allowed about five years, to October 2011. For about eight of those years, after the cancelled 2012 opening, the terminal stood unused while its technical systems were reworked.1
Sources
- Berlin Brandenburg Airport, Wikipedia (accessed October 25, 2026)
- Endlich - BER geht in Betrieb, Bund der Steuerzahler Deutschland (accessed October 25, 2026)
- Flughafen Berlin Brandenburg, Wikipedia (German) (accessed October 25, 2026)
- 1. Untersuchungsausschuss BER (17th electoral term), Abgeordnetenhaus Berlin (accessed October 25, 2026)
- Rechnungshof rügt mangelnde Kontrolle der Regierung über den BER (on the Brandenburg Landesrechnungshof report of July 2015), Aero International (accessed October 25, 2026)
Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.