Events · London (Stratford), United Kingdom · 2005–2012

London 2012 Olympic and Paralympic Games

+123% against the 2005 bid; £377m under the 2007 budget: London 2012 opened on schedule on July 27, 2012, at an anticipated public cost of £8.921 billion.

+123%cost overrun
On timeagainst the first plan
$19.8 billionactual cost in 2025 dollars
Over budgetconfidence: disputed

London 2012 as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Bid and award? – Jul 6, 20052003 – Jul 6, 2005
Delivery set-up and rebudgetingnot publishedApr 2006 – Mar 15, 2007
Olympic Park construction? – 2011Dec 2006 – Dec 2011
Test eventsnot published2011 – Jul 2012
GamesJul 27, 2012 – Aug 12, 2012Jul 27, 2012 – Aug 12, 2012
Post-Games review and legacy transfernot publishedAug 13, 2012 – Dec 5, 2012

The plan

London won the 2012 Olympic and Paralympic Games on July 6, 2005, beating Paris by 54 votes to 50 in the final round at the IOC session in Singapore.4 The bid put the estimated gross cost at just over £4 billion, to be met by £3.4 billion of public money and about £700 million from the private sector.2 The opening ceremony was fixed for July 27, 2012, a date that could not move.4

The bid figure did not survive its first contact with detailed planning. On March 15, 2007, the government announced a Public Sector Funding Package of about £9.3 billion, later restated as £9,298 million.41 The National Audit Office (NAO) explained that much of the increase came from items the bid had left out or underpriced: the Olympic Delivery Authority's program management budget, a £2.7 billion contingency, tax, and security. Public funding rose by about £6 billion, and expected private funding fell to £165 million.2

This page therefore carries two baselines, as the editor's headline does. Against the 2005 bid, the outturn of £8.921 billion is about 123 percent higher in nominal terms. Against the 2007 package, it is £377 million under budget.1 Both statements are true and answer different questions. They are also not perfectly like-for-like: the bid's gross figure included privately funded organizing costs, while the NAO's £8.921 billion covers the public package only.21

Official rebaseline: March 2007 public sector funding package, £9.32 billion (outturn -4% against it).

What actually happened

Bid and award, 2005

London's winning bid carried a contingency of 4.3 percent, a reserve that Oxford researchers Bent Flyvbjerg, Alexander Budzier and Daniel Lunn later set against the real-terms outcome.3 The headline figure of just over £4 billion became the number most people remembered.2

Delivery set-up and the new budget, 2006–2007

The Olympic Delivery Authority was set up in April 2006, and work on the Olympic Park in Stratford began in December 2006.4 The March 2007 package reset the financial frame for everything that followed, including a £2.7 billion contingency that reflected how much was still uncertain.42 The NAO's July 2007 report warned that the new figure should be treated as a budget, not a target, meaning spending still had to be contained.2

Building the Olympic Park, 2006–2011

The Olympic Stadium went up between May 22, 2008 and March 29, 2011 for £486 million.5 Across the park, the NAO found that the Olympic Delivery Authority's venues and infrastructure were expected to cost about £6.7 billion against the £8.1 billion originally available to it, and the Comptroller and Auditor General said the construction program was completed on time and within budget.1 On a planned versus actual schedule, London's construction bars line up unusually well.

Security and the Games, 2012

The main late pressure was security. Venue security required about £500 million more, for which the package had made no original provision, and 13,500 armed forces personnel supported the police-led operation.14 The Olympics opened on July 27, 2012 as scheduled, and the Paralympics followed.4

Post-Games review, December 2012

On December 5, 2012 the NAO put the anticipated final cost at £8,921 million, about £377 million under the package, while noting that the exact figure would not be known until 2014.1 Flyvbjerg, Budzier and Lunn measured London's sports-related cost at $14.957 billion in 2015 dollars, the highest of any Summer Games in their dataset, and a 76 percent overrun in real terms against the bid.3 They called the public claim that London came in under budget misleading, because it rested on the revised 2007 baseline.3

Why it went the way it did

The bid left out whole cost categories

The NAO's 2007 analysis is blunt about where the money went: program management, contingency, tax and security were new costs and provisions that accounted for much of the increase. More than £1 billion of the extra public funding covered potential tax costs that would flow back to the Treasury.2 The 2005 estimate was less a cost forecast than a partial list.

A token contingency at bid stage

A 4.3 percent reserve faced a 76 percent real overrun, an amplification about 18 times larger than the contingency allowed for.3 Across every Games since 1960 the Oxford team found an average real overrun of 172 percent, which makes small bid reserves a textbook case of optimism bias in estimates.3

Rebaselining moved the reference point

Once the budget was reset in 2007, subsequent reporting measured performance against the new figure. Delivery against that figure was genuinely disciplined, but the Oxford researchers argue that presenting it as under budget, without the bid comparison, gave the public an incomplete picture.13

Lessons for project managers

  1. Name the baseline every time you report. An overrun of 123 percent and an underspend of £377 million describe the same project. Publish both baselines side by side, with dates, and let readers see the gap.
  2. Price tax, security and management into the first estimate. London's bid omitted or underpriced categories that later added about £6 billion of public money. A first estimate that leaves them out is not a budget anyone can hold.
  3. Size contingency to the evidence, not the pitch. A 4.3 percent reserve on a project class that averages 172 percent real overruns was never going to hold. Reference-class data belong in the bid, not the post-mortem.
  4. Ring-fence a real reserve once you have one. The 2007 package's £2.7 billion contingency let the delivery body absorb late shocks such as the £500 million security increase. Good project planning treats contingency as a managed line, not a slush fund.

London 2012 by the numbers

PlannedActualSource
Cost against the 2005 bidJust over £4 billion gross (2005 bid)£8.921 billion anticipated final public cost (NAO, December 2012); about +123% nominal[2]
Cost against the 2007 budget£9.298 billion Public Sector Funding Package (March 2007, restated)£8.921 billion, about £377 million under[1]
Contingency4.3% in the 2005 bid£2.7 billion in the 2007 package[2]
Real-terms overrun on sports-related cost (Oxford)Bid estimate+76% ($14.957 billion in 2015 dollars)[3]
AwardJuly 6, 2005July 6, 2005[4]
Opening ceremonyJuly 27, 2012July 27, 2012 (on schedule)[4]
Olympic StadiumBuilt May 2008 to March 2011£486 million, completed March 29, 2011[5]

From the history of managing work: Reference class forecasting (2002–2006), How Big Things Get Done (2023), Kahneman and Tversky name the planning fallacy (1977–1979).

Frequently asked questions about London 2012

How much over budget was London 2012?
It depends on the baseline. Against the 2005 bid of just over £4 billion, the NAO's anticipated final public cost of £8.921 billion is about 123 percent higher in nominal terms.21 Oxford researchers, using sports-related costs in real terms, put the overrun at 76 percent.3 Against the £9.3 billion budget set in March 2007, the Games came in about £377 million under.1
Was London 2012 really under budget?
Only against the revised budget. The NAO forecast a final cost £377 million below the £9,298 million package set in 2007.1 That package was more than double the 2005 bid, because it added contingency, tax, security and program management.2 Flyvbjerg, Budzier and Lunn describe the under-budget claim as misleading for that reason.3
Was London 2012 finished on time?
Yes. The NAO said the construction program was completed on time and within budget, and the Games opened on the fixed date of July 27, 2012.14 The Olympic Stadium was completed on March 29, 2011, more than a year before the opening ceremony.5
Why did the London 2012 budget more than double?
The NAO found that the bid had left out or underestimated major items. The 2007 budget added the delivery authority's program management, a £2.7 billion contingency, tax, and security, while expected private funding fell from about £700 million to £165 million. Public funding rose by about £6 billion as a result.2
How much did the London Olympic Stadium cost?
The stadium cost £486 million to build, with work running from May 22, 2008 to March 29, 2011.5 It sat within the delivery authority's venues and infrastructure program, which the NAO expected to cost about £6.7 billion against £8.1 billion available.1

Sources

  1. The London 2012 Olympic Games and Paralympic Games: post-Games review, National Audit Office, December 5, 2012 (accessed October 25, 2026)
  2. The budget for the London 2012 Olympic and Paralympic Games, National Audit Office, July 20, 2007 (accessed October 25, 2026)
  3. Regression to the Tail: Why the Olympics Blow Up (Flyvbjerg, Budzier & Lunn, Environment and Planning A, 2021), arXiv / University of Oxford (accessed October 25, 2026)
  4. 2012 Summer Olympics, Wikipedia (accessed October 25, 2026)
  5. London Stadium, Wikipedia (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart

The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.

See Kanbanchi’s Gantt chart Start your free trial Back to all 100 great projects