Energy · Boulder City, Nevada / Black Canyon, United States · 1931–1936

Hoover Dam (Boulder Canyon Project)

Six Companies was given seven years to build Hoover Dam and finished all features by 1 March 1936, more than two years early, within a $165 million project appropriation.

-15%cost overrun
2 years earlyagainst the first plan
$3.24 billionactual cost in 2025 dollars
On time and on budgetconfidence: medium

Hoover Dam as a Gantt chart: planned vs actual

Schedule by phase
PhasePlannedActual
Authorization and contract awardDec 21, 1928 – ?Dec 21, 1928 – Mar 1931
River diversion tunnelsApr 20, 1931 – Oct 1, 19331931 – Nov 13, 1932
Cofferdams and foundation excavationnot publishedSep 1932 – Jun 6, 1933
Concrete placementnot publishedJun 6, 1933 – May 29, 1935
Dedication and completion of all features? – Apr 20, 1938Sep 30, 1935 – Mar 1, 1936
Power generation startnot publishedMar 1, 1936 – Sep 11, 1936

The plan

Hoover Dam was authorized by the Boulder Canyon Project Act, which President Coolidge signed on 21 December 19282. The act appropriated $165 million for the whole project, which also covered Imperial Dam and the All-American Canal, so the figure is a program budget rather than a price for the dam alone2.

Bid documents were released on 10 January 1931, and Six Companies, Inc., a joint venture of western construction firms, submitted the lowest of three valid bids, at $48,890,95523. The contractor had seven years from 20 April 1931 to complete the work1. It also had to post a $5 million performance bond, and the diversion tunnel contract carried a fine of $3,000 a day for any delay2.

The schedule had one hard interim date: the river diversion tunnels had to be finished by 1 October 1933, because nothing else in the canyon could start until the Colorado was out of the way2.

What actually happened

Authorization and contract award, 1928–1931

Between the 1928 act and the 1931 contract came financing, design and the bid process2. Six Companies brought in Frank Crowe of Morrison-Knudsen as general superintendent, described by Wikipedia as the nation's leading dam builder2.

River diversion tunnels, 1931–1932

The first year was hard on the workforce. On 7 August 1931 the company cut wages for tunnel workers, and a strike followed; most workers were laid off on 9 August, rehired on 13 August, and the strike ended two days later without their demands being met2. Tunneling continued, and the river was diverted into the two Arizona tunnels on 13 November 1932, almost eleven months before the contract deadline2.

Cofferdams and foundations, 1932–1933

With the river diverted, crews built cofferdams to keep the site dry and excavated the riverbed down to bedrock2. Pulling diversion forward meant this work, and everything after it, started almost a year earlier than the contract required.

Concrete placement, June 1933–May 1935

The first concrete went in on 6 June 1933 and the last on 29 May 19351. The dam holds about three and a quarter million cubic yards1. To stop the mass from cracking as it cured, it was poured in blocks cooled by more than 582 miles of embedded one-inch steel pipe1. That allowed placement rates of 10,462 cubic yards in one day and slightly over 275,000 in one month1.

Dedication and handover, 1935–1936

President Franklin D. Roosevelt dedicated the dam on 30 September 19352. All features were completed by 1 March 1936, when the dam was turned over to the federal government more than two years ahead of schedule12. The first generator produced power on 11 September 19362. The 1939 Public Works Administration survey put the expenditure at nearly $140 million, of which $38 million came from the PWA3.

Why it went the way it did

A contract that paid for speed

Six Companies had won on a bid price, with a seven-year window and penalties for delay12. Under that structure every month saved cut the contractor's overhead and raised its margin, so the incentive to finish early was built into the deal.

The critical path was pulled forward

Diversion was the first link in the chain: cofferdams, excavation and concrete all depended on it. Finishing it in November 1932 rather than October 1933 moved every later task earlier2. It is the positive version of the problem described in task dependencies explained, where one late task holds up everything after it.

A large labor pool and an engineered process

The Depression supplied workers: 21,000 men worked on the dam in total, an average of 3,500 a day, with a peak of 5,218 in June 19341. The cooled-block method turned concrete placement from a waiting game into a production process1. The cost was human as well as financial: 112 deaths were reported in connection with construction2.

A schedule drawn as bars

Hoover Dam was built when bar-chart scheduling was already established in American industry; Henry Gantt had designed and popularized his chart around 1910–19154. The sources opened here do not document which scheduling tools Crowe's office used, but the job's structure, a few long sequential phases tied to one interim deadline, is exactly what a Gantt chart is designed to show.

Lessons for project managers

  1. Tie the contractor's profit to the date. A bid price, a long window and penalties for delay made finishing early the contractor's best financial outcome2.
  2. Find the enabling task and attack it first. River diversion unlocked every downstream activity, and finishing it eleven months early moved the whole program2.
  3. Engineer the process, not only the product. Embedded cooling pipes made record pour rates possible without cracking the dam1.
  4. Count the human cost in the plan. The fast schedule came with 112 reported deaths and a strike over pay and conditions in 19312. Speed targets need safety and welfare targets beside them.

Hoover Dam by the numbers

PlannedActualSource
Cost (whole Boulder Canyon Project)$165 million appropriation (1928)nearly $140 million (1939 PWA survey)[3]
Dam contract$48,890,955 bid (1931)not separately published[2]
Contract start20 April 193120 April 1931[1]
River diversionby 1 October 193313 November 1932[2]
Completion20 April 1938 (seven years)1 March 1936[1]
Duration84 monthsabout 58 months[1]
Concreteabout 3.25 million cubic yardspeak 10,462 cubic yards in one day[1]
Workforcenot published21,000 in total; peak 5,218 (June 1934)[1]

From the history of managing work: Scheduling the Hoover Dam (1931–1936), Henry Gantt charts work against time (c. 1910–1915), The Principles of Scientific Management (1911).

Frequently asked questions about Hoover Dam

How long did it take to build Hoover Dam?
About five years. Six Companies' seven-year allowance started on 20 April 1931, and all features were completed by 1 March 19361. Concrete placement itself ran from 6 June 1933 to 29 May 19351. The first generator began producing power on 11 September 19362.
Was Hoover Dam finished on time?
It was finished early. The contract allowed seven years from April 1931, and the dam was turned over to the federal government on 1 March 1936, more than two years ahead of schedule12. The river diversion, the key interim milestone, was done almost eleven months before its October 1933 deadline2.
How much did Hoover Dam cost?
The Boulder Canyon Project Act of 1928 appropriated $165 million for the whole project, including the All-American Canal2. A 1939 federal survey put the expenditure at nearly $140 million, with $38 million from the Public Works Administration3. The dam contract itself was won with a bid of $48,890,9552.
Who built Hoover Dam?
Six Companies, Inc., a joint venture of western construction firms led by figures including Henry Kaiser, built the dam under contract to the federal government3. Frank Crowe was general superintendent2. In total 21,000 men worked on the project, an average of 3,500 a day1.
How many people died building Hoover Dam?
There were 112 deaths reported as associated with the construction of the dam2. Conditions in the early camps were harsh, and a wage cut in August 1931 led to a short strike that ended without the workers' demands being met2.

Sources

  1. Hoover Dam - Frequently Asked Questions, US Bureau of Reclamation (accessed October 25, 2026)
  2. Hoover Dam, Wikipedia (accessed October 25, 2026)
  3. Hoover Dam - Boulder City NV, The Living New Deal (accessed October 25, 2026)
  4. Gantt chart, Wikipedia (accessed October 25, 2026)

Data: Kanbanchi, kanbanchi.com/gantt-chart-tool/great-projects, licensed CC BY 4.0. Planned means the first publicly approved budget and schedule; see the methodology. Last updated October 25, 2026.

Plan your own project with a Gantt chart

The people who built these had paper and pencils. You have a Gantt chart that lives in Google Drive.

See Kanbanchi’s Gantt chart Start your free trial Back to all 100 great projects