Historic · Giza, Egypt · 2600 BC–2574 BC

Great Pyramid of Giza (Pyramid of Khufu)

About 2.3 million stone blocks were set in place in roughly 26 years, within a deadline fixed by one king's reign of about 23 to 29 years.

Not publiccost overrun
Unknownagainst the first plan
Not publicactual cost in 2025 dollars
Incomplete dataconfidence: disputed

Great Pyramid as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Site survey, leveling and alignmentnot published2600 BC – 2598 BC
Quarrying and core coursesnot published2598 BC – 2585 BC
Upper structure and granite chambersnot published2585 BC – 2578 BC
Casing with Tura limestonenot published2580 BC – 2574 BC
Completion and capstonenot published2576 BC – 2574 BC

The plan

No plan for the Great Pyramid survives, and there is no budget to compare it with. Old Kingdom Egypt ran on rations and labor obligations rather than money, and no accounts for the project are known, so its cost is not public in any modern sense. What existed instead was a deadline. The tomb was built for Khufu, second king of the Fourth Dynasty, who reigned in the early 26th century BC, and it had to be ready to receive him when he died.13

That deadline is the closest thing to a baseline. The Turin King List gives Khufu 23 years, while graffiti in a pit south of the pyramid record a 28th or 29th regnal year, so the window was roughly 23 to 29 years.3 Herodotus said the pyramid took 20 years; modern estimates put construction at about 26 years, beginning around 2600 BC.1 Every date on this page, including the phase boundaries in the chart, is a scholarly estimate rather than a recorded milestone.

The scope was large by any standard: about 2.3 million blocks weighing roughly 6 million tonnes, rising to an original height of 146.6 m, or 280 royal cubits, on a base about 230 m on each side.1

What actually happened

Site survey, leveling and alignment, c. 2600–2598 BC

The builders began with the ground. A strip around the perimeter was leveled to within about 21 mm, and the sides were set to the cardinal directions with an average error of about 3 minutes 38 seconds of arc, roughly a tenth of a degree.1 The base corners are square to a mean error of 12 arc seconds.1 An error at this stage would have been carried into every course above it, so precision here was a schedule decision as much as an aesthetic one.

Quarrying and core courses, c. 2598–2585 BC

Most core blocks were cut on the Giza plateau itself, close to the work face, and many are irregular in size and shape, a sign that speed mattered more than finish inside the mass.1 An experimental study by Franck Burgos estimated that about 3,500 quarrymen producing 250 blocks a day could have supplied the stone in 27 years, which fits inside the reign-length window.1 Herodotus described crews working in three-month shifts.1

Upper structure and granite chambers, c. 2585–2578 BC

The internal chambers called for granite, which came from Aswan, more than 900 km up the Nile.1 The pyramid contains an estimated 8,000 tonnes of granite and about 500,000 tonnes of mortar alongside some 5.5 million tonnes of limestone.1 Moving heavy stone that far made river transport a project of its own, with its own crews and calendar.

Casing with Tura limestone, c. 2580–2574 BC

The best evidence for how the work was managed comes from this late phase. In 2013 a French mission led by Pierre Tallet and Gregory Marouard found papyri at Wadi al-Jarf on the Red Sea coast, including the logbook of an official named Merer.2 It dates to Khufu's 26th and 27th regnal years and records about forty boatmen ferrying fine white limestone from the Tura quarries to Giza: two or three round trips about every ten days, roughly 30 blocks of 2 to 3 tonnes per cycle, or about 200 a month.2

The deliveries were overseen by Ankhhaf, Khufu's half-brother, who appears in the papyri as overseer of Ra-shi-Khufu, which Tallet identifies as the harbor at Giza where casing stones were landed.2

Completion and capstone, c. 2576–2574 BC

If Merer's crew was still delivering casing stone in year 27, the pyramid was being finished close to the end of the reign, which leaves little slack against the deadline.23 The finished structure stood 146.6 m tall and remained the tallest human-made structure in the world for more than 3,700 years.1 It has since lost most of its casing and now stands about 138.5 m high.1

Why it went the way it did

A deadline set by the client's lifespan

The schedule was fixed by the king's life rather than by a contract. That made the end date uncertain but its consequence absolute, and the evidence suggests the builders front-loaded the slow, precise survey work and then kept production steady for two decades.13

Organized, fed and housed labor

A 1999 construction-management study carried out with Egyptologist Mark Lehner estimated an average workforce of about 13,200 and a peak of about 40,000, far below the 100,000 often taken from Herodotus.1 Workers' camps found near the pyramids point to conscripted laborers working in rotation rather than slaves.1 Lehner's excavations at Heit el-Ghurab, the town beside the pyramids, show it was also a busy Nile port, with goods arriving from as far as the Levant.4

Logistics run as a separate stream

Stone came from three directions: core blocks from the plateau, casing from Tura across the river and granite from Aswan.1 The Merer papyri show the river leg run by a dedicated crew on a recorded cycle under a named supervisor.2 That matters because casing is the classic case of one late task holding up everything after it: the outer courses cannot be dressed until the stone arrives.

Lessons for project managers

  1. Plan backwards from a fixed deadline. When the end date cannot move, derive the production rate from it. Roughly 2.3 million blocks in about 26 years means hundreds of blocks per working day, and sound project planning starts with that arithmetic.
  2. Give the supply chain its own owner. Tura limestone and Aswan granite had their own boats, crews and supervisor. Treat materials logistics as a workstream with a schedule, not a footnote in someone else's plan.
  3. Keep a short daily log. Merer recorded trips, places and dates in a few lines a day. It is among the oldest known progress reports, and it is the main reason the casing phase can be dated at all.
  4. Label estimates as estimates. Almost every date for the pyramid is inferred. Saying which figures are measured and which are modeled is also what keeps deadlines realistic on modern projects.

Great Pyramid by the numbers

PlannedActualSource
CostNo recordNot public (no money economy, no surviving accounts)[1]
StartNo recordc. 2600 BC (scholarly estimate)[1]
Deadline / finishWithin Khufu's reign (about 23–29 years)c. 2574 BC (scholarly estimate)[3]
Duration20 years (Herodotus)About 26 years (modern estimate)[1]
Workforce100,000 (Herodotus)About 13,200 average, 40,000 peak (1999 estimate)[1]
BlocksNo recordAbout 2.3 million, roughly 6 million tonnes[1]
Height280 royal cubits146.6 m original, about 138.5 m today[1]

Frequently asked questions about Great Pyramid

How long did it take to build the Great Pyramid of Giza?
Modern estimates put construction at about 26 years, beginning around 2600 BC, while Herodotus said 20 years.1 The outer limit is Khufu's reign, which the Turin King List gives as 23 years and graffiti near the pyramid extend to a 28th or 29th year.3 The Diary of Merer shows casing stone still arriving in the king's 27th year, so the work ran close to the end of the reign.2
How many people built the Great Pyramid?
A 1999 construction-management study with Egyptologist Mark Lehner estimated an average of about 13,200 workers and a peak of about 40,000, far fewer than the 100,000 often cited from Herodotus.1 Workers' camps near the pyramids point to conscripted laborers who worked in rotation and were housed and fed, rather than slaves.14
How much did the Great Pyramid cost?
There is no figure. The Old Kingdom economy ran on rations and labor duties rather than money, and no accounts for the project survive, so the cost is not public and cannot be converted into dollars. The best proxies are physical: about 2.3 million blocks, roughly 6 million tonnes of material and a workforce in the tens of thousands at its peak.1
What is the Diary of Merer?
It is a papyrus logbook found at Wadi al-Jarf on the Red Sea coast in 2013 by a mission led by Pierre Tallet.2 Kept by an official who led about forty boatmen, it records limestone shipments from Tura to Giza in Khufu's 26th and 27th years, about 200 blocks a month, under the oversight of Ankhhaf.2
Was the Great Pyramid finished on time?
As far as the evidence goes, yes. There was no written schedule, but the tomb had to be usable when Khufu died, and his reign lasted about 23 to 29 years.3 Casing deliveries recorded in year 27 and an estimated build of about 26 years both fall inside that window.12

Sources

  1. Great Pyramid of Giza, Wikipedia (accessed October 25, 2026)
  2. Diary of Merer, Wikipedia (accessed October 25, 2026)
  3. Khufu, Wikipedia (accessed October 25, 2026)
  4. Port of the Pyramids, Archaeology (Archaeological Institute of America) (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart

The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.

See Kanbanchi’s Gantt chart Start your free trial Back to all 100 great projects