Vehicles and aircraft · Everett, United States · 2004–2011

Boeing 787 Dreamliner development

Boeing approved a development budget of about $7 billion and promised ANA its first 787 in May 2008; after seven delays the jet was delivered in September 2011, and the program reportedly cost $32 billion.

+357%cost overrun
3 years lateagainst the first plan
$45.8 billionactual cost in 2025 dollars
Over budget and lateconfidence: medium

Boeing 787 Dreamliner as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Design and supplier developmentApr 2004 – Jul 2007Apr 26, 2004 – Jul 8, 2007
Rollout to first flightJul 8, 2007 – Aug 2007Jul 8, 2007 – Dec 15, 2009
Flight test and certificationAug 2007 – May 2008Dec 15, 2009 – Aug 26, 2011
First delivery and service entryMay 2008 – May 2008Sep 25, 2011 – Oct 26, 2011

The plan

Boeing's board approved the 787 in 2003 with a development budget estimated at $7 billion.1 The program launched on April 26, 2004, when All Nippon Airways placed a firm order for 50 aircraft with deliveries to begin in late 2008; ANA was due to receive its first jet in May 2008.12

The plan rested on two novelties at once. The airframe would be mostly carbon-fiber composite, and partners around the world would design and build whole sections of it: Mitsubishi Heavy Industries and Subaru the wing and center wing box, Alenia Aeronautica and Korea Aerospace Industries the horizontal stabilizers, and Spirit AeroSystems and Kawasaki fuselage sections, flown to Everett in converted 747 Dreamlifters.1 Boeing said outside partners contributed 65 percent of the airframe.3

Boeing set rollout for July 8, 2007, and the first flight for the end of August 2007.1 There was no single published rebaseline; instead the company announced a series of delays.

What actually happened

Design and supplier development, 2004–2007

Rollout happened on schedule, on July 8, 2007, but the aircraft on stage was not what it seemed. Its major systems were not installed, and many parts were held together with temporary non-aerospace fasteners.1 The date was met; the work behind it was not.

Rollout to first flight, 2007–2009

The delays came in quick succession. In September 2007 Boeing blamed a shortage of fasteners and incomplete software; in October 2007, supply chain problems, missing documentation from overseas suppliers and flight guidance software; in January 2008, insufficient progress on traveled work, the assembly that suppliers had left for Boeing to finish.1 A fourth delay followed in April 2008, and in November 2008 Boeing cited incorrect fastener installation and the machinists' strike, which lasted 58 days.12

Boeing began buying back parts of its own supply chain. In March 2008 it announced plans to buy Vought's interest in Global Aeronautica, and on July 30, 2009 it completed the purchase of Vought's North Charleston operations, which built 787 aft fuselage sections.14 In between, on June 23, 2009, the first flight was postponed again for structural reasons.1 The 787 finally flew on December 15, 2009, from Paine Field in Everett.1

Flight test and certification, 2009–2011

Flight testing took about 20 months. The FAA and the European Aviation Safety Agency certified the 787 on August 26, 2011, at a ceremony in Everett.1

First delivery, 2011

Boeing and ANA signed the delivery documents on September 25, 2011, and held the ceremony and flyaway the next day, more than three years after the original May 2008 date.2 By CAPA's count the program had announced seven delays, caused by engineering and supply chain problems and the 2008 strike.2 The first commercial flight followed in October 2011.1

Why it went the way it did

A supply chain built on dependencies Boeing did not control

Under the 787 model, a supplier's late or incomplete section stopped the final assembly line, because nothing downstream could proceed without it. Missing documentation from overseas suppliers, a fastener shortage and sections arriving with unfinished traveled work all appear in Boeing's own delay announcements.1 This is the textbook case of task dependencies at scale: one late task holds up everything that follows it.

Boeing's response was to take work back, buying Vought's stake in Global Aeronautica and then its Charleston plant to gain more control over the supply chain.14 Boeing workers interviewed by Reuters in 2011 blamed part of the trouble on outsourcing and lost local production knowledge.3

Too many novelties at once

The 787 combined a new composite airframe with a new way of building airplanes, so problems in materials, design and supply could not be separated from each other.1 CAPA attributed the delays to engineering and supply chain problems together.2

Milestones that hid real progress

Rolling out an aircraft without its major systems kept the July 2007 milestone but told little about readiness; the first flight then slipped by more than two years.1 A milestone is only useful if it measures finished work.

Lessons for project managers

  1. Outsourcing work does not outsource integration risk. Partners built most of the airframe, but Boeing still owned the schedule and ended up finishing their work and buying their plants.34 Plan the oversight and the integration effort as real work.
  2. Measure milestones by completed work. The 2007 rollout met its date with temporary fasteners and no systems installed.1 Comparing the planned and actual schedule only helps if milestones mean done.
  3. Limit simultaneous novelties on one program. A new material and a new supply model together made each problem harder to isolate.1 Budgets set for one novelty rarely survive two; the 787's $7 billion figure is a familiar case of estimates versus reality.

Boeing 787 Dreamliner by the numbers

PlannedActualSource
Development costAbout $7 billion (board-approved budget, 2003)About $32 billion (reported program cost)[1]
Program launchApril 26, 2004April 26, 2004[1]
RolloutJuly 8, 2007July 8, 2007 (systems not installed)[1]
First flightEnd of August 2007December 15, 2009[1]
First delivery to ANAMay 2008September 25–26, 2011[2]
Delivery delayn/aAbout 40 months[2]
Announced delaysn/aSeven[2]
Airframe share built by partnersn/a65 percent (Boeing figure)[3]

From the history of managing work: Kahneman and Tversky name the planning fallacy (1977–1979), Reference class forecasting (2002–2006), How Big Things Get Done (2023).

Frequently asked questions about Boeing 787 Dreamliner

How much over budget was the Boeing 787?
Boeing's board approved a development budget of about $7 billion, and the program has reportedly cost Boeing $32 billion.1 CAPA attributes the $32 billion figure to Seattle Times reporting.2 Because it is a press figure rather than a Boeing statement of development cost, and may include production costs, the ratio between the two numbers is indicative rather than exact.1
How late was the first Boeing 787?
ANA was due to receive its first 787 in May 2008. Delivery documents were signed on September 25, 2011, with the handover ceremony on September 26, about 40 months late.2 The first flight, planned for the end of August 2007, happened on December 15, 2009.1
Why was the Boeing 787 delayed?
Boeing's delay announcements cited a fastener shortage, incomplete software, missing documentation from overseas suppliers, unfinished traveled work from suppliers, incorrect fastener installation, a 2008 machinists' strike and, in June 2009, a structural problem.1 CAPA counts seven delays in all, caused by engineering and supply chain problems and the 58-day strike.2
Who builds the parts of the Boeing 787?
Major structures came from partners: Mitsubishi Heavy Industries and Subaru built the wing and center wing box, Alenia Aeronautica and Korea Aerospace Industries the horizontal stabilizers, and Spirit AeroSystems and Kawasaki fuselage sections.1 Boeing said partners contributed 65 percent of the airframe.3 In 2009 Boeing bought the North Charleston aft-fuselage plant from Vought.4
Was outsourcing to blame for the 787's problems?
It was a major factor. Several of Boeing's own delay announcements named supplier problems, and Boeing bought supplier operations in 2008 and 2009 to gain more control over the supply chain.14 Boeing workers interviewed by Reuters in 2011 blamed excessive outsourcing and lost production knowledge for some of the failures.3

Sources

  1. Boeing 787 Dreamliner, Wikipedia (accessed October 25, 2026)
  2. Boeing completes delivery of first B787 to ANA, CAPA - Centre for Aviation (accessed October 25, 2026)
  3. A Wing and a Prayer: Outsourcing at Boeing (Kyle Peterson, Reuters), YaleGlobal Online (accessed October 25, 2026)
  4. Boeing Completes Acquisition of Vought Operations in South Carolina, Boeing (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart